Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site, RWHS, STP, Furniture etc at Sector 18, Rohini. (SH: Civil and Electrical Composite Work).
Office Name
Education North West Maint Divn/Education Elect Maint Division 2
T.S. Amount
3360.39 Lacs
Dated
02/01/2020
Tender Amount
2606.13 Lacs
Dated
21/05/2020
Progress Details
Date of Start: 23/05/2020
Date of Completion: 23/05/2021
Expected Date of Completion: 28/02/2023
Actual Completion Date: 31/01/2023
Contractor
M/s Tewatia Construction Pvt. Ltd.
Payment
Civil:  2667.27 Lacs (Mar 2024)
% Progress : % (Mar 2024)
Present Position
Civil :  06/03/2023
Work completed