Public Works Department
Govt. of NCT of Delhi
लोक निर्माण विभाग, दिल्ली सरकार
लोक निर्माण विभाग
राष्ट्रीय राजधानी क्षेत्र, दिल्ली सरकार
S. No.क्र. सं. | Name of Workकार्य का नाम | Date of Start | Cost (In Lac) | Target Progress | Agency | Present Position | Satisfactory | Viewदेखें | ||
---|---|---|---|---|---|---|---|---|---|---|
Stp. Completion | ||||||||||
Exp. Completion | Expenditure | Phy. Progress | Bottleneck | Quality | Safety | Progress | ||||
1 | Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment |
18/04/2015
17/10/2017 31/12/2023 |
96400.00 138894.87 (Mar'23) |
0.00 (Mar'23) |
Larson & Toubro Limited |
Work in progress
Work in progress |
Detail Report
Graph / Photo |
|||
2 | C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwakra, New Delhi on turn-key basis |
27/08/2014
26/02/2017 31/08/2022 |
54511.43 1039.10 (Feb'23) |
0.00 (Feb'23) |
Larson & Toubro Limited |
Minor rectifications & left out works is under progress.
|
Detail Report
Graph / Photo |
|||
3 | setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) |
23/09/2021
22/02/2022 04/08/2022 |
40775.18 9915.49 (Mar'23) |
0.00 (Mar'23) |
SAM India Builtwell |
GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave.
|
Detail Report
Graph / Photo |
|||
4 | Co Admn Blk, Acdmc Bldg, Aud. Bldg, Activity Ctr, Workshop Bldg, Hostel, Resi. Blk ic Ext Devt. wks, Int. Elect. Instl, Ext. Ltng, lifts, FF sys, F.A. with PA Sys, DG Sets, Electric Sub-Stn and allied wks, HVAC wks |
|
38552.29 |
|
(i) Building Plan has been uploaded to MCD portal on 07.12.2022 for obtaining Fire, DUAC and Delhi jal Board NOC again along with all the required documents and drawings. MCD fees has been waived off on 20.01.2023. All window for issue of NOCs are opened on 20.01.2023.
(ii) NOC from Delhi Jal Board has been received vide letter No. DJB/EE(M)-51/2022-23/196 Dated 27.01.2023.
(iii) Building plan will be approved by MCD after receipt of NOCs from DUAC and Fire.
nil |
Detail Report
Graph / Photo |
||||
5 | CONSTRUCTION OF NEW HOSPITAL AT SIRASPUR, NEW DELHI (ON EPC MODE -I) INCLUDING ALL CIVIL, ELECTRICAL, MECHANICAL, HORTICULTURE AND MEDICAL SERVICES. |
10/08/2020
09/05/2023 27/02/2024 |
38439.53 15429.40 (Mar'23) |
94.00 % 0.00 (Mar'23) |
Ramacivil India Construction Private Limited |
work in progress
|
Detail Report
Graph / Photo |
|||
6 | Setting up of Semi-permanent temporary I.C.U Hospital at Chacha Nehru Bal Chikitsalaya (G plus 4) (596 beds) and GTB Hospital Complex (G plus 4) (1912 Beds) Package II |
|
35533.93 10453.18 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
7 | Construction of Flyover with Ramps, Footpath, Road Work including Road Signage, Street Light works, Drainage, Horticulture, Mural Works & allied works at Road No. 56 between Anand Vihar ROB and Apsara Border ROB, New Delhi |
|
33420.85 |
|
tender under process null |
Detail Report
Graph / Photo |
||||
8 | Construction of New Hospital Block at Babu Jagjivan Ram Memorial Hospital, Jahangirpuri, New Delhi |
|
31879.73 |
|
Revised PE in process
|
Detail Report
Graph / Photo |
||||
9 | Setting up of Semi-permanent temporary I.C.U Hospital at Sarita Vihar (G plus 4) (336beds) and Raghubir Nagar (G plus 3)(1577 Beds) Package III |
|
29175.20 2715.41 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
10 | Corridor improvement of outer ring road from IIT to NH-8 and its influence area (1)C/o flyover from Munirka to Army RR Hospital on outer ring road (2) C/o underpass & skywalk etc. at juncture of BJ Marg, Ring Road |
27/11/2014
26/11/2016 31/12/2022 |
27807.81 27597.16 (Sep'19) |
70.00 % (Sep'19) |
Hindustan Construction Co. Ltd |
Flyover open to public on 16-07-2019. The Underpass work has been completed and inaugurated by Hon'ble Dy CM Delhi on 02-07-2022 only touch-up, minor work, ramp covering and finishing work is in progress
|
Detail Report
Graph / Photo |
|||
11 | Construction of Hospital at Jwalapuri, New Delhi |
07/08/2020
13/08/2022 14/09/2023 |
26950.37 7029.55 (Mar'23) |
0.00 (Mar'23) |
Parnika Commercial and Estates Pvt. Ltd. |
Structure RCC work completed. Flooring work, masonry work, façade work, road work, water proofing, gypsum plaster etc. & electrical work is in progress.
|
Detail Report
Graph / Photo |
|||
12 | Construction of Hospital at Hastsal, New Delhi |
17/06/2021
16/06/2023 31/12/2023 |
23695.11 70.11 (Mar'23) |
89.00 % 0.00 (Mar'23) |
Work is under progress and overall physical progress (Civil part) of work is 27%.
|
Detail Report
Graph / Photo |
||||
13 | C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi SH Co Academic Bldg, Auditorium Bldg, Sports Hall, Boys, Girls, Teachers Hostel, Type II III IV and V Qtrs ic Ext Dev. works, Int Elect Inst, Ext Lighting, lifts, fire fighting system, fire alarm with PA System, D.G. Sets, Elect Sub Stn, HVAC works |
09/08/2017
09/11/2019 20/03/2023 |
23127.43 6589.16 (Mar'23) |
0.00 (Mar'23) |
NKG Infrastructure Limited |
Physical Progress of the work is 98%.
nil |
Detail Report
Graph / Photo |
|||
14 | C/o Police Housing project at Mandoli, Delhi-93(SH: C/o 300 Nos. Type-II and 60 Type-IV qtrs and its related development works) |
|
22130.16 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
15 | Operation and comprehensive maintenance of 4 Nos. X 1010 KVA & 2 Nos. X 500 KVA DG sets installed at Mandoli Prison Complex. |
|
18858.16 |
|
tender called (opening date 13.03.2023)
|
Detail Report
Graph / Photo |
||||
16 | C/o 750 Bedded Hospital at Dwarka, New Delhi. |
|
16355.70 402.66 (Jul'22) |
0.00 (Jul'22) |
|
Detail Report
Graph / Photo |
||||
17 | Construction of Flyover at Nand Nagri and Gagan Cinema Junction of Mangal Paney Marg including Elevated Corridor Footpath Road Work and Road Signages Electrical Works Drainage Rain Water Harvesting and Allied works on EPC mode |
03/02/2023
31/07/2024 31/07/2024 |
15785.00 |
5.00 % |
Ram Kumar Contractor |
Work just awarded.
Necessary approvals and formalities is in process.
|
Detail Report
Graph / Photo |
|||
18 | Construction of 144 Nos Temporary Courtroom in the existing court complexes of Saket Stilt plus 3 Tis Hazari Stilt plus G plus 3 and Karkardooma G plus 4 |
04/10/2019
03/07/2020 15/03/2023 |
14316.00 1598.26 (Mar'23) |
0.00 (Mar'23) |
Quality Buildcon Pvt. Ltd. |
140 Temporary court rooms at Karkardooma, Saket and Tis Hazari
The Work is in progress with upto date progress is approx. 99.5%.
(i) Karkardooma: The work is completed and inaugurated on 13.05.2022, possession taken on 26.08.22. Keys have been taken over by caretaking branch during the course of third week of November.
(ii) Saket: The work is completed, courts made functional dated 01.09.22. Some additional work has been proposed by court authorities which has been started and will be completed by January.
(iii) Tis Hazari: Work is completed and defect rectification work is underway and final furniture placing, interconnection of fiber cable between old & new building is in progress. Fire clearance obtained dated 14.10.22. Some additional work has been proposed by court authorities has also been completed and the building has been made ready for handover pending certain costly fixtures which will be fixed and final testing and commissioning of all services will be completed within 10 days, once the security personnel are provided by the district court authorities. An estimate regarding basic housekeeping and security had also been sent to the court authorities and to the dedicated maintenance wing to facilitate the handover as well.
15th December is the tentative date of handing over to the district court authorities as decided during site visit dated 5th December however, security protocol is yet to be given.
Certain minor defects were pointed out by court authorities again during 30.12.22 visit which will be rectified by year end and building will be tentatively handed over during 15 Feb 2023.
|
Detail Report
Graph / Photo |
|||
19 | Addition & Remodelling work for Bhagwan Mahavir Hospital at Pitampura Delhi including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. |
10/12/2019
01/06/2020 31/12/2023 |
13992.80 2103.50 (Mar'23) |
0.00 (Mar'23) |
Kamladitya Construction Private Limited |
OPD block is completed. The deceision of Health Ministry for change in scope of work is awaited.
|
Detail Report
Graph / Photo |
|||
20 | Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi |
18/10/2019
10/04/2021 30/04/2023 |
13447.15 3634.52 (Feb'23) |
99.00 % 0.00 (Feb'23) |
Roshan Real Estate Pvt Ltd. |
Work is under progress.
|
Detail Report
Graph / Photo |
|||
21 | Extension of Ashram Flyover to DND Flyover. |
19/06/2020
18/06/2021 31/03/2022 |
12879.00 14254.02 (Jan'23) |
0.00 (Jan'23) |
KCC Buildcon Pvt. LTD |
Work in progress.
|
Detail Report
Graph / Photo |
|||
22 | Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. |
04/03/2020
03/09/2021 03/09/2021 |
10708.84 3123.00 (Mar'23) |
0.00 (Mar'23) |
Quality Buildcon Pvt. Ltd. |
work in progress
|
Detail Report
Graph / Photo |
|||
23 | C/o Haji House at Sector-22, Phase-II, Dwarka, New Delhi |
|
9566.03 0.00 (Mar'19) |
0.00 (Mar'19) |
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
24 | C/o New DC office at Mandawali, Fazalpur, Delhi |
|
8432.86 |
|
A/A & E/S awaited
|
Detail Report
Graph / Photo |
||||
25 | Construction of Delhi Fire Service Headquarter Building at Connaught Place, New Delhi-110001 |
|
8094.10 0.00 (Mar'19) |
0.00 (Mar'19) |
The Hon'ble Minister (Home) Govt. of NCT of Delhi has desired that as per FAR and Ground Coverage has already been increase as per MPD-2021 from 120 to 300 and 30% to 50% respectively The Fire Services Deptt. To advice for re-calling the tenders for consultancy services of above work seems justified. A letter has been received from consultant M/s Gian P. Mathur & Association (P) Ltd. (Copy enclosed) for revised escalation of consultancy fees for FAR increased 120 to 300% and Ground Coverage 30 to 50%. The case was sent to the C.E. (OP) . The above case has been review/scrutiny in the C.E. (OP) after review/scrutiny of the case the C.E. (OP) has required to provide current prevailing market rate with justification. The EE (OPD-I) directed to the consultant to provide current prevailing market rate with justification to this office on 28.11.2022.
After scrutiny proposal, the competent authority has been decided on 14.02.2023 to prepare the revised preliminary estimate to obtain revised A/A & E/S from client department before call a fresh tender for consultancy work. A letter has also been received from Delhi Fire Service authority vide No. F6/DFS/MS/BP/2023/271 dated 13.02.2023 for calling fresh tender. The Revised PE amounting to Rs. 2,23,46,965/- for consultancy work has been sent CE (OP), PWD vide this office letter No. 23(1)/EE/OPD-I)/PWD/83 dt. 17.02.2023.
|
Detail Report
Graph / Photo |
||||
26 | Maintenance of P.C. in Divn and SD Office. |
|
7122.82 |
|
PNSC Infrastructure Pvt. Ltd |
|
Detail Report
Graph / Photo |
|||
27 | C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. |
04/09/2019
03/03/2021 31/12/2022 |
7122.09 1553.62 (Mar'23) |
0.00 (Mar'23) |
PNSC Infrastructure Pvt. Ltd |
work in progress.
|
Detail Report
Graph / Photo |
|||
28 | Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. |
06/08/2019
29/10/2020 30/06/2023 |
6563.40 1143.07 (Mar'23) |
0.00 (Mar'23) |
PNSC Infrastructure Pvt. Ltd |
Work is under progress.
|
Detail Report
Graph / Photo |
|||
29 | Construction of New block Forensic Science Laboratory, Rohini, New Delhi |
06/03/2020
05/09/2021 05/09/2021 |
5216.00 212.87 (Aug'21) |
0.00 (Aug'21) |
work in progress
|
Detail Report
Graph / Photo |
||||
30 | Construction of underpass along Mathura Road at Ashram Chowk New Delhi |
05/07/2019
04/07/2020 12/07/2022 |
4907.38 6164.87 (Feb'23) |
0.00 (Feb'23) |
Dharamraj Contracts (I) Pvt. Ltd. |
Underpass has been opened for Traffic on 24.04.2022. Work almost completed except some defects, which are being attended.
|
Detail Report
Graph / Photo |
|||
31 | C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) |
14/01/2019
09/11/2019 31/03/2023 |
4874.05 5266.28 (Mar'23) |
0.00 (Mar'23) |
Shri kamal singh |
Work in progress
|
Detail Report
Graph / Photo |
|||
32 | C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) |
20/01/2019
15/11/2019 31/03/2023 |
4603.38 4716.31 (Mar'23) |
0.00 (Mar'23) |
Sh. Kamal Singh |
Work in progress
|
Detail Report
Graph / Photo |
|||
33 | Providing furniture in various govt. schools under Education, PWD, Delhi. (Package – B) |
|
4497.90 3761.10 (Mar'23) |
0.00 (Mar'23) |
work in progress
work in progress |
Detail Report
Graph / Photo |
||||
34 | Providing furniture in various govt schools for additional classrooms under Education PWD Delhi Package A |
|
4441.35 6969.00 (Mar'23) |
0.00 (Mar'23) |
work in progress
work in progress |
Detail Report
Graph / Photo |
||||
35 | Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) 43,50,79,456 |
|
4350.79 |
|
|
Detail Report
Graph / Photo |
||||
36 | Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) |
|
4350.79 |
|
|
Detail Report
Graph / Photo |
||||
37 | Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) |
|
4350.79 7.43 (Jun'19) |
0.00 (Jun'19) |
Technical bid opened
|
Detail Report
Graph / Photo |
||||
38 | Construction of underpass by jack pushing of pre-cast RCC boxes at outer ring road near Mukarba Chowk including construction of approach road from Badli Junction to Haiderpur Metro Station. |
14/10/2022
13/10/2023 13/10/2023 |
4329.32 200.00 (Mar'23) |
40.00 % 0.00 (Mar'23) |
Dharamraj Contracts (I) Pvt. Ltd. |
The work has been awarded. The site was handed over to the agency on 14.10.2022. Progress of work was effected due to the construction ban by NGT.
Work stopped due to the non-availability of NOC from the I&FC Deptt as well as the shifting of IGL lines and TPDDL OHT lines.. |
Detail Report
Graph / Photo |
|||
39 | C/o Three Lane Flyover, Road Work, Footpath, Drainage System, Landscaping, Railing, Road Signages, Street Light & Allied works. |
15/07/2022
14/07/2023 14/07/2023 |
4199.50 1520.14 (Mar'23) |
65.00 % 0.00 (Mar'23) |
Gawar Construction Ltd., |
work in progress
|
Detail Report
Graph / Photo |
|||
40 | C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi |
|
4172.51 1099.45 (Mar'23) |
0.00 (Mar'23) |
Initially site was encroached by local peoples. Encroachment the major part of land has been removed with help of education department and Delhi Police on dated 22.03.2022, but some portion of site is still encroached by local person. Partly site handed over to the agency for boundary wall and building construction on dated 23.03.2022, hence the actual work started from 23.03.2022. . Due to High Court stay order dated 30.08.2022, work stopped in disputed area. Work is in progress in undisputed area. Structural work in L shape block completed. Flooring finishing in progress. In U- shaped portion level 3 to 4 is in progress.
|
Detail Report
Graph / Photo |
||||
41 | Covering of the ramps of all the underpass (entry & exit) i.e. Underpass 1 to 6 as well as the main tunnel entry and exit ramps, branch tunnel entry ramps developed in the construction of Integrated Transit Corridor Development plan in and around Pragati Maidan. |
|
4148.84 193.50 (Sep'22) |
0.00 (Sep'22) |
not pertains to this office
|
Detail Report
Graph / Photo |
||||
42 | Covering of the ramps of all the underpass (entry & exit) i.e. Underpass 1 to 6 as well as the main tunnel entry and exit ramps, branch tunnel entry ramps developed in the construction of Integrated Transit Corridor Development plan in and around Pragati Maidan. |
21/05/2022
20/11/2022 20/11/2022 |
4144.69 |
|
R S Sharma Contractors Pvt. Ltd. |
Work is in progress |
Detail Report
Graph / Photo |
|||
43 | C/o 56 Nos. additional (G+3) SPS equivalent Class Rooms including 1 stilt , 8 nos toilet, 4 nos staircase, lift, RWH & UGR at Govt. Co Senior Secondary School at Usmanpur, Delhi (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) |
|
3910.36 |
|
The work was foreclosed under Clause 3A. Site not clear.
The work was foreclosed under Clause 3A. Site not clear. |
Detail Report
Graph / Photo |
||||
44 | W/O Mahrauli Mahipalpur Road. SH: from 4 lanes to 8 lanes and Service Road from Andheria More to Masoodpur Village. |
30/10/2012
29/04/2013 29/04/2013 |
3812.11 |
|
KCC Buildcon Pvt. LTD |
.
|
Detail Report
Graph / Photo |
|||
45 | Construction of 140 nos additional SPS Classrooms in DOE Schools GGSSS No. 1 Tukhmirpur, Delhi (1104262) 40 Class rooms, GGSSS No. 2 Tukhmirpur, Delhi (1104419) 32 Class rooms & GSKV Khajuri Khas, Delhi (1104022) 68 Class rooms including Laboratory, staircases, toilets and ramps, internal water supply, sanitary installations, Internal electrification and fire fighting arrangements. |
|
3713.27 |
|
Competent Authority has withdrawal the tender and the letter issued to agency on 29.08.2022.Work shall only be taken up after sufficient fund is released to PWD.The fund has not alloted by SSA
and vide CE office letter No. 23(45)/ 22/CE(Proj.)/PWD/E&NE/852 dated: 22.09.2022 informed the Education Department/SSA for withdrawn the sanction.
Competent Authority has withdrawal the tender and the letter issued to agency on 29.08.2022.Work shall only be taken up after sufficient fund is released to PWD.The fund has not alloted by SSA and vide CE office letter No. 23(45)/ 22/CE(Proj.)/PWD/E&NE/852 dated: 22.09.2022 informed the Education Department/SSA for withdrawn the sanction. |
Detail Report
Graph / Photo |
||||
46 | Const 182 Nos. of additional SPS class rooms (Package-C) |
17/03/2019
11/12/2019 14/07/2022 |
3699.32 3727.61 (Feb'23) |
0.00 (Feb'23) |
SPS Infrabuild Pvt. Ltd. |
Work completed.
Work completed. |
Detail Report
Graph / Photo |
|||
47 | Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW |
24/12/2018
19/09/2019 20/10/2022 |
3675.76 3278.89 (Jan'23) |
0.00 (Jan'23) |
RAMA Contractor |
Work completed.
Work completed. |
Detail Report
Graph / Photo |
|||
48 | Const 180 Nos. of additional SPS class rooms (Package-B) |
17/03/2019
11/12/2019 12/10/2022 |
3636.43 19151.12 (Oct'22) |
0.00 (Oct'22) |
RAMA Contractor |
Handed over to HOS.
Handed over to HOS. |
Detail Report
Graph / Photo |
|||
49 | Const 174 Nos. of additional SPS class rooms in various schools (Package-E) |
17/03/2019
11/12/2019 14/07/2022 |
3553.31 3181.90 (Mar'23) |
0.00 (Mar'23) |
SPS Infrabuild Pvt. Ltd. |
Handed over to HOS
Handed over to HOS |
Detail Report
Graph / Photo |
|||
50 | Up gradation and Construction of an additional multi- story building in the premise of Forensic Science Laboratory, Rohini, Delhi. |
14/11/2019
13/02/2021 31/03/2023 |
3541.69 863.13 (Jan'23) |
0.00 (Jan'23) |
Tewatia Construction Pvt. Ltd. |
work in progress
|
Detail Report
Graph / Photo |
|||
51 | Supply, Installation, Testing and Commissioning of additional CCTV cameras to be integrated with existing (BOSCH Make) CCTV Surveillance System installed at Tihar, Rohini and Mandoli Prison Complexes |
24/12/2022
23/06/2023 23/06/2023 |
3483.10 261.11 (Mar'23) |
49.00 % 0.00 (Mar'23) |
OPTIMUM SECURITY SOLUTIONS PVT. LTD. |
Work in progress
|
Detail Report
Graph / Photo |
|||
52 | Const 184 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW |
17/03/2019
11/12/2019 06/10/2022 |
3455.84 3857.92 (Mar'23) |
0.00 (Mar'23) |
RAMA Contractor |
Work completed.
Work completed. |
Detail Report
Graph / Photo |
|||
53 | Civil & Electrical Works |
|
3385.59 2669.18 (Jan'23) |
0.00 (Jan'23) |
|
Detail Report
Graph / Photo |
||||
54 | Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works) |
|
3368.55 532.77 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
55 | Construction of Bridge on Supplementary Drain on NH-10, Nangloi, Delhi to cover complete width of 60 m with road improvement in 100 meter length on either side of bridge including making of drainage scheme, footpath etc. complete (after dismantling ). |
06/03/2019
05/12/2020 31/03/2023 |
3350.31 2977.03 (Feb'23) |
100.00 % 0.00 (Feb'23) |
Ram Kumar Contractor |
Approach Road work and finishings work is in progress.
|
Detail Report
Graph / Photo |
|||
56 | Comprehensive Maintenance of Ring Road/Outer Ring Road under North Maintenance Zone, PWD, Delhi SH: Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work |
30/05/2020
29/05/2022 29/05/2022 |
3194.88 1149.43 (Feb'23) |
0.00 (Feb'23) |
MAHAVIR PRASAD GUPTA AND SONS |
Work in Progress
|
Detail Report
Graph / Photo |
|||
57 | Civil work and Internal E.I. work |
24/04/2007
23/07/2009 31/12/2011 |
3002.21 |
|
Globe Civil Project Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
58 | SKV Sangam Vihar J Block Sch. ID 1923346 |
17/03/2019
11/12/2019 31/03/2023 |
3002.10 3233.23 (Mar'23) |
0.00 (Mar'23) |
Devinder Singh |
Work is in progress
work is in progress |
Detail Report
Graph / Photo |
|||
59 | Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. |
17/10/2022
16/10/2023 16/10/2023 |
3000.18 395.49 (Feb'23) |
40.00 % 0.00 (Feb'23) |
Jai Bhagwan |
Plinth beam & stilt floor column in progress.
Plinth beam & stilt floor column in progress. |
Detail Report
Graph / Photo |
|||
60 | Construction of Pucca School Building G plus 3 with ancillary facilities including internal water supply sanitary installation, internal electrical installation and development of sites RWHS STP etc at Sector 05 Rohini Delhi |
29/05/2020
28/05/2021 31/03/2023 |
2931.78 4013.36 (Mar'23) |
0.00 (Mar'23) |
The Krishna Construction Co. |
Work in progress
|
Detail Report
Graph / Photo |
|||
61 | Street Scaping of Ring Road from Moolchand Junction to Ashram Chowk |
|
2880.35 |
|
|
Detail Report
Graph / Photo |
||||
62 | SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW |
17/10/2019
12/07/2020 31/03/2023 |
2849.35 2549.96 (Feb'23) |
0.00 (Feb'23) |
A. K. Builders |
work in progress.
work in progress. |
Detail Report
Graph / Photo |
|||
63 | Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work. |
|
2820.52 34.01 (Mar'22) |
0.00 (Mar'22) |
|
Detail Report
Graph / Photo |
||||
64 | Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. |
28/06/2019
22/06/2020 31/03/2023 |
2806.33 268.76 (Feb'23) |
0.00 (Feb'23) |
Roshan Real Estate Pvt Ltd. |
Work in progress (40% progress)
|
Detail Report
Graph / Photo |
|||
65 | Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc. |
11/10/2022
05/09/2023 05/09/2023 |
2783.15 423.78 (Mar'23) |
45.00 % 0.00 (Mar'23) |
DND Infra Private Limit |
Pile work & Block-1 plinth beam steel binding in progress. Boundary wall lintel beam in progress & drain work completed.
Pile work & Block-1 plinth beam steel binding in progress. Boundary wall lintel beam in progress & drain work completed. |
Detail Report
Graph / Photo |
|||
66 | Civil works and Electrical works. |
|
2705.68 |
|
|
Detail Report
Graph / Photo |
||||
67 | Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi |
23/08/2021
22/05/2022 23/05/2023 |
2373.12 965.09 (Mar'23) |
92.00 % 0.00 (Mar'23) |
M/s PK Gupta & Co. |
RCC work of Admin cum Rest Room, Toilet Block, Workshop buildings are in progress.
Work is being hampered due to :
1) Non availability of permission from SDM office for playing of Good Earth truck.
2) Progress of work effected due to NGT construction ban.
In progress.. |
Detail Report
Graph / Photo |
|||
68 | SBV Jonapur, School ID: 1923359 |
08/12/2018
04/08/2019 31/03/2023 |
2342.87 1530.26 (Mar'23) |
0.00 (Mar'23) |
Reliance Elektrik works |
Work is in progress
|
Detail Report
Graph / Photo |
|||
69 | Uttam Nagar T Point Ram Mandir Marg Mall Rd C1 to C1A Block Rd under Sub Division WR12 Lala Ganesh Das Khatri Marg G-1 Block Vikaspuri Rd Rd No 235 Rd Adjacent to PVR under SubDivision WR13 80 Feet Chowkhandi Rd Shakti Mandir Marg Major Sudesh Marg |
|
2305.99 |
|
|
Detail Report
Graph / Photo |
||||
70 | Strengthening / Resurfacing of carriageway of Auchandi Border to Tatesar Village Road, Princess Road, Model Town II Road, Model Town III Road, Fire Station to Pump House Road, Kushal Cinema Road............... under North Road Division, Delhi |
|
2242.83 |
|
|
Detail Report
Graph / Photo |
||||
71 | Civil works and Electrical works. |
|
2141.13 |
|
|
Detail Report
Graph / Photo |
||||
72 | Strengthening of SSN Marg ID- 392 and 100 Foota Road ID- 1187 New Delhi. |
10/09/2020
09/01/2021 09/01/2021 |
1893.62 3407.76 (Oct'22) |
0.00 (Oct'22) |
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
73 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. |
|
1887.50 |
|
Technical Bid opened on 19.10.2022 and Technical Bid has been opened on 03.02.2023 and documents are under scrutiny.
|
Detail Report
Graph / Photo |
||||
74 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. |
|
1874.71 3.99 (Jan'23) |
0.00 (Jan'23) |
Technical bid opened on 19.10.2022 and Technical Bid has been opened on 03.02.2023 and documents are under scrutiny.
|
Detail Report
Graph / Photo |
||||
75 | Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. |
31/05/2020
30/05/2021 30/06/2023 |
1874.70 1184.94 (Mar'23) |
0.00 (Mar'23) |
SSP Promoters and Builders Private Limited |
WORK IN PROGRESS
|
Detail Report
Graph / Photo |
|||
76 | STREET SCAPING OF 1000 METER OF NELSON MANDELA ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1870.18 |
|
|
Detail Report
Graph / Photo |
||||
77 | Street Scaping of 800 meter length of Ring Road, Bhairon Road T-Junction to Shantivan Crossing to make it Model Stretch of Street Scaping Project |
|
1859.21 |
|
|
Detail Report
Graph / Photo |
||||
78 | Furniture Work RECALL |
04/11/2019
18/12/2019 |
1858.08 6.26 (Sep'21) |
0.00 (Sep'21) |
Rajdhani Furnitures PVT. LTD. |
|
Detail Report
Graph / Photo |
|||
79 | STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1848.01 647.29 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
80 | Co Hostel Bldg inclu External Development works Internal Elect Installation External Lighting lifts fire fighting system fire alarm with PA System CCTV Audio video system HVAC works |
27/02/2023
26/07/2024 26/07/2024 |
1839.86 |
5.00 % |
KALYAN CHANDRA GOYAL & CO. |
v
|
Detail Report
Graph / Photo |
|||
81 | Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project |
|
1814.36 0.79 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
82 | Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project |
|
1814.36 0.10 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
83 | Balance Civil, Electrical and Horticulture Work as per revised concept |
|
1809.71 |
|
|
Detail Report
Graph / Photo |
||||
84 | C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc |
01/04/2022
24/02/2023 30/09/2023 |
1798.93 215.50 (Mar'23) |
100.00 % 0.00 (Mar'23) |
K. L. ARORA & SON |
St. Eknath SKV J&K Block Dilshad Garden
Tower A- 3rd floor slab beam shuttering in progress.
MP Hall- Truss work in progress.
DIET J&K block Dilshad Garden, Delhi.
Above 2nd floor Column steel binding in progress.
St. Eknath SKV J&K Block Dilshad Garden Tower A- 3rd floor slab beam shuttering in progress. MP Hall- Truss work in progress. DIET J&K block Dilshad Garden, Delhi. Above 2nd floor Column steel binding in progress. |
Detail Report
Graph / Photo |
|||
85 | Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi |
22/11/2021
17/10/2022 31/03/2023 |
1773.27 2048.30 (Mar'23) |
0.00 (Mar'23) |
Harbel Singh & Sons |
Work is in progress. Sub structural work completed. Girder assembling and launching is in progress.
|
Detail Report
Graph / Photo |
|||
86 | C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) |
29/12/2018
26/07/2019 31/03/2023 |
1743.19 4490.50 (Dec'22) |
0.00 (Dec'22) |
AMAR CONSTRUCTION COMPANY |
Work in progress
|
Detail Report
Graph / Photo |
|||
87 | STREET SCAPING OF 700 METER LENGTH OF K.N. KATJU MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1644.08 |
|
|
Detail Report
Graph / Photo |
||||
88 | Providing Manpower services of Clericals, Drivers, Multitasking and Staff (Un-skilled, Semi -skilled, Clerical and Non- Technical Supervisory Staff) in various offices under the jurisdiction of Health Maintenance Zone, PWD |
03/04/2019
02/04/2021 |
1625.72 |
|
RAKSHAK SECURITAS PVT. LTD. |
|
Detail Report
Graph / Photo |
|||
89 | Construction of conventional Cluster Bus Depot No. II at Burari, Delhi.(SH: Civil & Electrical works). |
|
1620.46 |
|
Nafees Ahmed |
Tender for the work invited on 04.03.2022. Letter of commencement issued on 30.04.2022. Date of start and date of completion will be decided after getting approval from Forest Department. |
Detail Report
Graph / Photo |
|||
90 | Development of Synthetic Athletic Track with Football field and Synthetic Hockey Turf in Rajiv Gandhi Sports Complex Singhu Delhi |
08/03/2021
02/11/2021 31/03/2023 |
1583.17 773.07 (Dec'22) |
0.00 (Dec'22) |
Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 |
90%
|
Detail Report
Graph / Photo |
|||
91 | C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc |
26/03/2022
19/02/2023 31/07/2023 |
1553.88 471.58 (Mar'23) |
0.00 (Mar'23) |
K L Arora & Son |
St. Eknath SKV J&K Block Dilshad Garden
Tower A- 3rd floor slab beam shuttering in progress.
MP Hall- Truss work in progress.
DIET J&K block Dilshad Garden, Delhi.
Above 2nd floor Column steel binding in progress.
St. Eknath SKV J&K Block Dilshad Garden Tower A- 3rd floor slab beam shuttering in progress. MP Hall- Truss work in progress. DIET J&K block Dilshad Garden, Delhi. Above 2nd floor Column steel binding in progress. |
Detail Report
Graph / Photo |
|||
92 | C/o 72 Nos. Equivalent SPS Class Rooms in addition to boundary wall i/c Internal & External water supply, sanitary installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting System etc. for new school building at GBSSS Jharoda kalan (School ID 1822065) , New Delhi |
|
1542.27 457.52 (Mar'23) |
0.00 (Mar'23) |
The Krishna Construction Co. |
Initially some delay in start of work due to revision of layout and land apportioning between the new school and existing school.. Layout plan was finalised by client department on 15.07.2022 and now boundary work level 2 to 3 is in progress.
|
Detail Report
Graph / Photo |
|||
93 | C/o 56 Nos. additional (G+3) SPS equivalent Class Rooms including 1 stilt , 8 nos toilet, 4 nos staircase, lift, RWH & UGR at Govt. Co Senior Secondary School at Usmanpur, Delhi (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) |
|
1530.73 |
|
WORK FORE CLOSED
SITE NOT CLEAR
WORK FORE CLOSED SITE NOT CLEAR |
Detail Report
Graph / Photo |
||||
94 | Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project |
|
1524.43 56.90 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
95 | Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project |
|
1524.43 |
|
|
Detail Report
Graph / Photo |
||||
96 | Strengthening of Vandematram Marg from Dhaula Kuan to Dayal Chowk and Shanker Road from Pusa Chowk to Shanker Chowk under PWD Division South West Road-1, Sub Division-IV New Delhi. (Road ID:212 and ID :213). |
|
1494.67 |
|
|
Detail Report
Graph / Photo |
||||
97 | STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1480.89 2233.49 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
98 | STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT. |
|
1480.89 |
|
|
Detail Report
Graph / Photo |
||||
99 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24 |
|
1462.16 269.56 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
100 | Construction of 48 Nos G plus 3 SPS Eq. classroom including 3 staircase 1 lift and 1 toilet block in Mustafabad School Delhi Including internal and external water supply sanitary installations electrical installations development of site Boundary W |
|
1442.22 |
|
After modification NIT was uploaded on 06.02.2023 and M/s Amocon is L-1 and Acceptance letter has been issued to M/s Amocon vide this office letter No. 54(77) Edu. M. (East & North East)/PWD/48 dated: 28.02.2023
After modification NIT was uploaded on 06.02.2023 and M/s Amocon is L-1 and Acceptance letter has been issued to M/s Amocon vide this office letter No. 54(77) Edu. M. (East & North East)/PWD/48 dated: 28.02.2023 |
Detail Report
Graph / Photo |
||||
101 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 |
03/06/2022
02/06/2024 02/06/2024 |
1438.47 263.05 (Mar'23) |
38.00 % 0.00 (Mar'23) |
Work in progress.
|
Detail Report
Graph / Photo |
||||
102 | STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1379.62 |
|
|
Detail Report
Graph / Photo |
||||
103 | Construction of 80 Nos G plus 3 equivalent SPS Class Rooms at Govt Co Ed Sr Secondary School Gandhi Brahampur Delhi including 8 toilet blocks, 4 nos staircase 1 lift and internal and external water supply sanitary installations, electrical installations, development of site, RWH & UGR fire fighting system etc. |
26/03/2022
19/02/2023 19/02/2023 |
1377.43 |
|
K. L. ARORA & SON |
Work foreclosed.
Work foreclosed. |
Detail Report
Graph / Photo |
|||
104 | Operation & Maintenance of EI & Fans, HVAC, Sub Stations, DG Sets, UPS, Fire Fighting System, Fire Alarm System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 |
|
1369.68 249.70 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
105 | C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc |
02/04/2022
25/02/2023 30/09/2023 |
1359.28 486.49 (Mar'23) |
100.00 % 0.00 (Mar'23) |
K. L. ARORA & SON |
Columns of Block-3 from 1st floor level to 2nd level in progress. In Block-1, Reinforcement binding of raft in progress. Plinth beams & column casting in progress in Block-2. Work delay due to insufficient labour & resources.
Columns of Block-3 from 1st floor level to 2nd level in progress. In Block-1, Reinforcement binding of raft in progress. Plinth beams & column casting in progress in Block-2. Work delay due to insufficient labour & resources. |
Detail Report
Graph / Photo |
|||
106 | Operation & Maintenance of EI & Fans, DG Sets, Fire Engine, HVAC Works, Fire Alarm System, Fire Fighting and Wet Riser System, Sub Station, Solar Water Heating System etc. for the year 2022-23 and 2023-24. |
|
1350.14 102.55 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
107 | Civil works relating to day to day maintenance, A/R & M/O Works & Special Repair Works |
10/05/2022
08/05/2024 08/05/2024 |
1313.79 457.21 (Mar'23) |
42.00 % 0.00 (Mar'23) |
Raghav Engineers |
work completed work completed |
Detail Report
Graph / Photo |
|||
108 | Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) |
12/03/2022
04/02/2023 31/03/2023 |
1275.84 174.07 (Feb'23) |
100.00 % 0.00 (Feb'23) |
M/s SURENDRA KUMAR |
Work in progress
|
Detail Report
Graph / Photo |
|||
109 | Resurfacing improvement strengthening riding surface of roads ..... road division |
13/01/2020
08/04/2020 |
1272.87 882.72 (Jan'23) |
0.00 (Jan'23) |
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
110 | STREET SCAPING OF 800 METER LENGTH OF RING ROAD, BHAIRON ROAD T-JUNCTION TO SHANTIVAN CROSSING TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1226.77 |
|
|
Detail Report
Graph / Photo |
||||
111 | GGSS No. 3 Sec IV, Ambedkar Nagar |
03/03/2016
15/07/2016 31/01/2017 |
1212.87 1221.00 (Jan'18) |
100.00 % (Jan'18) |
Devinder Singh |
completed
null |
Detail Report
Graph / Photo |
|||
112 | Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project |
|
1193.08 |
|
|
Detail Report
Graph / Photo |
||||
113 | Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project |
|
1193.08 |
|
|
Detail Report
Graph / Photo |
||||
114 | Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping projec |
|
1193.08 2182.65 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
115 | Comprehensive Maintenance of Civil works including day to day maintenance, Annual Repair works and Special Repair works under Maulana Azad Medical College & Guru Nanak Eye Centre New Delhi |
25/05/2022
23/05/2024 23/05/2024 |
1184.23 180.93 (Jan'23) |
42.00 % 0.00 (Jan'23) |
Swastik Electrotech Pvt. Ltd. |
work completed work completed |
Detail Report
Graph / Photo |
|||
116 | Widening of Mehrauli Mahipal pur Road from 4 lanes to 8 lanes and service road from Andheria More to Fortis Hospital.(SH- Balance work for available land from Chainage 700Mtr. to 2100mtr.) |
|
1157.23 |
|
|
Detail Report
Graph / Photo |
||||
117 | STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
1119.07 |
|
|
Detail Report
Graph / Photo |
||||
118 | C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and Placing of Non-Medical Furnitures at Indira Gandhi Hospital, Dwarka, New Delhi). |
11/07/2021
23/09/2021 31/03/2023 |
1118.83 89.89 (Jan'23) |
97.00 % 99.00 % (Jan'23) |
M/s Rajdhani Furnitures Pvt. Ltd. |
99.6% work physically completed.
|
Detail Report
Graph / Photo |
|||
119 | Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi |
06/04/2022
05/04/2025 05/04/2025 |
1099.29 53.87 (Oct'22) |
30.00 % 0.00 (Oct'22) |
SIKKA ASSOCIATES REGD. |
The proposal was submitted to VC, Delhi Sports University as on . The approval has been communincated as on dated . The PE has been submitted by the consultant and same is under scrutiny.
|
Detail Report
Graph / Photo |
|||
120 | Comprehensive Maint. of Civil, Electrical and Horticulture Operations relating Day to day Maint., Special Repair etc of Dr. BSAH Complex, Sector 6, Rohini, Delhi incl. Main Hospital Bldg., Medical College, Hostel and Residential Qtrs. Dg. 2019-20-21. |
|
1097.15 371.30 (Aug'22) |
0.00 (Aug'22) |
work in progress
|
Detail Report
Graph / Photo |
||||
121 | C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) |
18/04/2022
13/03/2023 31/07/2023 |
1090.67 413.13 (Mar'23) |
0.00 (Mar'23) |
K. L. ARORA & SON |
In Block A, Plinth beam & casting of columns in progress. In Block -B, columns from 1st floor level to 2nd floor level in progress. Work delay due to insufficient labour & resources.
In Block A, Plinth beam & casting of columns in progress. In Block -B, columns from 1st floor level to 2nd floor level in progress. Work delay due to insufficient labour & resources. |
Detail Report
Graph / Photo |
|||
122 | Reconstruction of CC Road including raising of Railway Road at SamaypurBadli Village, Durga Chowk to Gujjar Chowk at Bhalswa Dairy and Mangal Bazar Road at Jahangirpuri, Delhi |
|
1080.14 |
|
|
Detail Report
Graph / Photo |
||||
123 | Reconstruction of CC Road including raising of Railway Road at SamaypurBadli Village, Durga Chowk to Gujjar Chowk at Bhalswa Dairy and Mangal Bazar Road at Jahangirpuri, Delhi(Second Call) |
|
1080.14 |
|
|
Detail Report
Graph / Photo |
||||
124 | Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi (Balance Work) |
|
1076.89 |
|
|
Detail Report
Graph / Photo |
||||
125 | Strengthening of Josip Broz Tito Marg (BRT Road) from Defence Colony Flyover to Chirag Delhi Flyover under PWD Sub-Division SER-11 of Division SER-1. (Road ID No. 1717). |
|
1069.49 |
|
|
Detail Report
Graph / Photo |
||||
126 | C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. |
09/03/2023
01/02/2024 01/02/2024 |
1058.78 |
|
AMOCON |
After modification NIT was uploaded on 06.02.2023 and M/s Amocon is L-1 and Acceptance letter has been issued to M/s Amocon vide this office letter No. 54(77) Edu. M. (East & North East)/PWD/48 dated: 28.02.2023
After modification NIT was uploaded on 06.02.2023 and M/s Amocon is L-1 and Acceptance letter has been issued to M/s Amocon vide this office letter No. 54(77) Edu. M. (East & North East)/PWD/48 dated: 28.02.2023 |
Detail Report
Graph / Photo |
|||
127 | Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project |
|
1041.75 |
|
|
Detail Report
Graph / Photo |
||||
128 | Operation & Maintenance of EI & Fans, HVAC, DG Sets & Sub Stations, Fire Alarm System, Fire Fighting and Wet Riser System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 |
|
1031.52 126.61 (Jan'23) |
0.00 (Jan'23) |
|
Detail Report
Graph / Photo |
||||
129 |
|
1026.09 0.38 (Aug'20) |
0.00 (Aug'20) |
100%
completed |
Detail Report
Graph / Photo |
|||||
130 | Providing services of various category of Outsourced staff in various office under Flyover Zone, PWD, New Delhi, New Delhi |
|
970.31 |
|
|
Detail Report
Graph / Photo |
||||
131 | Strengthening of road surface of Outer Ring Road from Modi Mill to Chirag Delhi (Masjid Moth). |
27/05/2018
26/07/2018 |
966.91 436.54 (Apr'19) |
73.00 % (Apr'19) |
-
In progress |
Detail Report
Graph / Photo |
||||
132 | Strengthening of Outer Ring Road from Modi Mill to Chirag Delhi Masjid Moth |
|
966.91 |
|
|
Detail Report
Graph / Photo |
||||
133 | Strengthening of various roads of Shalimar Bagh area under PWD Division North West Road-1 and under Sub Division NWR-14 During 2022-23 |
|
960.08 |
|
|
Detail Report
Graph / Photo |
||||
134 | Strengthening of various roads under PWD Division North West Road-1 under Sub Division NWR-12 During 2022-23 |
|
954.00 |
|
|
Detail Report
Graph / Photo |
||||
135 | Strengthening of Nangloi-Najafgarh Road from Nilothi Mor to Airforce Bani Camp under WR-14, PWD New Delhi |
|
953.94 671.44 (Sep'22) |
0.00 (Sep'22) |
|
Detail Report
Graph / Photo |
||||
136 | Strengthening of Ring Road from Prembari Pull to Azadpur Flyover including recarpeting of wearing course of Shalimar Bagh Elevated Road |
|
953.71 |
|
|
Detail Report
Graph / Photo |
||||
137 | Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 |
|
940.18 |
|
|
Detail Report
Graph / Photo |
||||
138 | Construction of 45 Nos. Porta Cabin Aam Admi Mohalla Clinics in schools under Sub Division-I, II, III and IV under South West Building Maintenance Division, New Delhi. (SH- Civil and Electrical Works). |
12/02/2019
11/06/2019 11/06/2019 |
939.06 383.25 (Jul'22) |
0.00 (Jul'22) |
WORK IN PROGRESS
|
Detail Report
Graph / Photo |
||||
139 | Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi |
|
935.00 15.80 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
140 | Construction of FoB/Skywalk from Supreme Court Metro Station to Additional Building Supreme Court and Supreme Court Main Campus on Mathura Road, New Delhi |
|
926.03 |
|
Not pertains to this office
|
Detail Report
Graph / Photo |
||||
141 | Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi.(Balance Work) |
|
919.83 511.88 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
142 | STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT |
|
910.96 287.40 (May'22) |
0.00 (May'22) |
|
Detail Report
Graph / Photo |
||||
143 | Running operation of lifts |
06/05/2021
05/05/2024 05/05/2024 |
909.76 |
60.00 % |
Guruji Elevator |
|
Detail Report
Graph / Photo |
|||
144 | Strengthening of Shyamji Krishan Verma Marg, Sardar Balbir Singh Sindhu Marg, Kabir Dass Marg, Rampura Main Road & Lala Lajpat Rai Marg under PWD Division North West Road-1 and under Sub Division NWR-11 During 2022-23 |
|
899.50 |
|
|
Detail Report
Graph / Photo |
||||
145 | Strengthening of various roads under sub division NWR-24, Division NWR-2, SainikVihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW |
|
880.22 652.65 (Oct'22) |
0.00 (Oct'22) |
|
Detail Report
Graph / Photo |
||||
146 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc. of Lal Bahadur Shastri Hospital Campus Khichripur, Delhi, Jag Pravesh Chandra Hospital, Campus Shastri Park Delhi and Chacha Nehru Bal Chikitsalya, Hospital, Campus, Geeta Colony, DGD-12/113, Geeta Colony, DGD, New Lahore, Shastri Nagar, Delhi during 2022-23 and 2023-24 |
14/05/2022
13/05/2024 13/05/2024 |
874.44 |
|
Work is in progress.
nil |
Detail Report
Graph / Photo |
||||
147 | Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi. (Civil and Electrical Work) |
|
871.75 |
|
|
Detail Report
Graph / Photo |
||||
148 | Strengthening of road at Dev Parkash Shastri Marg under PWD Sub Division-III, S.W.R-I, New Delhi |
|
871.07 |
|
|
Detail Report
Graph / Photo |
||||
149 | Operation and Maintenance of EI and FANS Sub Station and DG Set HVAC Works Fire Fighting and Wet Riser System Fire Alarm System Lifts RO Plant etc |
|
866.40 |
|
|
Detail Report
Graph / Photo |
||||
150 | Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) |
17/09/2022
15/12/2022 15/12/2022 |
861.04 200.00 (Feb'23) |
0.00 (Feb'23) |
SBG Infracon Pvt Ltd |
|
Detail Report
Graph / Photo |
|||
151 | Replacement of Bearings and Expansion joint and repair of Bearing Pedestal |
|
859.23 |
|
1
|
Detail Report
Graph / Photo |
||||
152 | Replacement of Bearings and Expansion joint and repair of Bearing Pedestal |
|
859.23 |
|
.
|
Detail Report
Graph / Photo |
||||
153 | Construction of Pedestrian Underpass Subway Across Aurobindo Marg Between Delhi Haat and Entry No 4 of East Kidwai Nagar. |
27/10/2020
26/08/2021 30/11/2022 |
856.26 100.22 (Nov'22) |
0.00 (Nov'22) |
M/s Satish Builders |
Civil work completed and some electric works is remained which will be completed soon
|
Detail Report
Graph / Photo |
|||
154 | Construction of 66 feet Libaspur Gurudwara Road including providing street light fittings (SH- Civil and Electrical Work) |
|
849.98 |
|
|
Detail Report
Graph / Photo |
||||
155 | Operation & Maintenance of EI & FANS, Sub Station & DG Set, HVAC Works , Firen Fighting and Wet Riser System, Fire Alarm System, Lifts, RO Plant etc. |
|
843.88 |
|
|
Detail Report
Graph / Photo |
||||
156 | Upgradation of staff rooms in 120 Schools under South West Building Maintenance Division, NCC Building, safdarjung Enclave, New Delhi.(SH- Civil, Electrical and furniture works). |
11/02/2019
10/06/2019 10/06/2019 |
833.12 540.13 (Jul'22) |
0.00 (Jul'22) |
WORK IN PROGRESS
|
Detail Report
Graph / Photo |
||||
157 | Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc |
|
831.74 |
|
|
Detail Report
Graph / Photo |
||||
158 | Construction of 55 Nos. Aam Admi Mohalla Clinic at various locations under South-East (M), Circle, New Delhi during 2018-19. |
15/12/2018
12/06/2019 12/06/2019 |
827.90 430.96 (Jan'23) |
0.00 (Jan'23) |
S. P. Construction |
Work in progress
|
Detail Report
Graph / Photo |
|||
159 | Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). |
30/09/2022
29/03/2023 29/03/2023 |
818.33 50.00 (Feb'23) |
99.00 % 0.00 (Feb'23) |
SATYA PARKASH AND BROS PVT LTD |
|
Detail Report
Graph / Photo |
|||
160 | Strengthening of various roads of Pitampura area under PWD Division North West Road-1 and under Sub Division NWR-14 During 2022-23 |
|
802.14 |
|
|
Detail Report
Graph / Photo |
||||
161 | Strengthening of Ring Road, Haytt Regency to Moti Bagh (Road ID No. 3), Kama Koti Marg (Road ID No. 343), Premnath Dogra Marg (Road ID No. 342) and Restoration of Road from Ch. Jhandhu Singh Marg to Africa Avenue Crossing cut by RailTel Under PWD Sub Division 2 of Division SWR I, New Delhi |
|
793.03 |
|
|
Detail Report
Graph / Photo |
||||
162 | Strengthening of Road No. 235, Guru Virjanand Marg, Road between Jupiter Appt. to Priya Appt., Nalanda Appt. to Nightingale Appt., Navyug Appt. to IFC drain (Brotherhood Appt.), Road between Devdoot Appt. to Parmarth Appt., Road between Kirti Appt. to DAV school, Road between Lok Vihar Appt. (PWD Road) to F-block Market, Road Sunrise Appt. to DAV School, Road from F-234 to IFC drain (Over head tank) Vikaspuri, Road from ITICorner to Central School, Road starting from Oxford School to Airport Appt. and Road No. 236 at Vikaspuri under sub division WR-14, Division WR-1 |
|
790.08 560.02 (Aug'22) |
0.00 (Aug'22) |
|
Detail Report
Graph / Photo |
||||
163 | Addition Alternation in Residence of Honble Chief Minister at 6 Flag Road, Civil Lines, Delhi during 2020 21 (SH:Providing additional Accommodation Civil and Electrical works) |
|
761.07 2807.78 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
164 | Operation & Maintenance of E.I, pumps, sub-station, DG Sets, firefighting & fire alarm system, HVAC & AC units & R.O. Plant etc |
24/05/2022
23/05/2024 23/05/2024 |
754.12 15.00 (Feb'23) |
42.00 % 0.00 (Feb'23) |
SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. |
|
Detail Report
Graph / Photo |
|||
165 | Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi |
14/07/2022
13/10/2022 13/10/2022 |
751.50 |
|
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
166 | Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054 |
|
747.65 |
|
|
Detail Report
Graph / Photo |
||||
167 | Providing furniture in various schools for additional SPS class rooms under Zone West Delhi Education Zone 16 17 and other schools Priority-I |
|
744.08 |
|
GEEKEN SEATING COLLECTION PVT LTD |
work in progress
|
Detail Report
Graph / Photo |
|||
168 | Comprehensive Maintenance of Civil works relating Day to day Maintenance, Annual Repair, Special Repair and routine maintenance work etc. of Deep Chand Bandhu Hospital, Ashok Vihar, Phase-IV, Delhi, Babu Jagjivan Ram Hospital, Jahangirpuri, Delhi, Attar Sain Jain Eye Hospital, various dispensaries at Jahangirpuri, Delhi and Bhagwan Mahavir Hospital, Pitampura, Delhi during 2022-23 and 2023-24 |
06/06/2022
05/06/2024 05/06/2024 |
741.51 |
38.00 % |
Dilshad Khan |
Work in Progress (35% Progress)
|
Detail Report
Graph / Photo |
|||
169 | Strengthening of road of Bawana to Auchandi Border under Sub-Division NR-15, PWD Division North Roads, Delhi |
28/04/2022
24/10/2022 24/10/2022 |
718.31 762.78 (Dec'22) |
0.00 (Dec'22) |
SBG Infracon Pvt Ltd |
|
Detail Report
Graph / Photo |
|||
170 | Strengthening of Outer Ring Road from Wazirabad Flyover to Gandhi Vihar Subway under Sub Division-1, Division C&ND-Road, PWD, New Delhi. |
24/06/2022
23/08/2022 23/08/2022 |
717.68 727.82 (Feb'23) |
0.00 (Feb'23) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
171 | (A) Strengthening of Major Somnath Marg (Road ID -338) from Rao Tula Ram Marg to Outer Ring Road Under PWD Division South West Road-I, Under Sub Division-I, New Delhi. (B) Strengthening of Babu Genu Marg (Road ID -341) from RTR Marg to Major Somnath Marg Red Light Under PWD Division South West Road-I, Under Sub Division-I, New Delhi. (C) Road restoration cut by DRDO and various agencies at Moti Bagh Ring Road Crossing to Sangam Cinema on Major Somnath Marg and Outer Ring Road (Subroto Park) Under PWD Division South West Road-I Under Sub Division-I, New Delhi. |
|
704.50 |
|
|
Detail Report
Graph / Photo |
||||
172 | Laying of RCC Drain/pipe and raising of levels of existing carriage way of Ring Road in between toe of IP Flyover and opposite of WHO Building including laying of 1200mm dia. Pipe through trenchless pushing to solve water logging problem, New Delhi. |
28/04/2022
11/07/2022 11/07/2022 |
694.86 665.13 (Feb'23) |
0.00 (Feb'23) |
A S INFRATECH |
|
Detail Report
Graph / Photo |
|||
173 | Strengthening of Outer Ring Road from Gandhi Vihar to Burari Flyover under Sub Division-1, Division C&ND-Road New Delhi. |
24/06/2022
23/08/2022 23/08/2022 |
690.38 877.25 (Mar'23) |
0.00 (Mar'23) |
SBG Infracon Pvt Ltd |
|
Detail Report
Graph / Photo |
|||
174 | Civil work Desilting of drains and other Misc repair work of footpaths Central verge Services Roads etc on various roads except Ring Road under Sub Division NW R 14 |
|
684.86 |
|
|
Detail Report
Graph / Photo |
||||
175 | Re laying of World Athletics approved 400 Mtr. synthetic athletic track at Chhatrasal Stadium, Delhi |
26/03/2022
24/07/2022 24/07/2022 |
679.06 340.61 (Mar'23) |
0.00 (Mar'23) |
ADVANCED SPORT TECHNOLOGIES LLP |
Work in progress
Work in progress |
Detail Report
Graph / Photo |
|||
176 | Construction of Old Age Home including electrical work at BG-6, Paschim Vihar, Delhi. (Composite work). |
|
668.69 |
|
Work is held up for Architectural Plan & revised plan submitted to fire department for approval by SA |
Detail Report
Graph / Photo |
||||
177 | Remodeling of drain from 25 futa road, Meet nagar to Loni Gole Chakkar at Road No.-63, Construction of sump well at loni Gole Chakkar & MIG/ LIG Flat, Providing and laying K-9 pipe from Loni gole Chakkar to Drain No-01 & Construction of pump House, Electrical & mechanical Services at Loni Gole Chakkar & MIG/ LIG Flat. |
31/03/2022
28/07/2022 28/07/2022 |
657.45 120.00 (Feb'23) |
0.00 (Feb'23) |
K. L. ARORA & SON |
|
Detail Report
Graph / Photo |
|||
178 | Providing Automated Housekeeping at Honble CM Residence and Bungalow of Delhi Council of Ministers Delhi |
|
649.40 506.58 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
179 | Balance Work. |
|
645.72 |
|
..
|
Detail Report
Graph / Photo |
||||
180 | Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi |
28/04/2022
24/10/2022 24/10/2022 |
643.92 241.89 (Nov'22) |
0.00 (Nov'22) |
Kundu Nirma |
|
Detail Report
Graph / Photo |
|||
181 | Construction installation and commissioning and there after Operation and Maintenance for Five Years of Bio remediation waste water treatment plant using Inert Solid Removal ISR technology of capacity 2.5 MLD and construction of under Ground |
|
643.55 118.47 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
182 | Construction of 30 Nos. Porta Cabin Aam Admi Mohalla Clinics under Sub division- I,II,III and IV under South West Building Maintenance Division New Delhi. (SH Civil works and Electrical works). |
06/12/2018
02/08/2019 02/08/2019 |
642.82 308.01 (May'22) |
0.00 (May'22) |
WORK IN PROGRESS
|
Detail Report
Graph / Photo |
||||
183 | BITUMINOUS WORK, LENGTH 2.15 KM. |
|
642.71 |
|
work completed
|
Detail Report
Graph / Photo |
||||
184 | Strengthening of roads from Nangli Poona to Mohan Adda, Khera Kalan Road, Safiabad Mor to Safiabad Border, Holambi Kalan Crossing to Bawana Narela Road via Metro Vihar, under Sub-Division NR-13 of North Road Division, PWD, Delhi |
20/03/2022
17/07/2022 17/07/2022 |
640.59 574.70 (Oct'22) |
0.00 (Oct'22) |
SATYA PARKASH AND BROS PVT LTD |
|
Detail Report
Graph / Photo |
|||
185 | Resurfacing of roads from (i) Lampur Mor to Lampur Border, (ii) Ramdev Chowk to Railway crossing Narela, (iii) Y-section Narela to Shahpur Garhi Turn, under Sub-Division NR-13, North Roads Division, PWD, Delhi |
20/03/2022
17/07/2022 17/07/2022 |
617.72 171.52 (Aug'22) |
0.00 (Aug'22) |
Sethi Construction |
|
Detail Report
Graph / Photo |
|||
186 | Civil and Electrical Work. |
05/03/2023
29/11/2023 29/11/2023 |
617.03 |
|
CHANDRA CONSTRUCTION COMPANY |
|
Detail Report
Graph / Photo |
|||
187 |
|
616.71 5.76 (Nov'19) |
0.00 (Nov'19) |
|
Detail Report
Graph / Photo |
|||||
188 | Strengthening of Apeejay School Road Sheikh Sarai Phase-1 Road no.1 and Road no.-2 Khirki Road Birla Vidya Niketan Marg Mandir Marg Main Road Sector-1 Pushp Vihar Pankaj Juyal Marg H-Block Road and NBCC Plaza Road under sub division SR-14. |
15/11/2019
14/05/2020 14/05/2020 |
615.93 909.27 (Jan'23) |
0.00 (Jan'23) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
189 | Strengthening of Road No. 56 i.c Service Road from Gazipur Grade Separator to Apsara Border and its subsequent maintenance for three years. |
27/11/2021
26/03/2022 26/03/2022 |
615.26 670.71 (Feb'23) |
0.00 (Feb'23) |
Pawan Kumar |
|
Detail Report
Graph / Photo |
|||
190 | Co Missing drain and Footpath from Jharoda Stand to Mungeshpur Drain and Drains upto Bahadurgarh Border with Footpath at Border area under PWD Division SWR II New Delhi ID 1231 |
|
612.10 |
|
WORK COMPLETED 19/08/2019
WORK COMPLETED 19/08/2019 |
Detail Report
Graph / Photo |
||||
191 | Upgradation/Renovation of one staff room in each 951 schools, Civil and Electrical work (SH- Staff rooms 75 no. under south Building Maintenance Division). |
14/03/2019
13/09/2019 29/02/2020 |
610.61 221.28 (Mar'21) |
0.00 (Mar'21) |
S.M. Builders |
work in progress
work in progreess |
Detail Report
Graph / Photo |
|||
192 | Construction of 30 Nos. additional SPS hostel rooms and 2 Nos. staircase i/c internal and external water supply i/c sanitary installation, development of site and fire fighting system and provision of EI and Fans and other misc works at KISS Issapur. |
13/02/2019
11/08/2019 11/08/2019 |
598.97 464.10 (Jan'23) |
0.00 (Jan'23) |
WORK IN PROGRESS
|
Detail Report
Graph / Photo |
||||
193 | Upgradation of one staff room, each at 951 School under Delhi Govt. SH 123 Nos. of staff rooms under West Maintenance Circle. |
|
593.40 156.62 (Oct'22) |
0.00 (Oct'22) |
|
Detail Report
Graph / Photo |
||||
194 | Strengthening of various roads of Sector-11 & Rama Road under sub division NWR-22, Rohini, Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23 |
|
587.47 |
|
|
Detail Report
Graph / Photo |
||||
195 | Construction of 30 Nos. Aam Admi Mohalla Clinic at various places under south building (M) Division/South District. |
10/01/2019
08/07/2019 30/09/2019 |
585.53 123.30 (Dec'22) |
0.00 (Dec'22) |
P S ASSOCIATES |
work in progress
work in progreess |
Detail Report
Graph / Photo |
|||
196 | Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB |
25/09/2022
24/01/2023 24/01/2023 |
583.83 |
|
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
197 | Providing stone Matrix Asphalt(SMA) under Sub Division-II, South West Road-II Najafgarh, New Delhi |
23/11/2021
21/01/2022 21/01/2022 |
581.89 224.77 (Oct'22) |
0.00 (Oct'22) |
Pawan Kumar |
|
Detail Report
Graph / Photo |
|||
198 | Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work |
28/01/2022
27/12/2022 27/12/2022 |
579.95 261.54 (Nov'22) |
0.00 (Nov'22) |
R.K ENTERPRISES |
Work is in progress 3%
|
Detail Report
Graph / Photo |
|||
199 | Strengthening of various roads such as prof. Joginder Singh Marg Major Deepak Tyagi Marg Lal Sai Marg 60 Futa Road Possangi Pur Road A 1 Block Main Road Opp A 1 Block Main Road and Asalat Pur Road 1 under Sub Division WR 12 Division WR-1 PWD New Delh |
25/09/2022
24/01/2023 24/01/2023 |
578.76 |
|
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
200 | Strengthening of Najafgarh Jharoda Road ic raising of depressed road at Ekta Vihar under Sub Division II South West Road II PWD New Delhi. ID 1231 |
16/10/2019
12/02/2020 12/02/2020 |
567.80 236.37 (Jul'20) |
0.00 (Jul'20) |
Pawan Kumar |
WORK IN PROGRESS
WORK IN PROGRESS |
Detail Report
Graph / Photo |
|||
201 | Construction of Inter-connecting RCC box type storm water drain between JhaitkaraMorh via Chhawla Village to IandFC Najafgarh drain, NajafgarhBijwasan Road (ID 1173) under PWD Division SWR-II, New Delhi. |
17/03/2023
12/09/2023 12/09/2023 |
564.26 |
|
Rajan Builders |
|
Detail Report
Graph / Photo |
|||
202 | Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 |
|
559.69 |
|
|
Detail Report
Graph / Photo |
||||
203 | Strengthening / Resurfacing of (1) Road No. 70, (2) Road 62, (3) Road from Seemapuri Bus depot Road no. 70 to GTB Hospital Road (Gurudwara road), (4) Road from Labour chowk (Seemapuri link road) to General Hospital Road no. 64 (Divider Road), (5) Road from Rajiv Gandhi Super Specialty Hospital to GTB Hospital Road. |
26/01/2023
25/05/2023 25/05/2023 |
554.25 |
48.00 % |
Kundu Nirman |
|
Detail Report
Graph / Photo |
|||
204 | Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW |
27/02/2022
26/06/2022 26/06/2022 |
548.07 550.78 (Feb'23) |
0.00 (Feb'23) |
RK Brothers |
|
Detail Report
Graph / Photo |
|||
205 | Construction of Crash Barrier Expansion Joints and replacement of Bearings |
|
545.00 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
206 | Construction of Crash Barrier Expansion Joints and replacement of Bearings |
|
545.00 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
207 | Construction of Back to back U-turn near Aali Village Red-light and Single U-Turn for Sarita Vihar Colony to facilitate signal free and congestion free movement of traffic on Mathura Road under SER-2/22.(Road ID-961) |
|
542.85 0.15 (Jun'22) |
0.00 (Jun'22) |
|
Detail Report
Graph / Photo |
||||
208 | Providing services of Maintenance vehicle with labour & T&P etc. for all Sub-Division for two year |
|
542.39 |
|
|
Detail Report
Graph / Photo |
||||
209 | Improvement and strengthening of Road No. 63, Delhi (From Bhopura Border to Loni Gol Chakkar except flyover). |
14/12/2019
12/03/2020 |
541.95 |
|
M/s Roadtech |
|
Detail Report
Graph / Photo |
|||
210 | Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. |
02/11/2018
01/11/2019 01/11/2019 |
539.98 214.77 (Sep'19) |
0.00 (Sep'19) |
Work in progress
No |
Detail Report
Graph / Photo |
||||
211 | Civil work Mechanized Desilting of drains and other Misc repair work of footpaths Central verge Services Roads etc on others roads than outer ring road under Sub Division NW R 13 |
|
538.80 |
|
|
Detail Report
Graph / Photo |
||||
212 | Civil work comprehensive maintenance of Shanker Road and Vandematram Marg including carriageway, footpaths, central verge, Service road etc within the right... |
|
535.97 |
|
|
Detail Report
Graph / Photo |
||||
213 | Strengthening of Arterial Roads having right of way more than 30.00 metre like Satyagrah Marg, IG Slip Road, Velodrome Road, Sachivalya Road, Club Road & Flag Staff Road under Sub Division – 3 of Division C & ND – Roads, New Delhi |
31/03/2022
30/06/2022 30/06/2022 |
535.88 469.00 (Jun'22) |
0.00 (Jun'22) |
A S INFRATECH |
|
Detail Report
Graph / Photo |
|||
214 | Renovation / construction works at Rajiv Gandhi Stadium, Bawana |
07/07/2022
04/11/2022 04/11/2022 |
535.01 |
|
M/s Vinod Kumar & Company |
Work in progress
Work in progress |
Detail Report
Graph / Photo |
|||
215 | Providing services of Maintenance vehicle with labour and T and P etc for Division NW R 1 for two year |
|
533.23 |
|
|
Detail Report
Graph / Photo |
||||
216 | CIVIL Works - Comprehensive maintenance of various roads i/c carriageway, footpaths, central verge within right of way, mechanised desilting of drains etc and other mi |
|
533.12 |
|
|
Detail Report
Graph / Photo |
||||
217 | Resurfacing of roads from (i) Shahpur Garhi Turn to Old GTK road Alipur, (ii) Shubhash Chowk to Palla Village via Bakhtawarpur, (iii) Holambi Khurd Crossing to Shahpur Garhi turn, (iv) New GTK Road to Old GTK Road (via Shani Mandir), (v) New GTK Road to Old GTK Road (via PHC Alipur) under Sub-Division NR13, PWD North Roads Division, Delhi. |
20/03/2022
17/07/2022 17/07/2022 |
526.50 528.46 (Aug'22) |
0.00 (Aug'22) |
SATYA PARKASH AND BROS PVT LTD |
|
Detail Report
Graph / Photo |
|||
218 | Strengthening of Swaroop Nagar Road with Construction of footpath on existing drain and improvement of road side berm from Main Burari Road to Kathia Baba Ashram under Sub Division-1, C&ND-Road Division Delh |
28/04/2022
27/06/2022 27/06/2022 |
523.21 676.87 (Feb'23) |
0.00 (Feb'23) |
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
219 | Strengthening of Asiad Games Village Road (ID 1137), NIFT Road (ID-1139), Subhash Chopra Road (ID-1138) and August Kranti Marg (ID-16) through cold milling and recycling process under Sub-Division-1 of Division South Road-2 PWD, New Delhi |
06/10/2022
05/01/2023 05/01/2023 |
516.92 |
|
MAHAVIR PRASAD GUPTA AND SONS |
Work in Progress
Work in Progress |
Detail Report
Graph / Photo |
|||
220 | Strengthening of various roads of Sector-3,5,6 & 7 under sub division NWR22, Rohini, Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23 |
|
513.31 |
|
|
Detail Report
Graph / Photo |
||||
221 | Strengthening of Mandi Road (ID- 548) and Aya Nagar Road (ID- 1191) of Division SR-1 under Sub-Division SR-13 at New Delhi |
|
493.83 168.54 (Dec'22) |
0.00 (Dec'22) |
|
Detail Report
Graph / Photo |
||||
222 | Construction of Two No. Foot Over Bridge across Sri Aurobindo Marg (ID-96) at (i) PTS Bus Stop (ii) T.B. Hospital with staircase and lift including Electrical Installations under Sub Division-II of Division South Road-II, PWD New Delhi. |
21/03/2020
20/09/2020 20/09/2020 |
489.85 255.38 (Nov'22) |
0.00 (Nov'22) |
S S Chauhan & Sons |
Work in Progress.
Work in Progress. |
Detail Report
Graph / Photo |
|||
223 | Construction of Two No Foot Over Bridge across (i)Sri Aurobindo Marg (ID-96) at Adhchini Village (ii) Hauz Khas Enclave (Near Padmini Enclave) with staircase and lift including Electrical Installation under Sub Division-II of Division South Road-II |
21/03/2020
20/09/2020 20/09/2020 |
489.30 335.56 (Nov'22) |
0.00 (Nov'22) |
S S Chauhan & Sons |
Work in Progress.
Work in Progress. |
Detail Report
Graph / Photo |
|||
224 | Running and Maintenance of lifts installed in residential and non-residential buildings at GTB Hospital complex, Shahdara, Delhi Sub Head Running operation of lifts |
17/01/2019
16/01/2021 16/01/2021 |
485.43 |
|
Guruji Elevator |
Work in progress 3RD RA 40220380
|
Detail Report
Graph / Photo |
|||
225 | Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 |
06/08/2022
03/12/2022 03/12/2022 |
484.07 91.18 (Feb'23) |
0.00 (Feb'23) |
AVNG INFRASTRUCTURES PRIVATE LIMITED |
|
Detail Report
Graph / Photo |
|||
226 | Nazafgarh Road to A-71, Rajauri Garden, A-31 Rajauri Garden, 20-Block Tilak Vihar Road, Radhaswami Satsang Marg and Tilak Nagar Main Market Road under PWD Division WR-1, New Delhi. |
|
481.51 |
|
|
Detail Report
Graph / Photo |
||||
227 |
|
477.75 |
|
|
Detail Report
Graph / Photo |
|||||
228 | Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 |
30/09/2014
26/05/2015 31/01/2016 |
474.90 61.36 (May'19) |
0.00 (May'19) |
Work completed on 31/12/2017 final payment yet to be made
EOT, Deviation under process of sanction by the competent authority now the sanction has been received and final payment yet to be made |
Detail Report
Graph / Photo |
||||
229 | EOR and face-lifting to Existing building of RPVV (Rajakiya Pratibha Vikas Vidyalaya) for Establishment of New DIET at Thyagraj Nagar, New Delhi during 2021-22 (Civil and Electrical works) |
|
469.68 172.68 (Sep'22) |
0.00 (Sep'22) |
|
Detail Report
Graph / Photo |
||||
230 | Construction of Foot Over Bridge with staircase and lift for padestrian at Rao Tula Ram Marg (Road ID-98) near Petrol Pump, New Delhi. |
|
465.11 |
|
|
Detail Report
Graph / Photo |
||||
231 | Repair and Rehabilitation of facade and other RCC members ic water tank and water proofing of terrace of Vyaapar Bhawan Deptt of Trade and Taxes Building IP Estate New Delhi |
|
463.67 |
|
|
Detail Report
Graph / Photo |
||||
232 | Remodeling of Drain with Development of Kuccha Portion along the ESI Hospital Road and Road along B-Block Jhilmil under Sub Division M-2112 during 2021-22 |
02/04/2022
28/09/2022 28/09/2022 |
462.00 283.40 (Feb'23) |
0.00 (Feb'23) |
PRATAP SINGH |
|
Detail Report
Graph / Photo |
|||
233 | Providing and installation of informatory directional sign boards on various roads under Division NWR1 and NWR2 for DSEU Campus Ashok Vihar DSEU Campus Pitampura DSEU Campus Rohini DSEU |
|
460.45 |
|
|
Detail Report
Graph / Photo |
||||
234 | Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone |
|
460.45 |
|
|
Detail Report
Graph / Photo |
||||
235 | Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone |
|
460.45 |
|
|
Detail Report
Graph / Photo |
||||
236 | Civil Work Mechanized Desilting of drains and other Misc repair work of footpaths central verge Services Roads etc roads under Sub Division NWR 11 RECALL |
|
460.24 |
|
|
Detail Report
Graph / Photo |
||||
237 | Civil Work Mechanized Desilting of drains and other Misc repair work of footpaths central verge Services Roads etc roads under Sub Division NWR 11 |
|
460.24 |
|
|
Detail Report
Graph / Photo |
||||
238 | Comprehensive repair and maintenance of various roads under sub division M- 2132. |
21/11/2019
20/11/2020 |
460.10 504.82 (Sep'22) |
0.00 (Sep'22) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
239 | Widening and Strengthening of Bandh Road of Division SR-1 under Sub-Division SR-13 at New Delhi i/c shifting and installation of Electrical Poles Street lights etc. |
01/12/2019
31/05/2020 |
459.03 354.65 (Jul'22) |
0.00 (Jul'22) |
Bansal Associates |
|
Detail Report
Graph / Photo |
|||
240 | Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc. |
04/06/2022
03/06/2024 03/06/2024 |
457.53 |
38.00 % |
M/s Jain Electric Works |
|
Detail Report
Graph / Photo |
|||
241 | Rehabilitation and strengthening of Janak Setu Flyover in New Delhi (Balance Work) |
29/03/2020
29/09/2020 31/03/2021 |
457.44 23.39 (Sep'21) |
0.00 (Sep'21) |
Work in progress null |
Detail Report
Graph / Photo |
||||
242 | A/R & M/O Various roads under East Road Sub Division-III, Division East Road (M 212) during 2019-20. (SH:- Comprehensive maintenance of road) |
15/10/2019
14/10/2020 |
455.11 418.02 (May'22) |
0.00 (May'22) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
243 | A/R and M/O Roads under PWD North-Roads, PWD dg. 2018-19 (SH -Providing services of Computer Operators, MTS, LMV Drivers, Clerical Staff, maintenance staff, chowkidars etc. in the office of North Maintenance Circle, PWD ..... |
|
448.46 |
|
|
Detail Report
Graph / Photo |
||||
244 | Civil Works - Mechanised Sweeping and Cleaning of Roads including Carriageway, Footpaths, Central Verge, Service Roads etc. within the right of way, Mechanised Desilting |
|
448.15 |
|
|
Detail Report
Graph / Photo |
||||
245 | Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24 |
|
445.82 34.74 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
246 | Providing services of Computer Operators MTS and Drivers etc |
06/05/2022
05/05/2023 05/05/2023 |
441.58 359.16 (Mar'23) |
82.00 % 0.00 (Mar'23) |
M/s R D Excellent Services Pvt. Ltd. |
work in progress
|
Detail Report
Graph / Photo |
|||
247 | Comprehensive Maintenance of Civil works including day to day maintenance, Annual Repair works of A&U Tibbia College, Dr. N.C. Joshi Hospital, Aruna Asaf Ali Govt. Hospital, Sushruta Trauma Centre, Subzi Mandi, Mortuary & 34 Nos. Delhi Givt. Dispensaries/ Polyclinic under HMD (Central) New Delhi (Revised) |
|
438.63 24.34 (Mar'23) |
0.00 (Mar'23) |
work completed work completed |
Detail Report
Graph / Photo |
||||
248 | Strengthening of Arterial Road (Bahadur Shah Zafar Marg) having right of way more than 60.00 metre under Sub Division - 3 of Division C and ND - Roads, New Delhi |
|
437.49 |
|
|
Detail Report
Graph / Photo |
||||
249 | Balance Renovation and Misc. works of Main Academic, Administrative and Printing Blocks i/c Class Rooms &Laboratories, C/o Security Guards rooms and Toilet Water Proofing Treatment of existing building roofs of PIT, DSEU Campus, Pusa, New Delhi. |
|
436.21 |
|
|
Detail Report
Graph / Photo |
||||
250 | Widening and strengthening of Bandh Road of Division SR-1 under Sub-Division SR-13 at New Delhi ic shifting and installation of Electrical Poles, Street lights etc. (Balance Work) |
|
435.13 78.52 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
251 | Construction of precast drain and Improvement of side berm including footpath from Amrit Vihar to Nathupura road on Main Burari Road |
28/04/2022
12/07/2022 12/07/2022 |
434.22 561.37 (Feb'23) |
0.00 (Feb'23) |
Amit Buildcon |
|
Detail Report
Graph / Photo |
|||
252 | Comprehensive repair and maintenance of various roads under sub division M- 2134. |
21/11/2019
20/11/2020 |
433.62 599.23 (Sep'22) |
0.00 (Sep'22) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
253 | Improvement and strengthening of Road No. 59, Delhi (From Khajuri Gole Chakkar to outer Ring Road Except Wazirabad Yamuna Bridge). |
13/01/2020
05/04/2020 |
432.05 281.82 (Nov'20) |
0.00 (Nov'20) |
M/s Roadtech |
|
Detail Report
Graph / Photo |
|||
254 | Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road II PWD New Delhi |
|
429.94 |
|
WORK IN PROGRESS
WORK IN PROGRESS |
Detail Report
Graph / Photo |
||||
255 | Comprehensive maintenance of various roads under Sub-Division South East Road-13 |
|
425.32 14.60 (Jun'20) |
0.00 (Jun'20) |
|
Detail Report
Graph / Photo |
||||
256 | Providing and operating truck mounted, compact and mobile road repair machines for repair and maintenance of pot holes, small patches and other |
|
421.96 |
|
|
Detail Report
Graph / Photo |
||||
257 | Construction of Boundary Wall on Vacant land at Dwarka sector 12 & 13 at New Delhi |
03/09/2022
02/01/2023 06/04/2023 |
421.69 137.23 (Mar'23) |
0.00 (Mar'23) |
PCC work, footing casting, column casting &casting of plinth beam is in progress. Brick work above plinth is in progress.
|
Detail Report
Graph / Photo |
||||
258 | Civil and Electrical work |
|
420.91 |
|
|
Detail Report
Graph / Photo |
||||
259 | Remodeling of Maujpur drain from Road No. 66 to Ghonda Chowk and Main Brahmpuri Road drain from Ghonda Chowk to MCD Dhalav. |
28/10/2018
27/04/2019 31/07/2019 |
419.30 364.66 (Feb'23) |
0.00 (Feb'23) |
Gee International |
work in progress
|
Detail Report
Graph / Photo |
|||
260 | Op. of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I |
|
417.30 |
|
|
Detail Report
Graph / Photo |
||||
261 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of Maharishi Valmiki Hospital Campus and DGD Dispensaries at Pooth Khurd Delhi, SRHC Hospital Complex and DGD Dispensaries at Narela Delhi during 2022-23 and 2023-24 |
15/05/2022
14/05/2024 14/05/2024 |
416.87 |
42.00 % |
Mahavir Parsad Gupta & Sons |
Work in Progress (50% progress)
|
Detail Report
Graph / Photo |
|||
262 | Construction of RCC drain in Narela Alipur road along the DDA land from Bhorgarh to Shahpur Garhi turn under Sub Division NR-13, North Roads Division,PWD, Delhi |
07/01/2022
05/07/2022 05/07/2022 |
412.34 111.83 (Jun'22) |
0.00 (Jun'22) |
R K Enterprises |
|
Detail Report
Graph / Photo |
|||
263 | Replacement of bearings and expansion joints of Karampura Flyover and rehabilitation of RCC jacketing of two piers of Mukundpur Flyover. |
|
406.38 |
|
tender under process null |
Detail Report
Graph / Photo |
||||
264 | Replacement of bearings and expansion joints of Karampura Flyover and rehabilitation of RCC jacketing of two piers of Mukundpur Flyover. |
|
406.38 |
|
tender under process
|
Detail Report
Graph / Photo |
||||
265 | Construction of New SPS workshop cum classroom G+1 at Sir C.V. Raman ITI Dheerpur Delhi. (Civil & Electrical Works) |
|
404.63 |
|
|
Detail Report
Graph / Photo |
||||
266 | Thermoplastic painting on various roads under Division M-413, New Delhi dg. 2013-14. |
29/10/2013
28/02/2014 |
404.14 |
|
K.L. Arora & Son |
|
Detail Report
Graph / Photo |
|||
267 | Strengthening of Narwana Road from Mother Dairy T-Point to Panch Mahal Awas during 2017-18 |
19/04/2018
17/07/2018 |
402.83 79.00 (Jun'19) |
0.00 (Jun'19) |
A S INFRATECH |
Work in Progress
|
Detail Report
Graph / Photo |
|||
268 | AR MO to Various Residential Buildings Type III IV V and VI under Sub Division M 3231 at 16 Rajpur Road Delhi dg 2022 23 |
|
401.13 |
|
|
Detail Report
Graph / Photo |
||||
269 | Civil and Electrical works |
|
398.73 |
|
|
Detail Report
Graph / Photo |
||||
270 | General Day to Day Civil Maintenance Work |
|
392.66 130.07 (Nov'20) |
0.00 (Nov'20) |
|
Detail Report
Graph / Photo |
||||
271 | Rehabilitation and strengthening of Okhla flyover on Mathura Road, New Delhi |
|
392.44 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
272 | Construction of Boundary wall at Plot No. FA 6 for District office and bataliyan, Women training college, Police line and Advanced research and Training Institute of Delhi Police Officers Narela, Delhi 110040 |
20/01/2022
20/05/2022 20/05/2022 |
391.04 |
|
Work in Progress
Work in Progress |
Detail Report
Graph / Photo |
||||
273 | Strengthening of Prithvi Singh Dagar Marg ID 1175 from RawtaMorh Dhansa Road to Daurala Border under PWD Division- South West Road-II New Delhi. |
16/10/2019
12/02/2020 |
388.15 0.84 (Apr'22) |
0.00 (Apr'22) |
Pawan Kumar |
UNDER TENDERING PROCESS
UNDER TENDERING PROCESS |
Detail Report
Graph / Photo |
|||
274 | Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain |
25/09/2022
24/12/2022 24/12/2022 |
386.35 |
|
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
275 | Improvement of Khari Bawali and HC Sen Marg |
27/09/2013
26/05/2015 |
382.36 |
|
Satya Parkash & Bros. Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
276 | C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) |
02/03/2022
26/11/2022 31/03/2023 |
382.04 |
|
M/s. Satyam Construction |
work is in progress
work is in progress |
Detail Report
Graph / Photo |
|||
277 | Rehabilitation and strengthening of Okhla flyover on Mathura Road, New Delhi |
|
381.57 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
278 | Repair and Rehabilitation of Vehicular Under Pass (VUP) and its approaches and Approaches of three RoBs at PulMithai on SPM Marg, Delhi |
16/01/2020
15/10/2020 31/03/2021 |
379.24 40.81 (Apr'21) |
0.00 (Apr'21) |
Work in progress null |
Detail Report
Graph / Photo |
||||
279 | Civil works, Furniture works & Electrical works |
|
377.11 |
|
|
Detail Report
Graph / Photo |
||||
280 | Comprehensive repair of road footpath, drain, painting, Speed breakers, Patch repairs and other misc. repair works in SectionI & Section-II for 1 year |
|
376.63 |
|
|
Detail Report
Graph / Photo |
||||
281 | Comprehensive repair of road footpath, drain, painting, Speed breakers, patch repairs and other misc. repair works in SectionI & Section-II for 1 year |
|
376.63 |
|
|
Detail Report
Graph / Photo |
||||
282 | Operation & Maintenance of E.I, pumps, substation, DG Sets, fire fighting & fire alarm system, HVAC & ductable AC system, lift, Cold Room & solar water heating system etc. |
10/05/2022
09/05/2024 09/05/2024 |
376.50 |
42.00 % |
M/s Vivek Associates |
|
Detail Report
Graph / Photo |
|||
283 | (i) Civil work Comprehensive maintenance of Ring Road including carriageway, footpaths, central verge, service road etc. within the right of way, mechanised desilting |
|
375.34 |
|
|
Detail Report
Graph / Photo |
||||
284 | Strengthening of Shamnath Marg along with Improvement of Footpath, Storm Water Drain, Central Verge etc. from I.P. College Xing to Petrol Pump near Boulevard Road under Sub-Division-3 of Division CandND-Roads, New Delhi. |
|
375.32 |
|
|
Detail Report
Graph / Photo |
||||
285 | Improvement and beautification of road between Dhaula Kuan to IGI airport NSG Xing (R.H.S) (Phase-2) |
|
373.34 |
|
|
Detail Report
Graph / Photo |
||||
286 | Providing, running and maintaining truck mounted Anti Smog Gun on hire basis at various locations |
19/05/2022
18/05/2023 18/05/2023 |
372.34 104.71 (Mar'23) |
0.00 (Mar'23) |
P. R. S. Yash & Co. |
|
Detail Report
Graph / Photo |
|||
287 | Construction of RMCRoad From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22 |
|
369.30 |
|
|
Detail Report
Graph / Photo |
||||
288 | Construction of RMC Road From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22 |
|
369.30 |
|
|
Detail Report
Graph / Photo |
||||
289 | Rehabilitation and strengthening of Okhla flyover on Mathura Road, New Delhi |
|
366.25 |
|
Work in progress null |
Detail Report
Graph / Photo |
||||
290 | Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24 |
|
366.09 |
|
|
Detail Report
Graph / Photo |
||||
291 |
|
364.89 0.00 (Sep'16) |
0.01 % (Sep'16) |
M. C. Construction Co. |
work yet to be awarding
|
Detail Report
Graph / Photo |
||||
292 | Major repair maintenance work i.e. outer plaster, chajjas of windows, balcony, damaged cemented water tank causing seepage, repair of staircase, road, blocked sewer line i/c strengthening, retrofitting works and misc. civil and Electrical works |
|
363.36 156.58 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
293 | Strengthening of Geeta Colony Yamuna Bridge Road from Ring Road Crossing to Pusta Road by cold milling and recycling process. Sub-Division East Road-I under Division East Road/(M-212) Delhi. dg. 2021-22 |
25/02/2022
25/05/2022 25/05/2022 |
362.56 430.06 (Sep'22) |
0.00 (Sep'22) |
Pawan Kumar |
|
Detail Report
Graph / Photo |
|||
294 | Construction of 16 Nos. additional SPS class rooms (G+3) in GGSSS, Qadipur, Delhi ( Sch Id 1309265) (SH: C/o main SPS type building including internal & external water supply, sanitary installation, electrical installations, development of site i/c Fire fighting system etc. at GGSSS Qadipur Delhi -110036. (Sch. ID: 1309265) |
14/04/2022
11/10/2022 15/03/2023 |
361.24 180.21 (Mar'23) |
100.00 % 0.00 (Mar'23) |
Finishing works are in progress. |
Detail Report
Graph / Photo |
||||
295 | Civil Works: Mechanised Desilting of Drains & Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other Misc. Repair works of footpaths, Central Verge, Service roads etc. on other roads than ring road under Sub-Division NWR-21 |
|
359.74 1.30 (Sep'22) |
0.00 (Sep'22) |
|
Detail Report
Graph / Photo |
||||
296 | Re-Surfacing of various roads of Vasant Vihar Roads (Poorvi Marg (Road ID - 781), Paschimi Marg (Road ID - 782 ), Basant Marg 1 (Road ID - 778), Basant Marg 2 (Road ID - 779), Munirka Marg 1 and2 (Road ID - 783)) and Providing and Laying of Stone Ma |
|
359.35 |
|
|
Detail Report
Graph / Photo |
||||
297 | Construction of Foot Over Bridge at Gurudwara Majnu ka Tila on Road No. 45 under Sub-Division-4 of Division C and ND-R, New Delhi. |
06/09/2022
05/03/2023 05/03/2023 |
358.46 |
99.00 % |
Fiberfill Engineer |
|
Detail Report
Graph / Photo |
|||
298 | Improvement of RUB surrounding area and construction of new additional sump at RUB Badarpur under Sub Division SER-24 in Division SER-2, New Delhi and Enhancement of substation, etc. |
|
357.12 |
|
|
Detail Report
Graph / Photo |
||||
299 | Improvement of RUB surrounding area and construction of new additional sump at RUB Badarpur under Sub Division SER-24 in Division SER-2, New Delhi and Enhancement of substation, etc |
|
357.12 |
|
|
Detail Report
Graph / Photo |
||||
300 | Improvement and Strengthening of Loni Road from G.T. Road to Loni Gole Chakkar. |
08/05/2022
05/08/2022 05/08/2022 |
357.04 207.93 (Dec'22) |
0.00 (Dec'22) |
Pawan Kumar |
|
Detail Report
Graph / Photo |
|||
301 | Comprehensive Maintenance and Operation of Trauma Block, New Ward Block, OT, Gynae, Old Ward Block, Doctors and Nurses Hospital and Residential Complex Lifts at DDU Hospital, Hari Nagar, New Delhi (SH Operation of Lifts) |
30/04/2019
29/04/2021 |
355.16 46.14 (Oct'22) |
0.00 (Oct'22) |
Guruji Elevator |
|
Detail Report
Graph / Photo |
|||
302 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021 22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
303 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
304 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
305 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22 |
|
354.88 |
|
|
Detail Report
Graph / Photo |
||||
306 | Comprehensive repair works of footpaths, central verge, service roads etc. on other roads under Sub division NWR-23 |
|
350.32 |
|
|
Detail Report
Graph / Photo |
||||
307 | Strengthening of various roads under Sub Division SR-11/South Road-1 PWD New Delhi.Phirni Road West End Marg Durbal Nath Marg H Block Dakshin Puri Road Maharishi Balmiki Marg and Raja Ram Marg. |
06/11/2019
05/02/2020 05/02/2020 |
348.51 461.79 (Jul'22) |
0.00 (Jul'22) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
308 | Comprehensive maintenance of Civil works at Guru Gobind Singh Govt. Hospital, Raghubir Nagar, Delhi and Rao Tula Ram Memorial Govt. Hospital, Jaffarpur Kalan, Delhi P.W.D. (GNCTD), New Delhi for 2 years 2021-22, 2022-23. |
23/05/2022
21/05/2024 21/05/2024 |
343.73 0.00 (Jan'23) |
42.00 % 27.00 % (Jan'23) |
Aliyan Constaruction Company |
Work is under progress.
|
Detail Report
Graph / Photo |
|||
309 | Strengthening of various roads by cold milling of sub-Div. East road-III under East road/(M-212) Delhi during 2022-23. 1. Sadhabhawna Marg (Road No. 111) 2. Club Avenue Marg (Road No. 112) 3. Sekarita Marg (Road No. 113) 4. Ambedkar Marg. 5. Subhash Market road. 6. Block No. 1 to 11 Trilokpuri. 7. Khudiram Bose Marg |
29/08/2022
24/02/2023 24/02/2023 |
342.13 |
100.00 % |
SATYA PARKASH AND BROS PVT LTD |
|
Detail Report
Graph / Photo |
|||
310 | Strengthening of Dera Bhatti Road of Sub-Division SR-13 under Division SR-1 at New Delhi. |
27/11/2019
26/02/2020 |
341.72 501.17 (Mar'22) |
0.00 (Mar'22) |
Bansal Associates |
|
Detail Report
Graph / Photo |
|||
311 | Providing and fixing road signage boards on various roads Under Sub Division I,II,III,IV,V PWD SWR-I New Delhi. |
|
341.49 |
|
|
Detail Report
Graph / Photo |
||||
312 | Replacement of damaged old 900mm Dia RCC pipe with Providing and Laying 1200mm dia RCC Pipe from Som Bazar Chowk to Mungeshpur drain at Najafgarh Nangloi Road. (Road ID -1230) |
18/04/2022
14/10/2022 14/10/2022 |
339.47 131.12 (Oct'22) |
0.00 (Oct'22) |
Dilshad Khan |
|
Detail Report
Graph / Photo |
|||
313 | AR MO to Various Residential Building Type III IV V and VI under Sub Division M3231N at 16 Rajpur Road Delhi During 2021 22 |
|
339.03 290.62 (Jan'23) |
0.00 (Jan'23) |
|
Detail Report
Graph / Photo |
||||
314 | Construction of Foot Over Bridge with Staircase and lift for padestrians crossing near Mohammadpur Village at Africa Avenue Road, New Delhi during 2017-18 |
|
338.01 |
|
|
Detail Report
Graph / Photo |
||||
315 | Construction of Foot Over Bridge with Staircase and lift for padestrians crossing near Mohammadpur Village at Africa Avenue Road, New Delhi during 2017-18. |
|
338.01 |
|
Work Completed
|
Detail Report
Graph / Photo |
||||
316 | CONSTRUCTION OF 40 NOS SPS CLASS ROOMS |
|
336.15 |
|
|
Detail Report
Graph / Photo |
||||
317 | Strengthening of Western Approaches of Signature Bridge from Signature Bridge to Majnu ka Tila, Signature Bridge to Timarpur, Azadpur and Slip road from Wazirabad flyover to Signature Bridge, Burari flyover and Tagore Park under Sub Division-1, C&ND-Roads, New Delhi |
31/03/2022
30/06/2022 30/06/2022 |
336.11 484.99 (Jul'22) |
0.00 (Jul'22) |
SATYA PARKASH AND BROS PVT LTD |
|
Detail Report
Graph / Photo |
|||
318 | Micro Surfacing on Outer Ring Road from Vikas Puri to Meera Bagh |
|
334.06 20.48 (Jun'22) |
0.00 (Jun'22) |
|
Detail Report
Graph / Photo |
||||
319 | Construction of drains, footpath Central Verge and improvement of side berm portion of S-Bend road (Maharishi Dayanand Marg ID-539) New Delhi. |
24/10/2019
23/01/2020 23/01/2020 |
330.83 376.66 (Jul'22) |
0.00 (Jul'22) |
S S Chauhan & Sons |
Work in Progress
Work in Progress |
Detail Report
Graph / Photo |
|||
320 | Up gradation of one staffroom in 86 Nos. Schools under South-East Building Maintenance Division, Hauz Khas, New Delhi during 2018-19. (Civil and Electrical work). |
23/03/2019
22/09/2019 22/09/2019 |
329.84 160.77 (Jan'23) |
0.00 (Jan'23) |
S. P. CONSTRUCTION COMPANY |
Work in progress
|
Detail Report
Graph / Photo |
|||
321 |
|
328.66 |
|
|
Detail Report
Graph / Photo |
|||||
322 | Comprehensive Maintenance of various Roads under SRD Project Division-I, Sub-Division-I, PWD, Delhi. (SH- Civil Works- Mechanised Desilting of Drains, Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other misc. Repair wor |
27/08/2019
23/08/2020 |
323.91 485.41 (May'21) |
0.00 (May'21) |
Awasthi Construcion Co. |
|
Detail Report
Graph / Photo |
|||
323 | C/o Foot Over Bridge at Block-D, Okhla Phase-I on Shri Maa Anandmayee Marg, New Delhi (Road-ID-946) including EI and Lift |
|
320.49 |
|
|
Detail Report
Graph / Photo |
||||
324 | A/R and M/O to Educational Building under SWBMD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19. (Sh -Internal and external finishing and other misc works). |
03/08/2018
01/10/2018 01/10/2018 |
320.20 0.25 (May'22) |
0.00 (May'22) |
WORK IN PROGRESS
|
Detail Report
Graph / Photo |
||||
325 | Remodelling of drain from 5th Pusta to Ghonda Chowk at Gamri Road Delhi |
13/01/2020
05/04/2020 |
318.40 352.26 (Sep'22) |
0.00 (Sep'22) |
Thermal Enginners & Insulators Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
326 | A/R and M/O to Sub Division-14 of South Road-1 for Comprehensive Maintenance of Press Enclave Road, Mandir Marg, Pankaj Juyal Marg, NBCC Plaza Road, Pramod Mahajan Marg, Family Court Road J-Block Road, H-Block Road Gurudwara Road, Asian market Road, Khirki Road, Sheikh Sarai Phase-I Road no.1 & Road No.2, Road from H.No. C-11 to C-20 Malviya Nagar and Road in front of Mother International School during 2019-20. |
01/11/2019
31/10/2020 |
317.62 488.34 (Jun'22) |
0.00 (Jun'22) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
327 | Building work i/c Water Supply, Sanitary installation,Development Work and providing EI & Fire fighting system |
26/05/2015
25/05/2016 31/01/2023 |
316.66 |
|
Sudesh Kumar |
Work is completed except fittings and fixtures due to delay in taking over of DGD by DGHS. Delay due to non-receipt of funds & revised A/A & E/S from Client Department and covid-19 pandemic since March 2020. Client being requested regularly.
Delay due to non-receipt of funds & revised A/A & E/S from Client Department and covid-19 pandemic since March 2020. Client being requested regularly. |
Detail Report
Graph / Photo |
|||
328 | Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work) |
|
316.48 |
|
|
Detail Report
Graph / Photo |
||||
329 | Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work) |
|
316.48 |
|
|
Detail Report
Graph / Photo |
||||
330 | Civil & Electrical Work |
|
316.48 |
|
|
Detail Report
Graph / Photo |
||||
331 | RMO E and M Services at SRHC Hospital Narela Delhi during the year 2021-23 |
|
315.90 |
|
|
Detail Report
Graph / Photo |
||||
332 | Strengthening of Rajpura Road from Tis Hazari Red Light to Civil Line Thana under SubDivision-4 of Division C& ND-Roads, New Delhi. (Width- ROW Below 30.00 meter) |
24/06/2022
23/10/2022 23/10/2022 |
313.49 |
|
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
333 | Strengthening of Road No. 68 (from Road No. 66 T-Point to Junction of Road No. 69). (From Railway line to Road No. 66 T-Point). |
02/09/2019
30/11/2019 31/12/2019 |
309.88 302.32 (Dec'21) |
0.00 (Dec'21) |
MAHAVIR PRASAD GUPTA AND SONS |
work in progress
|
Detail Report
Graph / Photo |
|||
334 | Automated Housekeeping Service of MSO Building |
|
308.94 72.34 (Feb'23) |
0.00 (Feb'23) |
|
Detail Report
Graph / Photo |
||||
335 | Comprehensive maintenance and operation of UPS and CVCF systems |
26/01/2022
25/01/2024 25/01/2024 |
305.92 38.24 (Mar'23) |
59.00 % 0.00 (Mar'23) |
ARECA TECHNOLOGIES |
|
Detail Report
Graph / Photo |
|||
336 | Repair of Box girder of entry and exit loop with carbon fiber lamination, Expansion Joints and Bearing |
|
305.15 |
|
|
Detail Report
Graph / Photo |
||||
337 | Strengthening of Mall Road from Timarpur Red Light to GTB Metro Station under Sub-Division-2 of Division C& ND-Roads, New Delhi. (Width- ROW Above 60.00 meter). |
28/04/2022
27/06/2022 27/06/2022 |
302.96 505.42 (Jan'23) |
0.00 (Jan'23) |
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
338 | Resurfacing of Road and Repairing of footpath and Central Verge at Asaf Ali Road and Chaman Lal Marg under Division SRD Project I, under Sub Division II, PWD during 2019 20 New Delhi |
23/09/2019
20/03/2020 |
302.16 285.99 (Dec'21) |
0.00 (Dec'21) |
Chaudhary Construction Company Pvt. Ltd. |
|
Detail Report
Graph / Photo |
|||
339 | Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub Division-1, C and ND-Road Division |
|
300.87 |
|
|
Detail Report
Graph / Photo |
||||
340 | Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road-II PWD New Delhi |
10/09/2019
07/01/2020 07/01/2020 |
298.81 194.61 (Jul'20) |
0.00 (Jul'20) |
SBG Infracon Pvt Ltd |
WORK IN PROGRESS
WORK IN PROGRESS |
Detail Report
Graph / Photo |
|||
341 | Installation of target system, bullet proofing and Anti ricochet treatment, ventilation and acoustical works) (Composite work Civil and Electrical) |
07/02/2023
06/06/2023 06/06/2023 |
298.45 |
23.00 % |
|
Detail Report
Graph / Photo |
||||
342 | Strengthening of Shah Alam Bandh Road under Sub-Division NR-11 of North Roads Division, PWD, Delhi. |
|
298.31 |
|
|
Detail Report
Graph / Photo |
||||
343 | Painting of Kerb Stone, railing, jersey barrier and central verge etc. of Sub-Division R-11, R-12, R-13 and R-14 for the occasion of Republic Day |
|
298.11 |
|
|
Detail Report
Graph / Photo |
||||
344 | Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi |
27/12/2018
26/04/2019 |
296.85 335.77 (Aug'21) |
0.00 (Aug'21) |
Ram Krishan Yudhister Parkash |
work completed null |
Detail Report
Graph / Photo |
|||
345 | Running operation and comprehensive maintenance of online UPS, TVSS, APFF, PAC and Isolation transformer of different capacity installed at RGSS Hospital, Tahirpur, Delhi |
26/01/2022
25/01/2024 25/01/2024 |
296.84 61.84 (Sep'22) |
59.00 % 0.00 (Sep'22) |
ISSAR INDUSTRIES |
|
Detail Report
Graph / Photo |
|||
346 | Providing & fixing 80 mm thick Paver Block over Unpaved Shoulder Portion of Road in view of Anti Air Dust Pollution Measures for Rao Laxmi Chand Marg (ID 1174) under Sub Division 23 Division SWR-II, PWD, Delhi |
14/04/2022
11/08/2022 11/08/2022 |
296.33 411.26 (Feb'23) |
0.00 (Feb'23) |
Bliss Associates |
|
Detail Report
Graph / Photo |
|||
347 | Providing and fixing M.S Steel railing at central verge of SSN Marg. |
03/11/2019
02/05/2020 |
295.66 394.81 (Oct'22) |
0.00 (Oct'22) |
B M & Sons |
|
Detail Report
Graph / Photo |
|||
348 | Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). |
28/02/2019
27/06/2019 31/03/2021 |
294.21 58.25 (Feb'22) |
0.00 (Feb'22) |
AASRA Martech Pvt.Ltd. |
Work in progress.
|
Detail Report
Graph / Photo |
|||
349 | Civil and Electrical work. |
05/05/2019
04/03/2020 04/03/2020 |
292.64 |
|
Dheeraj Singh & Company |
Work just awarded
|
Detail Report
Graph / Photo |
|||
350 | Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). |
09/08/2022
08/08/2023 08/08/2023 |
292.57 8.79 (Mar'23) |
57.00 % 0.00 (Mar'23) |
Nand gopal Gupta |
|
Detail Report
Graph / Photo |
|||
351 | Providing and Laying Bituminous concrete and Retro reflective road marking |
|
291.21 72.69 (May'21) |
0.00 (May'21) |
Work completed
|
Detail Report
Graph / Photo |
||||
352 | Strengthening of Arterial Road (Bahadur Shah Zafar Marg) having right of way more than 60.00 metre under Sub Division – 3 of Division C & ND – Roads, New Delhi |
31/03/2022
30/05/2022 30/05/2022 |
289.31 260.08 (Sep'22) |
0.00 (Sep'22) |
A S INFRATECH |
|
Detail Report
Graph / Photo |
|||
353 | Comprehensive Maintenance of Aacharya Shree Tulsi Marg M.G.Road Aya Nagar Road Ghitorni Road to CPWD Land Ghitorni Village Road M.G.Road to Ghitorni Village Road and Mandi Road under the Jurisdiction SD-15 under SR-1 during 2019-20 |
01/11/2019
31/10/2020 |
288.88 426.77 (Jan'22) |
0.00 (Jan'22) |
S S Chauhan & Sons |
|
Detail Report
Graph / Photo |
|||
354 |
|
288.73 |
|
|
Detail Report
Graph / Photo |
|||||
355 | Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi |
16/01/2022
15/10/2024 15/10/2024 |
288.00 |
42.00 % |
Arcop Associates Pvt. Ltd. |
Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval.
NIL |
Detail Report
Graph / Photo |
|||
356 | Comprehensive architectural consultancy services for Construction of SPS School of Specialized Excellence (SoSEs) Buildings (G Plus 3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Lajpat Nagar, Hari Nagar, Karol Bagh, Gandhi Nagar & Nand Nagri (Package-A) |
20/07/2022
19/07/2023 19/07/2023 |
286.66 |
65.00 % |
Design Accord Consultant |
Tenders for appointment of Architectural Consultants on Q.C.B.S. were invited in two packages one each for Pucca Construction and for SPS construction and accordingly M/s Design Accord Consultants were awarded the work.
M/s Design Accord Consultants had visited all the sites of Package-A & B and have prepared initial proposal for presentation and formal approval Date & Time yet to be fixed by the DoE to present the proposal by the consultant at Directorate of Education in presence of all stake holders.
Detailed presentation has been made on 06.01.2023 in Directorate of Education.
Modified proposal / Presentation after incorporating suggestion of HOS /DDE /DoE being resubmitted shortly.
Tenders for appointment of Architectural Consultants on Q.C.B.S. were invited in two packages one each for Pucca Construction and for SPS construction and accordingly M/s Design Accord Consultants were awarded the work. M/s Design Accord Consultants had visited all the sites of Package-A & B and have prepared initial proposal for presentation and formal approval Date & Time yet to be fixed by the DoE to present the proposal by the consultant at Directorate of Education in presence of all stake holders. Detailed presentation has been made on 06.01.2023 in Directorate of Education. Modified proposal / Presentation after incorporating suggestion of HOS /DDE /DoE being resubmitted shortly. |
Detail Report
Graph / Photo |
|||
357 | Comprehensive Maintenance of various Roads under SRD Project Division-I, Sub-Division-II, PWD, Delhi. (SH- Civil Works- Mechanised Desilting of Drains, Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other misc. Repair wo |
24/08/2019
23/08/2020 |
285.85 569.67 (Aug'21) |
0.00 (Aug'21) |
Awasthi Construcion Co. |
|
Detail Report
Graph / Photo |
|||
358 | Construction prefab hut for HQ at PTS Wazirabad, Delhi |
21/07/2018
20/11/2018 |
285.56 |
|
Aliyan Constaruction Company |
work completed null |
Detail Report
Graph / Photo |
|||
359 | Construction of Foot Over Bridge across Shaheed Jeet Singh Marg (ID-22) at Katwaria Sarai wth staircase and lift including Electrical installation for pedestrians under Sub Division-III of Division South Road-II, PWD, New Delhi. |
|
284.19 |
|
|
Detail Report
Graph / Photo |
||||
360 | Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021-22 |
26/12/2022
25/02/2023 25/02/2023 |
282.98 255.41 (Mar'23) |
100.00 % 0.00 (Mar'23) |
RUDRA CONSTRUCTIONS |
|
Detail Report
Graph / Photo |
|||
361 | Operation and Maintenance of EI and FANS Sub Station HVAC Works Fire Fighting and Wet Riser System Solar Water Heating System Cold Storage Lifts etc |
|
282.78 |
|
|
Detail Report
Graph / Photo |
||||
362 | Strengthening of Madhu Vihar Road (Road No. 57 to Joshi Colony T-Point) and Mandawali Road (House Tax Building to Agrasen Apartment) at I.P. Extension under PWD Division East (Road) |
16/04/2018
14/07/2018 |
280.65 117.06 (Feb'22) |
0.00 (Feb'22) |
JAP BUILDCON PRIVATE LIMITED |
Work in Progress
|
Detail Report
Graph / Photo |
|||
363 | Renovation/Upgradation of the GST Office i/c A,B and C Wing at 4th Floor, Deptt. of Trade & Taxes Bldg. , IP Estate, New Delhi |
|
276.70 |
|
|
Detail Report
Graph / Photo |
||||
364 | Renovation Upgradation of the GST Office I/c A B and C Wing at 4th Floor Deptt of Trade and Taxes Building I P Estate New Delhi RECALL |
|
276.70 2.23 (Jan'23) |
0.00 (Jan'23) |
|
Detail Report
Graph / Photo |
||||
365 | Providing Tractor driven positive displacement rotary lobe pump & diesel engine pump set at different locations for removing water logging etc. during rainy season. 1st RECALL |
16/06/2022
15/10/2022 15/10/2022 |
274.22 566.14 (Mar'23) |
0.00 (Mar'23) |
Aliyan Construction Company |
|
Detail Report
Graph / Photo |
|||
366 | Construction of 12 Nos. Aam Admi Mohalla Clinic at various locations under South-East (Bldg)-M, Division, Hauz Khas, New Delhi during 2021-22. (Civil and Electrical works) |
|
271.15 176.14 (Mar'23) |
0.00 (Mar'23) |
|
Detail Report
Graph / Photo |
||||
367 | Construction of store room 01 nos., Shed 2 nos. behind old building, Toe Wall in Park and Ramp for new Building Block, Renovation of all toilet and guard room, Fixing granite on stage |
|
269.83 |
|
|
Detail Report
Graph / Photo |
||||
368 | Construction of 2 nos. Additional Basket Ball Court in Warmup Area, Acoustics Treatment in Basket Ball Hall, Renovation of boundary wall and Sitting Chairs in sitting gallery at Sarvodaya Bal Vidyalaya, Anand Vas (Lok Vihar), Delhi |
26/12/2022
24/05/2023 24/05/2023 |
267.31 50.47 (Mar'23) |
59.00 % 0.00 (Mar'23) |
Sham Lal Gupta and Sons |
the work has been recently awarded to the agency. the design acoustics Treatment for Basketball Hall submitted by the agency and the same is under checking
|
Detail Report
Graph / Photo |
|||
369 | Remodeling of old damaged Brick Masonry drain of Shani Bazar Road With new RCC Box Drain at Sultanpuri, Delhi. |
|
264.96 |
|
|
Detail Report
Graph / Photo |
||||
370 | Civil and Electrical Works |
|
263.87 |
|
|
Detail Report
Graph / Photo |
||||
371 | Regarding Establishing Migrant labour Facilitation Centre at West District, Labour Office, Karampura). (Civil Work and Electrical Work). |
|
263.20 |
|
|
Detail Report
Graph / Photo |
||||
372 | Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool |
23/12/2020
20/06/2021 31/03/2023 |
262.79 54.92 (Feb'23) |
0.00 (Feb'23) |
Maa Narayan Constuction Co. |
62%
|
Detail Report
Graph / Photo |
|||
373 | AR and MO to various roads under PWD South Zone during 2017 18 SH Global Tender for Mechanized Vacuum Sweeping and Cleaning of Various PWD Roads under PWD South Zone for one year |
|
261.26 |
|
Work not executed
|
Detail Report
Graph / Photo |
||||
374 | Beautification Upgradation of lift lobby and Corridor area ic flooring, Wall dado and False Ceiling from 1st Floor to 13th floor Civil and Electrical Work |
|
259.34 135.56 (Jul'22) |
0.00 (Jul'22) |
|
Detail Report
Graph / Photo |
||||
375 | Construction of Foot over bridge with Staircase & lifts for Pedestrians across road at Ganesh Chowk ROB-36 Road. |
23/02/2023
22/06/2023 22/06/2023 |
258.65 |
23.00 % |
SS Chauhan & Sons |
|
Detail Report
Graph / Photo |
|||
376 | Operation and Maintenance of EI and FANS Sub Station and DG Set HVAC Works Fire Fighting and Wet Riser System Fire Alarm System Lifts Solar Water Heating System RO plant etc. |
|
254.53 |
|
|
Detail Report
Graph / Photo |
||||
377 | C/o 08 equivalent Room (06 Nos. Class Room + M.P. Hall), GGSSS Urdu Medium (ID – 212705) and Lift internal & external electrical installations, development of site and fire fighting system etc. at Chasma Building |
|
254.28 |
|
tender opened on 04.07.2022
|
Detail Report
Graph / Photo |
||||
378 | C/o 08 equivalent Room (06 Nos. Class Room + M.P. Hall), GGSSS Urdu Medium (ID – 212705) and Lift internal & external electrical installations, development of site and fire fighting system etc. at Chasma Building |
|
254.28 |
|
Financial bid opened
|
Detail Report
Graph / Photo |
||||
379 | Co 08 equivalent Room 06 Nos Class Room MP Hall GGSSS Urdu Medium ID 212705 and Lift internal and external electrical installations, development of site and fire fighting |
|
254.28 |
|
tender under process
tender under process |
Detail Report
Graph / Photo |
||||
380 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (Re-call) |
|
249.39 |
|
|
Detail Report
Graph / Photo |
||||
381 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. |
|
249.39 |
|
|
Detail Report
Graph / Photo |
||||
382 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi |
|
249.39 |
|
|
Detail Report
Graph / Photo |
||||
383 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi |
|
249.39 |
|
|
Detail Report
Graph / Photo |
||||
384 | Civil and Electrical Works |
|
249.03 |
|
|
Detail Report
Graph / Photo |
||||
385 | A/R and M/O to various Roads under Division South Road -II, PWD during 2021-22 (SH:Filling the pot holes / patch repair on PWD Roads by Mobile Infrared Recycling Road Repair Machine under Sub-Division-I, II, III and IV) |
03/09/2021
02/09/2022 02/09/2022 |
246.96 295.79 (Jul'22) |
0.00 (Jul'22) |
Trans Metalite India Limited |
Work in Progress
Work in Progress |
Detail Report
Graph / Photo |
|||
386 | Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub Division-1, C&ND-Road Division. 2nd RECALL |
20/07/2022
19/11/2022 19/11/2022 |
243.86 |
|
MAHAVIR PRASAD GUPTA AND SONS |
|
Detail Report
Graph / Photo |
|||
387 | Providing and fixing road signage boards under Sub-Division SER-21, SER-22, SER-23, SER-24 and SER-25 |
|
242.62 |
|
|
Detail Report
Graph / Photo |
||||
388 | Providing and fixing road signage boards under Sub-Division SER-21, SER-22, SER-23, SER-24 and SER-25 |
|
242.62 |
|
|
Detail Report
Graph / Photo |
||||
389 | Widening of IGNOU Road and construction of RCC drain and footpath at IGNOU Road from Z more to M.B. Road T-Point. |
18/07/2018
16/09/2018 30/06/2019 |
242.58 392.31 (Aug'21) |
0.00 (Aug'21) |
Y. D. Builders & Hotel Pvt Ltd |
Work in progress
Work in progress |
Detail Report
Graph / Photo |
|||
390 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (2nd call) |
|
242.04 |
|
|
Detail Report
Graph / Photo |
||||
391 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (Revised) |
|
242.04 |
|
|
Detail Report
Graph / Photo |
||||
392 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi |
|
242.04 |
|
|
Detail Report
Graph / Photo |
||||
393 | Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (Re-call) |
|
242.04 |
|
|
Detail Report
Graph / Photo |
||||
394 | Upgradation/Renovation of one staff room in each of 951 schools (SH- Civil and Electrical works in Mangolpuri, Sultanpuri, Kirari, Shakurbasti and Mundka constituency Schools, Total 74 Nos. Schools of NWB-2) |
|
239.47 |
|
|
Detail Report
Graph / Photo |
||||
395 | Development of road side of DAV School road stretch in front of Govt. School and DAV School for making it pedestrian student friendly under Sub-Division-III of Division South Road-II, PWD, New Delhi (Civil Elect. works) |
26/07/2022
25/11/2022 25/11/2022 |
238.89 |
|
Bhawani Constructions |
Work in Progress
Work in Progress |
Detail Report
Graph / Photo |
|||
396 | Resurfacing of Satguru Ram Singh Marg (Road ID 1226), and improvement of footpath with Enhancement of exiting drain capacity under Sub Division- 21, SWR-II, PWD, New Delhi. |
18/01/2023
17/05/2023 17/05/2023 |
238.30 |
48.00 % |
Surender Singh |
|
Detail Report
Graph / Photo |
|||
397 | Providing, supplying, running and maintaining WATER SPRINKLER on hire basis at various locations |
|
235.98 |
|
|
Detail Report
Graph / Photo |
||||
398 | Providing and fixing Foot Over Bridge including electrical installation etc. |
|
233.06 |
|
|
Detail Report
Graph / Photo |
||||
399 | Restoration of MB Road and Phirni Road cut by DTL and JIO Digital under PWD Division South Road-1 Sub Division-11 during 2021-22 |
|
232.84 199.00 (Dec'22) |
0.00 (Dec'22) |
|
Detail Report
Graph / Photo |
||||
400 | Construction of Foot over Bridge With Staircase and lift for pedestrian at Baba Gang Nath Mandir on Nelson Mandela Marg, New Delhi |
|
229.69 |
|
|
Detail Report
Graph / Photo |
||||
401 | Construction of Foot Over Bridge with Staircase and Lift for pedestrians crossing near Mohan Singh Market at Tamil Sangam Marg (Road ID No. 141), New Delhi |
|
228.64 35.00 (Apr'20) |
0.00 (Apr'20) |
|
Detail Report
Graph / Photo |
||||
402 | Comprehensive Maintenance of SSN Marg, 100 Foota Road and 60 Foota Road under the Jurisdiction SD-12 under SR-1 during 2019-20. |
01/11/2019
31/10/2020 |
227.39 326.28 (Feb'22) |
0.00 (Feb'22) |
Amrit Lal behl & Sons |
|
Detail Report
Graph / Photo |
|||
403 | Providing, running and maintaining Anti Smog Gun on hire basis at various locations |
|
227.34 |
|
|
Detail Report
Graph / Photo |
||||
404 | Providing, running and maintaining Anti Smog Gun on hire basis at various locations |
|
227.34 |
|
|
Detail Report
Graph / Photo |
||||
405 | Providing, running and maintaining Anti Smog Gun on hire basis at various locations |
|
227.34 |
|
|
Detail Report
Graph / Photo |
||||
406 | Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub. Division-1, C and ND-Road Division. (1st RECALL) |
09/03/2022
08/07/2022 08/07/2022 |
225.35 |
|
Sethi Construction |
|
Detail Report
Graph / Photo |
|||
407 | Civil and Electrical Works |
|
222.89 |
|
|
Detail Report
Graph / Photo |
||||
408 | Construction of Foot Over Bridge with staircase, electrical works and lift for pedestrian across press Enclave Road near Select City Mall, New Delhi. |
31/08/2019
29/02/2020 |
222.53 187.92 (Jul'20) |
0.00 (Jul'20) |
S. S. Chauhan & Sons |
|
Detail Report
Graph / Photo |
|||
409 | Balance Work |
|
219.85 |
|
|
Detail Report
Graph / Photo |
||||
410 | Civil & Electrical Works |
|
219.42 |
|
|
Detail Report
Graph / Photo |
||||
411 | Civil & Electrical Works |
|
219.42 |
|
|
Detail Report
Graph / Photo |
||||
412 | Renovation of school building and Multipurpose hall (Composite work Civil & Electrical) |
22/05/2022
21/01/2023 21/01/2023 |
217.86 186.74 (Jan'23) |
0.00 (Jan'23) |
Nafees Ahmed |
|
Detail Report
Graph / Photo |
|||
413 | Comprehensive Annual Maintenance of all roads including Carriageway, Footpaths, Central Verge, Planter, Service Roads etc. within the Right of Way, Mechanized/Manual Desilting of Drains, Repairing of Potholes, Maintenance and other Misc. Repair Works under West Road -1 Division, Sub Division WR-12 during 2022-23. |
|
217.69 |
|
|
Detail Report
Graph / Photo |
||||
414 | Construction of Training-cum Production Centre at Indira Nagar, Azadpur, Delhi-33. (Civil & Electrical Work). |
|
215.93 |
|
|
Detail Report
Graph / Photo |
||||
415 | Comprehensive Annual Maintenance of all roads including Carriageway, Footpaths, Central Verge, Planter, Service Roads etc. within the Right of Way, Mechanized/Manual Desilting of Drains, Repairing of Potholes, Maintenance and Cleaning of FOB’s and other Misc. Repair Works under West Road-1 Division, Sub Division WR-11 during 2022-23 |
|
215.66 |
|
|
Detail Report
Graph / Photo |
||||
416 | Construction of RCC drain from Road no. 64 to Road no. 62 at Mother dairy Road in Dilshad Garden, New Delhi |
25/12/2022
20/09/2023 20/09/2023 |
212.33 |
32.00 % |
Digital Controls & Automation |
|
Detail Report
Graph / Photo |
|||
417 |
|
211.19 |
|
|
Detail Report
Graph / Photo |
|||||
418 | Annual comprehensive maintenance of Street lighting under the jurisdiction of NED |
|
209.42 |
|
Updated . |
Detail Report
Graph / Photo |
||||
419 | Upgradation/Renovation of one staff room in each of 73 schools (Morning and Evening Shift) located at (NE) District of Delhi under the jurisdiction of PWD Building Maintenance Division M-222 |
25/01/2019
24/04/2019 30/09/2019 |
209.29 192.52 (Jan'22) |
0.00 (Jan'22) |
Shyam Sunder Tyagi |
work completed null |
Detail Report
Graph / Photo |
|||
420 | 1. Infrastructural Improvement and Renovation of Office Building, Toilet and open Ground at Science Centre no 3, Plot no 3, Link Road, Karol Bagh, New Delhi under Sub-Division-I of SRDP-II, PWD, New Delhi). (2) Infrastructural Improvement and Renovation at of the Building of Science Centre No. 3 Plot NO. 3, Link Road, Karol Bagh, New Delhi (Electrical works) |
|
208.72 36.54 (Jul'22) |
0.00 (Jul'22) |
|