Zoneअंचल
Divisionमंडल
Sectorकार्य का प्रकार
Sectorकार्य का प्रकार
Categoryश्रेणी
Other Project Health Project North Maint. East Maint. South Maint. Flyover
Construction Work 45 132 33 1025 754 1089 17
Maintenance Work 64 2422 8 2482 6014 3144 25 5
Total 109 2554 41 3507 6768 4233 42 5
S. No.क्र. सं. Name of Workकार्य का नाम Date of Start Cost (In Lac) Target Progress Agency Present Position Satisfactory Viewदेखें
Stp. Completion
Exp. Completion Expenditure Phy. Progress Bottleneck Quality Safety Progress
1 Redevelopment of Tis Hazari District Court

519981.00
0.00 (Mar'19)

0.00 (Mar'19)
A/A & E/S AWAITED
Detail Report
Graph / Photo
2 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 18/04/2015
17/10/2017
31/10/2024
96400.00
142609.37 (Nov'23)
94.00 %
0.00 (Nov'23)
Larson & Toubro Limited lower pylon 1st lift in progress
LRP4 well Sinking extremely slow
Detail Report
Graph / Photo
3 Underground Tunnel, Underpass, FOB, Loops, Ramps, Footpath, Road Work including Road Signage, Road/Street Lighting works, Tunnel furnishing (FF& FA system, PA system, Automated drainage, integrated tunnel management system etc.), landscaping/horticulture work & allied works 08/11/2017
29/08/2019
31/08/2023
77700.00
44561.05 (Nov'23)

0.00 (Nov'23)
M/s L&T Ltd. work is in progress
Detail Report
Graph / Photo
4 C/o New Block for Medicaine, Maternity and advance pediatric centre at L.N.Hospital 04/11/2020
03/05/2023
31/12/2024
46552.58
4.75 (Jul'22)

0.00 (Jul'22)
In LN1 steel Col. erected upto 21st floor, 22nd floor slab is casted in pour 1. 22nd floor slab casted in pour 3. 19th floor slab casted in pour2. In LN2, pour 2, 9th floor slab has been casted. In Pour II, 12th floor slab casted. In Pour III, 8th floor slab has been casted, 13th floor in progress.
N.A.
Detail Report
Graph / Photo
5 Construction of New Block For Medicine, Maternity And Advanced Pediatric Centre ( Composite Steel plus RCC framed 2B plus G plus 22 Storyed building At LN Hospital including internal water supply, Sanitary installation, External Development works, Dr 04/11/2020
03/05/2023
31/10/2023
46552.58
17215.59 (Jul'23)

0.00 (Jul'23)
Swadeshi Civil Infrastructure Pvt. Ltd., 302, DLF Tower B Jasola, New Delhi-110025 In LN1 steel Col. erected upto 17 th floor, 20th floor slab has been casted pour 1. 19th floor slab casted in pour 3. 16th floor slab casted in pour2. In LN2, pour I, 6th floor slab has been casted. In Pour II, 10th floor slab casted. In Pour III, 6th floor slab has been casted, erection of 11th floor is in progress.
No
Detail Report
Graph / Photo
6 Setting up of Semi permanent temporary I.C.U. Hospital at Shalimar Bagh(G plus 3) (1430beds), Kirari (G plus 4)(458 Beds) and Sultanpuri (G plus 3)(525 Beds) Package I

43132.08
1961.57 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
7 Supply, installation, testing, commissioning of CCTV camera in Delhi. (Sub: Empanelment of firms for supply, installation, testing, commissioning & CAMC of CCTV system in Delhi). 24/11/2018
23/11/2019
14/11/2027
42798.32
8328.67 (Nov'23)

0.00 (Nov'23)
Bharat Electronics Ltd work completed. The work of CAMC which is part of the project, is going on.
Detail Report
Graph / Photo
8 setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) 23/09/2021
22/02/2022
04/08/2022
40775.18
12389.92 (Jun'23)

0.00 (Jun'23)
SAM India Builtwell GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave.
Detail Report
Graph / Photo
9 Setting up of Semi-permanent temporary I.C.U Hospital at Chacha Nehru Bal Chikitsalaya (G plus 4) (596 beds) and GTB Hospital Complex (G plus 4) (1912 Beds) Package II

35533.93
16968.61 (Oct'23)

0.00 (Oct'23)

Detail Report
Graph / Photo
10 C/o Additional Court Rooms on the existing Court Bldg. in District Court Complex at Rohini

33532.67

A/A & E/S awaited
Detail Report
Graph / Photo
11 Construction of Flyover with Ramps, Footpath, Road Work including Road Signage, Street Light works, Drainage, Horticulture, Mural Works & allied works at Road No. 56 between Anand Vihar ROB and Apsara Border ROB, New Delhi (EPC Mode 10/09/2022
08/12/2023
08/12/2023
33420.85
7348.57 (Nov'23)

0.00 (Nov'23)
carpeting over ramp A2

none

Detail Report
Graph / Photo
12 Construction of New Hospital Block at Babu Jagjivan Ram Memorial Hospital, Jahangirpuri, New Delhi

31879.73

PE of Civil Work submitted to the O/o Chief Engineer on dated 10/05/2023
Detail Report
Graph / Photo
13 Setting up of 1912 bedded semi permanent/temporary ICU Hospital at GTB. 23/09/2021
22/02/2022
31/03/2024
31608.00
0.00 (Jul'23)

82.00 % (Jul'23)
Work stopped due to non availability of funds.
The work is delayed due to non-availability of site for GTB, many revisions in drawings by consultant, ban on construction works due to pollution followed by restrictions. STP & water tanks works delayed due to changes in capacity of sizes.
Detail Report
Graph / Photo
14 Corridor Development and Street Network/ Connectivity Plan for the influence zone of the corridor between Punjabi Bagh Flyover and Raja Garden Flyover 10/09/2022
08/12/2023
08/12/2023
30848.06
2257.79 (Nov'23)
100.00 %
0.00 (Nov'23)

Work is in progress.


Work is in progress.

Detail Report
Graph / Photo
15 Construction of Home for Assisted Living at Narela, Delhi

30528.15

Land available. A/A & E/S is yet to be received
Detail Report
Graph / Photo
16 Providing 600 Nos. LED Screens at Various Locations in Delhi.

29481.84

The tender has been cancelled on 07.07.2023 due to administrative reasons.
Detail Report
Graph / Photo
17 Setting up of Semi-permanent temporary I.C.U Hospital at Sarita Vihar (G plus 4) (336beds) and Raghubir Nagar (G plus 3)(1577 Beds) Package III

29175.20
2715.41 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
18 Repairing of fire alarm system installed at Lawyers chamber block 3 28/02/2020
27/03/2020
27388.89

Ekta Enterprises
Detail Report
Graph / Photo
19 Construction of Hospital at Madipur, New Delhi 11/11/2020
10/11/2022
31/03/2024
26970.58
15112.52 (Nov'23)

0.00 (Nov'23)
Ramacivil India Construction Private Limited Physical progress 87%. & Financial Progress Rs. 140.66Cr.
1. RCC structure of the building is completed. Finishing work such as tile work, Granite work, POP, putty etc is in progress at Ground floor to 8th floor level and service floor level. 2. Development work such as C.C. pavement for Road work, laying kerb stone, paver block & strom water line etc. is in progress. 3. Stone & ACP Cladding is also is in progress at site. 4. Structural glazing work is yet to be commenced & approval of factory has been given by the Competent authority.
Detail Report
Graph / Photo
20 Construction of Hospital at Jwalapuri, New Delhi 07/08/2020
13/08/2022
31/03/2024
26950.37
12987.51 (Dec'23)

0.00 (Dec'23)
Parnika Commercial and Estates Pvt. Ltd. Structure RCC work & masonry work completed. External development sanitary installation work 95 % completed, façade work, development work & electrical work is in progress.
N.A.
Detail Report
Graph / Photo
21 Construction of Hospital at Hastsal, New Delhi 17/06/2021
16/06/2023
31/12/2024
23695.11
3571.41 (Nov'23)

47.00 % (Nov'23)
Casting of 7th floor slab has been completed. 8th floor centering & shuttering and placing of reinforcement is under progress. The masonry work in 1st, 2nd & 3rd floor are in progress. Granite flooring in upper basement and ground floor is in progress.
Detail Report
Graph / Photo
22 REWIRING/REPAIRING OF ELECTRICAL ACCESSORIES IN TOILETS AT VARIOUS DELHI GOVT. SCHOOL 09/08/2017
09/11/2019
23127.43

NKG Infrastructure Limited
Detail Report
Graph / Photo
23 C/o Additional Lawyer Chambers near District Court, Dwarka, Sec-10, New Delhi.

22764.65
0.00 (Mar'19)

0.00 (Mar'19)
M/s Kapoor & Associates has already been appointed as consultant for this work but Hon'ble High Court of Delhi has desired to appoint M/s TCS Consultant @450/- sqm on single source selection basis but proposal was not accepted by the competent authority.
Detail Report
Graph / Photo
24 Construction of 132 Type-V Quarters and 52 Type-VI Quarters for Judges at Anand Vihar Delhi.

22456.97

Land allotment issue
Detail Report
Graph / Photo
25 C/o Police Housing project at Mandoli, Delhi-93(SH: C/o 300 Nos. Type-II and 60 Type-IV qtrs and its related development works)

22130.16

A/A & E/S awaited
Detail Report
Graph / Photo
26 C/o New Building for office of Deputy Commissioner & District Magistrate (South-west) at Sector-10, Dwarka, New Delhi

19481.76
0.00 (Mar'19)

0.00 (Mar'19)
Dy. Commissioner called two-three meetings to get proper area required by various department for mini secretariat. Last meeting was called on 04.10.2023 to discuss the drawings for new office of the District Magistrate (South-West) proposed to be constructed in Dwarka. The revised drawings is being submitted shortly. This work is being carried out in House by PWD Sr. Architect (Project), PWD.
Detail Report
Graph / Photo
27 Supply, Installation, Testing and Commissioning and CAMC of CCTV Camera system in Delhi Phase-II Package-II. 14/01/2020
11/07/2020
30/09/2023
19053.31
2596.04 (Nov'23)

0.00 (Nov'23)
Target date of completion is for the 61885 no. approved cameras out of 70000 CCTV cameras.
Detail Report
Graph / Photo
28 Supply, Installation, Testing and Commissioning and CAMC of CCTV Camera system in Delhi Phase-II Package-1 14/01/2020
11/07/2020
30/09/2023
19050.80
2876.27 (Nov'23)

0.00 (Nov'23)
Target date of completion is for the 45055 no. approved cameras out of 70000 CCTV cameras.
Detail Report
Graph / Photo
29 Construction additional courts at new plot at Karkardooma in front of existing Karkardooma Court Complex, Delhi.

17394.78

A/A & E/S awaited
Detail Report
Graph / Photo
30 C/o 750 Bedded Hospital at Dwarka, New Delhi.

16355.70
441.02 (Jun'23)

0.00 (Jun'23)

Work has been transferred to EE(E) South West Health Maintenance Division.

Detail Report
Graph / Photo
31 Construction of Flyover at Nand Nagri and Gagan Cinema Junction of Mangal Paney Marg including Elevated Corridor Footpath Road Work and Road Signages Electrical Works Drainage Rain Water Harvesting and Allied works on EPC mode 03/02/2023
31/07/2024
31/07/2024
15785.00
5532.28 (Nov'23)
57.00 %
0.00 (Nov'23)
Ram Kumar Contractor Piling work, pile cap, pier, girder casting and pier reinforcement work in progress. Utilities of BSES, TPDDL, DJB etc are to be shifted. Tree cutting permission awaited.
Detail Report
Graph / Photo
32 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 18/10/2019
10/04/2021
31/12/2023
13447.15
6679.45 (Nov'23)
100.00 %
99.00 % (Nov'23)
Roshan Real Estate Pvt Ltd. Road work & external development works has been completed. Rainwater harvesting, MGPS, Painting and false ceiling work of Block-A is in progress.
Slow progress of electrical work
Detail Report
Graph / Photo
33 Extension of Ashram Flyover to DND Flyover. 19/06/2020
18/06/2021
31/12/2023
12879.00
620.06 (Nov'23)

0.00 (Nov'23)
KCC Buildcon Pvt. LTD The extended Ashram Flyover has been inaugurated by the Hon'ble CM, Delhi on 06.03.2023. Horticulatuer and development Art work is in progress. RE has been submitted and approval of EFC is awaited. Payment of the final bill can not be made without the same.
Detail Report
Graph / Photo
34 Setting up of 610 bedded semi permanent/temporary Hospital at CNBC. 23/09/2021
22/02/2022
31/12/2023
9709.00
0.00 (Jun'23)

88.00 % (Jun'23)
Work stopped due to non availability of funds.
The work of ground floor, 3rd floor and 4th floor in CNBC held up due to changes desired by MD/DGHS. The consultant has modified the plans to be approved by DGHS. This complete exercise will take some time, after that the work in these areas will be taken up. Decision regarding skywalk in CNBC to be issued for execution.
Detail Report
Graph / Photo
35 C/o Family Court Complex at Rohini, New Delhi

9579.83
4.13 (Sep'23)

0.00 (Sep'23)
Tender has been called and the date of time of tender has been extended and finally has to be opened on 31.10.2023 due to administrative reason.
Detail Report
Graph / Photo
36 C/o Haji House at Sector-22, Phase-II, Dwarka, New Delhi

9566.03
0.00 (Mar'19)

0.00 (Mar'19)
A/A & E/S awaited
Detail Report
Graph / Photo
37 C/o New DC office at Mandawali, Fazalpur, Delhi

8432.86

A/A & E/S awaited
Detail Report
Graph / Photo
38 Construction of Delhi Fire Service Headquarter Building at Connaught Place, New Delhi-110001

8094.10
0.00 (Mar'19)

0.00 (Mar'19)
The Hon'ble Minister (Home) Govt. of NCT of Delhi has desired that as per FAR and Ground Coverage has already been increase as per MPD-2021 from 120 to 300 and 30% to 50% respectively The Fire Services Deptt. To advice for re-calling the tenders for consultancy services of above work seems justified. A letter has been received from consultant M/s Gian P. Mathur & Association (P) Ltd. (Copy enclosed) for revised escalation of consultancy fees for FAR increased 120 to 300% and Ground Coverage 30 to 50%. The case was sent to the C.E. (OP) . The above case has been review/scrutiny in the C.E. (OP) after review/scrutiny of the case the C.E. (OP) has required to provide current prevailing market rate with justification. The EE (OPD-I) directed to the consultant to provide current prevailing market rate with justification to this office on 28.11.2022. After scrutiny proposal, the competent authority has been decided on 14.02.2023 to prepare the revised preliminary estimate to obtain revised A/A & E/S from client department before call a fresh tender for consultancy work. A letter has also been received from Delhi Fire Service authority vide No. F6/DFS/MS/BP/2023/271 dated 13.02.2023 for calling fresh tender. The Revised PE amounting to Rs. 2,23,46,965/- for consultancy work has been sent CE (OP), PWD vide this office letter No. 23(1)/EE/OPD-I)/PWD/83 dt. 17.02.2023. Preliminary Drawings are being prepared by Sr. Architect (Projects) and a meeting was also held in the O/o ADG (Projects) among the PWD and Fire Headquarter authorities on 23.03.2023.
Detail Report
Graph / Photo
39 Maintenance of P.C. in Divn and SD Office.

7122.82

PNSC Infrastructure Pvt. Ltd
Detail Report
Graph / Photo
40 Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A6 Paschim Vihar, New Delhi (Package - 7). 18/07/2021
17/07/2022
31/07/2023
6988.57
5020.55 (Dec'23)

0.00 (Dec'23)
A. K. Mehta & Co.

Work is in progress.


Null

Detail Report
Graph / Photo
41 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 06/08/2019
29/10/2020
31/03/2024
6563.40
2715.99 (Nov'23)

83.00 % (Nov'23)
PNSC Infrastructure Pvt. Ltd Finishing works, waterproofing, external façade and external development works are under progress.
Detail Report
Graph / Photo
42 Construction of Police Station and Multi storyed Staff Quarters at Paschim Vihar, Delhi.

5120.46


Detail Report
Graph / Photo
43 Civil and Electrical Composite Work (Dwarka Sector-16 & Qutubapur). 18/07/2021
17/07/2022
31/05/2024
5058.13
492.80 (Sep'23)

0.00 (Sep'23)
PNSC Infrastructure Pvt. Ltd The process for local body approvals is in progress. DUAC approval received on 19.09.2022. Fire NOC received. Building Plans uploaded on MCD Portal by the consultant for approval. C/o of boundary wall and other misc. work at Dwarka Sector -16 school is in progress. MCD require Extainsion of time for constrcution from DDA for which request has been made to DDA by L&Estate office vide No.F-16/site/Estate/4210-12 dt. 11.10.2022. As required by DDA, letter requesting waiver of composition Fee for 'Extension of Time" submitted to DDA on 24.11.2022. Building Plans have been approved by SE (Bldg.), MCD . Approved Building Plans are expected to be released shortly. All local body approval has been recevied. Structure drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed .superstructure work started.
Qutubapur- SANCTION WITHDRAWN (i). Site layout plan has been uploaded to MCD by consultant for approval on dated 25.05.2022 and property tax of land also has been deposited. (ii). There is no tree cutting and no transplanting required. (iii). Additional Commissioner MCD & CTP, MCD during meeting 3.10.2022 informed that due to urbanization of villages, this gram sabha land is now under control of DDA .MCD is yet to upload their observation regardfing Layout Plan . (iv) DO dated 17.11.2022 issed by E-in-C to VC, DDA regarding clarification required by MCD. Response is still awaited. (v) LoP was discussed during meeting in MCD on 27.03.2023. Minutes of Meeting is still awaited. Above Sanction Withdrawn by DoE vide letter no.F.16/Estate/Cons./ Pucca School/Qutubapur/ 1594-1601 Dated: 24.05.2023 .
Detail Report
Graph / Photo
44 Strengthening of Rohtak Road (NH-10) from Punjabi Bagh Round about to Metro Pillar No. 526 under PWD, Maintenance Division West-2 Roads, New Delhi

4613.56

Estimate submitted to MORTH for approval
Detail Report
Graph / Photo
45 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work)

4350.79
7.43 (Jun'19)

0.00 (Jun'19)

Technical bid opened


Work transffered to Street scapping Division

Detail Report
Graph / Photo
46 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work)

4350.79


Detail Report
Graph / Photo
47 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) 43,50,79,456

4350.79


Detail Report
Graph / Photo
48 Construction of underpass by jack pushing of pre-cast RCC boxes at outer ring road near Mukarba Chowk including construction of approach road from Badli Junction to Haiderpur Metro Station. 14/10/2022
13/10/2023
03/06/2024
4329.32
140.12 (Nov'23)
68.00 %
0.00 (Nov'23)
Dharamraj Contracts (I) Pvt. Ltd. Work affected due to non-shifting of utilities like IGL, TPDDL etc. Inspite of continuous effort IGL is taking more time than expected. The casting of thrust bed completed. 90 % of shifting of IGL gas pipe line has been completed. During the last ETC meeting in the month of September, the expenditure with respect to the shifting of HT lines was finalized.
Work affected due to non-availibility of NOC from I & FC Department, non shifting of utility by IGL, TPDDL etc.
Detail Report
Graph / Photo
49 C/o Three Lane Flyover, Road Work, Footpath, Drainage System, Landscaping, Railing, Road Signages, Street Light & Allied works. 15/07/2022
14/07/2023
31/10/2023
4199.50
2105.39 (Oct'23)

0.00 (Oct'23)
Gawar Construction Ltd., Work completed and inaugurated by Hon’ble Chief Minister, Delhi on 22.10.2023
NA
Detail Report
Graph / Photo
50 W/O Mahrauli Mahipalpur Road. SH: from 4 lanes to 8 lanes and Service Road from Andheria More to Masoodpur Village. 30/10/2012
29/04/2013
29/04/2013
3812.11

KCC Buildcon Pvt. LTD .
Detail Report
Graph / Photo
51 Supplying and installation of Modular Operation Theatre and Medical Gas Pipe line System at orthopedic department of LNH including Emergency Trauma Services and Intensive Care Beds (50)

3742.21


Detail Report
Graph / Photo
52 Construction of 140 nos additional SPS Classrooms in DOE Schools GGSSS No. 1 Tukhmirpur, Delhi (1104262) 40 Class rooms, GGSSS No. 2 Tukhmirpur, Delhi (1104419) 32 Class rooms & GSKV Khajuri Khas, Delhi (1104022) 68 Class rooms including Laboratory, staircases, toilets and ramps, internal water supply, sanitary installations, Internal electrification and fire fighting arrangements.

3713.27

The fund has not alloted by SSA and vide CE office letter No. 23(45)/ 22/CE(Proj.)/ PWD /E&NE/852 dated: 22.09.2022 informed the Education Department/SSA for withdrawn the sanction.
The fund has not alloted by SSA and vide CE office letter No. 23(45)/ 22/CE(Proj.)/ PWD /E&NE/852 dated: 22.09.2022 informed the Education Department/SSA for withdrawn the sanction.
Detail Report
Graph / Photo
53 E & M works relating to all day to day operation & maintenance, A/R & M/O Works & Special Repair Works etc 27/05/2022
26/05/2024
26/05/2024
3516.35
1784.88 (Nov'23)
81.00 %
0.00 (Nov'23)
Swastik Electrotech Pvt. Ltd.

Work in progress


Work in progress

Detail Report
Graph / Photo
54 Supply, Installation, Testing and Commissioning of additional CCTV cameras to be integrated with existing (BOSCH Make) CCTV Surveillance System installed at Tihar, Rohini and Mandoli Prison Complexes 24/12/2022
23/06/2023
31/12/2023
3483.10
2874.20 (Oct'23)

0.00 (Oct'23)
OPTIMUM SECURITY SOLUTIONS PVT. LTD. Work in progress
Detail Report
Graph / Photo
55 Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works)

3385.59
2858.20 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
56 Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works)

3368.55
678.56 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
57 Construction of Six Storeyed conventional multilevel Parking at Dr. Baba Saheb Ambedkar Hospital at Rohini Sector-6,Delhi.

3266.00

work
Detail Report
Graph / Photo
58 Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. 17/10/2022
16/10/2023
31/12/2023
3000.18
655.60 (Dec'23)
97.00 %
0.00 (Dec'23)
Jai Bhagwan 2nd floor slab casting work for 40 % are in progress, 3rd floor column reinforcement work for 40% area in progress and balance 20% are terrace parapet column casting in progress, brick masonary work at 1st and 2nd floor in progress
2nd floor slab casting work for 40 % are in progress, 3rd floor column reinforcement work for 40% area in progress and balance 20% are terrace parapet column casting in progress, brick masonary work at 1st and 2nd floor in progress
Detail Report
Graph / Photo
59 Construction of DTC Bus Depot in resettlement colony at Sawada Ghevra, Delhi 05/04/2022
04/12/2022
28/02/2024
2915.78
199.30 (Nov'23)
91.00 %
0.00 (Nov'23)
SVK Infrastructures Building Work: RCC work of Admin cum Rest Room is in progress. Reinforcement work of the 4th floor slab has been completed. RCC work and Brickwork of the workshop building has been completed. Hardstanding/CC Pavement: 85% of EarthWork has been completed and 75% of WMM layer work has been completed. Boundary Wall: The work of construction of the boundary has been completed. Finishing work has also been completed Drainage Work: 90% of the drainage work completed. The structure for the underground water tank and septic tank has been completed.
Detail Report
Graph / Photo
60 Providing services of Data Entry / Computer Operators, Personal Secretary, Clerical Staff, Messengers, Messenger cum Peon & Peon for the office of E-in-C, Pr. Chief Engineer (M&F), Chief Engineer (East)-M, Chief Engineer (Flyover) along with its subordinate office, Circle C & ND – M & C & ND-Roads Division, Providing services of security guard for watch and ward for the office of Circle C & ND-M & C&ND-R Division & Watch and Ward of integrated tunnel in and around ITPO. 01/04/2023
31/03/2025
31/03/2025
2892.73
1020.07 (Dec'23)
34.00 %
0.00 (Dec'23)
RAKSHAK SECURITAS PVT. LTD. Work in progress
Detail Report
Graph / Photo
61 Street Scaping of Ring Road from Moolchand Junction to Ashram Chowk

2880.35


Detail Report
Graph / Photo
62 SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW 17/10/2019
12/07/2020
31/12/2023
2849.35
3102.53 (Dec'23)

0.00 (Dec'23)
A. K. Builders work in progress.
work in progress.
Detail Report
Graph / Photo
63 Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work.

2820.52
34.01 (Mar'22)

0.00 (Mar'22)

Detail Report
Graph / Photo
64 Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. 28/06/2019
22/06/2020
15/11/2023
2806.33
581.96 (Nov'23)

0.00 (Nov'23)
Roshan Real Estate Pvt Ltd. Work in progress (98% Progress)
Detail Report
Graph / Photo
65 C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi 12/02/2022
09/11/2022
31/12/2023
2800.59
1979.92 (Nov'23)

0.00 (Nov'23)
SVK Infrastructures Initially site was encroached by local peoples. Encroachment the major part of land has been removed with help of education department and Delhi Police on dated 22.03.2022, but some portion of site is still encroached by local person. Partly site handed over to the agency for boundary wall and building construction on dated 23.03.2022, hence the actual work started from 23.03.2022. . Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. work of swimming pool and MP hall is in progress.
Detail Report
Graph / Photo
66 Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc. 11/10/2022
05/09/2023
10/01/2024
2783.15
687.48 (Dec'23)
100.00 %
0.00 (Dec'23)
DND Infra Private Limit Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Detail Report
Graph / Photo
67 SITC and CAMC of CCTV System in Delhi Govt. Schools. SH- Providing and Maintenance of Internet lease line Connection. 17/08/2019
16/02/2020
30/09/2023
2691.32

Reliance Jio Infocomm Work is in progress and shall be completed along with main work of installation of CCTV camera in Delhi Government School.
Detail Report
Graph / Photo
68 Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi 23/08/2021
22/05/2022
28/02/2024
2373.12
2101.48 (Nov'23)
93.00 %
72.00 % (Nov'23)
M/s PK Gupta & Co.

Building Work: RCC work and Brickwork of Admin cum Rest Room, Toilet Block have been completed. Finishing work completed. Workshop Building-Steel Structural work has started. Hardstanding/CC Pavement: Earth Work has been completed. WMM is in advance stage.Boundary Wall: The work of construction of new boundary wall of approx. 1 Km has almost been completed. Drainage Work: 90% of the drainage work has been completed.The structure for RWH and underground water, septic tank has been completed.


work is in progress

Detail Report
Graph / Photo
69 Uttam Nagar T Point Ram Mandir Marg Mall Rd C1 to C1A Block Rd under Sub Division WR12 Lala Ganesh Das Khatri Marg G-1 Block Vikaspuri Rd Rd No 235 Rd Adjacent to PVR under SubDivision WR13 80 Feet Chowkhandi Rd Shakti Mandir Marg Major Sudesh Marg

2305.99


Detail Report
Graph / Photo
70 Construction of Old Age Home Sector-4, Rohini, Delhi

2240.23


Detail Report
Graph / Photo
71 Improvement and strengthening of Rama Road from Zakhira Crossing to Patel Road including construction of outfall drain 29/10/2012
28/08/2013
2197.33
308.84 (Mar'14)

193.00 % (Mar'14)
N.S.C. Project Pvt. Ltd.
Detail Report
Graph / Photo
72 Construction of Cluster Bus Depot at Kirari Village, Plot No.8 (PSP7), Sector-41, Rohini, Delhi. SH: Civil works and Electrical works. 24/05/2023
23/01/2024
23/01/2024
2107.18
0.00 (Nov'23)
87.00 %
3.00 % (Nov'23)
Kundu Nirma

Preparation of the architectural drawing has been completed. Earthwork and excavation for the boundary wall has started.The building work and boundary wall work is being affected due to high water table. Matter of constructing building and boundary wall on pile foundationis under consideration.


work is in progress

Detail Report
Graph / Photo
73 Widening and Stengthening of Road from Najafgarh Dhansa Road to Jhuljhuli Morh via Ghummanhera Village, Delhi. 08/01/2015
07/11/2015
2057.50

Mahavir Parsad Gupta & Sons Work in Progress
Detail Report
Graph / Photo
74 SITC of Modular Operation Theatre and MOT Integration System and MGPS 05/06/2023
04/03/2034
04/03/2034
1896.47
12.54 (Nov'23)
5.00 %
0.00 (Nov'23)
MDD Medical System (INDIA) Pvt. Ltd

work in progress


work in progress

Detail Report
Graph / Photo
75 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi.

1887.50

18%
In left hand side portion, casting of ground floor slab has been completed and column from 1st floor to 2nd floor has been casted. Rcc in beam at first floor level also completed. Fixing of girds and deck slab is in progress. In right hand side portion casting of column from ground floor slab has been casted and RCC in beam at ground floor slab almost completed.
Detail Report
Graph / Photo
76 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. 24/03/2023
19/09/2023
30/11/2023
1874.71
3.99 (Jan'23)

0.00 (Jan'23)
Demolition of existing Barrack completed. The plinth beam and column upto 2.50 m level for Left hand side portion completed. The excavation of footing and PCC completed for right hand side portion.
Detail Report
Graph / Photo
77 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 31/05/2020
30/05/2021
31/01/2024
1874.70
2236.79 (Dec'23)

0.00 (Dec'23)
SSP Promoters and Builders Private Limited WORK IN PROGRESS
Detail Report
Graph / Photo
78 STREET SCAPING OF 1000 METER OF NELSON MANDELA ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1870.18


Detail Report
Graph / Photo
79 Street Scaping of 800 meter length of Ring Road, Bhairon Road T-Junction to Shantivan Crossing to make it Model Stretch of Street Scaping Project

1859.21


Detail Report
Graph / Photo
80 STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1848.01
947.24 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
81 Construction of Residential Hostel at Chhattrasal Stadium, Model Town, Delhi. SH: C/o Hostel Building including External Development works, Internal Electrical Installation, External Lighting, lifts, fire fighting system, fire alarm with PA System, CCTV, Audio video system, HVAC works 27/02/2023
26/07/2024
26/07/2024
1839.86
285.08 (Oct'23)
57.00 %
0.00 (Oct'23)
KALYAN CHANDRA GOYAL & CO. Work is in progress. Foundation work done. RCC work upto plinth level is completed. Earth filling in footing is in progress.
Detail Report
Graph / Photo
82 Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project

1814.36
0.10 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
83 Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project

1814.36
1368.82 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
84 Balance Civil, Electrical and Horticulture Work as per revised concept

1809.71


Detail Report
Graph / Photo
85 Payment of monthly salaries to work charge staff including other payment relating to salary head like arrear, allowance ec.

1800.00


Detail Report
Graph / Photo
86 Payment of Electricity bills in respect of East Delhi Road Street Light.

1800.00
9.76 (May'19)

0.00 (May'19)

Detail Report
Graph / Photo
87 C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc 01/04/2022
24/02/2023
31/03/2024
1798.93
111.36 (Dec'23)

0.00 (Dec'23)
K. L. ARORA & SON Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Detail Report
Graph / Photo
88 Strengthening of Dev Prakash Shastri Marg (ID: 1255) from T-Point Loha Mandi to Rattan Puri Chowk, Dr. K.S. Krishnan Marg (ID: 216) from Rattan Puri Chowk to Pusa Round about and Girdhari Lal Goswami Marg (ID: 2126) from T- Point Naraina to Shadipur Red Light under Sub Division-III, Division South West Road -1, PWD, New Delhi.

1789.26
448.29 (Nov'23)

0.00 (Nov'23)
work in progress
budget allocations not adequate
Detail Report
Graph / Photo
89 Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi 22/11/2021
17/10/2022
31/01/2024
1773.27
441.49 (Sep'23)

0.00 (Sep'23)
Harbel Singh & Sons - Work in progress. - Girder launched of 4 slabs out of 5 - 4 Nos of slab out of 5 casted. --RE has to be submitted and approval of competent authority is required. Payment of the RA bills can not be made without the same.
Detail Report
Graph / Photo
90 Construction of New Teaching Block in DIET at Daryaganj, New Delhi

1764.30
109.73 (Jun'22)

0.00 (Jun'22)

Detail Report
Graph / Photo
91 C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) 29/12/2018
26/07/2019
15/11/2023
1743.19
4171.43 (Oct'23)

0.00 (Oct'23)
AMAR CONSTRUCTION COMPANY Work in progress
Detail Report
Graph / Photo
92 Construction of Skywalk FOB at Madhuban Chowk (on Outer Ring Road ) connecting Pitampura Metro Station and Rohini court, Delhi.

1736.00

Estimate submitted for obtaining A/A & E/S from competent authority.


Estimate submitted for obtaining A/A & E/S from competent authority.

Detail Report
Graph / Photo
93 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. 24/03/2023
19/09/2023
30/11/2023
1729.05
325.33 (Nov'23)

0.00 (Nov'23)
SPS Infrabuild Pvt. Ltd. work in progress
space constraints on site
Detail Report
Graph / Photo
94 Strengthening of road from Western Yamuna Canal to Bawana under Sub-Division NR-15, North Roads Division, PWD, Delhi(Second Call)

1715.38

15%
null
Detail Report
Graph / Photo
95 Remodelling and Upgradation of existing Blocks for Expantion of Government Hospitals situated in North West District Delhi.S.H. :- Construction of Multi Level Car Parking,Mortuary,ESS for Sanjay Gandhi Memorial Hospital,Mangolpuri,Delhi,

1700.00

work
Detail Report
Graph / Photo
96 Repair and Rehabilitation of ISBT Flyover (Yudhister Setu), Kashmere Gate, Delhi. (SH:Repair and Rehabilitation work). 27/11/2021
26/11/2022
31/12/2023
1677.86
175.15 (Oct'23)
98.00 %
0.00 (Oct'23)

Work in Progress


null

Detail Report
Graph / Photo
97 STREET SCAPING OF 700 METER LENGTH OF K.N. KATJU MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1644.08


Detail Report
Graph / Photo
98 Construction of Hostel for College Going Blind Students (Boys) at Sewa Kutir, Kingsway Camp, Delhi.

1573.00


Detail Report
Graph / Photo
99 C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. 27/03/2023
19/02/2024
30/04/2024
1554.26
602.43 (Dec'23)
74.00 %
0.00 (Dec'23)
SWASTIC CONSTRUCTION CO Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Detail Report
Graph / Photo
100 C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc 26/03/2022
19/02/2023
15/03/2024
1553.88
200.25 (Dec'23)

0.00 (Dec'23)
K L Arora & Son Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Detail Report
Graph / Photo
101 Construction of 66KV GIS Sub station at IGH Dwarka

1549.73
984.49 (Sep'23)

0.00 (Sep'23)

Detail Report
Graph / Photo
102 C/o 72 Nos. Equivalent SPS Class Rooms in addition to boundary wall i/c Internal & External water supply, sanitary installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting System etc. for new school building at GBSSS Jharoda kalan (School ID 1822065) , New Delhi 12/03/2022
06/12/2022
31/12/2023
1542.27
1199.34 (Nov'23)

0.00 (Nov'23)
The Krishna Construction Co. Initially some delay in start of work due to revision of layout and land apportioning between the new school and existing school. Layout plan was finalised by client department on 15.07.2022 and now Structure work completed. Stone work, Exterior Paint, False Celing, SS Railing, Sanitary work is in Progress.
Detail Report
Graph / Photo
103 Construction of New Academic Block (G+3) at DIET Keshavpuram, Delhi

1541.76


Detail Report
Graph / Photo
104 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1524.43


Detail Report
Graph / Photo
105 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1524.43
1488.08 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
106 Interior, furniture and auditorium Civil and electrical work

1512.30


Detail Report
Graph / Photo
107 C/o Cluster Bus Depot at village Gadaipur, District South, Delhi. SH: Civil works and Electrical works. 24/05/2023
23/01/2024
23/01/2024
1500.30
0.00 (Jun'23)
87.00 %
5.00 % (Jun'23)
Kundu Nirman Work just awarded. The site has been handed over to the agency on 30.05.2023. The architectural drawing has been finalised..
Detail Report
Graph / Photo
108 Strengthening of Vandematram Marg from Dhaula Kuan to Dayal Chowk and Shanker Road from Pusa Chowk to Shanker Chowk under PWD Division South West Road-1, Sub Division-IV New Delhi. (Road ID:212 and ID :213).

1494.67
710.30 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
109 Strengthening of G.T. Road (Shahdara Flyover to Dharampura T-point & service lane ) under sub-division M-2111

1491.26

Preliminary Estimate R.I.O. from Circle office vide letter no. 23(Road)/SE Shah./2980 dated 11.07.2019 Letter written to CRRI vide No. 23(QA)/ 4993 dated 16.10.2019 for milling method. Quotation/ Invoice received from CRRI vide letter No. CRRI/FBD/PWD/Shahdara/857 dated 31.10.2019 for Rs.1770000. Fresh estimate to be prepared after receiving of report from CRRI.
Detail Report
Graph / Photo
110 Strengthening of Sri Aurobindo Marg (ID - 96), Ch. Harsukh Marg (ID - 19), and Ch. Jhandu Singh Marg (ID - 13) by cold milling and recycling process under SubDivision-II of Division South Road-II PWD, New Delhi during 2022-23. 19/06/2023
16/09/2023
16/09/2023
1489.16
293.17 (Nov'23)

0.00 (Nov'23)
SBG INFRACON PRIVATE LIMITED Work in Progress
Work in Progress
Detail Report
Graph / Photo
111 STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1480.89
4362.04 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
112 STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT.

1480.89


Detail Report
Graph / Photo
113 Composite Work : C/o Prefab structures office, trainee, staff accommodation, class room, kitchen, store, toilet block, parking shed, road work and other misc. civil work and various Electrical works 01/11/2023
30/04/2024
30/04/2024
1462.98
19.00 %
Kalyan Chandra Goyal & Company
Detail Report
Graph / Photo
114 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24 01/05/2022
30/04/2024
30/04/2024
1462.16
171.38 (Nov'23)
81.00 %
0.00 (Nov'23)
work in porgress
Detail Report
Graph / Photo
115 Interior, furniture and auditorium Civil and electrical work (SW SITC of Audio visual system for Auditorium , Conference Room etc.)

1445.84
5.17 (Mar'22)

0.00 (Mar'22)

Detail Report
Graph / Photo
116 Construction of 48 Nos G plus 3 SPS Eq. classroom including 3 staircase 1 lift and 1 toilet block in Mustafabad School Delhi Including internal and external water supply sanitary installations electrical installations development of site Boundary W 09/03/2023
01/02/2024
30/04/2024
1442.22

Pile casting for 80% area is completed and pile cap casting for 50% area is in progress. Balance 25% area could not start due to space constraints, slow progress due to space scarcity at site.
Pile casting for 80% area is completed and pile cap casting for 50% area is in progress. Balance 25% area could not start due to space constraints, slow progress due to space scarcity at site.
Detail Report
Graph / Photo
117 STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1379.62


Detail Report
Graph / Photo
118 Operation & Maintenance of EI & Fans, HVAC, Sub Stations, DG Sets, UPS, Fire Fighting System, Fire Alarm System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 27/05/2022
26/05/2024
26/05/2024
1369.68
437.72 (Nov'23)

0.00 (Nov'23)
In Progress
Detail Report
Graph / Photo
119 C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc 02/04/2022
25/02/2023
10/03/2024
1359.28
311.42 (Dec'23)

0.00 (Dec'23)
K. L. ARORA & SON Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Detail Report
Graph / Photo
120 Operation & Maintenance of EI & Fans, DG Sets, Fire Engine, HVAC Works, Fire Alarm System, Fire Fighting and Wet Riser System, Sub Station, Solar Water Heating System etc. for the year 2022-23 and 2023-24. 26/05/2022
25/05/2024
25/05/2024
1350.14
302.55 (Oct'23)

0.00 (Oct'23)
In Progress
Detail Report
Graph / Photo
121 Strengthening/Reconstruction of Service Road of Rohtak Road (NH-10) from Metro Pillar No. 410 to 570 Mundka Industrial Area both sides (Actual length of One side 5.00 Km) under PWD, Maintenance Division West Road-2, New Delhi during 2022-23.

1296.54


Detail Report
Graph / Photo
122 Strengthening of S.A. Road under the jurisdiction of Division SER-2/21, New Delhi (Road ID: 946). 14/04/2023
12/07/2023
12/07/2023
1291.28
815.24 (Nov'23)

0.00 (Nov'23)
MAHAVIR PRASAD GUPTA AND SONS 12%
Work in Progress
Detail Report
Graph / Photo
123 Construction of New Academic Block (G+3) at Lakshmibai College, Ashok Vihar, Delhi

1280.15


Detail Report
Graph / Photo
124 Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) 12/03/2022
04/02/2023
31/03/2024
1275.84
752.77 (Nov'23)

0.00 (Nov'23)
M/s SURENDRA KUMAR Work in progress
Detail Report
Graph / Photo
125 Strengthening of roads from (i) Ramdev Chowk Narela to Singhu Border, NH44 (ii) Ramdev Chowk Narela to Piao Maniyari border (iii) Y-Section railway crossing to CRPF camp, under Sub-Division NR-13, PWD Division North Roads, Delhi

1244.87

90% work completed
null
Detail Report
Graph / Photo
126 STREET SCAPING OF 800 METER LENGTH OF RING ROAD, BHAIRON ROAD T-JUNCTION TO SHANTIVAN CROSSING TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1226.77
537.67 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
127 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project

1193.08


Detail Report
Graph / Photo
128 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping projec

1193.08
5024.37 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
129 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project

1193.08


Detail Report
Graph / Photo
130 Construction of NGO's Mess Tahirpur, Dilshad Garden, Delhi. (SH: Civil work, Electrical work and Horticulture work)

1162.30
0.50 (Nov'21)

0.00 (Nov'21)

Detail Report
Graph / Photo
131 Construction & connectivity between Anand Vihar Bus Terminal & Road No. 56 and extension of existing entry & exit of ISBT Terminal over trunk drain No. 2

1143.47

Modified PE submitted to Circle Office vide letter No. 23(5)/679 Dated 05.03.2020
Detail Report
Graph / Photo
132 Strengthening of various roads such as Najafgarh Road, Punjab Garden Road, Smt. Ginni Devi Road, Bhagwan Das Road, Hemwati Nandan Bahuguna Marg, road from Milan Cinema to H. No. 19/289 , Road from House no. H-1 to I-47 near Milan Cinema Karampura and Road from House HIL to bus terminal of 234, HIL Karampura, Lal Sai Mandir Marg D story, Pankaj Batra Marg under PWD Maintenance Division WR-2 / Sub Division WR-21, New Delhi during 2022-23. 28/04/2023
27/08/2023
27/08/2023
1124.92
261.43 (Nov'23)

0.00 (Nov'23)
MIA Construction Pvt. Ltd.
Detail Report
Graph / Photo
133 STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1119.07


Detail Report
Graph / Photo
134 Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi 06/04/2022
05/04/2025
05/04/2025
1099.29
114.42 (Jul'23)
54.00 %
0.00 (Jul'23)
SIKKA ASSOCIATES REGD. 7
Detail Report
Graph / Photo
135 C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) 18/04/2022
13/03/2023
31/03/2024
1090.67
265.77 (Dec'23)

0.00 (Dec'23)
K. L. ARORA & SON Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban.
Detail Report
Graph / Photo
136 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi (Balance Work)

1076.89


Detail Report
Graph / Photo
137 Strengthening of Josip Broz Tito Marg (BRT Road) from Defence Colony Flyover to Chirag Delhi Flyover under PWD Sub-Division SER-11 of Division SER-1. (Road ID No. 1717).

1069.49
1096.61 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
138 C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. 09/03/2023
01/02/2024
30/06/2024
1058.78
345.00 (Dec'23)
82.00 %
0.00 (Dec'23)
AMOCON Pile casting for 80% area is completed and pile cap casting for 80% area is completed, balance area could not start due to space constraints at site. plinth beam casting work in progress for 70% area. Slow progress due to space scarcity at site and constraints approach from main road to site. Since Last one month NGT Ban has implemented due to pollution.
Pile casting for 80% area is completed and pile cap casting for 80% area is completed, balance area could not start due to space constraints at site. plinth beam casting work in progress for 70% area. Slow progress due to space scarcity at site and constraints approach from main road to site. Since Last one month NGT Ban has implemented due to pollution.
Detail Report
Graph / Photo
139 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1041.75


Detail Report
Graph / Photo
140 Operation & Maintenance of EI & Fans, HVAC, DG Sets & Sub Stations, Fire Alarm System, Fire Fighting and Wet Riser System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 26/05/2022
25/05/2024
25/05/2024
1031.52
270.36 (Jun'23)

0.00 (Jun'23)
In Progress
Detail Report
Graph / Photo
141 Construction of Footpath, Improvement of drain widening, strengthening of road from Burari Morh RD 3000 to Amrit Vihar RD 4800 and construction of darin from RD 0.00 at ORR to RD 600 at Sahib Singh polyclinic.

1015.30


Detail Report
Graph / Photo
142 Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi.

988.53


Detail Report
Graph / Photo
143 Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi.

988.53


Detail Report
Graph / Photo
144 C/O OLD AGE HOME AT BG 6 PASCHIM VIHAR DELHI

987.85


Detail Report
Graph / Photo
145 Mechanised House Keeping and Security Services/Facility Management services (FMS) for Chandni Chowk Road and appurtenances/System installed from Lal Jain Mandir to Fatehpuri Mosque for the Period 2022-2023(1 Years) 26/08/2022
25/08/2023
25/08/2023
983.09
694.74 (Nov'23)

0.00 (Nov'23)
Soni Management & Allied Services Pvt. Ltd.
Detail Report
Graph / Photo
146 Providing Automated Housekeeping at Hon’ble CM residence & Bungalow of Delhi Council of Minister’s Delhi.

981.35
170.45 (Sep'23)

0.00 (Sep'23)

Detail Report
Graph / Photo
147 Repair and Rehabilitation of Shahdara Flyover Delhi. (SH: Construction of New Crash Barrier and Strengthening of edge beam after dismantling of old crash barrier) 12/03/2023
11/11/2023
11/11/2023
971.06
70.15 (Nov'23)
100.00 %
0.00 (Nov'23)

Work in Progress


null

Detail Report
Graph / Photo
148 Providing services of various category of Outsourced staff in various office under Flyover Zone, PWD, New Delhi, New Delhi

970.31


Detail Report
Graph / Photo
149 Repair and Rehabilitation of 10 Nos. Bridges- Timarpur Crossing (2 nos.), Mall Road Crossing, Maurice Nagar (2 Nos.), Gurmandi (Vijay Nagar Crossing), GT Road Crossing near Shakti Nagar (2 Nos.) and Bharat Nagar (2 Nos.) over Najafgarh Drain, Delhi.

964.90


Detail Report
Graph / Photo
150 Strengthening of various roads under PWD Division North West Road-1 under Sub Division NWR-12 During 2022-23

954.00

work completed
Nil
Detail Report
Graph / Photo
151 Strengthening of Nangloi-Najafgarh Road from Nilothi Mor to Airforce Bani Camp under WR-14, PWD New Delhi

953.94
671.44 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
152 Operation of E.I. and Fans, Pumps, Automatic Fire Fighting system, Fire Alarm system

951.12


Detail Report
Graph / Photo
153 Comprehensive Maintenance of Electrical, Civil & Horticulture Operations relating Day to day Maintenance, Special Repair etc of Ch. Brahm Prakash Auyrved Charak Sansthan, Khera Dabar, Najafgarh, Delhi during 2022-23 & 2023-24

950.40
43.91 (Dec'22)

0.00 (Dec'22)

Detail Report
Graph / Photo
154 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12

940.18

work is in progress


null
Detail Report
Graph / Photo
155 Improvement & strengthening of Road No. 63, Delhi (From Bhopura Border to loni Gol Chakkar except flyover).

935.18
38.95 (Mar'22)

0.00 (Mar'22)
A/A & E/S awaited
Detail Report
Graph / Photo
156 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi

935.00
15.80 (Feb'23)

0.00 (Feb'23)

Detail Report
Graph / Photo
157 Construction of FoB/Skywalk from Supreme Court Metro Station to Additional Building Supreme Court and Supreme Court Main Campus on Mathura Road, New Delhi 16/07/2022
16/01/2023
31/08/2023
926.03

Work in progress
NA
Detail Report
Graph / Photo
158 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi.(Balance Work)

919.83
939.93 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
159 STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

910.96
508.81 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
160 Running operation of lifts 06/05/2021
05/05/2024
05/05/2024
909.76
119.85 (Nov'23)
84.00 %
0.00 (Nov'23)
Guruji Elevator
Detail Report
Graph / Photo
161 Comprehensive Maintenance of Electrical, Civil & Horticulture Operations relating Day to day Maintenance, Special Repair etc of Ch. Brahm Prakash Ayurved Charak Sansthan, Khera Dabar, Najafgarh, Delhi during 2022-23 & 2023-24 (Balance works).

906.11
49.34 (Jun'23)

0.00 (Jun'23)

Detail Report
Graph / Photo
162 Construction of Police Post at Bakkarwala

900.00
147.82 (Aug'23)

0.00 (Aug'23)

Detail Report
Graph / Photo
163 C/o 40 Nos. equivalent Additional SPS Class rooms, Libraries, Toilets & Labs etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at Sarvodaya Vidyalaya, Mansarover Garden New Delhi (School ID - 1516003) (Civil work & Electrical Work )

897.31

Work Awarded
Detail Report
Graph / Photo
164 Strengthening of various roads under sub division NWR-24, Division NWR-2, SainikVihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW

880.22
721.84 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
165 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc. of Lal Bahadur Shastri Hospital Campus Khichripur, Delhi, Jag Pravesh Chandra Hospital, Campus Shastri Park Delhi and Chacha Nehru Bal Chikitsalya, Hospital, Campus, Geeta Colony, DGD-12/113, Geeta Colony, DGD, New Lahore, Shastri Nagar, Delhi during 2022-23 and 2023-24 14/05/2022
13/05/2024
13/05/2024
874.44
0.00 (Jul'23)
81.00 %
54.00 % (Jul'23)
Work is in progress.
nil
Detail Report
Graph / Photo
166 Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi. (Civil and Electrical Work)

871.75


Detail Report
Graph / Photo
167 Strengthening of road at Dev Parkash Shastri Marg under PWD Sub Division-III, S.W.R-I, New Delhi

871.07


Detail Report
Graph / Photo
168 Operation and Maintenance of EI and FANS Sub Station and DG Set HVAC Works Fire Fighting and Wet Riser System Fire Alarm System Lifts RO Plant etc

866.40


Detail Report
Graph / Photo
169 Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) 17/09/2022
15/12/2022
15/12/2022
861.04
653.41 (May'23)

0.00 (May'23)
Invalid
Detail Report
Graph / Photo
170 Repair and Rehabilitation of Gokul Puri Flyover Delhi. (SH: Replacement of Bearings and Expansion joint and repair of Bearing Pedestal). (Recall) 07/10/2022
12/01/2023
31/12/2023
859.23
67.22 (Oct'23)
97.00 %
0.00 (Oct'23)

Work in Progress


null

Detail Report
Graph / Photo
171 Two fixed single court and one doubles court with movable wall and SITC of EI, VRF, CCTV, LAN System, Fire Fighting System, Fire Alarm System & Signage Board) (Civil and Electrical work.

847.08


Detail Report
Graph / Photo
172 Operation & Maintenance of EI & FANS, Sub Station & DG Set, HVAC Works , Firen Fighting and Wet Riser System, Fire Alarm System, Lifts, RO Plant etc.

843.88


Detail Report
Graph / Photo
173 Operation of lifts

834.91


Detail Report
Graph / Photo
174 Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc

831.74


Detail Report
Graph / Photo
175 C/o Pucca School Building at Mandawali Fazalpur (I.P Extn) Delhi. 09/03/2012
08/06/2013
08/06/2013
827.32
935.50 (Apr'14)

100.00 % (Apr'14)
PNSC Infrastructure Pvt. Ltd.
Detail Report
Graph / Photo
176 Construction of Police Post Sadiq Nagar, New Delhi during 2020-21 (SH: Civil and Electrical work).

824.93
313.04 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
177 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). 30/09/2022
29/03/2023
29/03/2023
818.33
961.63 (Nov'23)

0.00 (Nov'23)
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
178 Strengthening of various road under North Roads, Division, Sub-Division NR-14, Shaheed Captain Vikram Batra Chowk PWD, New Delhi. 1. Mam Chand Dhaniya Marg from Old GTK Road to Siraspur Village 2. ITI Road at Jahangirpuri from Main Road to Metro Apartment & K-Block from Metro Apartment to dividing road K-Block.3. C-D Park Road from Main Road Jahangirpuri to Kushal Cinema Road. 4. I-Block Road & JBlock Road from Main Road Jahangirpuri to G.T. Road at Jahangirpuri.

804.85

work is in progress


null
Detail Report
Graph / Photo
179 Strengthening of various roads of Pitampura area under PWD Division North West Road-1 and under Sub Division NWR-14 During 2022-23

802.14
54.00 (Nov'23)

0.00 (Nov'23)
work in progress
DJB work at Gopal mandir marg not completed
Detail Report
Graph / Photo
180 Police Post Rampura Golden Park

798.00
148.18 (Jun'23)

0.00 (Jun'23)

Detail Report
Graph / Photo
181 Comprehensive Maintenance & Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical & Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

793.37


Detail Report
Graph / Photo
182 Comprehensive Maintenance & Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical & Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

793.37
938.94 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
183 Comprehensive Maintenance ,Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical ,Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

793.37


Detail Report
Graph / Photo
184 Strengthening of Road No. 235, Guru Virjanand Marg, Road between Jupiter Appt. to Priya Appt., Nalanda Appt. to Nightingale Appt., Navyug Appt. to IFC drain (Brotherhood Appt.), Road between Devdoot Appt. to Parmarth Appt., Road between Kirti Appt. to DAV school, Road between Lok Vihar Appt. (PWD Road) to F-block Market, Road Sunrise Appt. to DAV School, Road from F-234 to IFC drain (Over head tank) Vikaspuri, Road from ITICorner to Central School, Road starting from Oxford School to Airport Appt. and Road No. 236 at Vikaspuri under sub division WR-14, Division WR-1

790.08
638.21 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
185 Anticarbonation painting with designing and theme painting work on Britannia flyover, Wazirpur Flyover and Shalimar Bagh Elevated Flyover on Ring Road and Elevated Flyover from Mukarba Chowk to Mangolpuri Flyover on Outer Ring Road.

787.93


Detail Report
Graph / Photo
186 Strengthening of Road No.40 (Vir Banda Bairagi Marg) from Zakhira Pump House to Metro Pillar No.100 under PWD Division North West Road-1 under Sub Division NWR-13 During 2023-24.

774.14
27.00 (Nov'23)

0.00 (Nov'23)
work in progress
Nil
Detail Report
Graph / Photo
187 Addition Alternation in Residence of Honble Chief Minister at 6 Flag Road, Civil Lines, Delhi during 2020 21 (SH:Providing additional Accommodation Civil and Electrical works)

761.07
2926.01 (Oct'23)

0.00 (Oct'23)

Detail Report
Graph / Photo
188 Strengthening of Mall Road Extension from Azadpur H Point to Sanjay Enclave (GTK Depot) under Sub Division NR-12, North Roads Division, PWD, Delhi.

760.48

60%
null
Detail Report
Graph / Photo
189 Operation & Maintenance of E.I, pumps, sub-station, DG Sets, firefighting & fire alarm system, HVAC & AC units & R.O. Plant etc 24/05/2022
23/05/2024
23/05/2024
754.12
176.52 (Nov'23)
81.00 %
0.00 (Nov'23)
SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD.
Detail Report
Graph / Photo
190 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi 14/07/2022
13/10/2022
13/10/2022
751.50

Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
191 Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054 15/12/2021
14/06/2022
31/07/2023
747.65
289.55 (Oct'23)

0.00 (Oct'23)
Work In Progress. Site available in Parts.
Detail Report
Graph / Photo
192 Comprehensive Maintenance of Civil works relating Day to day Maintenance, Annual Repair, Special Repair and routine maintenance work etc. of Deep Chand Bandhu Hospital, Ashok Vihar, Phase-IV, Delhi, Babu Jagjivan Ram Hospital, Jahangirpuri, Delhi, Attar Sain Jain Eye Hospital, various dispensaries at Jahangirpuri, Delhi and Bhagwan Mahavir Hospital, Pitampura, Delhi during 2022-23 and 2023-24 06/06/2022
05/06/2024
05/06/2024
741.51
65.08 (Nov'23)
76.00 %
0.00 (Nov'23)
Dilshad Khan Work in Progress Deep Chand Bandhu 61% Progress, For BJRM 67% Progress, For Bhagwan Mahavir 51% Progress
Detail Report
Graph / Photo
193 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 03/06/2022
02/06/2024
02/06/2024
721.25
85.29 (Nov'23)
76.00 %
0.00 (Nov'23)
AZFARUDDIN Work in progress.
Detail Report
Graph / Photo
194 Strengthening of various roads (SGH Road, Kalamandir Cinema Road, LP Road, B Block and G/F Block Road - Mangolpuri, H Block Road and G Block Road - Sultanpuri, Road No. A2 sector 1/2 - Rohini) having ROW<30 meter under sub division NWR-21, Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23 and 2023-24.

714.93


Detail Report
Graph / Photo
195 Construction of Police Post Mianwali Nagar

714.00
118.89 (Oct'23)

0.00 (Oct'23)

Detail Report
Graph / Photo
196 Replacement of chillers installed at Delhi Secretariat Building

700.00


Detail Report
Graph / Photo
197 Construction of Police Post Paschimpuri (now Sayyad village at Nangloi)

700.00
138.00 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
198 Strengthening of various roads (Road No. 318, Road No. 319, Sir Chhotu Ram Ram Marg-A3 Road, N.S. Hardikar Marg-A1 Road) under Sub Division NW R-21, Division NW R-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling.

686.56
193.81 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
199 Providing and installing factory made Customized Galvanized Steel Sheet Modular Kitchen Cabinets and civil work at ‘A, B, C & D’ block of Judges Quarters, District Court Residential Complex, Saket, New Delhi.

684.19


Detail Report
Graph / Photo
200 Comprehensive maintenance of Civil services at Deen Dayal Upadhyaya Hospital & Residential Complex, Hari Nagar, Janakpuri Superspeciality Hospital C2B Janakpuri New Delhi, Shree Dada Dev Matri avum Shishu Chikitsalya, Dabri and DG at various places, P.W.D (GNCTD), New Delhi for 2 years i.e. 2022-2023, 2023-24 27/05/2022
26/05/2024
26/05/2024
683.47
63.79 (Oct'23)
81.00 %
0.00 (Oct'23)
Anand and Company

Work in Progress


Detail Report
Graph / Photo
201 Re laying of World Athletics approved 400 Mtr. synthetic athletic track at Chhatrasal Stadium, Delhi 26/03/2022
24/07/2022
24/07/2022
679.06
656.95 (Apr'23)

0.00 (Apr'23)
ADVANCED SPORT TECHNOLOGIES LLP Work in progress
Work in progress
Detail Report
Graph / Photo
202 Operation, Routine Maintenance and special repair of various Electrical & Mechanical installations at Delhi High Court, New Delhi

675.71
146.08 (Jul'23)

0.00 (Jul'23)

Detail Report
Graph / Photo
203 Operation, Routine Maintenance and special repair of various Electrical & Mechanical installations at Delhi High Court, New Delhi

675.71
89.84 (Feb'23)

0.00 (Feb'23)

Detail Report
Graph / Photo
204 Improvement of drainage system and C016-17/o sump well near 52 cusec drain at Mandoli Road, Shahdara Delhi. Agmt. No. 154/EE/2016-17 30/12/2016
29/10/2017
31/07/2020
671.15
127.12 (Aug'20)

0.00 (Aug'20)
Thruogh H/R on account of advance payment against 6th R/A bill Rs. 95 lac. Vide C.V. No. 61 Dated 31.03.2020
Detail Report
Graph / Photo
205 Construction of Old Age Home including electrical work at BG-6, Paschim Vihar, Delhi. (Composite work).

668.69

Work is held up for Architectural Plan & revised plan submitted to fire department for approval by SA


Detail Report
Graph / Photo
206 Repair and Rehabilitation of Vikas Marg Flyover & Ashram Chawk Flyover Delhi. (SH: Repair of Spalled and Honeycomb Concrete, RCC Jacketing of Piers, Carbon Fiber wrapping of Pier Cap, Replacement of Expansion joint, Repair of Bearing Pedestal and Maintenance of bearing) 26/03/2023
25/09/2023
25/09/2023
666.76
105.68 (Oct'23)

0.00 (Oct'23)

Work in Progress


null

Detail Report
Graph / Photo
207 Comprehensive Maintenance , Operation of Multi Level underground automated car parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

661.38
604.53 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
208 Supplying, Installation, Testing and Commissioning of Audio Video System 10/06/2022
07/10/2022
15/12/2023
660.62
1033.83 (Oct'23)

0.00 (Oct'23)
Installation of Audio Video System and other accessories completed. Testing and commissioning and handing over in progress.
Detail Report
Graph / Photo
209 Remodeling of drain from 25 futa road, Meet nagar to Loni Gole Chakkar at Road No.-63, Construction of sump well at loni Gole Chakkar & MIG/ LIG Flat, Providing and laying K-9 pipe from Loni gole Chakkar to Drain No-01 & Construction of pump House, Electrical & mechanical Services at Loni Gole Chakkar & MIG/ LIG Flat. 31/03/2022
28/07/2022
28/07/2022
657.45
352.61 (May'23)

0.00 (May'23)
K. L. ARORA & SON work is in progress
BSES HT Line shifting
Detail Report
Graph / Photo
210 Providing Automated Housekeeping at Honble CM Residence and Bungalow of Delhi Council of Ministers Delhi

649.40
662.63 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
211 ARMO Various Electrical and Mechanical services at District Court Rohini, Delhi. 05/09/2023
04/09/2025
04/09/2025
646.46
12.00 %
Anand and Company
Detail Report
Graph / Photo
212 Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi 28/04/2022
24/10/2022
24/10/2022
643.92
552.30 (Jun'23)

0.00 (Jun'23)
Kundu Nirma

work is in progress


null
Detail Report
Graph / Photo
213 Strengthening of DDU Marg, JLN Marg & NS Marg under Sub Division-2/Division SRDP-I dg. 2022-23 05/01/2023
19/02/2023
19/02/2023
638.88
150.00 (Nov'23)

0.00 (Nov'23)
ROAD TECH
Detail Report
Graph / Photo
214 Construction of Police Post Sector - 21 & 23 Rohini.

634.43


Detail Report
Graph / Photo
215 Remodelling of drain from PTS to IIT Both Side of Road on Sri Aurobindo Marg (ID -96) under Sub Division-II of Division South Road-II, New Delhi during 2022-23. (2nd Call). 25/03/2023
24/07/2023
24/07/2023
631.30
307.00 (Nov'23)

0.00 (Nov'23)
Mangat Ram Gupta work is in progress
Work is to be done on road carriageways at 2-3 critical locations for effectively removal of water logging issue.
Detail Report
Graph / Photo
216 E & M works relating to day to day operation & maintenance, A/R & M/O Works & Special Repair Works 26/05/2022
25/05/2024
25/05/2024
619.38
313.75 (Nov'23)
81.00 %
0.00 (Nov'23)
H. N. TRADERS & ENGINEERS

Work in progress


Work in progress

Detail Report
Graph / Photo
217 Resurfacing of roads from (i) Lampur Mor to Lampur Border, (ii) Ramdev Chowk to Railway crossing Narela, (iii) Y-section Narela to Shahpur Garhi Turn, under Sub-Division NR-13, North Roads Division, PWD, Delhi 20/03/2022
17/07/2022
17/07/2022
617.72
347.72 (Aug'23)

0.00 (Aug'23)
Sethi Construction

work is in progress


null
Detail Report
Graph / Photo
218 Civil and Electrical Work. 05/03/2023
29/11/2023
29/11/2023
617.03
20.90 (Nov'23)
100.00 %
0.00 (Nov'23)
CHANDRA CONSTRUCTION COMPANY
Detail Report
Graph / Photo
219 Making Building and Campus Barrier Free for accessibility of disabled persons CWDS.

614.92
5.08 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
220 Making Building and Campus Barrier Free for accessibility of disabled persons CWDS.

614.92


Detail Report
Graph / Photo
221 Repair and Rehabilitation of Tilak Nagar District Center Flyover, Tilak Nagar Near Metro Flyover & Punjabi Bagh Flyover (SH: Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joint, Repair of Bearing Pedestal, Replacement of Elastromeric Bearings, Maintenance of POT-PTFE Bearing and Installation of Height Barrier) 26/05/2023
25/01/2024
25/01/2024
612.17
87.00 %

Due to Grap restriction work stopped at site.


Due to Grap restriction work stopped at site.

Detail Report
Graph / Photo
222 Construction of RCC drain from NH-24 Ghazipur Dairy Farm to Kondli Bridge Shamshan Ghat Road

609.62

Work in progress


null
Detail Report
Graph / Photo
223 Comprehensive routine maintenance and operation of EI and Fans compound lights High Masts, Lifts, pumps, Fire Fighting System, AFA and PA system, HVAC plant, RO Plant and water softening plant, water coolers and substation DG sets at District Court Dwarka New Delhi 26/07/2022
25/07/2024
25/07/2024
600.77
103.74 (Nov'23)
72.00 %
0.00 (Nov'23)
Swastik Electrotech Pvt. Ltd.
Detail Report
Graph / Photo
224 Upgradation of one staff room, each at 951 School under Delhi Govt. SH 123 Nos. of staff rooms under West Maintenance Circle.

593.40
156.62 (Oct'22)

0.00 (Oct'22)

Detail Report
Graph / Photo
225 Structural Work. 21/02/2012
20/10/2012
30/11/2012
588.19

Rama Const. Co.
Detail Report
Graph / Photo
226 Strengthening of various roads of Sector-11 & Rama Road under sub division NWR-22, Rohini, Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23

587.47
395.43 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
227 Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB 25/09/2022
24/01/2023
24/01/2023
583.83
150.00 (Nov'23)

0.00 (Nov'23)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
228 Providing stone Matrix Asphalt(SMA) under Sub Division-II, South West Road-II Najafgarh, New Delhi 23/11/2021
21/01/2022
21/01/2022
581.89
320.63 (Mar'23)

0.00 (Mar'23)
Pawan Kumar
Detail Report
Graph / Photo
229 Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work 28/01/2022
27/12/2022
31/08/2023
579.95
650.97 (Nov'23)

0.00 (Nov'23)
Invalid Work is in progress.
Detail Report
Graph / Photo
230 Strengthening of Ring Road from I.P. Flyover to Raj Ghat Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi during 2022-23. 02/06/2023
01/08/2023
01/08/2023
579.40
405.00 (Nov'23)

0.00 (Nov'23)
MAHAVIR PRASAD GUPTA AND SONS Work in Progress.
Detail Report
Graph / Photo
231 Strengthening of various roads such as prof. Joginder Singh Marg Major Deepak Tyagi Marg Lal Sai Marg 60 Futa Road Possangi Pur Road A 1 Block Main Road Opp A 1 Block Main Road and Asalat Pur Road 1 under Sub Division WR 12 Division WR-1 PWD New Delh 25/09/2022
24/01/2023
24/01/2023
578.76
716.73 (Nov'23)

0.00 (Nov'23)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
232 Strengthening of Najafgarh Jharoda Road ic raising of depressed road at Ekta Vihar under Sub Division II South West Road II PWD New Delhi. ID 1231 16/10/2019
12/02/2020
12/02/2020
567.80
236.37 (Jul'20)

0.00 (Jul'20)
Pawan Kumar WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
233 Repair and Rehabilitation of Africa Avenue Flyover, Moti Bagh Flyover, Savitri Cinema & IIT Flyover, Delhi. (SH: Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joint, Maintenance of bearing and Installation of Height Barrier & Seismic Arrester) 26/05/2023
25/01/2024
25/01/2024
566.13
87.00 %
Work in Progress
null
Detail Report
Graph / Photo
234 Construction of Inter-connecting RCC box type storm water drain between JhaitkaraMorh via Chhawla Village to IandFC Najafgarh drain, NajafgarhBijwasan Road (ID 1173) under PWD Division SWR-II, New Delhi. 17/03/2023
12/09/2023
12/09/2023
564.26
129.53 (Nov'23)

0.00 (Nov'23)
Rajan Builders
Detail Report
Graph / Photo
235 Strengthening / Resurfacing of (1) Road No. 70, (2) Road 62, (3) Road from Seemapuri Bus depot Road no. 70 to GTB Hospital Road (Gurudwara road), (4) Road from Labour chowk (Seemapuri link road) to General Hospital Road no. 64 (Divider Road), (5) Road from Rajiv Gandhi Super Specialty Hospital to GTB Hospital Road. 26/01/2023
25/05/2023
25/05/2023
554.25
50.00 (Jun'23)

0.00 (Jun'23)
Kundu Nirman
Detail Report
Graph / Photo
236 C/o Police Post at Preet Vihar, Delhi.

552.89
0.78 (Mar'22)

0.00 (Mar'22)

Detail Report
Graph / Photo
237 Renovation / Upgradation of one room for Teachers Training at 5 nos. school under NWB-2, Delhi. SH: Civil Work

552.73


Detail Report
Graph / Photo
238 Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW 27/02/2022
26/06/2022
26/06/2022
548.07
565.02 (Nov'23)

0.00 (Nov'23)
RK Brothers
Detail Report
Graph / Photo
239 Strengthening of Kalyanvas road and LBS Hospital road and improvement of footpath and adjoing area.

545.60

Work in progress


null
Detail Report
Graph / Photo
240 Providing services of Maintenance vehicle with labour & T&P etc. for all Sub-Division for two year

542.39


Detail Report
Graph / Photo
241 RMO Electrical and Mechanical services installed at Delhi Sachivalya, New Delhi. (SH Maintenance and Operation of E and M services at Delhi Sachivalaya, New Delhi) 13/07/2017
12/07/2020
540.00

Swastik Electrotech Pvt. Ltd.
Detail Report
Graph / Photo
242 Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. 02/11/2018
01/11/2019
01/11/2019
539.98
214.77 (Sep'19)

0.00 (Sep'19)
Work in progress
No
Detail Report
Graph / Photo
243 SITC of structure cabling and CCTV System at District Court Rohini, Delhi

538.56


Detail Report
Graph / Photo
244 Improvement of footpath & Strengthening of road from Chandgi Ram Akhara Red Light to Timarpur Red Light Crossing under Sub Division-4,C&ND-R, New Delhi dg 2023-24. 10/06/2023
09/08/2023
09/08/2023
536.55
97.50 (Nov'23)

0.00 (Nov'23)
Sethi Construction Work in Progress.
Detail Report
Graph / Photo
245 Strengthening of Anuvrat Marg (ID-1198) through cold milling and recycling process under Sub-Division-3 of Division South Road-2 PWD, New Delhi. 19/04/2023
18/08/2023
18/08/2023
536.44
342.00 (Nov'23)

0.00 (Nov'23)
R K Brothers & Company Work in progress. ( Delayed due to unexpected rain in May and traffic police permission also received on dated 25.05.2023.)
Work in progress. ( Delayed due to unexpected rain in May and traffic police permission also received on dated 25.05.2023.)
Detail Report
Graph / Photo
246 Construction of Police Post at Sanjay Gandhi Transport Nagar, Delhi.

536.00

.
Detail Report
Graph / Photo
247 Civil work comprehensive maintenance of Shanker Road and Vandematram Marg including carriageway, footpaths, central verge, Service road etc within the right...

535.97


Detail Report
Graph / Photo
248 Renovation / construction works at Rajiv Gandhi Stadium, Bawana 07/07/2022
04/11/2022
04/11/2022
535.01
172.50 (Oct'23)

0.00 (Oct'23)
M/s Vinod Kumar & Company Work in progress
Work in progress
Detail Report
Graph / Photo
249 Providing services of Maintenance vehicle with labour and T and P etc for Division NW R 1 for two year

533.23
42.86 (Apr'23)

0.00 (Apr'23)
work completed on dated 6/11/23
nil
Detail Report
Graph / Photo
250 CIVIL Works - Comprehensive maintenance of various roads i/c carriageway, footpaths, central verge within right of way, mechanised desilting of drains etc and other mi

533.12


Detail Report
Graph / Photo
251 Development of Sports infrastructure in govt. Co-ed. Senior Secondary School, Najafgarh Dhansa Road, Mitraon Village (ID No.1822178), Najafgarh, Delhi.

532.93

Financial Bid opened on 01.09.2023 and sent to PM(Hr. Edu.Proj.) for approval
Detail Report
Graph / Photo
252 Widening of carriageway including shifting of central verge and footpath of Outer Ring Road from Majnu ka Tila Red Light to Wazirabad Flyover (Under 77 corridor improvement plan) in Division C&ND-R New Delhi dg. 2022-23 08/11/2022
07/03/2023
31/08/2023
532.40

AMOCON Work in Progress.
Detail Report
Graph / Photo
253 Strengthening of Main Burari Road from BurariMorh to Outer Ring Road and Outer Ring Road to upto Bengali Colony Culvert under jurisdiction of Sub Division-1, C&ND-Road Division Delhi.

525.02


Detail Report
Graph / Photo
254 Improvement and reconstruction of footpath on various roads (Mathura Road, Bhairon Marg and Ring Road under Division M-321, Delhi on urgent basis in view of G-20 SUMMIT 2023. 12/02/2023
14/04/2023
14/04/2023
518.84
123.07 (Nov'23)

0.00 (Nov'23)
In-progress
Detail Report
Graph / Photo
255 Strengthening/Raising of Road to prevent Water Logging on the Road Deenpur to Kachha Talab and Tazpur mod to police check post at goyala deenpur Road (ID 1168) under Sub Division-V, South West Road-II, PWD New Delhi. 28/03/2023
25/06/2023
25/06/2023
517.09
368.00 (Nov'23)

0.00 (Nov'23)
Mahavir Prasad Gupta & Sons
Detail Report
Graph / Photo
256 Strengthening of various roads of Sector-3,5,6 & 7 under sub division NWR22, Rohini, Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23

513.31
472.82 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
257 Repair & Rehabilitation of facade and other RCC members i/c water tank and water proofing of terrace of Vyaapar Bhawan, Deptt of Trade & Taxes Building, I. P Estate, New Delhi.

500.66


Detail Report
Graph / Photo
258 Repair & Rehabilitation of facade and other RCC members i/c water tank and water proofing of terrace of Vyaapar Bhawan, Deptt of Trade & Taxes Building, I. P Estate, New Delhi .

500.66
0.20 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
259 Strengthening of Mehrauli-Mahipalpur Bypass Road (Road Id: 2140) from NH-8 to CPWD Flyover.

492.92


Detail Report
Graph / Photo
260 Maintenance and Operation of various Electrical Installations.

491.77
16.90 (Dec'23)

0.00 (Dec'23)

Detail Report
Graph / Photo
261 Construction of Two No. Foot Over Bridge across Sri Aurobindo Marg (ID-96) at (i) PTS Bus Stop (ii) T.B. Hospital with staircase and lift including Electrical Installations under Sub Division-II of Division South Road-II, PWD New Delhi. 21/03/2020
20/09/2020
20/09/2020
489.85
255.38 (Nov'22)

0.00 (Nov'22)
S S Chauhan & Sons Work in Progress.
Work in Progress.
Detail Report
Graph / Photo
262 Construction of Two No Foot Over Bridge across (i)Sri Aurobindo Marg (ID-96) at Adhchini Village (ii) Hauz Khas Enclave (Near Padmini Enclave) with staircase and lift including Electrical Installation under Sub Division-II of Division South Road-II 21/03/2020
20/09/2020
20/09/2020
489.30
335.56 (Nov'22)

0.00 (Nov'22)
S S Chauhan & Sons Work in Progress.
Work in Progress.
Detail Report
Graph / Photo
263 Construction of Police Post Sawada Ghevra B Block Colony Delhi

487.01


Detail Report
Graph / Photo
264 Running and Maintenance of lifts installed in residential and non-residential buildings at GTB Hospital complex, Shahdara, Delhi Sub Head Running operation of lifts 17/01/2019
16/01/2021
16/01/2021
485.43
103.10 (Oct'23)

0.00 (Oct'23)
Guruji Elevator Work in progress 3RD RA 40220380
Detail Report
Graph / Photo
265 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 06/08/2022
03/12/2022
03/12/2022
484.07
356.26 (Nov'23)

0.00 (Nov'23)
Invalid

work is in progress


null
Detail Report
Graph / Photo
266 Nazafgarh Road to A-71, Rajauri Garden, A-31 Rajauri Garden, 20-Block Tilak Vihar Road, Radhaswami Satsang Marg and Tilak Nagar Main Market Road under PWD Division WR-1, New Delhi.

481.51


Detail Report
Graph / Photo
267 Resurfacing of various roads under PWD North West Road-2 Division during 2016-17.

477.75


Detail Report
Graph / Photo
268 Renovation of 64 Nos. Toilets of Lawyers Chamber Block D E F and G at Karkardooma Court Delhi dg. 2023 24 (Civil and Electrical Work).

477.50

dismantling and removal of malba is on progress
dismantling is on progress
Detail Report
Graph / Photo
269 (1) Operation, Routine, Preventive and Comprehensive Maintenance of upto and including 100 HP pump sets at various locations under PWD EMSD SW- II, Najafgarh, for clearing storm water drain & dewatering of PWD Roads of South West Delhi. (2) Operation, Routine, Preventive and Comprehensive Maintenance of upto and including 100 HP pump sets at various locations under PWD EMSD SW- III, R K Puram, for clearing storm water drain & dewatering of PWD Roads of South West Delhi.

475.35
87.78 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
270 Supply, Installation, Testing and Commissioning of Mike Based Communication System for Court Rooms at Saket Court Complex, New Delhi

472.59
417.19 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
271 Supply, Installation, Testing and Commissioning of Mike Based Communication System for Court Rooms at Saket Court Complex, New Delhi

472.59


Detail Report
Graph / Photo
272 Civil & Electrical Works.

471.61

steel erection work is in progress
work delayed due to existing service coming in layout
Detail Report
Graph / Photo
273 Construction of Foot Over Bridge with staircase and lift for padestrian at Rao Tula Ram Marg (Road ID-98) near Petrol Pump, New Delhi.

465.11


Detail Report
Graph / Photo
274 Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone

460.45

work in progress in parts.
All locations not decided by client Department. Hence full site not available.
Detail Report
Graph / Photo
275 Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone

460.45


Detail Report
Graph / Photo
276 Providing and installation of informatory directional sign boards on various roads under Division NWR1 and NWR2 for DSEU Campus Ashok Vihar DSEU Campus Pitampura DSEU Campus Rohini DSEU

460.45


Detail Report
Graph / Photo
277 Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc. 04/06/2022
03/06/2024
03/06/2024
457.53
80.00 (Oct'23)
76.00 %
0.00 (Oct'23)
M/s Jain Electric Works
Detail Report
Graph / Photo
278 Rehabilitation and strengthening of Janak Setu Flyover in New Delhi (Balance Work) 29/03/2020
29/09/2020
31/03/2021
457.44
88.68 (Aug'23)

0.00 (Aug'23)

Work in progress


null
Detail Report
Graph / Photo
279 Maintenance of E and M Services in Underpasses / RUB’s, Subways, FOB’s, Drains, Fountains and Lifts. 2. Maintenance of Street Lights.

450.40


Detail Report
Graph / Photo
280 Construction of approach roads for RUB (North side) along with ROB at Meet Nagar on Road No. 63.

450.13

A/A & E/S awaited
Detail Report
Graph / Photo
281 SITC of structure cabling and CCTV System at District Court Rohini, Delhi 06/03/2023
05/09/2023
05/09/2023
449.96
46.47 (Oct'23)

0.00 (Oct'23)
TIRUPATI CONSTRUCTION COMPANY First RA Bill Rs. 2390388/- dt. 08.08.2023
Detail Report
Graph / Photo
282 Improvement of Karawal Nagar Road from Wazirabad Road (Near Bhajanpura Mazaar) to Dayalpur Chowk( Length of Road- 1.75Km)

449.01

A/A & E/S awaited
Detail Report
Graph / Photo
283 Civil Works - Mechanised Sweeping and Cleaning of Roads including Carriageway, Footpaths, Central Verge, Service Roads etc. within the right of way, Mechanised Desilting

448.15


Detail Report
Graph / Photo
284 Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24 05/11/2022
04/11/2024
04/11/2024
445.82
30.70 (Nov'23)
55.00 %
0.00 (Nov'23)
work in progress, as per complaint received in sub division, the regular day to day compliance is made.
nil
Detail Report
Graph / Photo
285 Routine maintenance and operation of EI and fans Compound Lights High Masts Lifts Pumps Fire Fighting System AFA and PA system Sub Station and DG set and 4 x 400 TR Central HVAC Plant at Delhi Judicial Academy and National Law University at Sector 14 06/03/2023
05/03/2026
05/03/2026
443.54
90.91 (Nov'23)
24.00 %
0.00 (Nov'23)
GLOBAL ENTERPRISES
Detail Report
Graph / Photo
286 Remodelling of drain from 5th Pusta to Ghonda Chowk at Gamri Road Delhi.

440.84

A/A & E/S awaited
Detail Report
Graph / Photo
287 Civil & Electrical Works.

440.61
75.00 (Aug'23)

0.00 (Aug'23)

Detail Report
Graph / Photo
288 Strengthening of Arterial Road (Bahadur Shah Zafar Marg) having right of way more than 60.00 metre under Sub Division - 3 of Division C and ND - Roads, New Delhi

437.49


Detail Report
Graph / Photo
289 Construction of Old Age Home at Sarita Vihar, New Delhi including internal andexternal water supply sanitary installations, electric installations, Lift, SolarHeating System and fire Fighting (Civil + Electrical Works).

436.76


Detail Report
Graph / Photo
290 Balance Renovation and Misc. works of Main Academic, Administrative and Printing Blocks i/c Class Rooms &Laboratories, C/o Security Guards rooms and Toilet Water Proofing Treatment of existing building roofs of PIT, DSEU Campus, Pusa, New Delhi. 03/07/2022
30/10/2022
30/10/2022
436.21

Work completed.
Non-availability of budget.
Detail Report
Graph / Photo
291 Providing additional staircase from Skywalk towards Moti Bagh, MS staircase for underground sump, provision for additional railing over skywalk, Covering of Skywalk with CGI sheet roofing & C/o wall with MS Grill towards Moti bagh at FOB Durgabai Deshmukh Metro Station, Ring Road New Delhi. 29/06/2023
28/10/2023
28/10/2023
435.39
0.00 (Jun'23)

2.00 % (Jun'23)
Work in Progress
null
Detail Report
Graph / Photo
292 Operation & Comprehensive Maintenance of FOB Lifts,Security Guards, Maintenance of Electrical Installation & Other Electrical Work at Various FOB’s & Subways under AE(E), SD-I, Thyagraj Stadium, New Delhi.

434.57


Detail Report
Graph / Photo
293 Operation & Comprehensive Maintenance of FOB Lifts, Security Guards, Maintenance of Electrical Installation & Other Electrical Work at Various FOB’s & Subways under AE(E), SD-I, Thyagraj Stadium, New Delhi.

434.57


Detail Report
Graph / Photo
294 Construction of 200 Bedded Hospital at Kaushik Enclave, Burari, Delhi. (S.H. Supplying, installation, testing and commissioning of 11 Nos. additional prefabricated Modular Operation Theatre)

432.01
88.29 (Feb'23)

0.00 (Feb'23)

Work has been transferred to EE(E) Health Maintenance Elect Divn (N)


Detail Report
Graph / Photo
295 Replacement of existing metal halide sports flood lights with energy efficient LED Sports Flood Light including all the allied works at Chhatrasal Stadium Model Town Delhi

430.21
180.33 (Oct'23)

0.00 (Oct'23)

Updated


.

Detail Report
Graph / Photo
296 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road II PWD New Delhi

429.94

WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
297 Comprehensive improvement and maintenance of horticulture and landscaping work on soft areas of central verges and sides of footpath etc. on Inner Ring Road (from Mayapuri to Mall Road and Arihant Marg Road No. 51), Delhi under North Zone, PWD.

429.78


Detail Report
Graph / Photo
298 Providing services of 11 Nos. maintenance vehicles for regular use with required labour and T&P for Sub Division NR-11, NR-13, NR14 & NR-15 under North Roads Division. 05/05/2023
03/05/2024
03/05/2024
425.87
126.00 (Nov'23)
57.00 %
0.00 (Nov'23)
GLOBE BUILDERS work in Progress
null
Detail Report
Graph / Photo
299 Comprehensive maintenance of various roads under Sub-Division South East Road-13

425.32
14.60 (Jun'20)

0.00 (Jun'20)

Detail Report
Graph / Photo
300 Routine/Comprehensive Maintenance & Operation of Electrical & Mechanical Services

425.32
112.29 (Aug'23)

0.00 (Aug'23)

Detail Report
Graph / Photo
301 Civil and Electrical work

420.91


Detail Report
Graph / Photo
302 Operation and comprehensive maintenance of FOB lifts and escalators and other electrical work at various FOBs and subways under AE E SD III R K Puram New Delhi

419.48
4.64 (Feb'23)

0.00 (Feb'23)

Detail Report
Graph / Photo
303 Street Scaping of Nelson Mandela Road, New Delhi.

418.83
50.26 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
304 EI work (Composite Work) 19/01/2009
30/11/2013
30/11/2013
417.80

Bhart Eletricals (Associated of M/s ERA) 00
Detail Report
Graph / Photo
305 EI work (Composite Work) 19/01/2009
31/08/2012
31/08/2012
417.80

Bhart Eletricals (Associated of M/s ERA) 00
Detail Report
Graph / Photo
306 Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I.

417.30


Detail Report
Graph / Photo
307 Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I.

417.30


Detail Report
Graph / Photo
308 Op. of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I

417.30


Detail Report
Graph / Photo
309 Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I.

417.30


Detail Report
Graph / Photo
310 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of Maharishi Valmiki Hospital Campus and DGD Dispensaries at Pooth Khurd Delhi, SRHC Hospital Complex and DGD Dispensaries at Narela Delhi during 2022-23 and 2023-24 15/05/2022
14/05/2024
14/05/2024
416.87
78.76 (Nov'23)
81.00 %
0.00 (Nov'23)
Mahavir Parsad Gupta & Sons Work in Progress (Maharishi Valmiki 78% progress and SRHC 80% Progress)
Detail Report
Graph / Photo
311 Strengthening of various roads (Ahinsha Marg sector-9, Rohini, Babosachowk to Tulsi Aptt., Ring road to Maheswari Aptt., ORR to Road No. B-5 sector-14, Rohini, Internal road of sector-9, Rohini, Pkt.-14 to Pkt.C-1, Pkt.-10 to Pkt.D-4, sector-20, Rohini, Pkt. 8 to Pkt. 9, Pkt. B-2 to Park, Pkt. 13 to pkt. 9, Pkt. 5 to Pkt. 6 sector-21, Rohini) having ROW < 30 mtr. under Sub Division NWR-23, PWD Division NWR-2, Sainik Vihar Delhi under PWD North Zone by cold milling method with recycled material, dg. 2022-23 & 2023-24. 16/08/2023
15/02/2024
15/02/2024
415.97
65.00 %
R K Brothers & Company
Detail Report
Graph / Photo
312 Construction of Building for Old Age Home at Geeta Colony, New Delhi.

413.84


Detail Report
Graph / Photo
313 Strengthening of Ring Road from Shantivan to Hanuman Setu under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 02/06/2023
01/08/2023
01/08/2023
413.71

MAHAVIR PRASAD GUPTA AND SONS Work in progress
Detail Report
Graph / Photo
314 Providing X-ray Baggage scanner, DFMD security equipment at entry/security check points at Delhi High Court, New Delhi.

407.68
282.47 (Apr'23)

0.00 (Apr'23)

Detail Report
Graph / Photo
315 Improvement/providing and fixing of MS railing in central verge from Peeragarhi Chowk to Rama Road Round About (Zakhira Flyover) under PWD Division West Road-2/ Sub Division WR-21 & WR-24, New Delhi during 2019-20

406.91

Estimate sent to Circle office for approval
Detail Report
Graph / Photo
316 Repair and Rehabilitation Mukundpur and Karampura Flyover. SH: - (Replacement of bearings and expansion joints of Karampura Flyover and rehabilitation of RCC jacketing of two piers of Mukundpur Flyover.- (Recall) 05/10/2022
04/04/2023
31/10/2023
406.38
47.23 (Oct'23)

0.00 (Oct'23)

Work in Progress


null

Detail Report
Graph / Photo
317 AR MO to Various Residential Buildings Type III IV V and VI under Sub Division M 3231 at 16 Rajpur Road Delhi dg 2022 23

401.13
321.53 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
318 Main Burari Road from Bengali Colony culvert to Burari Morh (LHS) on side only under Sub Division-1 of Division C&ND-Roads, New Delhi.

400.00


Detail Report
Graph / Photo
319 Civil and Electrical works

398.73


Detail Report
Graph / Photo
320 Providing remedial measures for stopping vibration and noise due to flyover to Outer Ring Road near Ber Sarai, Munirka and Vasant Vihar. 26/02/2013
25/06/2013
31/05/2014
398.44

K.L. Arora & Son Sanctioned
Work Foreclosed
Detail Report
Graph / Photo
321 stopping vibration and noise 26/02/2013
25/06/2013
31/05/2014
398.44

K.L. Arora & Son Sanctioned
Detail Report
Graph / Photo
322 Repair and Rehabilitation of ISBT Flyover (Yudhister Setu), Kashmere Gate, Delhi. (SH: Providing and Laying Bituminous concrete and Retro reflective road marking). 26/01/2023
25/04/2023
30/07/2023
391.40
96.10 (Jul'23)

0.00 (Jul'23)

Work in Progress


null

Detail Report
Graph / Photo
323 Construction of RCC drain and side berm at Burari Road from Swaroop Nagar to Bhalswa, Delhi. 03/03/2023
30/07/2023
30/07/2023
389.94
353.41 (Nov'23)

0.00 (Nov'23)
AMIT BUILDCONE Work completed
null
Detail Report
Graph / Photo
324 Operation of lifts 22/10/2022
21/10/2024
21/10/2024
389.63
89.41 (Nov'23)
59.00 %
0.00 (Nov'23)
Akash enterprises 1st RA bill paid
Work in progress
Detail Report
Graph / Photo
325 Strengthening of MB Road (ID-390) Road through cold milling and recycling process under Sub-Division-1 of Division South Road-1 PWD, New Delhi. 20/06/2023
19/08/2023
19/08/2023
388.26
165.00 (Nov'23)

0.00 (Nov'23)
Pawan Kumar Work completed
Work completed
Detail Report
Graph / Photo
326 Strengthening of Prithvi Singh Dagar Marg ID 1175 from RawtaMorh Dhansa Road to Daurala Border under PWD Division- South West Road-II New Delhi. 16/10/2019
12/02/2020
388.15
0.84 (Apr'22)

0.00 (Apr'22)
Pawan Kumar UNDER TENDERING PROCESS
UNDER TENDERING PROCESS
Detail Report
Graph / Photo
327 Improvement and maintenance of horticulture and landscaping work on central verges and sides of footpath etc. on Inner Ring Road (from Mayapuri to Mall Road and Arihant Marg Road No. 51), Delhi under North Zone, PWD for 36 months.

387.36


Detail Report
Graph / Photo
328 Replacement of outlived Sub station equipment installed atDepartment of Trade , Taxes, Vyapar Bhawan Building, I.P. Estate New Delhi

387.07
58.97 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
329 Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain 25/09/2022
24/12/2022
24/12/2022
386.35
350.00 (Nov'23)

0.00 (Nov'23)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
330 C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) 02/03/2022
26/11/2022
31/01/2024
385.86
118.12 (Nov'23)

0.00 (Nov'23)
M/s. Satyam Construction Work is in progress
Work is in progress
Detail Report
Graph / Photo
331 SITC of Central Air conditioning Plant in upper 3.5 Three and Half stories including strengthening of sub station and provision of false ceiling of MCH Block 500 Bedded New Ward Block at G.T.B. Hospital Shahdara Delhi

385.28


Detail Report
Graph / Photo
332 Strengthening of Amar Shaheed Bismil Marg, Police Line road Parwana Road under Sub Division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW. 20/08/2023
19/12/2023
19/12/2023
381.30
98.00 %
SBG INFRACON PRIVATE LIMITED
Detail Report
Graph / Photo
333 Repair and Rehabilitation of Vehicular Under Pass (VUP) and its approaches and Approaches of three RoBs at PulMithai on SPM Marg, Delhi 16/01/2020
15/10/2020
31/03/2021
379.24
40.81 (Apr'21)

0.00 (Apr'21)

Work in progress


null
Detail Report
Graph / Photo
334 Comprehensive repair of road footpath, drain, painting, Speed breakers, Patch repairs and other misc. repair works in SectionI & Section-II for 1 year

376.63
147.49 (Apr'23)

0.00 (Apr'23)

Detail Report
Graph / Photo
335 Comprehensive repair of road footpath, drain, painting, Speed breakers, patch repairs and other misc. repair works in SectionI & Section-II for 1 year

376.63


Detail Report
Graph / Photo
336 Operation & Maintenance of E.I, pumps, substation, DG Sets, fire fighting & fire alarm system, HVAC & ductable AC system, lift, Cold Room & solar water heating system etc. 10/05/2022
09/05/2024
09/05/2024
376.50
129.67 (Nov'23)
81.00 %
0.00 (Nov'23)
M/s Vivek Associates
Detail Report
Graph / Photo
337 (i) Civil work Comprehensive maintenance of Ring Road including carriageway, footpaths, central verge, service road etc. within the right of way, mechanised desilting

375.34


Detail Report
Graph / Photo
338 Providing of services of Security Guard ,security supervisor & security manager &Mechanized Housekeeping Services for Internal and External areas of Tis Hazari court Extension block in Delhi-110054. 01/07/2023
31/12/2023
31/12/2023
373.04
249.39 (Nov'23)
99.00 %
0.00 (Nov'23)
SONI MANAGEMENT AND ALLIED SERVICES PVT. LTD.
Detail Report
Graph / Photo
339 Road Resurfacing of Savitri Cinema (Road ID-601) Road from Guru Ravi Dass Marg to Outer Ring Road under Sub Division SER-24. 15/04/2023
14/06/2023
31/08/2023
372.52
289.41 (Nov'23)

0.00 (Nov'23)
Kundu Nirman 80%
Work in progress
Detail Report
Graph / Photo
340 Providing, running and maintaining truck mounted Anti Smog Gun on hire basis at various locations 19/05/2022
18/05/2023
18/05/2023
372.34
1398.54 (Apr'23)

0.00 (Apr'23)
Invalid Work in progress
Detail Report
Graph / Photo
341 Thermoplastic paint on various roads under Sub-Division R11, R-12, R-13 and 14.

371.03
45.00 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
342 Construction of RMCRoad From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22

369.30


Detail Report
Graph / Photo
343 Construction of RMC Road From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22

369.30


Detail Report
Graph / Photo
344 Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24

366.09


Detail Report
Graph / Photo
345 Strengthening of Ring Road from Raj Ghat to Shanti Van Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 02/06/2023
01/08/2023
01/08/2023
364.49

MAHAVIR PRASAD GUPTA AND SONS Work in progress
Detail Report
Graph / Photo
346 Major repair maintenance work i.e. outer plaster, chajjas of windows, balcony, damaged cemented water tank causing seepage, repair of staircase, road, blocked sewer line i/c strengthening, retrofitting works and misc. civil and Electrical works

363.36
208.08 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
347 Up-gradation of Analog Camera to IP CCTV Surveillance Systems at District Court Karkardooma Delhi.

360.66


Detail Report
Graph / Photo
348 Civil Works: Mechanised Desilting of Drains & Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other Misc. Repair works of footpaths, Central Verge, Service roads etc. on other roads than ring road under Sub-Division NWR-21

359.74
5.35 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
349 Re-Surfacing of various roads of Vasant Vihar Roads (Poorvi Marg (Road ID - 781), Paschimi Marg (Road ID - 782 ), Basant Marg 1 (Road ID - 778), Basant Marg 2 (Road ID - 779), Munirka Marg 1 and2 (Road ID - 783)) and Providing and Laying of Stone Ma

359.35


Detail Report
Graph / Photo
350 Construction of Foot Over Bridge at Gurudwara Majnu ka Tila on Road No. 45 under Sub-Division-4 of Division C and ND-R, New Delhi. 06/09/2022
05/03/2023
05/03/2023
358.46

Fiberfill Engineer
Detail Report
Graph / Photo
351 Construction of Old Age Home at Sarita Vihar, New Delhi.

358.09
9.95 (Jun'23)

0.00 (Jun'23)
Sanction of Building Plan is under process
Detail Report
Graph / Photo
352 Strengthening of Timarpur Road (Chaudhary Fatah Singh Marg) from Mall Road to Wazirabad Crossing under Sub-Division-2 of Division C& ND-R.

357.04


Detail Report
Graph / Photo
353 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
354 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
355 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021 22

354.88


Detail Report
Graph / Photo
356 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
357 Improvement and Strengthening of MB Road Khajuri Chowk to Sabhapur Village at City Side.

353.93

A/A & E/S awaited
Detail Report
Graph / Photo
358 Civil & Electrical Work. 30/03/2023
29/09/2023
29/09/2023
352.07
27.95 (Jul'23)

10.00 % (Jul'23)
Engineers India Construction Ltd.
Detail Report
Graph / Photo
359 C/o 200 Bedded Hospital at Kaushik Enclave, Burari, Delhi. (S.H. SITC of Medical Gas Pipe Line System)

350.95
67.59 (Nov'23)

0.00 (Nov'23)
Tender Awarded
Detail Report
Graph / Photo
360 Strengthening of Roshnara Road from Pulbangash Metro Station to Malka Ganj Chowk under Sub-Division-2 of Division C& ND-R.

350.85


Detail Report
Graph / Photo
361 Comprehensive repair works of footpaths, central verge, service roads etc. on other roads under Sub division NWR-23

350.32


Detail Report
Graph / Photo
362 Desilting of road side storm water drain/ sewer line by Super Sucker Machine on Various roads, under SRD Project Division-I.) Recall of Tender. 26/03/2023
25/03/2024
25/03/2024
349.42
153.00 (Jun'23)
74.00 %
0.00 (Jun'23)
NITIN KUMAR SHARMA
Detail Report
Graph / Photo
363 (1) SITC of Additional Surveillance CCTV System at different locations of Dwarka Court Complex at Sector10, Dwarka, New Delhi. (2) Up-gradation of existing analog CCTV Surveillance system to I P Base CCTV Surveillance System at District Court, Sector-10, Dwarka, New Delhi 22/05/2022
21/11/2022
21/11/2022
348.67
30.00 (Aug'23)

0.00 (Aug'23)
Pan Intellecom Ltd
Detail Report
Graph / Photo
364 Renovation of 64 Nos. Toilets of Lawyers Chamber Block D E F and G at Karkardooma Court Delhi dg. 2023 24.(Civil and Electrical Work. 1st Recall) 27/08/2023
22/02/2024
22/02/2024
348.05
65.00 %
Mohd Aftab dismantling work in progress at E block
in progress
Detail Report
Graph / Photo
365 Comprehensive maintenance of Civil works at Guru Gobind Singh Govt. Hospital, Raghubir Nagar, Delhi and Rao Tula Ram Memorial Govt. Hospital, Jaffarpur Kalan, Delhi P.W.D. (GNCTD), New Delhi for 2 years 2021-22, 2022-23. 23/05/2022
21/05/2024
21/05/2024
343.73
0.00 (Nov'23)
81.00 %
76.00 % (Nov'23)
Aliyan Constaruction Company Work is under progress.
Detail Report
Graph / Photo
366 Strengthening of various roads by cold milling of sub-Div. East road-III under East road/(M-212) Delhi during 2022-23. 1. Sadhabhawna Marg (Road No. 111) 2. Club Avenue Marg (Road No. 112) 3. Sekarita Marg (Road No. 113) 4. Ambedkar Marg. 5. Subhash Market road. 6. Block No. 1 to 11 Trilokpuri. 7. Khudiram Bose Marg 29/08/2022
24/02/2023
24/02/2023
342.13
214.67 (Jul'23)

0.00 (Jul'23)
SATYA PARKASH AND BROS PVT LTD

Workin Progress


Detail Report
Graph / Photo
367 Comprehensive Maintenance and Operation of Trauma Block, New Ward Block, OT, Gynae, Old Ward Block, Doctors and Nurses Hospital and Residential Complex Lifts at DDU Hospital, Hari Nagar, New Delhi (SH Operation of Lifts)

341.50


Detail Report
Graph / Photo
368 Providing and fixing road signage boards on various roads Under Sub Division I,II,III,IV,V PWD SWR-I New Delhi.

341.49


Detail Report
Graph / Photo
369 C/o 17 Nos. additional SPS class rooms & 3 no. staircase i/c internal & external water supply sanitary installation electrical installations development of site fire fighting system at Govt. Sarvodaya Vidyalay, Badarpur, Khadar (School ID 1104418) in District North-East (Zone-4) Delhi

340.93

sanction awaited


null
Detail Report
Graph / Photo
370 Resurfacing of Ring Road under Division CBMD M-321, New Delhi. 27/05/2023
26/06/2023
26/06/2023
339.88
103.77 (Nov'23)

0.00 (Nov'23)
M/s Chaudhary Construction Company Pvt. Ltd. In-progress
Detail Report
Graph / Photo
371 Replacement of damaged old 900mm Dia RCC pipe with Providing and Laying 1200mm dia RCC Pipe from Som Bazar Chowk to Mungeshpur drain at Najafgarh Nangloi Road. (Road ID -1230) 18/04/2022
14/10/2022
14/10/2022
339.47
308.46 (Dec'23)

0.00 (Dec'23)
Dilshad Khan
Detail Report
Graph / Photo
372 Construction of RCC drains from Block-36 to Block-31 at Trilokpuri under Sub-Division East (Road)-III of Division East (Road)/M-212, Delhi.

335.20

Work in progress


null
Detail Report
Graph / Photo
373 Micro Surfacing on Outer Ring Road from Vikas Puri to Meera Bagh

334.06
173.92 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
374 PROVIDING, INSTALLATION, TESTING AND COMMISSIONING OF CENTRAL AC PLANT IN ADMINISTRATIVE BLOCK, DELHI HIGHT COURT, NEW DELHI

332.99


Detail Report
Graph / Photo
375 Construction of Back to back U-turn near Aali Village Red-light and Single U-Turn for Sarita Vihar Colony to facilitate signal free and congestion free movement of traffic on Mathura Road under SER-2/22.(Road ID-961) 19/03/2022
18/06/2022
30/09/2023
331.52
10.15 (May'23)

0.00 (May'23)
Satyam Construction Company 45%
Work in Progress
Detail Report
Graph / Photo
376 Up gradation of one staffroom in 86 Nos. Schools under South-East Building Maintenance Division, Hauz Khas, New Delhi during 2018-19. (Civil and Electrical work). 23/03/2019
22/09/2019
22/09/2019
329.84
160.77 (Jan'23)

0.00 (Jan'23)
S. P. CONSTRUCTION COMPANY

Work in progress


Detail Report
Graph / Photo
377 Comprehensive Maintenance of RO Filtration Units in Ortho Block Hostels LNRDH Various Location in LNH 02/01/2023
01/01/2026
01/01/2026
327.30
236.55 (Feb'23)
30.00 %
0.00 (Feb'23)
M/s Vivek Associates

Work in progress


Work in progress

Detail Report
Graph / Photo
378 Civil & Electrical Works. 30/03/2023
29/07/2023
29/07/2023
324.30

Mohd Ahson Infra Private Limited
Detail Report
Graph / Photo
379 Comprehensive Maintenance of RO Filtration Units in Ward Block , Gynae Block , OPD Block , Emergency and OT Block in LNH 21/10/2022
20/10/2025
20/10/2025
322.38
38.00 %
M/s Vivek Associates

Work in progress


Work in progress

Detail Report
Graph / Photo
380 Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work)

316.48


Detail Report
Graph / Photo
381 Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work)

316.48


Detail Report
Graph / Photo
382 Civil & Electrical Work

316.48


Detail Report
Graph / Photo
383 Construction of Reinforced Cement Concrete Retaining Wall along IandFC drain from Kali Mata Mandir to FOB near Janak Cinema on Pankha Road (ID 2027) under Sub Division-21, Division- SWR-II, PWD, New Delhi. 03/07/2023
31/08/2023
31/08/2023
316.12
174.28 (Nov'23)

0.00 (Nov'23)
Surender Singh
Detail Report
Graph / Photo
384 RMO E and M Services at SRHC Hospital Narela Delhi during the year 2021-23

315.90


Detail Report
Graph / Photo
385 Improvement and Strengthening of Old G.T. Road from Yamuna bridge to Y Point Delhi.

314.25

A/A & E/S awaited
Detail Report
Graph / Photo
386 RMO of various Electrical and Mechanical services at District Court Rohini, Delhi. dg. 2021-22

313.55


Detail Report
Graph / Photo
387 Strengthening of Rajpura Road from Tis Hazari Red Light to Civil Line Thana under SubDivision-4 of Division C& ND-Roads, New Delhi. (Width- ROW Below 30.00 meter) 24/06/2022
23/10/2022
23/10/2022
313.49
167.20 (Apr'23)

0.00 (Apr'23)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
388 Covering of all open courtyard of (6 nos) Civil side and (8 nos) western side by providing and fixing of tubular frame/truss and covering with M.S. wire mess including provision of openable side shutter at Tis Hazari Court, Delhi. 23/03/2023
26/06/2023
26/06/2023
312.65
166.21 (Nov'23)

0.00 (Nov'23)
In-progress
Detail Report
Graph / Photo
389 Automated Housekeeping Service of MSO Building

308.94
201.07 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
390 1. RMO of Central AC Plant at A BlockGIPMER2. RMOof Central AC Plant B BlockGIPMERSH Operation and Comprehensive maintenance of Blue Star Make Central AC Plant 11/09/2019
10/09/2021
10/09/2021
306.35
130.70 (Mar'23)

0.00 (Mar'23)
Blue Star Limited work in progress and 2nd R/A paid to M/s Blue Star Ltd.
work in progress and 2nd R/A paid to M/s Blue Star Ltd.
Detail Report
Graph / Photo
391 Day to Day Maintenance & Operation of Electrical Installation LT Panel Boards, DG Sets, Sub-Station and Pumps i.e. Rain Water/Storm Water/Sewage dewatering on various Underpass/RUB under the jurisdiction of NESD-1.

306.01


Detail Report
Graph / Photo
392 Comprehensive Maintenance of RO Filtration Units 03/03/2023
02/03/2026
02/03/2026
305.87
24.00 %
M/s Vivek Associates

work in progress


work in progress

Detail Report
Graph / Photo
393 Construction of Change Room including toilet, Guard Room, Office Room, Coach Room, S.S. fencing on Periphery of Athletic Track & Boundary wall with concertina coil fencing etc. and Renovation of existing block, pump house, entry road and provision of stone cladding on boundary wall at Pooth Kalan Sports Complex, Delhi. 01/07/2023
27/12/2023
27/12/2023
305.16
0.50 (Dec'23)
99.00 %
0.00 (Dec'23)
Sham Lal Gupta & Sons Dholpur stone cladding work is in progress and construction of front boundary wall is in progress.
Detail Report
Graph / Photo
394 Repair and Rehabilitation of Sarita Vihar Flyover, Delhi. (SH: Repair of Box girder of entry and exit loop with carbon fiber lamination, Expansion Joints and Bearing) 14/01/2023
13/07/2023
30/09/2023
305.15
0.00 (Jun'23)

40.00 % (Jun'23)

Work in Progress


null

Detail Report
Graph / Photo
395 Providing, running and maintaining Anti Smog Gun on hire basis at various locations 22/05/2023
21/05/2024
21/05/2024
303.86
57.00 %
Invalid Work in progress
Detail Report
Graph / Photo
396 Road Restoration work of Prathvi Singh Dagar Marg(Road ID-1175) under Sub Division -III, SWR-2, Division, PWD, New Delh. 05/09/2023
01/02/2024
01/02/2024
303.35
59.00 %
Pawan Kumar
Detail Report
Graph / Photo
397 EOR to Sports Complex, Opposite Nightingale Society, Vikaspuri, New Delhi.(SH:- Construction of Boundary wall, guard room at gate no.3, Repair and Renovation of Toilet Blocks, Providing chain link fencing at front side of visitors sitting area and colony side boundary wall in Sports complex, vikaspuri, New Delhi).

299.80
120.92 (Jul'23)

0.00 (Jul'23)

Detail Report
Graph / Photo
398 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road-II PWD New Delhi 10/09/2019
07/01/2020
07/01/2020
298.81
194.61 (Jul'20)

0.00 (Jul'20)
Invalid WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
399 Installation of target system, bullet proofing and Anti ricochet treatment, ventilation and acoustical works) (Composite work Civil and Electrical) 07/02/2023
06/06/2023
31/08/2023
298.45
72.35 (Mar'23)

0.00 (Mar'23)
Work in Progress
Detail Report
Graph / Photo
400 Strengthening of Shah Alam Bandh Road under Sub-Division NR-11 of North Roads Division, PWD, Delhi.

298.31

work completed
null
Detail Report
Graph / Photo
401 Painting of Kerb Stone, railing, jersey barrier and central verge etc. of Sub-Division R-11, R-12, R-13 and R-14 for the occasion of Republic Day

298.11
48.50 (Aug'23)

0.00 (Aug'23)

Detail Report
Graph / Photo
402 Improvement and Strengthening of Zero Pusta Road (Zero Pusta to Bharampuri culvert), Gurudwara Road & Seelampur Road Delhi.

298.00

A/A & E/S awaited
Detail Report
Graph / Photo
403 Providing and installing LAN System

296.99


Detail Report
Graph / Photo
404 Running operation and comprehensive maintenance of online UPS, TVSS, APFF, PAC and Isolation transformer of different capacity installed at RGSS Hospital, Tahirpur, Delhi 26/01/2022
25/01/2024
25/01/2024
296.84
111.84 (Jul'23)
97.00 %
0.00 (Jul'23)
Invalid
Detail Report
Graph / Photo
405 C/o East Delhi Campus of Guru Gobind Singh Indrasprastha University at Surajmal Vihar, Shahdara, Delhi. (SH: Supply, Installation, Testing & Commissioning of CCTV). 30/03/2021
28/07/2021
31/12/2023
296.70
222.63 (Jun'23)

0.00 (Jun'23)
Work completed. Final bill to be paid.
Detail Report
Graph / Photo
406 Providing & fixing 80 mm thick Paver Block over Unpaved Shoulder Portion of Road in view of Anti Air Dust Pollution Measures for Rao Laxmi Chand Marg (ID 1174) under Sub Division 23 Division SWR-II, PWD, Delhi 14/04/2022
11/08/2022
11/08/2022
296.33
411.26 (Feb'23)

0.00 (Feb'23)
Bliss Associates
Detail Report
Graph / Photo
407 Lift 21/06/2011
15/11/2013
15/11/2013
295.04

Johnson Lifts Pvt. Ltd. 00
Detail Report
Graph / Photo
408 Construction of FOB in between Metro Pillar No. 299 to 298 at Miyawali, Udhyog Nagar, Rohtak Road (NH-10), New Delhi.(Civil and Electrical Work)

294.40


Detail Report
Graph / Photo
409 Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). 28/02/2019
27/06/2019
31/03/2021
294.21
58.25 (Feb'22)

0.00 (Feb'22)
AASRA Martech Pvt.Ltd. Work in progress.
Detail Report
Graph / Photo
410 Civil and Electrical work. 05/05/2019
04/03/2020
04/03/2020
292.64

Dheeraj Singh & Company

Work just awarded


Detail Report
Graph / Photo
411 Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). 09/08/2022
08/08/2023
08/08/2023
292.57
28.79 (Oct'23)

0.00 (Oct'23)
Nand gopal Gupta
Detail Report
Graph / Photo
412 Air Pistol & Rifle 10m Shooting Hall cum all internal finishing fixtures fitting and development of complete setup of electronic type targets, shooting equipment etc. complete 18/03/2022
13/09/2022
30/11/2023
290.26
69.80 (Dec'23)

0.00 (Dec'23)
Dev Enterprises work is in progress
work is in progress
Detail Report
Graph / Photo
413 Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi 16/01/2022
15/10/2024
15/10/2024
288.00
69.00 %
Arcop Associates Pvt. Ltd. Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval.
NIL
Detail Report
Graph / Photo
414 C/o Sitting Block and development of drainage system at East Vinod Nagar Sports Complex.

287.15

Work in progress


null
Detail Report
Graph / Photo
415 Civil and Electrical work. 04/05/2023
05/06/2023
05/06/2023
283.09
133.77 (Nov'23)

0.00 (Nov'23)
BHARDWAJ ENTERPRISES
Detail Report
Graph / Photo
416 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021-22 26/12/2022
25/02/2023
25/02/2023
282.98
380.05 (Jul'23)

0.00 (Jul'23)
RUDRA CONSTRUCTIONS
Detail Report
Graph / Photo
417 Supply and Installation of ESP Filter in existing AHU’s for improvement in AQI at Delhi High Court, New Delhi

282.79
155.81 (Oct'23)

0.00 (Oct'23)

Detail Report
Graph / Photo
418 Supply and Installation of ESP Filter in existing AHUs for improvement in AQI at Delhi High Court, New Delhi

282.79


Detail Report
Graph / Photo
419 Operation and Maintenance of EI and FANS Sub Station HVAC Works Fire Fighting and Wet Riser System Solar Water Heating System Cold Storage Lifts etc

282.78
33.81 (Nov'23)

0.00 (Nov'23)