Zoneअंचल
Divisionमंडल
Sectorकार्य का प्रकार
Sectorकार्य का प्रकार
Categoryश्रेणी
Other Project Health Project North Maint. East Maint. South Maint. Flyover Pr. Chief Engineer (Projects)
Construction Work 56 557 81 1586 989 2392 516 1
Maintenance Work 56 413 420 837 753 135
Total 112 970 81 2006 1826 3145 651 1
S. No.क्र. सं. Name of Workकार्य का नाम Date of Start Cost (In Lac) Target Progress Agency Present Position Satisfactory Viewदेखें
Stp. Completion
Exp. Completion Expenditure Phy. Progress Bottleneck Quality Safety Progress
1 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 18/04/2015
17/10/2017
31/08/2023
96400.00
137337.57 (Sep'22)
100.00 %
0.00 (Sep'22)
Larson & Toubro Limited Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment, pylon, erection of segments is in progress
Work in progress
Detail Report
Graph / Photo
2 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwakra, New Delhi on turn-key basis 27/08/2014
26/02/2017
31/08/2022
54511.43
229.47 (Sep'22)

0.00 (Sep'22)
Larson & Toubro Limited Minor rectifications & left out works is under progress.
Detail Report
Graph / Photo
3 setting up of Semi- permanent / temporary ICU Hospital at shalimar Bagh (G+3) (14530Beds) Kirar (G+4) (458 Beds)and Sultanpuri (G+3) (525Beds) Package-I (Electrical) 23/09/2021
22/02/2022
22/02/2022
50680.19
3901.34 (Sep'22)

0.00 (Sep'22)
SAM India Builtwell
Detail Report
Graph / Photo
4 setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) 23/09/2021
22/02/2022
04/08/2022
40775.18
3271.33 (Sep'22)

0.00 (Sep'22)
SAM India Builtwell GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave.
Detail Report
Graph / Photo
5 Co Admn Blk, Acdmc Bldg, Aud. Bldg, Activity Ctr, Workshop Bldg, Hostel, Resi. Blk ic Ext Devt. wks, Int. Elect. Instl, Ext. Ltng, lifts, FF sys, F.A. with PA Sys, DG Sets, Electric Sub-Stn and allied wks, HVAC wks

38552.29

(i) Airport Authority approval received. (ii) DFS approval received. (iii) A/A & E/S of Rs. 526.66 Cr. issued on 01.04.2019. (iv) The tender has been floated and lowest bidder is M/s Kamladitya Construction Pvt. Ltd. The bid is accepted by Delhi Works Advisory Board with a direction to award the work after reciept of local bodies approvals, tree cutting permission and permission to demolish temporary and permanent structures." (v) Permission for demolition of temporary structure received from DTTE. (vi) The building plan is submitted in SDMC for further processing. (vii) The tree cutting permission received on 02.02.2021. (viii) Application for approval of layout plan has been submitted on 23.03.2021 by Joint Director (Planning), DTTE. (ix) The final layout plan has been submitted on 02.09.2021 after incorporating all corrections in the O/o Chief Town Planner, SDMC for approval of layout plan. (x) Layout plan approved by Standing Commiitte, SDMC vide Resolution No. 188 dt 23.02.2022. (xi) Consultant (M/s DDF Consultant) submitted layout plan along with undertakings, Indemnity bond & security deposit to SDMC for approval of Building Plan vide letter No. 54(6)/EE/EPD-I/PWD/2022-23/254 dated 11.04.2022. Approval of Building Plan from SDMC is still awaited. (xii) A presentation was made before Dy. CM on 06.05.2022 and it was directed to improve the building facade and design to the international level so that a presentation can be made before Dy. CM within next 15 days. The same was conveyed by Joint Director (Plg/Tech), DTTE vide his lettr No. F.75(123)/Re-Dev. Plan/PIT&ITI PUSA/PLG/2015-16/123 dated 09.05.2022. (xiii) The Building Plan submitted online to South MCD along with all civic agencies clearances on dated 09.05.2022 by the Consultant for approval. (xiv)Preliminary Estimate for C/o Temporary shed for workshop i/c shifting of equipments amounting to Rs. 11.71 crore has been submitted to Dy. Director (Plg.), DTTE on 16.08.2022 for A/A & E/S.
nil
Detail Report
Graph / Photo
6 CONSTRUCTION OF NEW HOSPITAL AT SIRASPUR, NEW DELHI (ON EPC MODE -I) INCLUDING ALL CIVIL, ELECTRICAL, MECHANICAL, HORTICULTURE AND MEDICAL SERVICES. 10/08/2020
09/05/2023
27/02/2024
38439.53
8548.79 (Sep'22)
79.00 %
0.00 (Sep'22)
Ramacivil India Construction Private Limited work in progress
Detail Report
Graph / Photo
7 Setting up of Semi-permanent temporary I.C.U Hospital at Chacha Nehru Bal Chikitsalaya (G plus 4) (596 beds) and GTB Hospital Complex (G plus 4) (1912 Beds) Package II

35533.93
4489.88 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
8 Construction of Flyover with Ramps, Footpath, Road Work including Road Signage, Street Light works, Drainage, Horticulture, Mural Works & allied works at Road No. 56 between Anand Vihar ROB and Apsara Border ROB, New Delhi

33420.85

tender under process


null
Detail Report
Graph / Photo
9 Construction of New Hospital Block at Babu Jagjivan Ram Memorial Hospital, Jahangirpuri, New Delhi

31879.73

work is in planning stage
Detail Report
Graph / Photo
10 Corridor Development and Street Network/ Connectivity Plan for the influence zone of the corridor between Punjabi Bagh Flyover and Raja Garden Flyover

30848.06

Work is in progress.


Work is in progress.

Detail Report
Graph / Photo
11 Setting up of Semi-permanent temporary I.C.U Hospital at Sarita Vihar (G plus 4) (336beds) and Raghubir Nagar (G plus 3)(1577 Beds) Package III

29175.20
847.24 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
12 Construction of Hospital at Hastsal, New Delhi 17/06/2021
16/06/2023
16/06/2023
23695.11
68.00 %
1%
WORK IS SHIFTED TO HPD DWARKA
Detail Report
Graph / Photo
13 C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi SH Co Academic Bldg, Auditorium Bldg, Sports Hall, Boys, Girls, Teachers Hostel, Type II III IV and V Qtrs ic Ext Dev. works, Int Elect Inst, Ext Lighting, lifts, fire fighting system, fire alarm with PA System, D.G. Sets, Elect Sub Stn, HVAC works 09/08/2017
09/11/2019
31/12/2022
23127.43
3668.44 (Sep'22)

0.00 (Sep'22)
NKG Infrastructure Limited Physical Progress of the work is 97%.
nil
Detail Report
Graph / Photo
14 C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road, Delhi (SH: C/o Academic Blocks AB-3 & AB-4, Boys Hostel H-5 & Girls Hostels HG-5 & HG-6 and all external and internal services including external development and landscaping, and allied civil and E&M works). 23/09/2019
23/12/2020
30/09/2022
22769.91
2628.29 (Sep'22)

0.00 (Sep'22)
SAM India Builtwell Boys Hostel and Girls Hostel has been completed. Academic Building is in final stage of completion. Work delayed due to NGT ban and Covid-19 pandamic. The progress of work is 99%.
Boys Hostel and Girls Hostel has been completed. Academic Building is in final stage of completion. Work delayed due to NGT ban and Covid-19 pandamic. The progress of work is 99%.
Detail Report
Graph / Photo
15 C/o Police Housing project at Mandoli, Delhi-93(SH: C/o 300 Nos. Type-II and 60 Type-IV qtrs and its related development works)

22130.16

A/A & E/S awaited
Detail Report
Graph / Photo
16 Additional and Remodeling Work for Cancer Block, Maternity Block and Screening OPD At Satyawadi Raja Harish Chandra Hospital, Narela For Delhi Govt. (Delhi) 09/08/2020
08/05/2023
08/05/2023
21785.66
492.91 (Jun'22)
79.00 %
0.00 (Jun'22)
Parnika Commercial and Estates Pvt. Ltd. Work in progress
Work in progress
Detail Report
Graph / Photo
17 C/o 750 Bedded Hospital at Dwarka, New Delhi.

16355.70
402.66 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
18 Construction of 144 Nos Temporary Courtroom in the existing court complexes of Saket Stilt plus 3 Tis Hazari Stilt plus G plus 3 and Karkardooma G plus 4 04/10/2019
03/07/2020
30/09/2022
14316.00
435.87 (Aug'22)

0.00 (Aug'22)
Quality Buildcon Pvt. Ltd. The Work is in progress with upto date progress is approx. 98.5%. 1- Karkardooma: The work is completed and inaugurated on 13.05.2022, possession is yet to be taken by court authorities. 2- Saket: The work is completed, inventories have been handed over to the court authorities and dedicated maintenance wing. 3- Tis Hazari : work of defect rectification work, external development work is underway, collection tank for sewer line has been made and waterproofing work is underway and C/o Rainwater harvesting pit has been almost completed and final furniture placing is in progress. Also, Final Testing & commissioning of lifts, escalators, fire alarm & fighting works, LV services; Gas filling work in VRV units, LV services; Interconnection of fiber cable between old & new bldg to be done is in progress. Fire clearance has been applied from the DFS.
Detail Report
Graph / Photo
19 Addition & Remodelling work for Bhagwan Mahavir Hospital at Pitampura Delhi including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 10/12/2019
01/06/2020
31/01/2021
13992.80
1836.94 (Sep'22)

0.00 (Sep'22)
Kamladitya Construction Private Limited Work in progress
Work in progress
Detail Report
Graph / Photo
20 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 18/10/2019
10/04/2021
12/12/2022
13447.15
1823.13 (Sep'22)

0.00 (Sep'22)
Roshan Real Estate Pvt Ltd. Work is under progress.
Detail Report
Graph / Photo
21 Extension of Ashram Flyover to DND Flyover. 19/06/2020
18/06/2021
30/09/2022
12879.00
11727.85 (Aug'22)

0.00 (Aug'22)
KCC Buildcon Pvt. LTD The work was delayed due to restriction of COVID-19 & non approval of traffic NOC. Now, the work in central portion has just started after receipt of Phase-II NOC on 24.09.2021. Now, the progress is at the desired pace. Subway finishing work is in progress. The FOB & Electrical work in progress.Extension of time is submitted in the office of CE (Flyover) for extension up to 13.11.2022.
Detail Report
Graph / Photo
22 Construction of 460 Beds Mother and Child Hospital Block at LBS Hospital Khichripur, Delhi 23/09/2019
23/09/2019
26/02/2023
11056.40
1077.48 (Sep'22)
90.00 %
0.00 (Sep'22)
Work is in progress.
Work is in progress.
Detail Report
Graph / Photo
23 Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 04/03/2020
03/09/2021
03/09/2021
10708.84
1704.47 (Sep'22)

0.00 (Sep'22)
Quality Buildcon Pvt. Ltd. work in progress
Detail Report
Graph / Photo
24 C/o Haji House at Sector-22, Phase-II, Dwarka, New Delhi

9566.03
0.00 (Mar'19)

0.00 (Mar'19)
A/A & E/S awaited
Detail Report
Graph / Photo
25 C/o New DC office at Mandawali, Fazalpur, Delhi

8432.86

A/A & E/s awaited
Detail Report
Graph / Photo
26 Construction of Delhi Fire Service Headquarter Building at Connaught Place, New Delhi-110001

8094.10
0.00 (Mar'19)

0.00 (Mar'19)
A/A & E/S awaited
Detail Report
Graph / Photo
27 Maintenance of P.C. in Divn and SD Office.

7122.82

PNSC Infrastructure Pvt. Ltd
Detail Report
Graph / Photo
28 C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 04/09/2019
03/03/2021
31/12/2022
7122.09
935.09 (Sep'22)

0.00 (Sep'22)
PNSC Infrastructure Pvt. Ltd work in progress.
Detail Report
Graph / Photo
29 Construction of (G+3) Pucca School Buildings at Tehkhand 18/07/2021
17/07/2022
31/12/2022
7047.98

PNSC Infrastructure Pvt. Ltd foreclosed
foreclosed
Detail Report
Graph / Photo
30 REMODELLING AND UPGRADING OF EXISTING DEEP CHAND BANDHU HOSPITAL AT KOKIWALA BAGH, ASHOK VIHAR, PH-IV, DELHI. 28/06/2019
22/06/2020
31/12/2020
6936.00
0.00 (Mar'19)

0.01 % (Mar'19)
Agency has gone in the arbitration. work in progress
work in progress
Detail Report
Graph / Photo
31 Expansion remodeling of ASBGH Moti Nagar New Delhi 06/08/2019
28/10/2020
28/10/2020
6759.71
283.97 (Sep'22)

0.00 (Sep'22)
Abhilasha Enterprises Work in Progress
Work in Progress
Detail Report
Graph / Photo
32 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 06/08/2019
29/10/2020
31/12/2022
6563.40
370.98 (Sep'22)

0.00 (Sep'22)
PNSC Infrastructure Pvt. Ltd Work is under progress.
Detail Report
Graph / Photo
33 Construction of (G+3) Pucca at Jaunapur, Site –II (Aya Nagar) New Delhi 110047 18/07/2021
17/07/2022
31/12/2022
6137.90
0.30 (Feb'21)

0.00 (Feb'21)
PNSC Infrastructure Pvt. Ltd Foreclosed
Foreclosed
Detail Report
Graph / Photo
34 Construction of Bridge on Najafgarh Drain at Tri Nagar/Inderlok, Karampura and Rampura, Delhi to cover the complete Right of Way (ROW) excluding area of already constructed bridge alongwith road improvement on either side of bridge including making. 16/03/2019
30/09/2021
30/09/2022
5388.53
5589.93 (Aug'22)

0.00 (Aug'22)
Ram Kumar Contractor work is in progress
work is in progress
Detail Report
Graph / Photo
35 Construction of New block Forensic Science Laboratory, Rohini, New Delhi 06/03/2020
05/09/2021
05/09/2021
5216.00
212.87 (Aug'21)

0.00 (Aug'21)
work in progress
Detail Report
Graph / Photo
36 Construction of underpass along Mathura Road at Ashram Chowk New Delhi 05/07/2019
04/07/2020
12/07/2022
4907.38
6043.94 (Aug'22)

0.00 (Aug'22)
Dharamraj Contracts (I) Pvt. Ltd. The work was delayed due to restriction of COVID-19 wave 1 & subsequently wave 2. The work is nearing completion. The underpass has been opened for traffic on 24.04.2022. The FOB & Electrical work in progress.
Detail Report
Graph / Photo
37 C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) 14/01/2019
09/11/2019
31/10/2022
4874.05
4634.36 (Sep'22)

0.00 (Sep'22)
Shri kamal singh Work in progress
Detail Report
Graph / Photo
38 C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) 20/01/2019
15/11/2019
31/10/2022
4603.38
3636.13 (Sep'22)

0.00 (Sep'22)
Sh. Kamal Singh Work in progress
Detail Report
Graph / Photo
39 Providing furniture in various govt. schools under Education, PWD, Delhi. (Package – B)

4497.90
688.11 (Aug'22)

0.00 (Aug'22)
work in progress
Detail Report
Graph / Photo
40 Providing furniture in various govt schools for additional classrooms under Education PWD Delhi Package A

4441.35
2140.54 (Sep'22)

0.00 (Sep'22)
work in progress
Detail Report
Graph / Photo
41 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work)

4350.79
7.43 (Jun'19)

0.00 (Jun'19)
Technical bid opened
Detail Report
Graph / Photo
42 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work)

4350.79


Detail Report
Graph / Photo
43 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) 43,50,79,456

4350.79


Detail Report
Graph / Photo
44 Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi.

4247.68

NIT opened on 31.08.2022 and Financial bid was sent to Competent Authority for approval
NIT opened on 31.08.2022 and Financial bid was sent to Competent Authority for approval
Detail Report
Graph / Photo
45 C/o Three Lane Flyover, Road Work, Footpath, Drainage System, Landscaping, Railing, Road Signages, Street Light & Allied works. 15/07/2022
14/07/2023
14/07/2023
4199.50
499.93 (Sep'22)
24.00 %
0.00 (Sep'22)
Gawar Construction Ltd., Work recently awarded
Detail Report
Graph / Photo
46 C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi

4172.51
519.74 (Sep'22)

0.00 (Sep'22)
Initially site was encroached by local peoples. Encroachment the major part of land has been removed with help of education department and delhi police on dated 22.03.2022, but some portion of site is still encroached by local person. Partly site handed over to the agency for boundary wall and building construction on dated 23.03.2022, hence the actual work started from 23.03.2022.
Detail Report
Graph / Photo
47 Covering of the ramps of all the underpass (entry & exit) i.e. Underpass 1 to 6 as well as the main tunnel entry and exit ramps, branch tunnel entry ramps developed in the construction of Integrated Transit Corridor Development plan in and around Pragati Maidan.

4148.84
193.50 (Sep'22)

0.00 (Sep'22)
not pertains to this office
Detail Report
Graph / Photo
48 Covering of the ramps of all the underpass (entry & exit) i.e. Underpass 1 to 6 as well as the main tunnel entry and exit ramps, branch tunnel entry ramps developed in the construction of Integrated Transit Corridor Development plan in and around Pragati Maidan. 21/05/2022
20/11/2022
20/11/2022
4144.69
82.00 %
R S Sharma Contractors Pvt. Ltd.
Detail Report
Graph / Photo
49 Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc.

3926.02

NIT opened on 21.07.2022 and Financial bid was sent to Competent Authority for approval.
NIT opened on 21.07.2022 and Financial bid was sent to Competent Authority for approval.
Detail Report
Graph / Photo
50 C/o 56 Nos. additional (G+3) SPS equivalent Class Rooms including 1 stilt , 8 nos toilet, 4 nos staircase, lift, RWH & UGR at Govt. Co Senior Secondary School at Usmanpur, Delhi (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.)

3910.36

The work was fore closed under Clause 3A
The work was fore closed under Clause 3A
Detail Report
Graph / Photo
51 W/O Mahrauli Mahipalpur Road. SH: from 4 lanes to 8 lanes and Service Road from Andheria More to Masoodpur Village. 30/10/2012
29/04/2013
29/04/2013
3812.11

KCC Buildcon Pvt. LTD .
Detail Report
Graph / Photo
52 Construction of 140 nos additional SPS Classrooms in DOE Schools GGSSS No. 1 Tukhmirpur, Delhi (1104262) 40 Class rooms, GGSSS No. 2 Tukhmirpur, Delhi (1104419) 32 Class rooms & GSKV Khajuri Khas, Delhi (1104022) 68 Class rooms including Laboratory, staircases, toilets and ramps, internal water supply, sanitary installations, Internal electrification and fire fighting arrangements.

3713.27

Competent Authority has withdrawal the tender and the letter issued to agency on 29.08.2022. Work shall only be taken up after sufficient fund is released to PWD.
Competent Authority has withdrawal the tender and the letter issued to agency on 29.08.2022. Work shall only be taken up after sufficient fund is released to PWD.
Detail Report
Graph / Photo
53 Const 182 Nos. of additional SPS class rooms (Package-C) 17/03/2019
11/12/2019
30/09/2022
3699.32
3486.58 (Sep'22)

0.00 (Sep'22)
SPS Infrabuild Pvt. Ltd. Work completed and Inventory submitted to HOS.
Work completed and Inventory submitted to HOS.
Detail Report
Graph / Photo
54 Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 24/12/2018
19/09/2019
10/10/2022
3675.76
2963.81 (Sep'22)

0.00 (Sep'22)
RAMA Contractor Building work completed. Development work under progress
Building work completed. Development work under progress
Detail Report
Graph / Photo
55 Const 180 Nos. of additional SPS class rooms (Package-B) 17/03/2019
11/12/2019
15/10/2022
3636.43
2114.12 (Sep'22)

0.00 (Sep'22)
RAMA Contractor 1. Building work completed and sewer connection yet to be done at GGSSS Mayur Vihar Ph-3 (Kondali Gharauli (School Id- 1002352). 2. SKV Gazipur (School Id- 1002184) Handed Over ON 26.08.2022 3. Structure work completed. GRC, Flooring, Plastering and finishing work in progress and development work also in progres at SKV Patparganj (School Id- 1002031)
1. Building work completed and sewer connection yet to be done at GGSSS Mayur Vihar Ph-3 (Kondali Gharauli (School Id- 1002352). 2. SKV Gazipur (School Id- 1002184) Handed Over ON 26.08.2022 3. Structure work completed. GRC, Flooring, Plastering and finishing work in progress and development work also in progres at SKV Patparganj (School Id- 1002031)
Detail Report
Graph / Photo
56 Const 174 Nos. of additional SPS class rooms in various schools (Package-E) 17/03/2019
11/12/2019
30/09/2022
3553.31
2860.77 (Mar'22)

0.00 (Mar'22)
SPS Infrabuild Pvt. Ltd. Inventory submitted to HOS in almost all schools
Inventory submitted to HOS in almost all schools
Detail Report
Graph / Photo
57 Up gradation and Construction of an additional multi- story building in the premise of Forensic Science Laboratory, Rohini, Delhi. 14/11/2019
13/02/2021
31/03/2023
3541.69
763.46 (Aug'22)

0.00 (Aug'22)
Tewatia Construction Pvt. Ltd. work in progress
Detail Report
Graph / Photo
58 Const 184 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 17/03/2019
11/12/2019
15/10/2022
3455.84
3396.76 (Sep'22)

0.00 (Sep'22)
RAMA Contractor Work is in Progress.
Work is in Progress.
Detail Report
Graph / Photo
59 Civil & Electrical Works

3385.59
1924.70 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
60 Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works)

3368.55
405.00 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
61 Construction of Bridge on Supplementary Drain on NH-10, Nangloi, Delhi to cover complete width of 60 m with road improvement in 100 meter length on either side of bridge including making of drainage scheme, footpath etc. complete (after dismantling ). 06/03/2019
05/12/2020
30/11/2022
3350.31
0.00 (Aug'22)
100.00 %
86.00 % (Aug'22)
Ram Kumar Contractor Traffic on newly constructed bridge (upstream & downstream side) had already been diverted. Dismantling of existing bridge and all piling work have been completed. Pile cap work is in progress.
Detail Report
Graph / Photo
62 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II.(Package-F) 27/01/2019
23/10/2019
15/10/2022
3347.23
3720.19 (Jul'22)

0.00 (Jul'22)
BCC DEVELOPERS AND PROMOTERS PVT LTD Work in progress.
Work in progress.
Detail Report
Graph / Photo
63 Comprehensive Maintenance of Ring Road/Outer Ring Road under North Maintenance Zone, PWD, Delhi SH: Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work 30/05/2020
29/05/2022
29/05/2022
3194.88
554.24 (Jul'22)

0.00 (Jul'22)
MAHAVIR PRASAD GUPTA AND SONS Work in Progress
Detail Report
Graph / Photo
64 Civil work and Internal E.I. work 24/04/2007
23/07/2009
31/12/2011
3002.21

Globe Civil Project Pvt. Ltd.
Detail Report
Graph / Photo
65 SKV Sangam Vihar J Block Sch. ID 1923346 17/03/2019
11/12/2019
31/12/2022
3002.10
2469.61 (Sep'22)

0.00 (Sep'22)
Devinder Singh Work is in progress
work is in progress
Detail Report
Graph / Photo
66 Remodelling of 94 nos. Delhi Govt. Dispensaries to Polyclinics. SH - Remodelling of 20 nos. DGD at various places in constituencies of District North of Delhi i/c Water supply, Sanitary, Elec installations, AC, Fire fighting system etc. (Package-I). 05/12/2018
31/07/2019
31/03/2021
2935.52
0.00 (Aug'19)

55.00 % (Aug'19)
Sh. Kamal Singh Work in progress
Work in progress
Detail Report
Graph / Photo
67 Construction of Pucca School Building G plus 3 with ancillary facilities including internal water supply sanitary installation, internal electrical installation and development of sites RWHS STP etc at Sector 05 Rohini Delhi 29/05/2020
28/05/2021
31/10/2022
2931.78
2900.99 (Sep'22)
97.00 %
0.00 (Sep'22)
The Krishna Construction Co. Work in progress
Detail Report
Graph / Photo
68 Street Scaping of Ring Road from Moolchand Junction to Ashram Chowk

2880.35


Detail Report
Graph / Photo
69 SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW 17/10/2019
12/07/2020
31/03/2023
2849.35
1547.54 (Jul'22)

0.00 (Jul'22)
A. K. Builders work in progress.
work in progress.
Detail Report
Graph / Photo
70 Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work.

2820.52
34.01 (Mar'22)

0.00 (Mar'22)

Detail Report
Graph / Photo
71 Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. 28/06/2019
22/06/2020
31/12/2022
2806.33

Roshan Real Estate Pvt Ltd. Work in progress
Work in progress
Detail Report
Graph / Photo
72 Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site, RWHS, STP, Furniture etc at Sector 18, Rohini. (SH: Civil and Electrical Composite Work). 23/05/2020
23/05/2021
31/12/2022
2606.13
794.64 (Sep'22)

0.00 (Sep'22)
Tewatia Construction Pvt. Ltd. Work in progress
Detail Report
Graph / Photo
73 SKV Hari Nagar, Ashram, School ID : 1924043 14/01/2019
10/09/2019
30/09/2022
2464.23
2364.94 (Sep'22)

0.00 (Sep'22)
Reliance Elektrik works work is in progress
work is in progress
Detail Report
Graph / Photo
74 Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi 23/08/2021
22/05/2022
21/11/2022
2373.12
394.52 (Sep'22)
93.00 %
0.00 (Sep'22)
M/s PK Gupta & Co. Earth & foundation work is in progress. Work is being hampered due to the non availability of permission from the SDM office for plying of Good Earth truck.
Detail Report
Graph / Photo
75 SBV Jonapur, School ID: 1923359 08/12/2018
04/08/2019
15/10/2022
2342.87
670.37 (Aug'22)

0.00 (Aug'22)
Reliance Elektrik works work is in progress
work is in progress
Detail Report
Graph / Photo
76 Uttam Nagar T Point Ram Mandir Marg Mall Rd C1 to C1A Block Rd under Sub Division WR12 Lala Ganesh Das Khatri Marg G-1 Block Vikaspuri Rd Rd No 235 Rd Adjacent to PVR under SubDivision WR13 80 Feet Chowkhandi Rd Shakti Mandir Marg Major Sudesh Marg

2305.99


Detail Report
Graph / Photo
77 Strengthening / Resurfacing of carriageway of Auchandi Border to Tatesar Village Road, Princess Road, Model Town II Road, Model Town III Road, Fire Station to Pump House Road, Kushal Cinema Road............... under North Road Division, Delhi

2242.83


Detail Report
Graph / Photo
78 Comprehensive Maintenance of Civil works including day to day maintenance, Annual Repair works and Special Repair works under Maulana Azad Medical College & Guru Nanak Eye Centre New Delhi

1897.81

work completed


work completed

Detail Report
Graph / Photo
79 Strengthening of SSN Marg ID- 392 and 100 Foota Road ID- 1187 New Delhi. 10/09/2020
09/01/2021
09/01/2021
1893.62
3363.83 (Jul'22)

0.00 (Jul'22)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
80 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi.

1887.50

DE submitted to Circle Office A/A & E/s is awaited.
Detail Report
Graph / Photo
81 GGSSS Dera Village School ID: 1923023 08/12/2018
04/08/2019
30/11/2022
1877.31
1736.77 (Sep'22)

0.00 (Sep'22)
Varun Gupta & Co. In progress
In progress
Detail Report
Graph / Photo
82 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 31/05/2020
30/05/2021
31/12/2022
1874.70
494.25 (Sep'22)
97.00 %
0.00 (Sep'22)
SSP Promoters and Builders Private Limited WORK IN PROGRESS
Detail Report
Graph / Photo
83 STREET SCAPING OF 1000 METER OF NELSON MANDELA ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1870.18


Detail Report
Graph / Photo
84 Street Scaping of 800 meter length of Ring Road, Bhairon Road T-Junction to Shantivan Crossing to make it Model Stretch of Street Scaping Project

1859.21


Detail Report
Graph / Photo
85 Furniture Work RECALL 04/11/2019
18/12/2019
1858.08
6.26 (Sep'21)

0.00 (Sep'21)
Rajdhani Furnitures PVT. LTD.
Detail Report
Graph / Photo
86 STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1848.01
647.29 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
87 Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project

1814.36
0.79 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
88 Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project

1814.36
0.10 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
89 Balance Civil, Electrical and Horticulture Work as per revised concept

1809.71


Detail Report
Graph / Photo
90 C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc 01/04/2022
24/02/2023
24/02/2023
1798.93
60.00 %
K. L. ARORA & SON Demolition completed at A C C GSBV at Jhilmil Colony, Delhi. Structural drawing issued to agency. Demolition completed & Pile work just started at Mustafabad
Demolition completed at A C C GSBV at Jhilmil Colony, Delhi. Structural drawing issued to agency. Demolition completed & Pile work just started at Mustafabad
Detail Report
Graph / Photo
91 Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi 22/11/2021
17/10/2022
17/10/2022
1773.27
821.69 (Jul'22)
100.00 %
0.00 (Jul'22)
Harbel Singh & Sons The work in progress..
Detail Report
Graph / Photo
92 C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) 29/12/2018
26/07/2019
30/11/2022
1743.19
3875.65 (Jul'22)

0.00 (Jul'22)
AMAR CONSTRUCTION COMPANY Work in progress
Detail Report
Graph / Photo
93 STREET SCAPING OF 700 METER LENGTH OF K.N. KATJU MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1644.08


Detail Report
Graph / Photo
94 Providing Manpower services of Clericals, Drivers, Multitasking and Staff (Un-skilled, Semi -skilled, Clerical and Non- Technical Supervisory Staff) in various offices under the jurisdiction of Health Maintenance Zone, PWD 03/04/2019
02/04/2021
1625.72

RAKSHAK SECURITAS PVT. LTD.
Detail Report
Graph / Photo
95 Construction of conventional Cluster Bus Depot No. II at Burari, Delhi.(SH: Civil & Electrical works).

1620.46

Nafees Ahmed

Tender for the work invited on 04.03.2022. Letter of commencement issued on 30.04.2022. Date of start and date of completion will be decided after getting approval from Forest Department.


Detail Report
Graph / Photo
96 Development of Synthetic Athletic Track with Football field and Synthetic Hockey Turf in Rajiv Gandhi Sports Complex Singhu Delhi 08/03/2021
02/11/2021
30/09/2022
1583.17
772.97 (Sep'22)

0.00 (Sep'22)
Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 Hockey field & synthetic Athletic Track is completed. Certificates from FIH and IAAF have been received. Structural work os construction of change rooms completed and plumbing work is in progress. Physical progress is 88%.
Detail Report
Graph / Photo
97 C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc 26/03/2022
19/02/2023
19/02/2023
1553.88
0.83 (Sep'22)
70.00 %
0.00 (Sep'22)
K L Arora & Son First floor slab beam bottom shuttering in progress. Foundation RCC in Progress in DIET Block. MP Hall above second level beam column steel binding in progress.
First floor slab beam bottom shuttering in progress. Foundation RCC in Progress in DIET Block. MP Hall above second level beam column steel binding in progress.
Detail Report
Graph / Photo
98 C/o 72 Nos. Equivalent SPS Class Rooms in addition to boundary wall i/c Internal & External water supply, sanitary installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting System etc. for new school building at GBSSS Jharoda kalan (School ID 1822065) , New Delhi

1542.27

The Krishna Construction Co. Work awarded to The Krishna Construction Co. .
Detail Report
Graph / Photo
99 C/o 56 Nos. additional (G+3) SPS equivalent Class Rooms including 1 stilt , 8 nos toilet, 4 nos staircase, lift, RWH & UGR at Govt. Co Senior Secondary School at Usmanpur, Delhi (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.)

1530.73

WORK FORE CLOSED SITE NOT CLEAR
WORK FORE CLOSED SITE NOT CLEAR
Detail Report
Graph / Photo
100 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1524.43


Detail Report
Graph / Photo
101 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1524.43
56.90 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
102 STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT.

1480.89


Detail Report
Graph / Photo
103 STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1480.89
2233.49 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
104 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24

1462.16


Detail Report
Graph / Photo
105 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 03/06/2022
02/06/2024
02/06/2024
1438.47
0.29 (May'22)

0.00 (May'22)
Work in progress.
Detail Report
Graph / Photo
106 STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1379.62


Detail Report
Graph / Photo
107 Construction of 80 Nos G plus 3 equivalent SPS Class Rooms at Govt Co Ed Sr Secondary School Gandhi Brahampur Delhi including 8 toilet blocks, 4 nos staircase 1 lift and internal and external water supply sanitary installations, electrical installations, development of site, RWH & UGR fire fighting system etc. 26/03/2022
19/02/2023
19/02/2023
1377.43
70.00 %
K. L. ARORA & SON The work is FORE CLOSED
The work is FORE CLOSED
Detail Report
Graph / Photo
108 Operation & Maintenance of EI & Fans, HVAC, Sub Stations, DG Sets, UPS, Fire Fighting System, Fire Alarm System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24

1369.68


Detail Report
Graph / Photo
109 C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc 02/04/2022
25/02/2023
30/09/2022
1359.28
60.00 %
K. L. ARORA & SON Foundation work in progress.
Foundation work in progress.
Detail Report
Graph / Photo
110 Operation & Maintenance of EI & Fans, DG Sets, Fire Engine, HVAC Works, Fire Alarm System, Fire Fighting and Wet Riser System, Sub Station, Solar Water Heating System etc. for the year 2022-23 and 2023-24.

1350.14


Detail Report
Graph / Photo
111 Civil works relating to day to day maintenance, A/R & M/O Works & Special Repair Works 10/05/2022
08/05/2024
08/05/2024
1313.79
102.59 (Aug'22)
21.00 %
0.00 (Aug'22)
Raghav Engineers

work completed


work completed

Detail Report
Graph / Photo
112 Comprehensive maintenance of Civil services at Deen Dayal Upadhyaya Hospital & Residential Complex, Hari Nagar, Janakpuri Superspeciality Hospital C2B Janakpuri New Delhi, Shree Dada Dev Matri avum Shishu Chikitsalya, Dabri and DG at various places, P.W.D (GNCTD), New Delhi for 2 years i.e. 2022-2023, 2023-24

1296.91


Detail Report
Graph / Photo
113 Operation & Maintenance of E.I, pumps, sub-station, DG Sets, firefighting & fire alarm system, HVAC & AC units & R.O. Plant etc

1286.89


Detail Report
Graph / Photo
114 Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) 12/03/2022
04/02/2023
04/02/2023
1275.84
64.00 %
M/s SURENDRA KUMAR Pile Load Test is completed. Earth filling in progress. Some minor changes to be required in architectural drawings.
Detail Report
Graph / Photo
115 Resurfacing improvement strengthening riding surface of roads ..... road division 13/01/2020
08/04/2020
1272.87
876.72 (Sep'21)

0.00 (Sep'21)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
116 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and Placing of Medical Furnitures at Indira Gandhi Hospital, Dwarka, New Delhi) 11/07/2021
23/09/2021
30/09/2022
1244.16
90.14 (Aug'22)

0.00 (Aug'22)
Godrej & Boyce Mfg. Co. Ltd. Work is under progress.
Detail Report
Graph / Photo
117 STREET SCAPING OF 800 METER LENGTH OF RING ROAD, BHAIRON ROAD T-JUNCTION TO SHANTIVAN CROSSING TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1226.77


Detail Report
Graph / Photo
118 GGSS No. 3 Sec IV, Ambedkar Nagar 03/03/2016
15/07/2016
31/01/2017
1212.87
1221.00 (Jan'18)

100.00 % (Jan'18)
Devinder Singh completed
null
Detail Report
Graph / Photo
119 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping projec

1193.08
2182.65 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
120 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project

1193.08


Detail Report
Graph / Photo
121 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project

1193.08


Detail Report
Graph / Photo
122 Widening of Mehrauli Mahipal pur Road from 4 lanes to 8 lanes and service road from Andheria More to Fortis Hospital.(SH- Balance work for available land from Chainage 700Mtr. to 2100mtr.)

1157.23


Detail Report
Graph / Photo
123 STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1119.07


Detail Report
Graph / Photo
124 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and Placing of Non-Medical Furnitures at Indira Gandhi Hospital, Dwarka, New Delhi). 11/07/2021
23/09/2021
30/09/2022
1118.83

M/s Rajdhani Furnitures Pvt. Ltd. Work is under progress.
Detail Report
Graph / Photo
125 Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi 06/04/2022
05/04/2025
05/04/2025
1099.29
16.00 %
SIKKA ASSOCIATES REGD. The work has been awarded to the agency. The presentation of the proposed University has been made with Dy. CM of GNCTD Delhi as on dt. 08.04.2022. Modification made as per observations of DSU Committee and Hon'ble Minister. Sent to Joint registraor approval vide letter No. 54(103)/EE/EPD-III//PWD/2022-23/443 dated 08.08.2022.
Detail Report
Graph / Photo
126 Comprehensive Maint. of Civil, Electrical and Horticulture Operations relating Day to day Maint., Special Repair etc of Dr. BSAH Complex, Sector 6, Rohini, Delhi incl. Main Hospital Bldg., Medical College, Hostel and Residential Qtrs. Dg. 2019-20-21.

1097.15
371.30 (Aug'22)

0.00 (Aug'22)
Work Completed
Work Completed
Detail Report
Graph / Photo
127 C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) 18/04/2022
13/03/2023
13/03/2023
1090.67
70.00 %
K. L. ARORA & SON Plinth beam casted in Block -A Footing in progress in Block -B
Plinth beam casted in Block -A Footing in progress in Block -B
Detail Report
Graph / Photo
128 Reconstruction of CC Road including raising of Railway Road at SamaypurBadli Village, Durga Chowk to Gujjar Chowk at Bhalswa Dairy and Mangal Bazar Road at Jahangirpuri, Delhi

1080.14


Detail Report
Graph / Photo
129 Reconstruction of CC Road including raising of Railway Road at SamaypurBadli Village, Durga Chowk to Gujjar Chowk at Bhalswa Dairy and Mangal Bazar Road at Jahangirpuri, Delhi(Second Call)

1080.14


Detail Report
Graph / Photo
130 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi (Balance Work)

1076.89


Detail Report
Graph / Photo
131 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1041.75


Detail Report
Graph / Photo
132 Operation & Maintenance of EI & Fans, HVAC, DG Sets & Sub Stations, Fire Alarm System, Fire Fighting and Wet Riser System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24

1031.52
77.82 (Aug'22)

0.00 (Aug'22)

Detail Report
Graph / Photo
133

1026.09
0.38 (Aug'20)

0.00 (Aug'20)
100%
completed
Detail Report
Graph / Photo
134 Mechanised House Keeping and Security Services/Facility Management services (FMS) for Chandni Chowk Road and appurtenances/System installed from Lal Jain Mandir to Fatehpuri Mosque for the Period 2022-2023(1 Years)

989.13
98.04 (Oct'22)

0.00 (Oct'22)

Detail Report
Graph / Photo
135 Strengthening of road surface of Outer Ring Road from Modi Mill to Chirag Delhi (Masjid Moth). 27/05/2018
26/07/2018
966.91
436.54 (Apr'19)

73.00 % (Apr'19)
-
In progress
Detail Report
Graph / Photo
136 Strengthening of Outer Ring Road from Modi Mill to Chirag Delhi Masjid Moth

966.91


Detail Report
Graph / Photo
137 Strengthening of various roads of Shalimar Bagh area under PWD Division North West Road-1 and under Sub Division NWR-14 During 2022-23

960.08


Detail Report
Graph / Photo
138 Strengthening of various roads under PWD Division North West Road-1 under Sub Division NWR-12 During 2022-23

954.00


Detail Report
Graph / Photo
139 Strengthening of Nangloi-Najafgarh Road from Nilothi Mor to Airforce Bani Camp under WR-14, PWD New Delhi

953.94
671.44 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
140 Strengthening of Ring Road from Prembari Pull to Azadpur Flyover including recarpeting of wearing course of Shalimar Bagh Elevated Road

953.71


Detail Report
Graph / Photo
141 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12

940.18


Detail Report
Graph / Photo
142 Construction of 45 Nos. Porta Cabin Aam Admi Mohalla Clinics in schools under Sub Division-I, II, III and IV under South West Building Maintenance Division, New Delhi. (SH- Civil and Electrical Works). 12/02/2019
11/06/2019
11/06/2019
939.06
534.29 (Jul'22)

0.00 (Jul'22)
WORK IN PROGRESS
Detail Report
Graph / Photo
143 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi

935.00


Detail Report
Graph / Photo
144 Construction of FoB/Skywalk from Supreme Court Metro Station to Additional Building Supreme Court and Supreme Court Main Campus on Mathura Road, New Delhi

926.03

Not pertains to this office
Detail Report
Graph / Photo
145 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi.(Balance Work)

919.83


Detail Report
Graph / Photo
146 Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc.

914.69


Detail Report
Graph / Photo
147 STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

910.96
287.40 (May'22)

0.00 (May'22)

Detail Report
Graph / Photo
148 Running operation of lifts 06/05/2021
05/05/2024
05/05/2024
909.76
46.00 %
Guruji Elevator
Detail Report
Graph / Photo
149 Strengthening of Shyamji Krishan Verma Marg, Sardar Balbir Singh Sindhu Marg, Kabir Dass Marg, Rampura Main Road & Lala Lajpat Rai Marg under PWD Division North West Road-1 and under Sub Division NWR-11 During 2022-23

899.50


Detail Report
Graph / Photo
150 Strengthening of various roads under sub division NWR-24, Division NWR-2, SainikVihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW

880.22
482.65 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
151 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc. of Lal Bahadur Shastri Hospital Campus Khichripur, Delhi, Jag Pravesh Chandra Hospital, Campus Shastri Park Delhi and Chacha Nehru Bal Chikitsalya, Hospital, Campus, Geeta Colony, DGD-12/113, Geeta Colony, DGD, New Lahore, Shastri Nagar, Delhi during 2022-23 and 2023-24

874.44

The work has been awarded to the M/s Jain Electric Works.
Detail Report
Graph / Photo
152 Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi. (Civil and Electrical Work)

871.75


Detail Report
Graph / Photo
153 Strengthening of road at Dev Parkash Shastri Marg under PWD Sub Division-III, S.W.R-I, New Delhi

871.07


Detail Report
Graph / Photo
154 Operation and Maintenance of EI and FANS Sub Station and DG Set HVAC Works Fire Fighting and Wet Riser System Fire Alarm System Lifts RO Plant etc

866.40


Detail Report
Graph / Photo
155 Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) 17/09/2022
15/12/2022
15/12/2022
861.04
32.00 %
SBG Infracon Pvt Ltd
Detail Report
Graph / Photo
156 Replacement of Bearings and Expansion joint and repair of Bearing Pedestal

859.23

.
Detail Report
Graph / Photo
157 Replacement of Bearings and Expansion joint and repair of Bearing Pedestal

859.23

1
Detail Report
Graph / Photo
158 Construction of Pedestrian Underpass Subway Across Aurobindo Marg Between Delhi Haat and Entry No 4 of East Kidwai Nagar. 27/10/2020
26/08/2021
31/08/2022
856.26
55.63 (Jun'22)

0.00 (Jun'22)
M/s Satish Builders Initially the work was delayed due to restriction of COVID-19. Work is in progress in Delhi HAAT side & NBCC side entry / exit. The traffic in central portion has been opened after construction of box. The shifting of NDMC water and sewage services are in progress.
Detail Report
Graph / Photo
159 Construction of 66 feet Libaspur Gurudwara Road including providing street light fittings (SH- Civil and Electrical Work)

849.98


Detail Report
Graph / Photo
160 Operation & Maintenance of EI & FANS, Sub Station & DG Set, HVAC Works , Firen Fighting and Wet Riser System, Fire Alarm System, Lifts, RO Plant etc.

843.88


Detail Report
Graph / Photo
161 Providing Data Entry/Computer Operators, Diary Dispatcher/LDC/ Office Clerk, MTS/Messengers, LMV Drivers, Peon etc. for various offices under Project Circle, SRD Project Division-I and DHC & ND/ Central (M-451)

840.52


Detail Report
Graph / Photo
162 Upgradation of staff rooms in 120 Schools under South West Building Maintenance Division, NCC Building, safdarjung Enclave, New Delhi.(SH- Civil, Electrical and furniture works). 11/02/2019
10/06/2019
10/06/2019
833.12
540.13 (Jul'22)

0.00 (Jul'22)
WORK IN PROGRESS
Detail Report
Graph / Photo
163 Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc

831.74


Detail Report
Graph / Photo
164 Construction of 55 Nos. Aam Admi Mohalla Clinic at various locations under South-East (M), Circle, New Delhi during 2018-19. 15/12/2018
12/06/2019
12/06/2019
827.90
290.07 (Oct'19)

17.00 % (Oct'19)
S. P. Construction Work in progress
Detail Report
Graph / Photo
165 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). 30/09/2022
29/03/2023
29/03/2023
818.33
16.00 %
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
166 Strengthening of various roads of Pitampura area under PWD Division North West Road-1 and under Sub Division NWR-14 During 2022-23

802.14


Detail Report
Graph / Photo
167 Strengthening of Ring Road, Haytt Regency to Moti Bagh (Road ID No. 3), Kama Koti Marg (Road ID No. 343), Premnath Dogra Marg (Road ID No. 342) and Restoration of Road from Ch. Jhandhu Singh Marg to Africa Avenue Crossing cut by RailTel Under PWD Sub Division 2 of Division SWR I, New Delhi

793.03


Detail Report
Graph / Photo
168 Strengthening of Asiad Games Village Road (ID 1137), NIFT Road (ID-1139), Subhash Chopra Road (ID-1138) and August Kranti Marg (ID-16) through cold milling and recycling process under Sub-Division-1 of Division South Road-2 PWD, New Delhi

792.82


Detail Report
Graph / Photo
169 Strengthening of Road No. 235, Guru Virjanand Marg, Road between Jupiter Appt. to Priya Appt., Nalanda Appt. to Nightingale Appt., Navyug Appt. to IFC drain (Brotherhood Appt.), Road between Devdoot Appt. to Parmarth Appt., Road between Kirti Appt. to DAV school, Road between Lok Vihar Appt. (PWD Road) to F-block Market, Road Sunrise Appt. to DAV School, Road from F-234 to IFC drain (Over head tank) Vikaspuri, Road from ITICorner to Central School, Road starting from Oxford School to Airport Appt. and Road No. 236 at Vikaspuri under sub division WR-14, Division WR-1

790.08
560.02 (Aug'22)

0.00 (Aug'22)

Detail Report
Graph / Photo
170 Addition Alternation in Residence of Honble Chief Minister at 6 Flag Road, Civil Lines, Delhi during 2020 21 (SH:Providing additional Accommodation Civil and Electrical works)

761.07
2690.72 (Aug'22)

0.00 (Aug'22)

Detail Report
Graph / Photo
171 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi 14/07/2022
13/10/2022
13/10/2022
751.50
99.00 %
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
172 Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054

747.65


Detail Report
Graph / Photo
173 Providing furniture in various schools for additional SPS class rooms under Zone West Delhi Education Zone 16 17 and other schools Priority-I

744.08

GEEKEN SEATING COLLECTION PVT LTD work in progress
Detail Report
Graph / Photo
174 Comprehensive Maintenance of Civil works relating Day to day Maintenance, Annual Repair, Special Repair and routine maintenance work etc. of Deep Chand Bandhu Hospital, Ashok Vihar, Phase-IV, Delhi, Babu Jagjivan Ram Hospital, Jahangirpuri, Delhi, Attar Sain Jain Eye Hospital, various dispensaries at Jahangirpuri, Delhi and Bhagwan Mahavir Hospital, Pitampura, Delhi during 2022-23 and 2023-24 06/06/2022
05/06/2024
05/06/2024
741.51
17.00 %
Dilshad Khan
Detail Report
Graph / Photo
175 Strengthening of road of Bawana to Auchandi Border under Sub-Division NR-15, PWD Division North Roads, Delhi 28/04/2022
24/10/2022
24/10/2022
718.31
432.60 (Aug'22)
98.00 %
0.00 (Aug'22)
SBG Infracon Pvt Ltd
Detail Report
Graph / Photo
176 Strengthening of Outer Ring Road from Wazirabad Flyover to Gandhi Vihar Subway under Sub Division-1, Division C&ND-Road, PWD, New Delhi. 24/06/2022
23/08/2022
23/08/2022
717.68
233.20 (Aug'22)

0.00 (Aug'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
177 (A) Strengthening of Major Somnath Marg (Road ID -338) from Rao Tula Ram Marg to Outer Ring Road Under PWD Division South West Road-I, Under Sub Division-I, New Delhi. (B) Strengthening of Babu Genu Marg (Road ID -341) from RTR Marg to Major Somnath Marg Red Light Under PWD Division South West Road-I, Under Sub Division-I, New Delhi. (C) Road restoration cut by DRDO and various agencies at Moti Bagh Ring Road Crossing to Sangam Cinema on Major Somnath Marg and Outer Ring Road (Subroto Park) Under PWD Division South West Road-I Under Sub Division-I, New Delhi.

704.50


Detail Report
Graph / Photo
178 Laying of RCC Drain/pipe and raising of levels of existing carriage way of Ring Road in between toe of IP Flyover and opposite of WHO Building including laying of 1200mm dia. Pipe through trenchless pushing to solve water logging problem, New Delhi. 28/04/2022
11/07/2022
11/07/2022
694.86
509.48 (Aug'22)

0.00 (Aug'22)
A S INFRATECH
Detail Report
Graph / Photo
179 Strengthening of Outer Ring Road from Gandhi Vihar to Burari Flyover under Sub Division-1, Division C&ND-Road New Delhi. 24/06/2022
23/08/2022
23/08/2022
690.38
423.88 (Sep'22)

0.00 (Sep'22)
SBG Infracon Pvt Ltd
Detail Report
Graph / Photo
180 Civil work Desilting of drains and other Misc repair work of footpaths Central verge Services Roads etc on various roads except Ring Road under Sub Division NW R 14

684.86


Detail Report
Graph / Photo
181 Re laying of World Athletics approved 400 Mtr. synthetic athletic track at Chhatrasal Stadium, Delhi 26/03/2022
24/07/2022
24/07/2022
679.06

ADVANCED SPORT TECHNOLOGIES LLP Work in progress
Work in progress
Detail Report
Graph / Photo
182 Construction of Old Age Home including electrical work at BG-6, Paschim Vihar, Delhi. (Composite work).

668.69

Work is held up for Architectural Plan & revised plan submitted to fire department for approval by SA


Detail Report
Graph / Photo
183 Remodeling of drain from 25 futa road, Meet nagar to Loni Gole Chakkar at Road No.-63, Construction of sump well at loni Gole Chakkar & MIG/ LIG Flat, Providing and laying K-9 pipe from Loni gole Chakkar to Drain No-01 & Construction of pump House, Electrical & mechanical Services at Loni Gole Chakkar & MIG/ LIG Flat. 31/03/2022
28/07/2022
28/07/2022
657.45
100.00 (Sep'22)

0.00 (Sep'22)
K. L. ARORA & SON
Detail Report
Graph / Photo
184 Providing Automated Housekeeping at Honble CM Residence and Bungalow of Delhi Council of Ministers Delhi

649.40
281.99 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
185 Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi 28/04/2022
24/10/2022
24/10/2022
643.92
1.88 (May'22)
98.00 %
0.00 (May'22)
Kundu Nirma
Detail Report
Graph / Photo
186 Construction installation and commissioning and there after Operation and Maintenance for Five Years of Bio remediation waste water treatment plant using Inert Solid Removal ISR technology of capacity 2.5 MLD and construction of under Ground

643.55
93.60 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
187 Construction of 30 Nos. Porta Cabin Aam Admi Mohalla Clinics under Sub division- I,II,III and IV under South West Building Maintenance Division New Delhi. (SH Civil works and Electrical works). 06/12/2018
02/08/2019
02/08/2019
642.82
308.01 (May'22)

0.00 (May'22)
WORK IN PROGRESS
Detail Report
Graph / Photo
188 BITUMINOUS WORK, LENGTH 2.15 KM.

642.71

work completed
Detail Report
Graph / Photo
189 Strengthening of roads from Nangli Poona to Mohan Adda, Khera Kalan Road, Safiabad Mor to Safiabad Border, Holambi Kalan Crossing to Bawana Narela Road via Metro Vihar, under Sub-Division NR-13 of North Road Division, PWD, Delhi 20/03/2022
17/07/2022
17/07/2022
640.59
428.55 (Sep'22)

0.00 (Sep'22)
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
190 Resurfacing of roads from (i) Lampur Mor to Lampur Border, (ii) Ramdev Chowk to Railway crossing Narela, (iii) Y-section Narela to Shahpur Garhi Turn, under Sub-Division NR-13, North Roads Division, PWD, Delhi 20/03/2022
17/07/2022
17/07/2022
617.72
171.52 (Aug'22)

0.00 (Aug'22)
Sethi Construction
Detail Report
Graph / Photo
191

616.71
5.76 (Nov'19)

0.00 (Nov'19)

Detail Report
Graph / Photo
192 Strengthening of Apeejay School Road Sheikh Sarai Phase-1 Road no.1 and Road no.-2 Khirki Road Birla Vidya Niketan Marg Mandir Marg Main Road Sector-1 Pushp Vihar Pankaj Juyal Marg H-Block Road and NBCC Plaza Road under sub division SR-14. 15/11/2019
14/05/2020
14/05/2020
615.93
841.57 (Sep'22)

0.00 (Sep'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
193 Strengthening of Road No. 56 i.c Service Road from Gazipur Grade Separator to Apsara Border and its subsequent maintenance for three years. 27/11/2021
26/03/2022
26/03/2022
615.26
404.49 (Jul'22)

0.00 (Jul'22)
Pawan Kumar
Detail Report
Graph / Photo
194 Co Missing drain and Footpath from Jharoda Stand to Mungeshpur Drain and Drains upto Bahadurgarh Border with Footpath at Border area under PWD Division SWR II New Delhi ID 1231

612.10

WORK COMPLETED 19/08/2019
WORK COMPLETED 19/08/2019
Detail Report
Graph / Photo
195 Upgradation/Renovation of one staff room in each 951 schools, Civil and Electrical work (SH- Staff rooms 75 no. under south Building Maintenance Division). 14/03/2019
13/09/2019
29/02/2020
610.61
221.28 (Mar'21)

0.00 (Mar'21)
S.M. Builders work in progress
work in progreess
Detail Report
Graph / Photo
196 Construction of 30 Nos. additional SPS hostel rooms and 2 Nos. staircase i/c internal and external water supply i/c sanitary installation, development of site and fire fighting system and provision of EI and Fans and other misc works at KISS Issapur. 13/02/2019
11/08/2019
11/08/2019
598.97
452.10 (Jun'22)

0.00 (Jun'22)
WORK IN PROGRESS
Detail Report
Graph / Photo
197 Upgradation of one staff room, each at 951 School under Delhi Govt. SH 123 Nos. of staff rooms under West Maintenance Circle.

593.40
154.27 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
198 Operation & Maintenance of E.I, pumps, substation, DG Sets, fire fighting & fire alarm system, HVAC & ductable AC system, lift, Cold Room & solar water heating system etc.

591.05


Detail Report
Graph / Photo
199 Construction of 30 Nos. Aam Admi Mohalla Clinic at various places under south building (M) Division/South District. 10/01/2019
08/07/2019
30/09/2019
585.53
102.73 (Oct'22)

0.00 (Oct'22)
P S ASSOCIATES work in progress
work in progreess
Detail Report
Graph / Photo
200 Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB 25/09/2022
24/01/2023
24/01/2023
583.83
24.00 %
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
201 Providing stone Matrix Asphalt(SMA) under Sub Division-II, South West Road-II Najafgarh, New Delhi 23/11/2021
21/01/2022
21/01/2022
581.89
103.00 (Sep'22)

0.00 (Sep'22)
Pawan Kumar
Detail Report
Graph / Photo
202 Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work 28/01/2022
27/12/2022
27/12/2022
579.95
194.03 (Sep'22)
81.00 %
0.00 (Sep'22)
R.K ENTERPRISES Work is in progress 3%
Detail Report
Graph / Photo
203 Construction of Two No Foot Over Bridge across (i)Sri Aurobindo Marg (ID-96) at Adhchini Village (ii) Hauz Khas Enclave (Near Padmini Enclave) with staircase and lift including Electrical Installation under Sub Division-II of Division South Road-II 21/03/2020
20/09/2020
20/09/2020
572.75
207.36 (Jun'22)

0.00 (Jun'22)
Work in Progress.
Work in Progress.
Detail Report
Graph / Photo
204 Strengthening of Najafgarh Jharoda Road ic raising of depressed road at Ekta Vihar under Sub Division II South West Road II PWD New Delhi. ID 1231 16/10/2019
12/02/2020
12/02/2020
567.80
236.37 (Jul'20)

0.00 (Jul'20)
Pawan Kumar WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
205 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12

559.69


Detail Report
Graph / Photo
206 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12

559.69


Detail Report
Graph / Photo
207 Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW 27/02/2022
26/06/2022
26/06/2022
548.07

RK Brothers
Detail Report
Graph / Photo
208 Construction of Crash Barrier Expansion Joints and replacement of Bearings

545.00

Work in progress


null
Detail Report
Graph / Photo
209 Construction of Crash Barrier Expansion Joints and replacement of Bearings

545.00

Work in progress


null
Detail Report
Graph / Photo
210 Construction of Back to back U-turn near Aali Village Red-light and Single U-Turn for Sarita Vihar Colony to facilitate signal free and congestion free movement of traffic on Mathura Road under SER-2/22.(Road ID-961)

542.85
0.15 (Jun'22)

0.00 (Jun'22)

Detail Report
Graph / Photo
211 Providing services of Maintenance vehicle with labour & T&P etc. for all Sub-Division for two year

542.39


Detail Report
Graph / Photo
212 Improvement and strengthening of Road No. 63, Delhi (From Bhopura Border to Loni Gol Chakkar except flyover). 14/12/2019
12/03/2020
541.95

M/s Roadtech
Detail Report
Graph / Photo
213 Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. 02/11/2018
01/11/2019
01/11/2019
539.98
214.77 (Sep'19)

0.00 (Sep'19)
Work in progress
No
Detail Report
Graph / Photo
214 Civil work Mechanized Desilting of drains and other Misc repair work of footpaths Central verge Services Roads etc on others roads than outer ring road under Sub Division NW R 13

538.80


Detail Report
Graph / Photo
215 Civil work comprehensive maintenance of Shanker Road and Vandematram Marg including carriageway, footpaths, central verge, Service road etc within the right...

535.97


Detail Report
Graph / Photo
216 Strengthening of Arterial Roads having right of way more than 30.00 metre like Satyagrah Marg, IG Slip Road, Velodrome Road, Sachivalya Road, Club Road & Flag Staff Road under Sub Division – 3 of Division C & ND – Roads, New Delhi 31/03/2022
30/06/2022
30/06/2022
535.88
469.00 (Jun'22)

0.00 (Jun'22)
A S INFRATECH
Detail Report
Graph / Photo
217 Renovation / construction works at Rajiv Gandhi Stadium, Bawana 07/07/2022
04/11/2022
04/11/2022
535.01
74.00 %
M/s Vinod Kumar & Company
Detail Report
Graph / Photo
218 Providing services of Maintenance vehicle with labour and T and P etc for Division NW R 1 for two year

533.23


Detail Report
Graph / Photo
219 Providing and Fixing Customized Furniture and Interior works 24/09/2020
22/11/2020
30/09/2022
533.13
67.22 (Sep'22)

0.00 (Sep'22)
M/s Rajasthan Decorators Work is in progress
Detail Report
Graph / Photo
220 CIVIL Works - Comprehensive maintenance of various roads i/c carriageway, footpaths, central verge within right of way, mechanised desilting of drains etc and other mi

533.12


Detail Report
Graph / Photo
221 Resurfacing of roads from (i) Shahpur Garhi Turn to Old GTK road Alipur, (ii) Shubhash Chowk to Palla Village via Bakhtawarpur, (iii) Holambi Khurd Crossing to Shahpur Garhi turn, (iv) New GTK Road to Old GTK Road (via Shani Mandir), (v) New GTK Road to Old GTK Road (via PHC Alipur) under Sub-Division NR13, PWD North Roads Division, Delhi. 20/03/2022
17/07/2022
17/07/2022
526.50
528.46 (Aug'22)

0.00 (Aug'22)
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
222 Strengthening of Swaroop Nagar Road with Construction of footpath on existing drain and improvement of road side berm from Main Burari Road to Kathia Baba Ashram under Sub Division-1, C&ND-Road Division Delh 28/04/2022
27/06/2022
27/06/2022
523.21

MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
223 Strengthening of Mandi Road (ID- 548) and Aya Nagar Road (ID- 1191) of Division SR-1 under Sub-Division SR-13 at New Delhi

493.83
106.22 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
224 Construction of Two No. Foot Over Bridge across Sri Aurobindo Marg (ID-96) at (i) PTS Bus Stop (ii) T.B. Hospital with staircase and lift including Electrical Installations under Sub Division-II of Division South Road-II, PWD New Delhi. 21/03/2020
20/09/2020
20/09/2020
489.85
203.60 (Jun'22)

0.00 (Jun'22)
S S Chauhan & Sons Work in Progress.
Work in Progress.
Detail Report
Graph / Photo
225 Running and Maintenance of lifts installed in residential and non-residential buildings at GTB Hospital complex, Shahdara, Delhi Sub Head Running operation of lifts 17/01/2019
16/01/2021
16/01/2021
485.43

Guruji Elevator Work in progress 3RD RA 40220380
Detail Report
Graph / Photo
226 Nazafgarh Road to A-71, Rajauri Garden, A-31 Rajauri Garden, 20-Block Tilak Vihar Road, Radhaswami Satsang Marg and Tilak Nagar Main Market Road under PWD Division WR-1, New Delhi.

481.51


Detail Report
Graph / Photo
227

477.75


Detail Report
Graph / Photo
228 Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 30/09/2014
26/05/2015
31/01/2016
474.90
61.36 (May'19)

0.00 (May'19)
Work completed on 31/12/2017 final payment yet to be made
EOT, Deviation under process of sanction by the competent authority now the sanction has been received and final payment yet to be made
Detail Report
Graph / Photo
229 EOR and face-lifting to Existing building of RPVV (Rajakiya Pratibha Vikas Vidyalaya) for Establishment of New DIET at Thyagraj Nagar, New Delhi during 2021-22 (Civil and Electrical works)

469.68
172.68 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
230 Construction of Foot Over Bridge with staircase and lift for padestrian at Rao Tula Ram Marg (Road ID-98) near Petrol Pump, New Delhi.

465.11


Detail Report
Graph / Photo
231 Repair and Rehabilitation of facade and other RCC members ic water tank and water proofing of terrace of Vyaapar Bhawan Deptt of Trade and Taxes Building IP Estate New Delhi

463.67


Detail Report
Graph / Photo
232 Remodeling of Drain with Development of Kuccha Portion along the ESI Hospital Road and Road along B-Block Jhilmil under Sub Division M-2112 during 2021-22 02/04/2022
28/09/2022
28/09/2022
462.00
86.51 (Sep'22)
100.00 %
0.00 (Sep'22)
PRATAP SINGH
Detail Report
Graph / Photo
233 Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone

460.45


Detail Report
Graph / Photo
234 Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone

460.45


Detail Report
Graph / Photo
235 Civil Work Mechanized Desilting of drains and other Misc repair work of footpaths central verge Services Roads etc roads under Sub Division NWR 11

460.24


Detail Report
Graph / Photo
236 Civil Work Mechanized Desilting of drains and other Misc repair work of footpaths central verge Services Roads etc roads under Sub Division NWR 11 RECALL

460.24


Detail Report
Graph / Photo
237 Comprehensive repair and maintenance of various roads under sub division M- 2132. 21/11/2019
20/11/2020
460.10
504.82 (Sep'22)

0.00 (Sep'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
238 Widening and Strengthening of Bandh Road of Division SR-1 under Sub-Division SR-13 at New Delhi i/c shifting and installation of Electrical Poles Street lights etc. 01/12/2019
31/05/2020
459.03
354.65 (Jul'22)

0.00 (Jul'22)
Bansal Associates
Detail Report
Graph / Photo
239 Rehabilitation and strengthening of Janak Setu Flyover in New Delhi (Balance Work) 29/03/2020
29/09/2020
31/03/2021
457.44
23.39 (Sep'21)

0.00 (Sep'21)

Work in progress


null
Detail Report
Graph / Photo
240 A/R & M/O Various roads under East Road Sub Division-III, Division East Road (M 212) during 2019-20. (SH:- Comprehensive maintenance of road) 15/10/2019
14/10/2020
455.11
418.02 (May'22)

0.00 (May'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
241 A/R and M/O Roads under PWD North-Roads, PWD dg. 2018-19 (SH -Providing services of Computer Operators, MTS, LMV Drivers, Clerical Staff, maintenance staff, chowkidars etc. in the office of North Maintenance Circle, PWD .....

448.46


Detail Report
Graph / Photo
242 Civil Works - Mechanised Sweeping and Cleaning of Roads including Carriageway, Footpaths, Central Verge, Service Roads etc. within the right of way, Mechanised Desilting

448.15


Detail Report
Graph / Photo
243 Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24

445.82


Detail Report
Graph / Photo
244 Providing services of Computer Operators MTS and Drivers etc 06/05/2022
05/05/2023
05/05/2023
441.58
115.48 (Sep'22)
41.00 %
0.00 (Sep'22)
M/s R D Excellent Services Pvt. Ltd. work in progress
Detail Report
Graph / Photo
245 Comprehensive Maintenance of Civil works including day to day maintenance, Annual Repair works of A&U Tibbia College, Dr. N.C. Joshi Hospital, Aruna Asaf Ali Govt. Hospital, Sushruta Trauma Centre, Subzi Mandi, Mortuary & 34 Nos. Delhi Givt. Dispensaries/ Polyclinic under HMD (Central) New Delhi (Revised)

438.63

work completed


work completed

Detail Report
Graph / Photo
246 Strengthening of Arterial Road (Bahadur Shah Zafar Marg) having right of way more than 60.00 metre under Sub Division - 3 of Division C and ND - Roads, New Delhi

437.49


Detail Report
Graph / Photo
247 Balance Renovation and Misc. works of Main Academic, Administrative and Printing Blocks i/c Class Rooms &Laboratories, C/o Security Guards rooms and Toilet Water Proofing Treatment of existing building roofs of PIT, DSEU Campus, Pusa, New Delhi.

436.21


Detail Report
Graph / Photo
248 Widening and strengthening of Bandh Road of Division SR-1 under Sub-Division SR-13 at New Delhi ic shifting and installation of Electrical Poles, Street lights etc. (Balance Work)

435.13
47.11 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
249 Construction of precast drain and Improvement of side berm including footpath from Amrit Vihar to Nathupura road on Main Burari Road 28/04/2022
12/07/2022
12/07/2022
434.22
195.90 (Sep'22)

0.00 (Sep'22)
Amit Buildcon
Detail Report
Graph / Photo
250 Comprehensive repair and maintenance of various roads under sub division M- 2134. 21/11/2019
20/11/2020
433.62
599.23 (Sep'22)

0.00 (Sep'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
251 Improvement and strengthening of Road No. 59, Delhi (From Khajuri Gole Chakkar to outer Ring Road Except Wazirabad Yamuna Bridge). 13/01/2020
05/04/2020
432.05
281.82 (Nov'20)

0.00 (Nov'20)
M/s Roadtech
Detail Report
Graph / Photo
252 Comprehensive maintenance of Civil works at Pt. Madan Mohan Malviya Hospital, Malviya Nagar, P.W.D. (GNCTD) and NHMC and BR Sur Hospital , Defence Colony and Moti Bagh and DGD at various places, New Delhi for 2 years i.e. 2021-22, 2022-23

432.02


Detail Report
Graph / Photo
253 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road II PWD New Delhi

429.94

WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
254 Comprehensive maintenance of various roads under Sub-Division South East Road-13

425.32
14.60 (Jun'20)

0.00 (Jun'20)

Detail Report
Graph / Photo
255 Construction of Boundary Wall on Vacant land at Dwarka sector 12 & 13 at New Delhi

421.69

Financial Bid received & Sent to SE office.
Detail Report
Graph / Photo
256 Civil and Electrical work

420.91


Detail Report
Graph / Photo
257 Remodeling of Maujpur drain from Road No. 66 to Ghonda Chowk and Main Brahmpuri Road drain from Ghonda Chowk to MCD Dhalav. 28/10/2018
27/04/2019
31/07/2019
419.30
324.29 (Feb'22)

0.00 (Feb'22)
Gee International work in progress
Detail Report
Graph / Photo
258 Op. of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I

417.30


Detail Report
Graph / Photo
259 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of Maharishi Valmiki Hospital Campus and DGD Dispensaries at Pooth Khurd Delhi, SRHC Hospital Complex and DGD Dispensaries at Narela Delhi during 2022-23 and 2023-24 15/05/2022
14/05/2024
14/05/2024
416.87
0.06 (May'22)
21.00 %
0.00 (May'22)
Mahavir Parsad Gupta & Sons
Detail Report
Graph / Photo
260 Construction of RCC drain in Narela Alipur road along the DDA land from Bhorgarh to Shahpur Garhi turn under Sub Division NR-13, North Roads Division,PWD, Delhi 07/01/2022
05/07/2022
05/07/2022
412.34
111.83 (Jun'22)

0.00 (Jun'22)
R K Enterprises
Detail Report
Graph / Photo
261 Replacement of bearings and expansion joints of Karampura Flyover and rehabilitation of RCC jacketing of two piers of Mukundpur Flyover.

406.38

tender under process


null
Detail Report
Graph / Photo
262 Replacement of bearings and expansion joints of Karampura Flyover and rehabilitation of RCC jacketing of two piers of Mukundpur Flyover.

406.38

tender under process
Detail Report
Graph / Photo
263 Construction of New SPS workshop cum classroom G+1 at Sir C.V. Raman ITI Dheerpur Delhi. (Civil & Electrical Works)

404.63


Detail Report
Graph / Photo
264 Thermoplastic painting on various roads under Division M-413, New Delhi dg. 2013-14. 29/10/2013
28/02/2014
404.14

K.L. Arora & Son
Detail Report
Graph / Photo
265 Strengthening of Narwana Road from Mother Dairy T-Point to Panch Mahal Awas during 2017-18 19/04/2018
17/07/2018
402.83
79.00 (Jun'19)

0.00 (Jun'19)
A S INFRATECH Work in Progress
Detail Report
Graph / Photo
266 Civil and Electrical works

398.73


Detail Report
Graph / Photo
267 General Day to Day Civil Maintenance Work

392.66
130.07 (Nov'20)

0.00 (Nov'20)

Detail Report
Graph / Photo
268 Rehabilitation and strengthening of Okhla flyover on Mathura Road, New Delhi

392.44

Work in progress


null
Detail Report
Graph / Photo
269 Construction of Boundary wall at Plot No. FA 6 for District office and bataliyan, Women training college, Police line and Advanced research and Training Institute of Delhi Police Officers Narela, Delhi 110040 20/01/2022
20/05/2022
20/05/2022
391.04

Work in Progress
Work in Progress
Detail Report
Graph / Photo
270 Strengthening of various roads by cold milling and recycling process of Sub. Division East Road-II under Division East Road/(M-212), Delhi during 2022-23:- 1. NH-24 Ghazipur to Kondli Bridge. 2. Sameer Bhan Marg. 3. Road from Live stock market to Gali No. 7 Block - C in Ghazipur Dairy Farm. 4. Bhagvan Mahavir Swami Marg. 5. Road from High land Apptt. To Soochna Apptt. In Vasundhara Enclave 29/08/2022
26/12/2022
26/12/2022
389.08
49.00 %
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
271 Strengthening of Prithvi Singh Dagar Marg ID 1175 from RawtaMorh Dhansa Road to Daurala Border under PWD Division- South West Road-II New Delhi. 16/10/2019
12/02/2020
388.15
0.84 (Apr'22)

0.00 (Apr'22)
Pawan Kumar UNDER TENDERING PROCESS
UNDER TENDERING PROCESS
Detail Report
Graph / Photo
272 Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain 25/09/2022
24/12/2022
24/12/2022
386.35
32.00 %
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
273 Improvement of Khari Bawali and HC Sen Marg 27/09/2013
26/05/2015
382.36

Satya Parkash & Bros. Pvt. Ltd.
Detail Report
Graph / Photo
274 C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) 02/03/2022
26/11/2022
26/11/2022
382.04
87.00 %
M/s. Satyam Construction work is in progress
work is in progress
Detail Report
Graph / Photo
275 Rehabilitation and strengthening of Okhla flyover on Mathura Road, New Delhi

381.57

Work in progress


null
Detail Report
Graph / Photo
276 Repair and Rehabilitation of Vehicular Under Pass (VUP) and its approaches and Approaches of three RoBs at PulMithai on SPM Marg, Delhi 16/01/2020
15/10/2020
31/03/2021
379.24
40.81 (Apr'21)

0.00 (Apr'21)

Work in progress


null
Detail Report
Graph / Photo
277 Civil works, Furniture works & Electrical works

377.11


Detail Report
Graph / Photo
278 Comprehensive repair of road footpath, drain, painting, Speed breakers, Patch repairs and other misc. repair works in SectionI & Section-II for 1 year

376.63


Detail Report
Graph / Photo
279 Comprehensive repair of road footpath, drain, painting, Speed breakers, patch repairs and other misc. repair works in SectionI & Section-II for 1 year

376.63


Detail Report
Graph / Photo
280 (i) Civil work Comprehensive maintenance of Ring Road including carriageway, footpaths, central verge, service road etc. within the right of way, mechanised desilting

375.34


Detail Report
Graph / Photo
281 Strengthening of Shamnath Marg along with Improvement of Footpath, Storm Water Drain, Central Verge etc. from I.P. College Xing to Petrol Pump near Boulevard Road under Sub-Division-3 of Division CandND-Roads, New Delhi.

375.32


Detail Report
Graph / Photo
282 Providing, running and maintaining truck mounted Anti Smog Gun on hire basis at various locations 19/05/2022
18/05/2023
18/05/2023
372.34
41.00 %
P. R. S. Yash & Co.
Detail Report
Graph / Photo
283 Construction of RMC Road From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22

369.30


Detail Report
Graph / Photo
284 Construction of RMCRoad From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22

369.30


Detail Report
Graph / Photo
285 Rehabilitation and strengthening of Okhla flyover on Mathura Road, New Delhi

366.25

Work in progress


null
Detail Report
Graph / Photo
286 Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24

366.09


Detail Report
Graph / Photo
287 Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24

366.09


Detail Report
Graph / Photo
288

364.89
0.00 (Sep'16)

0.01 % (Sep'16)
M. C. Construction Co. work yet to be awarding
Detail Report
Graph / Photo
289 Major repair maintenance work i.e. outer plaster, chajjas of windows, balcony, damaged cemented water tank causing seepage, repair of staircase, road, blocked sewer line i/c strengthening, retrofitting works and misc. civil and Electrical works

363.36


Detail Report
Graph / Photo
290 Strengthening of Geeta Colony Yamuna Bridge Road from Ring Road Crossing to Pusta Road by cold milling and recycling process. Sub-Division East Road-I under Division East Road/(M-212) Delhi. dg. 2021-22 25/02/2022
25/05/2022
25/05/2022
362.56
430.06 (Sep'22)

0.00 (Sep'22)
Pawan Kumar
Detail Report
Graph / Photo
291 Civil Works: Mechanised Desilting of Drains & Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other Misc. Repair works of footpaths, Central Verge, Service roads etc. on other roads than ring road under Sub-Division NWR-21

359.74


Detail Report
Graph / Photo
292 Civil Works: Mechanised Desilting of Drains & Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other Misc. Repair works of footpaths, Central Verge, Service roads etc. on other roads than ring road under Sub-Division NWR-21

359.74
1.30 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
293 Re-Surfacing of various roads of Vasant Vihar Roads (Poorvi Marg (Road ID - 781), Paschimi Marg (Road ID - 782 ), Basant Marg 1 (Road ID - 778), Basant Marg 2 (Road ID - 779), Munirka Marg 1 and2 (Road ID - 783)) and Providing and Laying of Stone Ma

359.35


Detail Report
Graph / Photo
294 Construction of Foot Over Bridge at Gurudwara Majnu ka Tila on Road No. 45 under Sub-Division-4 of Division C and ND-R, New Delhi. 06/09/2022
05/03/2023
05/03/2023
358.46
16.00 %
Fiberfill Engineer
Detail Report
Graph / Photo
295 Improvement of RUB surrounding area and construction of new additional sump at RUB Badarpur under Sub Division SER-24 in Division SER-2, New Delhi and Enhancement of substation, etc.

357.12


Detail Report
Graph / Photo
296 Improvement of RUB surrounding area and construction of new additional sump at RUB Badarpur under Sub Division SER-24 in Division SER-2, New Delhi and Enhancement of substation, etc

357.12


Detail Report
Graph / Photo
297 Improvement and Strengthening of Loni Road from G.T. Road to Loni Gole Chakkar. 08/05/2022
05/08/2022
05/08/2022
357.04

Pawan Kumar
Detail Report
Graph / Photo
298 Comprehensive Maintenance and Operation of Trauma Block, New Ward Block, OT, Gynae, Old Ward Block, Doctors and Nurses Hospital and Residential Complex Lifts at DDU Hospital, Hari Nagar, New Delhi (SH Operation of Lifts) 30/04/2019
29/04/2021
355.16

Guruji Elevator
Detail Report
Graph / Photo
299 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021 22

354.88


Detail Report
Graph / Photo
300 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
301 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
302 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
303 Civil work- Comprehensive repair works of footpaths, central verge, service roads etc. on other roads under Sub division NWR-23

350.32


Detail Report
Graph / Photo
304 Comprehensive repair works of footpaths, central verge, service roads etc. on other roads under Sub division NWR-23

350.32


Detail Report
Graph / Photo
305 Strengthening of various roads under Sub Division SR-11/South Road-1 PWD New Delhi.Phirni Road West End Marg Durbal Nath Marg H Block Dakshin Puri Road Maharishi Balmiki Marg and Raja Ram Marg. 06/11/2019
05/02/2020
05/02/2020
348.51
461.79 (Jul'22)

0.00 (Jul'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
306 Comprehensive maintenance of Civil works at Guru Gobind Singh Govt. Hospital, Raghubir Nagar, Delhi and Rao Tula Ram Memorial Govt. Hospital, Jaffarpur Kalan, Delhi P.W.D. (GNCTD), New Delhi for 2 years 2021-22, 2022-23. 23/05/2022
21/05/2024
21/05/2024
343.73
21.00 %
Aliyan Constaruction Company Work is under progress.
Detail Report
Graph / Photo
307 Strengthening of various roads by cold milling of sub-Div. East road-III under East road/(M-212) Delhi during 2022-23. 1. Sadhabhawna Marg (Road No. 111) 2. Club Avenue Marg (Road No. 112) 3. Sekarita Marg (Road No. 113) 4. Ambedkar Marg. 5. Subhash Market road. 6. Block No. 1 to 11 Trilokpuri. 7. Khudiram Bose Marg 29/08/2022
24/02/2023
24/02/2023
342.13
32.00 %
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
308 Strengthening of Dera Bhatti Road of Sub-Division SR-13 under Division SR-1 at New Delhi. 27/11/2019
26/02/2020
341.72
501.17 (Mar'22)

0.00 (Mar'22)
Bansal Associates
Detail Report
Graph / Photo
309 Replacement of damaged old 900mm Dia RCC pipe with Providing and Laying 1200mm dia RCC Pipe from Som Bazar Chowk to Mungeshpur drain at Najafgarh Nangloi Road. (Road ID -1230) 18/04/2022
14/10/2022
14/10/2022
339.47
30.38 (Jul'22)
98.00 %
0.00 (Jul'22)
Dilshad Khan
Detail Report
Graph / Photo
310 AR MO to Various Residential Building Type III IV V and VI under Sub Division M3231N at 16 Rajpur Road Delhi During 2021 22

339.03
146.28 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
311 Construction of Foot Over Bridge with Staircase and lift for padestrians crossing near Mohammadpur Village at Africa Avenue Road, New Delhi during 2017-18.

338.01

Work Completed
Detail Report
Graph / Photo
312 Construction of Foot Over Bridge with Staircase and lift for padestrians crossing near Mohammadpur Village at Africa Avenue Road, New Delhi during 2017-18

338.01


Detail Report
Graph / Photo
313 CONSTRUCTION OF 40 NOS SPS CLASS ROOMS

336.15


Detail Report
Graph / Photo
314 Strengthening of Western Approaches of Signature Bridge from Signature Bridge to Majnu ka Tila, Signature Bridge to Timarpur, Azadpur and Slip road from Wazirabad flyover to Signature Bridge, Burari flyover and Tagore Park under Sub Division-1, C&ND-Roads, New Delhi 31/03/2022
30/06/2022
30/06/2022
336.11
484.99 (Jul'22)

0.00 (Jul'22)
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
315 Micro Surfacing on Outer Ring Road from Vikas Puri to Meera Bagh

334.06
20.48 (Jun'22)

0.00 (Jun'22)

Detail Report
Graph / Photo
316 Construction of drains, footpath Central Verge and improvement of side berm portion of S-Bend road (Maharishi Dayanand Marg ID-539) New Delhi. 24/10/2019
23/01/2020
23/01/2020
330.83
376.66 (Jul'22)

0.00 (Jul'22)
S S Chauhan & Sons Work in Progress
Work in Progress
Detail Report
Graph / Photo
317 Up gradation of one staffroom in 86 Nos. Schools under South-East Building Maintenance Division, Hauz Khas, New Delhi during 2018-19. (Civil and Electrical work). 23/03/2019
22/09/2019
22/09/2019
329.84
94.22 (Sep'22)

0.00 (Sep'22)
S. P. CONSTRUCTION COMPANY Work in progress
Detail Report
Graph / Photo
318

328.66


Detail Report
Graph / Photo
319 Comprehensive Maintenance of various Roads under SRD Project Division-I, Sub-Division-I, PWD, Delhi. (SH- Civil Works- Mechanised Desilting of Drains, Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other misc. Repair wor 27/08/2019
23/08/2020
323.91
485.41 (May'21)

0.00 (May'21)
Awasthi Construcion Co.
Detail Report
Graph / Photo
320 C/o Foot Over Bridge at Block-D, Okhla Phase-I on Shri Maa Anandmayee Marg, New Delhi (Road-ID-946) including EI and Lift

320.49


Detail Report
Graph / Photo
321 A/R and M/O to Educational Building under SWBMD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19. (Sh -Internal and external finishing and other misc works). 03/08/2018
01/10/2018
01/10/2018
320.20
0.25 (May'22)

0.00 (May'22)
WORK IN PROGRESS
Detail Report
Graph / Photo
322 Remodelling of drain from 5th Pusta to Ghonda Chowk at Gamri Road Delhi 13/01/2020
05/04/2020
318.40
352.26 (Sep'22)

0.00 (Sep'22)
Thermal Enginners & Insulators Pvt. Ltd.
Detail Report
Graph / Photo
323 A/R and M/O to Sub Division-14 of South Road-1 for Comprehensive Maintenance of Press Enclave Road, Mandir Marg, Pankaj Juyal Marg, NBCC Plaza Road, Pramod Mahajan Marg, Family Court Road J-Block Road, H-Block Road Gurudwara Road, Asian market Road, Khirki Road, Sheikh Sarai Phase-I Road no.1 & Road No.2, Road from H.No. C-11 to C-20 Malviya Nagar and Road in front of Mother International School during 2019-20. 01/11/2019
31/10/2020
317.62
488.34 (Jun'22)

0.00 (Jun'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
324 Building work i/c Water Supply, Sanitary installation,Development Work and providing EI & Fire fighting system 26/05/2015
25/05/2016
31/05/2022
316.66

Sudesh Kumar Work is in progress. Delay due to non-receipt of funds & revised A/A & E/S from Client Department and covid-19 pandemic since March 2020. Balance works in final stage of completion.
Work is in progress. Delay due to non-receipt of funds & revised A/A & E/S from Client Department and covid-19 pandemic since March 2020. Balance works in final stage of completion.
Detail Report
Graph / Photo
325 Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work)

316.48


Detail Report
Graph / Photo
326 Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work)

316.48


Detail Report
Graph / Photo
327 Civil & Electrical Work

316.48


Detail Report
Graph / Photo
328 RMO E and M Services at SRHC Hospital Narela Delhi during the year 2021-23

315.90


Detail Report
Graph / Photo
329 Strengthening of Rajpura Road from Tis Hazari Red Light to Civil Line Thana under SubDivision-4 of Division C& ND-Roads, New Delhi. (Width- ROW Below 30.00 meter) 24/06/2022
23/10/2022
23/10/2022
313.49
98.00 %
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
330 Strengthening of Road No. 68 (from Road No. 66 T-Point to Junction of Road No. 69). (From Railway line to Road No. 66 T-Point). 02/09/2019
30/11/2019
31/12/2019
309.88
302.32 (Dec'21)

0.00 (Dec'21)
MAHAVIR PRASAD GUPTA AND SONS work in progress
Detail Report
Graph / Photo
331 Automated Housekeeping Service of MSO Building

308.94
30.78 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
332 Comprehensive maintenance and operation of UPS and CVCF systems 26/01/2022
25/01/2024
25/01/2024
305.92
38.00 %
ARECA TECHNOLOGIES
Detail Report
Graph / Photo
333 Strengthening of Mall Road from Timarpur Red Light to GTB Metro Station under Sub-Division-2 of Division C& ND-Roads, New Delhi. (Width- ROW Above 60.00 meter). 28/04/2022
27/06/2022
27/06/2022
302.96
382.19 (Aug'22)

0.00 (Aug'22)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
334 Resurfacing of Road and Repairing of footpath and Central Verge at Asaf Ali Road and Chaman Lal Marg under Division SRD Project I, under Sub Division II, PWD during 2019 20 New Delhi 23/09/2019
20/03/2020
302.16
285.99 (Dec'21)

0.00 (Dec'21)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
335 Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub Division-1, C and ND-Road Division

300.87


Detail Report
Graph / Photo
336 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road-II PWD New Delhi 10/09/2019
07/01/2020
07/01/2020
298.81
194.61 (Jul'20)

0.00 (Jul'20)
SBG Infracon Pvt Ltd WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
337 Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi 27/12/2018
26/04/2019
296.85
335.77 (Aug'21)

0.00 (Aug'21)
Ram Krishan Yudhister Parkash

work completed


null
Detail Report
Graph / Photo
338 Running operation and comprehensive maintenance of online UPS, TVSS, APFF, PAC and Isolation transformer of different capacity installed at RGSS Hospital, Tahirpur, Delhi 26/01/2022
25/01/2024
25/01/2024
296.84
61.84 (Sep'22)
38.00 %
0.00 (Sep'22)
ISSAR INDUSTRIES
Detail Report
Graph / Photo
339 Providing & fixing 80 mm thick Paver Block over Unpaved Shoulder Portion of Road in view of Anti Air Dust Pollution Measures for Rao Laxmi Chand Marg (ID 1174) under Sub Division 23 Division SWR-II, PWD, Delhi 14/04/2022
11/08/2022
11/08/2022
296.33
255.76 (Sep'22)

0.00 (Sep'22)
Bliss Associates
Detail Report
Graph / Photo
340 Providing and fixing M.S Steel railing at central verge of SSN Marg. 03/11/2019
02/05/2020
295.66
372.20 (Mar'22)

0.00 (Mar'22)
B M & Sons
Detail Report
Graph / Photo
341 Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). 28/02/2019
27/06/2019
31/03/2021
294.21
58.25 (Feb'22)

0.00 (Feb'22)
AASRA Martech Pvt.Ltd. Work in progress.
Detail Report
Graph / Photo
342 Civil and Electrical work. 05/05/2019
04/03/2020
04/03/2020
292.64

Dheeraj Singh & Company Work just awarded
Detail Report
Graph / Photo
343 Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). 09/08/2022
08/08/2023
08/08/2023
292.57
16.00 %
Nand gopal Gupta
Detail Report
Graph / Photo
344 Providing and Laying Bituminous concrete and Retro reflective road marking

291.21
72.69 (May'21)

0.00 (May'21)
Work completed
Detail Report
Graph / Photo
345 Air Pistol & Rifle 10m Shooting Hall cum all internal finishing fixtures fitting and development of complete setup of electronic type targets, shooting equipment etc. complete 18/03/2022
13/09/2022
15/10/2022
290.26
100.00 %
Dev Enterprises work is in progress
work is in progress
Detail Report
Graph / Photo
346 Strengthening of Arterial Road (Bahadur Shah Zafar Marg) having right of way more than 60.00 metre under Sub Division – 3 of Division C & ND – Roads, New Delhi 31/03/2022
30/05/2022
30/05/2022
289.31
260.08 (Sep'22)

0.00 (Sep'22)
A S INFRATECH
Detail Report
Graph / Photo
347 Comprehensive Maintenance of Aacharya Shree Tulsi Marg M.G.Road Aya Nagar Road Ghitorni Road to CPWD Land Ghitorni Village Road M.G.Road to Ghitorni Village Road and Mandi Road under the Jurisdiction SD-15 under SR-1 during 2019-20 01/11/2019
31/10/2020
288.88
426.77 (Jan'22)

0.00 (Jan'22)
S S Chauhan & Sons
Detail Report
Graph / Photo
348

288.73


Detail Report
Graph / Photo
349 Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi 16/01/2022
15/10/2024
15/10/2024
288.00
27.00 %
Arcop Associates Pvt. Ltd. Preliminary Concept report sent vide No. 199 dated 04.04.2022 to Client Department for in principle approval.
NIL
Detail Report
Graph / Photo
350 Comprehensive Maintenance of various Roads under SRD Project Division-I, Sub-Division-II, PWD, Delhi. (SH- Civil Works- Mechanised Desilting of Drains, Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other misc. Repair wo 24/08/2019
23/08/2020
285.85
569.67 (Aug'21)

0.00 (Aug'21)
Awasthi Construcion Co.
Detail Report
Graph / Photo
351 Construction prefab hut for HQ at PTS Wazirabad, Delhi 21/07/2018
20/11/2018
285.56

Aliyan Constaruction Company

work completed


null
Detail Report
Graph / Photo
352 Construction of Foot Over Bridge across Shaheed Jeet Singh Marg (ID-22) at Katwaria Sarai wth staircase and lift including Electrical installation for pedestrians under Sub Division-III of Division South Road-II, PWD, New Delhi.

284.19


Detail Report
Graph / Photo
353 Operation and Maintenance of EI and FANS Sub Station HVAC Works Fire Fighting and Wet Riser System Solar Water Heating System Cold Storage Lifts etc

282.78


Detail Report
Graph / Photo
354 Strengthening of Madhu Vihar Road (Road No. 57 to Joshi Colony T-Point) and Mandawali Road (House Tax Building to Agrasen Apartment) at I.P. Extension under PWD Division East (Road) 16/04/2018
14/07/2018
280.65
117.06 (Feb'22)

0.00 (Feb'22)
JAP BUILDCON PRIVATE LIMITED Work in Progress
Detail Report
Graph / Photo
355 Renovation Upgradation of the GST Office I/c A B and C Wing at 4th Floor Deptt of Trade and Taxes Building I P Estate New Delhi RECALL

276.70


Detail Report
Graph / Photo
356 Renovation/Upgradation of the GST Office i/c A,B and C Wing at 4th Floor, Deptt. of Trade & Taxes Bldg. , IP Estate, New Delhi

276.70


Detail Report
Graph / Photo
357 Improvement and beautification of road between Dhaula Kuan to IGI airport NSG Xing (L.H.S). Phase-II

275.48


Detail Report
Graph / Photo
358 Providing Tractor driven positive displacement rotary lobe pump & diesel engine pump set at different locations for removing water logging etc. during rainy season. 1st RECALL 16/06/2022
15/10/2022
15/10/2022
274.22
284.01 (Sep'22)

0.00 (Sep'22)
Aliyan Construction Company
Detail Report
Graph / Photo
359 Providing services of 11 Nos. maintenance vehicles for regular use with required labour and T and P for Sub Division NR-11, NR-13, NR-14 and NR-15 under North Roads Division

273.48


Detail Report
Graph / Photo
360 Construction of 12 Nos. Aam Admi Mohalla Clinic at various locations under South-East (Bldg)-M, Division, Hauz Khas, New Delhi during 2021-22. (Civil and Electrical works)

271.15
54.83 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
361 Construction of store room 01 nos., Shed 2 nos. behind old building, Toe Wall in Park and Ramp for new Building Block, Renovation of all toilet and guard room, Fixing granite on stage

269.83


Detail Report
Graph / Photo
362 Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool 23/12/2020
20/06/2021
30/09/2022
262.79
35.98 (Sep'22)

0.00 (Sep'22)
Maa Narayan Constuction Co. Structural work almost completed. Finishing work and Tensile structure work is in progress. Physical progress is 58%. Notice under Clause 3 issued to the agency.
Detail Report
Graph / Photo
363 AR and MO to various roads under PWD South Zone during 2017 18 SH Global Tender for Mechanized Vacuum Sweeping and Cleaning of Various PWD Roads under PWD South Zone for one year

261.26

Work not executed
Detail Report
Graph / Photo
364 Beautification Upgradation of lift lobby and Corridor area ic flooring, Wall dado and False Ceiling from 1st Floor to 13th floor Civil and Electrical Work

259.34
135.56 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
365 Construction of 2 nos. Additional Basket Ball Court in Warmup Area, Acoustics Treatment in Basket Ball Hall, Renovation of boundary wall and Sitting Chairs in sitting gallery at Sarvodaya Bal Vidyalaya, Anand Vas (Lok Vihar), Delhi

254.87

DE submitted to PM (Hr.Edu.Proj.) for T.S.
Detail Report
Graph / Photo
366 Operation and Maintenance of EI and FANS Sub Station and DG Set HVAC Works Fire Fighting and Wet Riser System Fire Alarm System Lifts Solar Water Heating System RO plant etc.

254.53


Detail Report
Graph / Photo
367 Co 08 equivalent Room 06 Nos Class Room MP Hall GGSSS Urdu Medium ID 212705 and Lift internal and external electrical installations, development of site and fire fighting

254.28

work in progress
work in progress
Detail Report
Graph / Photo
368 C/o 08 equivalent Room (06 Nos. Class Room + M.P. Hall), GGSSS Urdu Medium (ID – 212705) and Lift internal & external electrical installations, development of site and fire fighting system etc. at Chasma Building

254.28

tender opened on 04.07.2022
Detail Report
Graph / Photo
369 C/o 08 equivalent Room (06 Nos. Class Room + M.P. Hall), GGSSS Urdu Medium (ID – 212705) and Lift internal & external electrical installations, development of site and fire fighting system etc. at Chasma Building

254.28

Financial bid opened
Detail Report
Graph / Photo
370 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi.

249.39


Detail Report
Graph / Photo
371 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi

249.39


Detail Report
Graph / Photo
372 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi

249.39


Detail Report
Graph / Photo
373 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (Re-call)

249.39


Detail Report
Graph / Photo
374 Civil and Electrical Works

249.03


Detail Report
Graph / Photo
375 A/R and M/O to various Roads under Division South Road -II, PWD during 2021-22 (SH:Filling the pot holes / patch repair on PWD Roads by Mobile Infrared Recycling Road Repair Machine under Sub-Division-I, II, III and IV) 03/09/2021
02/09/2022
02/09/2022
246.96
295.79 (Jul'22)
100.00 %
0.00 (Jul'22)
Trans Metalite India Limited Work in Progress
Work in Progress
Detail Report
Graph / Photo
376 Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub Division-1, C&ND-Road Division. 2nd RECALL 20/07/2022
19/11/2022
19/11/2022
243.86
74.00 %
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
377 Widening of IGNOU Road and construction of RCC drain and footpath at IGNOU Road from Z more to M.B. Road T-Point. 18/07/2018
16/09/2018
30/06/2019
242.58
392.31 (Aug'21)

0.00 (Aug'21)
Y. D. Builders & Hotel Pvt Ltd Work in progress
Work in progress
Detail Report
Graph / Photo
378 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi

242.04


Detail Report
Graph / Photo
379 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (Re-call)

242.04


Detail Report
Graph / Photo
380 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (Revised)

242.04


Detail Report
Graph / Photo
381 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (2nd call)

242.04


Detail Report
Graph / Photo
382 Comprehensive maintenance of Civil Works at Acharya Shree Bhikshu Govt. Hospital and Residential Complex, Moti Nagar and SVBP Hospital and DGD at various places, P.W.D. (GNCTD), New Delhi for 2 years i.e. 2021-22, 2022-23.

241.03


Detail Report
Graph / Photo
383 Upgradation/Renovation of one staff room in each of 951 schools (SH- Civil and Electrical works in Mangolpuri, Sultanpuri, Kirari, Shakurbasti and Mundka constituency Schools, Total 74 Nos. Schools of NWB-2)

239.47


Detail Report
Graph / Photo
384 Providing, supplying, running and maintaining WATER SPRINKLER on hire basis at various locations

235.98


Detail Report
Graph / Photo
385 Restoration of MB Road and Phirni Road cut by DTL and JIO Digital under PWD Division South Road-1 Sub Division-11 during 2021-22

232.84
177.57 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
386 Construction of Foot over Bridge With Staircase and lift for pedestrian at Baba Gang Nath Mandir on Nelson Mandela Marg, New Delhi

229.69


Detail Report
Graph / Photo
387 Construction of Foot Over Bridge with Staircase and Lift for pedestrians crossing near Mohan Singh Market at Tamil Sangam Marg (Road ID No. 141), New Delhi

228.64
35.00 (Apr'20)

0.00 (Apr'20)

Detail Report
Graph / Photo
388 Civil+ Elect. works

228.23


Detail Report
Graph / Photo
389 Civil+ Elect. works

228.23


Detail Report
Graph / Photo
390 Development of road side of DAV School road stretch in front of Govt. School and DAV School for making it pedestrian student friendly under Sub-Division-III of Division South Road-II, PWD, New Delhi (Civil Elect. works)

228.23


Detail Report
Graph / Photo
391 Comprehensive Maintenance of SSN Marg, 100 Foota Road and 60 Foota Road under the Jurisdiction SD-12 under SR-1 during 2019-20. 01/11/2019
31/10/2020
227.39
326.28 (Feb'22)

0.00 (Feb'22)
Amrit Lal behl & Sons
Detail Report
Graph / Photo
392 Providing, running and maintaining Anti Smog Gun on hire basis at various locations

227.34


Detail Report
Graph / Photo
393 Providing, running and maintaining Anti Smog Gun on hire basis at various locations

227.34


Detail Report
Graph / Photo
394 Providing, running and maintaining Anti Smog Gun on hire basis at various locations

227.34


Detail Report
Graph / Photo
395 Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub. Division-1, C and ND-Road Division. (1st RECALL) 09/03/2022
08/07/2022
08/07/2022
225.35

Sethi Construction
Detail Report
Graph / Photo
396 Construction of Foot Over Bridge with staircase, electrical works and lift for pedestrian across press Enclave Road near Select City Mall, New Delhi. 31/08/2019
29/02/2020
222.53
187.92 (Jul'20)

0.00 (Jul'20)
S. S. Chauhan & Sons
Detail Report
Graph / Photo
397 Balance Work

219.85


Detail Report
Graph / Photo
398 Civil & Electrical Works

219.42


Detail Report
Graph / Photo
399 Civil & Electrical Works

219.42


Detail Report
Graph / Photo
400 Renovation of school building and Multipurpose hall (Composite work Civil & Electrical) 22/05/2022
21/01/2023
21/01/2023
217.86
84.44 (Sep'22)
62.00 %
0.00 (Sep'22)
Nafees Ahmed
Detail Report
Graph / Photo
401 Comprehensive Annual Maintenance of all roads including Carriageway, Footpaths, Central Verge, Planter, Service Roads etc. within the Right of Way, Mechanized/Manual Desilting of Drains, Repairing of Potholes, Maintenance and other Misc. Repair Works under West Road -1 Division, Sub Division WR-12 during 2022-23.

217.69


Detail Report
Graph / Photo
402 Construction of Training-cum Production Centre at Indira Nagar, Azadpur, Delhi-33. (Civil & Electrical Work).

215.93


Detail Report
Graph / Photo
403 Comprehensive Annual Maintenance of all roads including Carriageway, Footpaths, Central Verge, Planter, Service Roads etc. within the Right of Way, Mechanized/Manual Desilting of Drains, Repairing of Potholes, Maintenance and Cleaning of FOB’s and other Misc. Repair Works under West Road-1 Division, Sub Division WR-11 during 2022-23

215.66


Detail Report
Graph / Photo
404 Multi Modal Integration (MMI) Development works at existingPanchsheel Park Metro Station at Outer Ring Road (ID-1369) under Sub Division-IV of Division South Road-II, PWD, New Delhi

213.61


Detail Report
Graph / Photo
405 Civil: A/R & M/O and Special repair work

212.14


Detail Report
Graph / Photo
406

211.19


Detail Report
Graph / Photo
407 Multi Modal Integration (MMI) Development works at existing IIT Metro Station at Outer Ring Road (ID-1369) under Sub Division-IV of Division South Road-II, PWD, New Delhi

211.01


Detail Report
Graph / Photo
408 Upgradation/Renovation of one staff room in each of 73 schools (Morning and Evening Shift) located at (NE) District of Delhi under the jurisdiction of PWD Building Maintenance Division M-222 25/01/2019
24/04/2019
30/09/2019
209.29
192.52 (Jan'22)

0.00 (Jan'22)
Shyam Sunder Tyagi

work completed


null
Detail Report
Graph / Photo
409 1. Infrastructural Improvement and Renovation of Office Building, Toilet and open Ground at Science Centre no 3, Plot no 3, Link Road, Karol Bagh, New Delhi under Sub-Division-I of SRDP-II, PWD, New Delhi). (2) Infrastructural Improvement and Renovation at of the Building of Science Centre No. 3 Plot NO. 3, Link Road, Karol Bagh, New Delhi (Electrical works)

208.72
36.54 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
410 Providing and laying K-9 pipe from Pump House at Bhagat Singh Park to Drain No. 1 05/05/2022
04/08/2022
04/08/2022
208.39
132.94 (Jun'22)

0.00 (Jun'22)
Vinod Kumar
Detail Report
Graph / Photo
411 Providing for installation of fixing of false ceiling and VRF System in New College Building OPD and IPD in Nehru Homeopathic Medical College and Hospital, B-Block, Defence Colony, New Delhi-110024 15/03/2019
14/10/2019
208.35

HILLTOP REFRIGERATION
Detail Report
Graph / Photo
412 Repair of Spalled and Honeycomb Concrete, Replacement of Expansion Joints and Bearing

208.08

.
Detail Report
Graph / Photo
413 Establishing migrant labour facilitation centre at West District Labour Office, Karampura. (Electrical Works)

207.97


Detail Report
Graph / Photo
414 Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joints and Bearing

203.61

.
Detail Report
Graph / Photo
415 Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joints and Bearing

203.61

.
Detail Report
Graph / Photo
416 Repair of footpath and Central Verge and Misc. Repair work.

202.64


Detail Report
Graph / Photo
417 A/R and M/O to Sub Division-11 of South Road-1 for Comprehensive Maintenance of Road under jurisdiction of Sub Division-11 during 2019-20 01/11/2019
31/10/2020
199.05
303.89 (Jan'22)

0.00 (Jan'22)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
418 Providing and fixing Paver Block on both side berm from KhairaMorh to Mitraon village and laying NP-4 pipe line from Dilawarpiao to Mitraon Sump under Sub Division-II, South West Road-II.(Road ID1227) 26/02/2022
26/05/2022
26/05/2022
196.78
70.47 (Jul'22)

0.00 (Jul'22)
Surender Singh
Detail Report
Graph / Photo
419 Construction of Aam Aadmi Mohalla Clinic Primary Health Centre at various places under Central and New Delhi M Circle PWD Delhi SH Civil and Electrical work

194.54
112.46 (Nov'20)

0.00 (Nov'20)

Detail Report
Graph / Photo
420 Maintenance of footpath, Central Verge, railing including disposal of Malba etc. under Sub Division-I, PWD, New Delhi

193.34


Detail Report
Graph / Photo
421 A/R and M/O to various roads under PWD East Zone during 2017-18.

192.57


Detail Report
Graph / Photo
422 Improvement of riding surface of flyovers namely Nand Nagri flyover, Loni Flyover, Gokalpuri and Khajuri Gol Chakkar Flyover on Wazirabad Road (Road No- 63 and 59) 15/07/2019
14/10/2019
14/10/2019
192.33
245.19 (Dec'21)

0.00 (Dec'21)
Pawan Kumar Work in progress.
Detail Report
Graph / Photo
423

191.84

work completed


work completed

Detail Report
Graph / Photo
424 Improvement of Sewadham Road from road No.-63 to UP Border. 01/03/2019
30/04/2019
15/07/2019
190.73
226.00 (Jul'19)

0.00 (Jul'19)
Pawan Kumar work in progress
Detail Report
Graph / Photo
425

190.49