Public Works Department

Govt. of NCT of Delhi

लोक निर्माण विभाग, दिल्ली सरकार


 
GBSSS Site-2 Clock Tower, Hari Nagar (School ID - 1514112).
Office Name
Education West Maint Divn/Education Elect Maint Division 2
T.S. Amount
2762.43 Lacs
Dated
31/08/2018
Progress Details
Date of Start: 07/12/2018
Date of Completion: 04/08/2019
Expected Date of Completion: 30/09/2020
Actual Completion Date:
Payment
Civil:  1005.41 Lacs (Jun 2020)
Present Position
Civil :  15/06/2020
(Block-A) (32 CR) Structure, Mumty done. Brick/AAC block work, fixing of door/window frame, kota stone, vitrified tile flooring, POP, plaster, GRC Tile in progress. (Block-B) (4 CR) Structure done. GF, FF, SF, TF Brick/AAC block work in progress.GRC Tile in progress.
Bottlenecks
Civil :  15/06/2020
Null