Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini.
Office Name
Education North West Maint Divn/Education Elect Maint Division 2
T.S. Amount
2498.28 Lacs
Dated
02/01/2020
Tender Amount
1874.70 Lacs
Dated
03/06/2020
Progress Details
Date of Start: 31/05/2020
Date of Completion: 30/05/2021
Expected Date of Completion: 30/11/2023
Actual Completion Date:
Contractor
M/s SSP Promoters and Builders Private Limited
Payment
Civil:  1818.34 Lacs (Sep 2023)
% Progress : % (Sep 2023)
Present Position
Civil :  01/09/2023
WORK IN PROGRESS