Public Works Department

Govt. of NCT of Delhi

लोक निर्माण विभाग, दिल्ली सरकार


 
EOR to Aditi Mahavidyalaya, Bawana, Delhi.
Office Name
North Building Division
History Sheet         Background Note    
T.S. Amount
97.92 Lacs
Dated
15/10/2019
Tender Amount
55.81 Lacs
Dated
08/11/2019
Progress Details
Date of Start: 08/11/2019
Date of Completion: 07/05/2020
Expected Date of Completion: 31/07/2020
Actual Completion Date:
Contractor
M/s M/s Ravi Construction Co.
Payment
Civil:   Lacs (May 2020)
% Progress :48.00 % (May 2020)
  
Present Position
Civil :  30/05/2020
work is in progress
Bottlenecks
Civil :  30/05/2020
work is in progress