A/R and M/O to Providing and laying RCC NP-2 pipe M.S Sheet door, roller blind Settee in lawyers chamber block and Almirahs in ahlmed room of District Judge (South and South East) and Misc. works at District Court Complex, Saket New Delhi.
Office Name
South Bldg & Saket Court Maintenance Division
History Sheet                 NIT Document
T.S. Amount
11.83 Lacs
Dated
19/02/2019
Tender Amount
9.85 Lacs
Dated
19/03/2019
Progress Details
Date of Start: 19/03/2019
Date of Completion: 18/05/2019
Expected Date of Completion: 18/05/2019
Actual Completion Date: 12/03/2020
Contractor
Shri Burhanuddin
Payment
Civil:  3.51 Lacs (Mar 2021)
% Progress : % (Mar 2021)
  
Present Position
Civil :  10/03/2023
work completed
Bottlenecks
Civil :  10/03/2023