Repair/De-silting and Re-boring of RWH and water proofing and tiling in UG tank
Office Name
South East Building Maintenance Division
History Sheet                 NIT Document
T.S. Amount
4.80 Lacs
Dated
06/10/2018
Progress Details
Date of Start: 30/10/2017
Date of Completion: 29/11/2017
Expected Date of Completion: 29/11/2017
Actual Completion Date: 29/11/2017
Payment
Civil:  4.21 Lacs (Dec 2017)
% Progress :100.00 % (Dec 2017)
  
Present Position
Civil :  04/06/2019
Work completed