Road Work
Cost more than 30 Cr.
Road : Work in Progress
S. No.क्र. सं. Project Name A/A & E/S Date of Start
Completion
Expected
Expenditure
Progress
Remarks View
1 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 1260.63 Cr.
10/12/2014
23 (156)/CE/FPZ/F-I/PWD/2014-15/17446-57
18/04/2015
17/10/2017
31/10/2024
1481.80 Cr. (Mar'24)
0.00 (Mar'24)
Work in progress Detail Report
Graph / Photo
2 Supply, installation, testing, commissioning of CCTV camera in Delhi. (Sub: Empanelment of firms for supply, installation, testing, commissioning & CAMC of CCTV system in Delhi). 571.40 Cr.
05/09/2018
SS/PWD/05/2018-19 Issued vide No. 23(6)/CPM/CCTV/PWD/part-II/dispwd/12312-12324 dated:05-09-2018 CD No.:057405162
24/11/2018
23/11/2019
14/11/2027
86.66 Cr. (Mar'24)
0.00 (Mar'24)
work completed. The work of CAMC which is part of the project, is going on. Detail Report
Graph / Photo
3 Comprehensive Maintenance of computers, Printers, Photocopier at office of the Project Manager, All Divisions & Sub Divisions of CCTV Project, PWD, GNCTD, MSO Building, New Delhi. 571.40 Cr.
05/09/2018
SS/PWD/05/2018-19 Issued vide No. 23(6)/CPM/CCTV/PWD/part-II/dispwd/12312-12324 dated:05-09-2018 CD No.:057405162
03/06/2022
02/12/2023
31/03/2024

work is in progress. Detail Report
Graph / Photo
4 Construction of Flyover at Nand Nagri and Gagan Cinema Junction of Mangal Paney Marg including Elevated Corridor Footpath Road Work and Road Signages Electrical Works Drainage Rain Water Harvesting and Allied works on EPC mode 341.20 Cr.
30/09/2022
F. No. ENC/PWD/W/CIORR/8206/449-464
03/02/2023
31/07/2024
11/10/2024
93.32 Cr. (Mar'24)
0.00 (Mar'24)
Work of pier caps, PSC girders and erection of PSC girders is in progress. The work of shifting of 66kva lines is in progress by BSES. permissions of tree cutting is awaited . Detail Report
Graph / Photo
5 Construction of integrated structure for 6 lane flyover from Karawal Nagar to Brijpuri, Mangal Pandey Marg along with Maujpur-Majlispark corridor of DMRC Phase-IV line 210.20 Cr.
12/06/2021
F. No. ENC/DIR/W/PE/1696/11158-70
--
--
--
16.00 Cr. (Sep'23)
0.00 (Sep'23)
Work in Progress : 73%. Details of payment made to DMRC till date:- Rs. 173 Cr. Details of Monthly inspection by EE:- Inspection done on 06.01.2024 Requiremnet of funds:- Additonal Rs.20 Cr. required for CFY Detail Report
Graph / Photo
6 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) 46.56 Cr.
18/12/2018
Sanction No. SS/PWD/14/2018-19 vide letter no. ENC/PWD/W/SSCP/16401-13 dated 18/12/2018 amounting to Rs. 46.56 Crore
--
--
--
0.07 Cr. (Jun'19)
0.00 (Jun'19)

Technical bid opened

Detail Report
Graph / Photo
7 Comprehensive Maintenance of Ring Road/Outer Ring Road under North Maintenance Zone, PWD, Delhi SH: Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work 43.16 Cr.

Not required
30/05/2020
29/05/2022
29/05/2022
21.55 Cr. (Jan'24)
0.00 (Jan'24)

work completed

Detail Report
Graph / Photo
8 Strengthening & resurfacing of varioius roads under PWD M-Z M-1. (SH:: Stg. of Road No. 28, 29, 235, 237 under pWD CRMD M-112(N) by using plastic waste and Resurfacing of Service Road of ORR No. 26 fr 35.78 Cr.
23/06/2011
null
--
--
--

work completed Detail Report
Graph / Photo
9 Corridor Development and Street Network/ Connectivity Plan for the influence zone of the corridor between Punjabi Bagh Flyover and Raja Garden Flyover 35.23 Cr.
03/06/2022
SS/PWD/05/2022-23
10/09/2022
08/12/2023
08/12/2023
101.21 Cr. (Mar'24)
0.00 (Mar'24)

Moti Nagar Flyover is completed and inaugurated by Hon’ble Chief Minister, Delhi  on 13.03.2024 , and opened for public use. 

 

Punjabi Bagh flyover work is in progress. 

Detail Report
Graph / Photo