S. No.क्र. सं. | Name of Workकार्य का नाम | Date of Startकार्य आरम्भ करने की तिथि | Date of Completionकार्य समाप्त करने की तिथि | Cost (In Lac) |
Expenditure (In Lac) |
Progress | Agency | Status | Viewदेखें |
---|---|---|---|---|---|---|---|---|---|
1 | C/o New Block for Medicaine, Maternity and advance pediatric centre at L.N.Hospital | 2020.11.04 | 2023.05.03 | 46552.58 | 4.75 (Jul'22) | 0.00 (Jul'22) | In LN1 steel Col. erected upto 21st floor, 22nd floor slab is casted in pour 1. 22nd floor slab casted in pour 3. 19th floor slab casted in pour2. In LN2, pour 2, 9th floor slab has been casted. In Pour II, 12th floor slab casted. In Pour III, 8th floor slab has been casted, 13th floor in progress. |
Detail Report
Graph / Photo |
|
2 | Construction of New Block For Medicine, Maternity And Advanced Pediatric Centre ( Composite Steel plus RCC framed 2B plus G plus 22 Storyed building At LN Hospital including internal water supply, Sanitary installation, External Development works, Dr | 2020.11.04 | 2023.05.03 | 46552.58 | 17206.66 (Jun'23) | 0.00 (Jul'23) | Swadeshi Civil Infrastructure Pvt. Ltd., 302, DLF Tower B Jasola, New Delhi-110025 | In LN1 steel Col. erected upto 17 th floor, 20th floor slab has been casted pour 1. 19th floor slab casted in pour 3. 16th floor slab casted in pour2. In LN2, pour I, 6th floor slab has been casted. In Pour II, 10th floor slab casted. In Pour III, 6th floor slab has been casted, erection of 11th floor is in progress. |
Detail Report
Graph / Photo |
3 | setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) | 2021.09.23 | 2022.02.22 | 40775.18 | 12389.92 (Jun'23) | 0.00 (Jun'23) | SAM India Builtwell | GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave. |
Detail Report
Graph / Photo |
4 | Construction of Hospital at Madipur, New Delhi | 2020.11.11 | 2022.11.10 | 26970.58 | 10425.19 (Jun'23) | 0.00 (Nov'23) | Ramacivil India Construction Private Limited | Physical progress 87%. & Financial Progress Rs. 140.66Cr. |
Detail Report
Graph / Photo |
5 | Construction of Hospital at Jwalapuri, New Delhi | 2020.08.07 | 2022.08.13 | 26950.37 | 10513.98 (Jun'23) | 0.00 (Dec'23) | Parnika Commercial and Estates Pvt. Ltd. | Structure RCC work & masonry work completed. External development sanitary installation work 95 % completed, façade work, development work & electrical work is in progress. |
Detail Report
Graph / Photo |
6 | Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi | 2019.10.18 | 2021.04.10 | 13447.15 | 5225.16 (Jun'23) | 99.00 % (Nov'23) | Roshan Real Estate Pvt Ltd. | Road work & external development works has been completed. Rainwater harvesting, MGPS, Painting and false ceiling work of Block-A is in progress. |
Detail Report
Graph / Photo |
7 | Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A6 Paschim Vihar, New Delhi (Package - 7). | 2021.07.18 | 2022.07.17 | 6988.57 | 2658.53 (Jul'23) | 0.00 (Dec'23) | A. K. Mehta & Co. | Work is in progress. |
Detail Report
Graph / Photo |
8 | Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. | 2019.08.06 | 2020.10.29 | 6563.40 | 2087.72 (Jul'23) | 83.00 % (Nov'23) | PNSC Infrastructure Pvt. Ltd | Finishing works, waterproofing, external façade and external development works are under progress. |
Detail Report
Graph / Photo |
9 | Civil and Electrical Composite Work (Dwarka Sector-16 & Qutubapur). | 2021.07.18 | 2022.07.17 | 5058.13 | 255.98 (Jul'23) | 0.00 (Sep'23) | PNSC Infrastructure Pvt. Ltd | The process for local body approvals is in progress. DUAC approval received on 19.09.2022. Fire NOC received. Building Plans uploaded on MCD Portal by the consultant for approval. C/o of boundary wall and other misc. work at Dwarka Sector -16 school is in progress. MCD require Extainsion of time for constrcution from DDA for which request has been made to DDA by L&Estate office vide No.F-16/site/Estate/4210-12 dt. 11.10.2022. As required by DDA, letter requesting waiver of composition Fee for 'Extension of Time" submitted to DDA on 24.11.2022. Building Plans have been approved by SE (Bldg.), MCD . Approved Building Plans are expected to be released shortly. All local body approval has been recevied. Structure drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed .superstructure work started. |
Detail Report
Graph / Photo |
10 | Supply, Installation, Testing and Commissioning of additional CCTV cameras to be integrated with existing (BOSCH Make) CCTV Surveillance System installed at Tihar, Rohini and Mandoli Prison Complexes | 2022.12.24 | 2023.06.23 | 3483.10 | 2253.60 (Jun'23) | 0.00 (Oct'23) | OPTIMUM SECURITY SOLUTIONS PVT. LTD. | Work in progress |
Detail Report
Graph / Photo |
11 | Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. | 2022.10.17 | 2023.10.16 | 3000.18 | 1296.26 (Oct'23) | 0.00 (Dec'23) | Jai Bhagwan | 2nd floor slab casting work for 40 % are in progress, 3rd floor column reinforcement work for 40% area in progress and balance 20% are terrace parapet column casting in progress, brick masonary work at 1st and 2nd floor in progress |
Detail Report
Graph / Photo |
12 | Construction of DTC Bus Depot in resettlement colony at Sawada Ghevra, Delhi | 2022.04.05 | 2022.12.04 | 2915.78 | 1077.04 (Mar'23) | 0.00 (Nov'23) | SVK Infrastructures | Building Work: RCC work of Admin cum Rest Room is in progress. Reinforcement work of the 4th floor slab has been completed. RCC work and Brickwork of the workshop building has been completed. Hardstanding/CC Pavement: 85% of EarthWork has been completed and 75% of WMM layer work has been completed. Boundary Wall: The work of construction of the boundary has been completed. Finishing work has also been completed Drainage Work: 90% of the drainage work completed. The structure for the underground water tank and septic tank has been completed. |
Detail Report
Graph / Photo |
13 | SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW | 2019.10.17 | 2020.07.12 | 2849.35 | 2817.38 (Mar'23) | 0.00 (Dec'23) | A. K. Builders | work in progress. |
Detail Report
Graph / Photo |
14 | Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. | 2019.06.28 | 2020.06.22 | 2806.33 | 381.24 (Mar'23) | 0.00 (Nov'23) | Roshan Real Estate Pvt Ltd. | Work in progress (98% Progress) |
Detail Report
Graph / Photo |
15 | C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi | 2022.02.12 | 2022.11.09 | 2800.59 | 1318.22 (Jun'23) | 0.00 (Nov'23) | SVK Infrastructures | Initially site was encroached by local peoples. Encroachment the major part of land has been removed with help of education department and Delhi Police on dated 22.03.2022, but some portion of site is still encroached by local person. Partly site handed over to the agency for boundary wall and building construction on dated 23.03.2022, hence the actual work started from 23.03.2022. . Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. work of swimming pool and MP hall is in progress. |
Detail Report
Graph / Photo |
16 | Construction of 108 Nos. additional G plus 3 SPS equivalent classrooms including staff rooms labs 6 nos stair cases 16 nos toilets and 1 lift on vacant plot of SKV Sonia Vihar in District North East Zone I Delhi SH:SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site &fire fighting system etc. | 2022.10.11 | 2023.09.05 | 2783.15 | 1872.39 (Sep'23) | 0.00 (Dec'23) | DND Infra Private Limit | Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban. |
Detail Report
Graph / Photo |
17 | Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi | 2021.08.23 | 2022.05.22 | 2373.12 | 1117.89 (Mar'23) | 72.00 % (Nov'23) | M/s PK Gupta & Co. | Building Work: RCC work and Brickwork of Admin cum Rest Room, Toilet Block have been completed. Finishing work completed. Workshop Building-Steel Structural work has started. Hardstanding/CC Pavement: Earth Work has been completed. WMM is in advance stage.Boundary Wall: The work of construction of new boundary wall of approx. 1 Km has almost been completed. Drainage Work: 90% of the drainage work has been completed.The structure for RWH and underground water, septic tank has been completed. |
Detail Report
Graph / Photo |
18 | Construction of Cluster Bus Depot at Kirari Village, Plot No.8 (PSP7), Sector-41, Rohini, Delhi. SH: Civil works and Electrical works. | 2023.05.24 | 2024.01.23 | 2107.18 | 3.00 % (Nov'23) | Kundu Nirma | Preparation of the architectural drawing has been completed. Earthwork and excavation for the boundary wall has started.The building work and boundary wall work is being affected due to high water table. Matter of constructing building and boundary wall on pile foundationis under consideration. |
Detail Report
Graph / Photo |
|
19 | Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. | 2020.05.31 | 2021.05.30 | 1874.70 | 1644.00 (Jun'23) | 0.00 (Dec'23) | SSP Promoters and Builders Private Limited | WORK IN PROGRESS |
Detail Report
Graph / Photo |
20 | Construction of Residential Hostel at Chhattrasal Stadium, Model Town, Delhi. SH: C/o Hostel Building including External Development works, Internal Electrical Installation, External Lighting, lifts, fire fighting system, fire alarm with PA System, CCTV, Audio video system, HVAC works | 2023.02.27 | 2024.07.26 | 1839.86 | 217.20 (Jun'23) | 0.00 (Oct'23) | KALYAN CHANDRA GOYAL & CO. | Work is in progress. Foundation work done. RCC work upto plinth level is completed. Earth filling in footing is in progress. |
Detail Report
Graph / Photo |
21 | C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc | 2022.04.01 | 2023.02.24 | 1798.93 | 374.04 (Jun'23) | 0.00 (Dec'23) | K. L. ARORA & SON | Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban. |
Detail Report
Graph / Photo |
22 | C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) | 2018.12.29 | 2019.07.26 | 1743.19 | 4117.15 (Jun'23) | 0.00 (Oct'23) | AMAR CONSTRUCTION COMPANY | Work in progress |
Detail Report
Graph / Photo |
23 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. | 2023.03.24 | 2023.09.19 | 1729.05 | 0.00 (Nov'23) | SPS Infrabuild Pvt. Ltd. | work in progress |
Detail Report
Graph / Photo |
|
24 | C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. | 2023.03.27 | 2024.02.19 | 1554.26 | 307.14 (Jun'23) | 0.00 (Dec'23) | SWASTIC CONSTRUCTION CO | Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban. |
Detail Report
Graph / Photo |
25 | C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc | 2022.03.26 | 2023.02.19 | 1553.88 | 642.50 (Jul'23) | 0.00 (Dec'23) | K L Arora & Son | Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban. |
Detail Report
Graph / Photo |
26 | C/o 72 Nos. Equivalent SPS Class Rooms in addition to boundary wall i/c Internal & External water supply, sanitary installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting System etc. for new school building at GBSSS Jharoda kalan (School ID 1822065) , New Delhi | 2022.03.12 | 2022.12.06 | 1542.27 | 696.74 (May'23) | 0.00 (Nov'23) | The Krishna Construction Co. | Initially some delay in start of work due to revision of layout and land apportioning between the new school and existing school. Layout plan was finalised by client department on 15.07.2022 and now Structure work completed. Stone work, Exterior Paint, False Celing, SS Railing, Sanitary work is in Progress. |
Detail Report
Graph / Photo |
27 | C/o Cluster Bus Depot at village Gadaipur, District South, Delhi. SH: Civil works and Electrical works. | 2023.05.24 | 2024.01.23 | 1500.30 | 5.00 % (Jun'23) | Kundu Nirman | Work just awarded. The site has been handed over to the agency on 30.05.2023. The architectural drawing has been finalised.. |
Detail Report
Graph / Photo |
|
28 | Composite Work : C/o Prefab structures office, trainee, staff accommodation, class room, kitchen, store, toilet block, parking shed, road work and other misc. civil work and various Electrical works | 2023.11.01 | 2024.04.30 | 1462.98 | Kalyan Chandra Goyal & Company |
Detail Report
Graph / Photo |
|||
29 | C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc | 2022.04.02 | 2023.02.25 | 1359.28 | 613.77 (Jul'23) | 0.00 (Dec'23) | K. L. ARORA & SON | Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban. |
Detail Report
Graph / Photo |
30 | Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) | 2022.03.12 | 2023.02.04 | 1275.84 | 476.42 (Jul'23) | 0.00 (Nov'23) | M/s SURENDRA KUMAR | Work in progress |
Detail Report
Graph / Photo |
31 | Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi | 2022.04.06 | 2025.04.05 | 1099.29 | 114.42 (Jul'23) | 0.00 (Jul'23) | SIKKA ASSOCIATES REGD. | 7 |
Detail Report
Graph / Photo |
32 | C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) | 2022.04.18 | 2023.03.13 | 1090.67 | 699.55 (Jul'23) | 0.00 (Dec'23) | K. L. ARORA & SON | Since Last one month NGT Ban has implemented due to pollution. Target date revised due to NGT Ban. |
Detail Report
Graph / Photo |
33 | C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. | 2023.03.09 | 2024.02.01 | 1058.78 | 91.00 (Mar'23) | 0.00 (Dec'23) | AMOCON | Pile casting for 80% area is completed and pile cap casting for 80% area is completed, balance area could not start due to space constraints at site. plinth beam casting work in progress for 70% area. Slow progress due to space scarcity at site and constraints approach from main road to site. Since Last one month NGT Ban has implemented due to pollution. |
Detail Report
Graph / Photo |
34 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 | 2022.06.03 | 2024.06.02 | 721.25 | 351.65 (Aug'23) | 0.00 (Nov'23) | AZFARUDDIN | Work in progress. |
Detail Report
Graph / Photo |
35 | Civil and Electrical Work. | 2023.03.05 | 2023.11.29 | 617.03 | 16.00 (Sep'23) | 0.00 (Nov'23) | CHANDRA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
36 | Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB | 2022.09.25 | 2023.01.24 | 583.83 | 0.00 (Nov'23) | MAHAVIR PRASAD GUPTA AND SONS |
Detail Report
Graph / Photo |
||
37 | Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work | 2022.01.28 | 2022.12.27 | 579.95 | 360.97 (May'23) | 0.00 (Nov'23) | Invalid | Work is in progress. |
Detail Report
Graph / Photo |
38 | SITC of structure cabling and CCTV System at District Court Rohini, Delhi | 2023.03.06 | 2023.09.05 | 449.96 | 0.00 (Oct'23) | TIRUPATI CONSTRUCTION COMPANY | First RA Bill Rs. 2390388/- dt. 08.08.2023 |
Detail Report
Graph / Photo |
|
39 | Construction of RCC drain and side berm at Burari Road from Swaroop Nagar to Bhalswa, Delhi. | 2023.03.03 | 2023.07.30 | 389.94 | 175.50 (May'23) | 0.00 (Nov'23) | AMIT BUILDCONE | Work completed |
Detail Report
Graph / Photo |
40 | C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) | 2022.03.02 | 2022.11.26 | 385.86 | 0.00 (Nov'23) | M/s. Satyam Construction | Work is in progress |
Detail Report
Graph / Photo |
|
41 | Civil & Electrical Work. | 2023.03.30 | 2023.09.29 | 352.07 | 10.00 % (Jul'23) | Engineers India Construction Ltd. |
Detail Report
Graph / Photo |
||
42 | Up gradation of one staffroom in 86 Nos. Schools under South-East Building Maintenance Division, Hauz Khas, New Delhi during 2018-19. (Civil and Electrical work). | 2019.03.23 | 2019.09.22 | 329.84 | 160.77 (Jan'23) | 0.00 (Jan'23) | S. P. CONSTRUCTION COMPANY | Work in progress |
Detail Report
Graph / Photo |
43 | Construction of Change Room including toilet, Guard Room, Office Room, Coach Room, S.S. fencing on Periphery of Athletic Track & Boundary wall with concertina coil fencing etc. and Renovation of existing block, pump house, entry road and provision of stone cladding on boundary wall at Pooth Kalan Sports Complex, Delhi. | 2023.07.01 | 2023.12.27 | 305.16 | 0.00 (Dec'23) | Sham Lal Gupta & Sons | Dholpur stone cladding work is in progress and construction of front boundary wall is in progress. |
Detail Report
Graph / Photo |
|
44 | Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). | 2019.02.28 | 2019.06.27 | 294.21 | 58.25 (Feb'22) | 0.00 (Feb'22) | AASRA Martech Pvt.Ltd. | Work in progress. |
Detail Report
Graph / Photo |
45 | Civil and Electrical work. | 2019.05.05 | 2020.03.04 | 292.64 | Dheeraj Singh & Company | Work just awarded |
Detail Report
Graph / Photo |
||
46 | Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). | 2022.08.09 | 2023.08.08 | 292.57 | 8.79 (Mar'23) | 0.00 (Oct'23) | Nand gopal Gupta |
Detail Report
Graph / Photo |
|
47 | Air Pistol & Rifle 10m Shooting Hall cum all internal finishing fixtures fitting and development of complete setup of electronic type targets, shooting equipment etc. complete | 2022.03.18 | 2022.09.13 | 290.26 | 55.31 (Jul'23) | 0.00 (Dec'23) | Dev Enterprises | work is in progress |
Detail Report
Graph / Photo |
48 | Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi | 2022.01.16 | 2024.10.15 | 288.00 | Arcop Associates Pvt. Ltd. | Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval. |
Detail Report
Graph / Photo |
||
49 | Construction of 2 nos. Additional Basket Ball Court in Warmup Area, Acoustics Treatment in Basket Ball Hall, Renovation of boundary wall and Sitting Chairs in sitting gallery at Sarvodaya Bal Vidyalaya, Anand Vas (Lok Vihar), Delhi | 2022.12.26 | 2023.05.24 | 267.31 | 208.25 (Jul'23) | 0.00 (Nov'23) | Sham Lal Gupta & Sons | 95% |
Detail Report
Graph / Photo |
50 | Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool | 2020.12.23 | 2021.06.20 | 262.79 | 113.45 (Jul'23) | 0.00 (Nov'23) | Maa Narayan Constuction Co. | finishing work in progress |
Detail Report
Graph / Photo |
51 | Road between Block No. 11-15 from Block-15 to LBS Hospital Through jalebi Chowk, Kalyanpuri.(SH:- Construction of RCC drain from Jalebi Chowk to LBS Hospital) | 2023.08.24 | 2023.12.21 | 179.62 | Dinesh Chand Sharma |
Detail Report
Graph / Photo |
|||
52 | Remodelling of RCC Drain from Shekhar Apartment to UP Link Road via Chilla Sai Mandir Mayur Vihar Phase-1 Delhi | 2023.09.29 | 2024.04.25 | 162.48 | Chaudhary Construction Company Pvt. Ltd. |
Detail Report
Graph / Photo |
|||
53 | Construction of Boundary Wall of vacant Land at Madan Halwai Farm Loni, Johripur, Delhi. | 2023.09.01 | 2024.02.27 | 152.17 | 0.00 (Dec'23) | CBC and Sons | Since Last one month NGT Ban has implemented due to pollution. Target revised due to NGT Ban. |
Detail Report
Graph / Photo |
|
54 | Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). | 2019.01.25 | 2019.05.24 | 140.44 | 216.46 (Oct'21) | 0.00 (Oct'21) | Uma Shankar | work in progress |
Detail Report
Graph / Photo |
55 | Remodeling of drain in opposite side of Mansarovar Park to Kendriya Vidhalaya along with G.T. Road under Sub Division M-2111 during 2022-23. | 2023.04.21 | 2023.10.17 | 136.64 | Chaudhary Construction Company Pvt. Ltd. |
Detail Report
Graph / Photo |
|||
56 | Construction of boundary wall at vacant lying land measuring 09 Bigha 15 Biswa(7000 sqm. Approx.) bearing khasra No. 1937/1307 to 1990/1307 situated in village-Fahepur Beri. | 2022.12.19 | 2023.06.01 | 129.24 | 0.25 (Jun'23) | 46.00 % (Sep'23) | SIROHI CONSTRUCTION CO. | Work is in progress |
Detail Report
Graph / Photo |
57 | Construction of Migrant workers support centre at the office joint labour commissioner Vishwakarma Nagar Jhilmil colony Delhi (Civil and Electrical Work) | 2022.04.23 | 2023.01.22 | 124.05 | 9.97 (Feb'23) | 0.00 (Aug'23) | Dheeraj Singh & Company | In Progress. |
Detail Report
Graph / Photo |
58 | C/o Extention of MADI of Dental Sciences,Ph-II at Bahadur Shah Zafar Marg,ND.SH SITCof Medical Gas Pipeline System including 3 Years Comprehensive Maintenance | 2019.08.12 | 2019.11.09 | 115.37 | Med Freshe Pvt. Ltd. | work in progress by Med Freshe Pvt. Ltd |
Detail Report
Graph / Photo |
||
59 | Changes in infrastructure of CHB to develop it as OHB Model Home.(Civil and Electrical work) | 2019.10.24 | 2020.02.23 | 112.72 | 20.64 (Dec'22) | 0.00 (Dec'22) | Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 |
Detail Report
Graph / Photo |
|
60 | Construction of RCC wall in place of existing boundary wall above ground level and Fencing work | 2022.12.21 | 2023.03.20 | 96.02 | 85.00 % (Jun'23) | Work in progress. |
Detail Report
Graph / Photo |
||
61 | Designing Manufacturing Installation and Commissioning of ceiling mounted Facade Access System on external facade and inner facade in Atrium at S Block Delhi High Court New Delhi | 2022.12.16 | 2023.03.15 | 91.53 | 78.12 (Mar'23) | 0.00 (Aug'23) | M P BHATIA | Work in progress |
Detail Report
Graph / Photo |
62 | Construction of Extention of Maulana Azad Dental Institute of Dental Sciences, phaseII at Bahadur Shah Zafar Marg, New Delhi.SH Supplying, installation, testing and Commissioning of Modular Operation Theatre | 2019.08.12 | 2019.11.09 | 83.93 | 21.56 (Feb'22) | 0.00 (Feb'22) | MDD Medical System (INDIA) Pvt. Ltd | work in progress by MDD Medical System (I) Pvt.Ltd. |
Detail Report
Graph / Photo |
63 | Up-gradation of swimming pool and other misc. civil works including electrical work | 2021.08.11 | 2021.12.08 | 83.39 | 90.41 (Mar'23) | 0.00 (Aug'23) | M/s Tanishq Ions | In Progress. |
Detail Report
Graph / Photo |
64 | Replacement of Water Tanks & M.S. framed platform at various floors of Delhi Secretariat Building | 2022.05.21 | 2022.07.20 | 81.25 | 0.00 (Nov'23) | Work in progress.70% |
Detail Report
Graph / Photo |
||
65 | Renovation of gate no. 1 & 3 with GRC mouldings/cornices). (Civil & Electrical Works) | 2022.06.25 | 2022.08.23 | 78.59 | 135.99 (Jun'23) | 0.00 (Aug'23) | Uma Shankar |
Detail Report
Graph / Photo |
|
66 | A A to Karkardooma Court Complex Delhi SH Replacement of damaged Kota stone flooring into Granite stone flooring P F false ceiling and wall tiles in corridor and common area of ground floor including Electrical Work of A C and I block. | 2023.04.05 | 2023.07.03 | 75.02 | 0.00 (Nov'23) | Rakesh Kumar Rai | In Progress. |
Detail Report
Graph / Photo |
|
67 | 1 Govt. Middle School, Sarita Vihar 2 Govt. Sr. Sec. School, Sultanpur 3 Sr. Sec. School, Tehkhand 4 Jonapur-1 5 Jonapur-2 6 RPVV at Sector A, Vasant Kunj Package-C. | 2017.11.20 | 2018.01.19 | 71.50 | 42.22 (Oct'21) | 0.00 (Oct'21) | SPACE DESIGN GROUP | In progress |
Detail Report
Graph / Photo |
68 | Changes in Infrastructure of Model Home to convert it as CHB and JJB in front of Building (Civil and Electrical work). | 2019.10.24 | 2020.01.23 | 71.13 | 20.78 (Dec'22) | 0.00 (Dec'22) | AJAY CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|
69 | SH Work of UTCS Complex Employment exchange JJB Court Working Women Hostel HLTB Complex Sanskar Ashram, Department of Social Welfare and CDMO Shahdara KKD Court Division under SD M 2312 during 2022 23. | 2023.01.07 | 2024.01.06 | 64.35 | 26.08 (Aug'23) | 0.00 (Nov'23) | In Progress. |
Detail Report
Graph / Photo |
|
70 | Construction of 4 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of SRD Project Division-2, PWD, Delhi. (Civil & Electrical Work) | 2022.06.01 | 2022.11.27 | 63.68 | 0.00 (Nov'23) | R K Construction Co. |
Detail Report
Graph / Photo |
||
71 | Comprehensive maintenance of 310 DA staff qtrs. Supply of materials and providing services of manpower for day to day maintenance work of 310 DA staff qtrs. KKD Court Divn. under SD M-2313 Karkardooma Delhi dg. 2021 22 | 2022.02.07 | 2023.02.06 | 63.52 | 48.72 (Feb'23) | 0.00 (Feb'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
72 | Supply, installation, testing and commissioning of Router at Rouse Avenue District Court Complex, DDU Marg, New Delhi. | 2023.06.01 | 2023.08.29 | 63.36 | 0.00 (Oct'23) | TRACOM ENTERPRISES | Work in progress |
Detail Report
Graph / Photo |
|
73 | Comprehensive maintenance, Supply of material and providing services of manpower for day to day maintenance work of lawyer’s chamber blocks (ie. D,E,F,G& H- Blocks) Under SubDivision M-2311, KKD Court, PWD, Delhi | 2022.01.22 | 2023.01.21 | 62.58 | 78.03 (Jun'23) | 0.00 (Jun'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
74 | Providing of EI AC RO Water Cooler EPABX system and Fire Alarm System work including CIVIL works | 2021.12.19 | 2022.02.18 | 59.70 | 3.69 (Jul'23) | 0.00 (Jul'23) | V. S. ENTERPRISES |
Detail Report
Graph / Photo |
|
75 | Making casting of factory made modular cupboard with fire retardant and boiling water proof Boilo Board in Alhmad rooms of C Block of KKD Court Complex Delhi 2nd Recall | 2022.03.14 | 2022.06.11 | 59.19 | 70.85 (Jan'23) | 0.00 (Sep'23) | Srishti Assosiates |
Detail Report
Graph / Photo |
|
76 | Construction of Boundary wall at vacant lying land measuring 02 Bigha 08 Biswa bearing Khasra no. 86/12/2 (02-08) of Directorate situated in Village-Ladpur (District-North-West) Delhi through, PWD. | 2022.08.26 | 2022.12.23 | 58.39 | 0.00 (Nov'23) | Parth Garg | Work in progress |
Detail Report
Graph / Photo |
|
77 | Making casting of factory made modular cupboard with fire retardant and boiling water proof Board in Court rooms North East District of KKD Court Complex Delhi | 2021.11.21 | 2022.02.18 | 54.92 | 26.82 (Apr'23) | 0.00 (Apr'23) | Millennium Furniture |
Detail Report
Graph / Photo |
|
78 | C/o Medical store and Surgical Store in basement area of Indira Gandhi Hospital, Sector-9, Dwarka, New Delhi | 2022.09.13 | 2022.11.11 | 54.60 | 11.04 (Jun'23) | 90.00 % (Nov'23) | DEEPAK CONSTRUCTION AND COMPANY | Work is under progress. |
Detail Report
Graph / Photo |
79 | Renovation of 2nd floor Medical Block IT Cell at first floor Medical Block and Library room no. 5 18 240 and 241 at A Block Delhi High Court New Delhi. | 2023.08.05 | 2023.11.02 | 52.03 | R L WADHWA | Work in progress |
Detail Report
Graph / Photo |
||
80 | Construction of shed for Gate No. 1, 2 and 3 at District Court Complex, Saket, New Delhi. | 2023.03.17 | 2023.06.16 | 51.74 | IZHAR AHMED |
Detail Report
Graph / Photo |
|||
81 | Construction of 100 Bedded Portable Hospital reserved for Covid 19 at A and U Tibbia College and Hospital, Karol Bagh, New Delhi (Electrical Works) | 2021.12.28 | 2022.02.20 | 51.44 | 52.14 (May'22) | 0.00 (May'22) | Jain Electric Works |
Detail Report
Graph / Photo |
|
82 | Construction of Lift well including civil work in Utility block from Basement to Top floor at District Court Complex, Saket, New Delhi-110017 Civil + Electrical Work. | 2023.04.07 | 2023.06.06 | 51.11 | Anand Electricals | Work in Progress 5% |
Detail Report
Graph / Photo |
||
83 | Replacement of Carpets in Courts of A block Extension block and wooden texture laminated flooring in Chambers of Extension block at Delhi High Court New Delh | 2017.06.27 | 2017.07.26 | 50.20 | Bansal Builder | Agreement closed PG forfeited |
Detail Report
Graph / Photo |
||
84 | False Ceiling, Granite and Wooden Flooring work in court rooms of Shahdara district Karkardooma Court Complex Delhi. Civil and Electrical Work. | 2023.03.16 | 2023.06.13 | 50.09 | 18.00 (Jun'23) | 0.00 (Sep'23) | M.N Construction | In progress |
Detail Report
Graph / Photo |
85 | Waterproofing treatment and Heat resistant tile work at terrace of A, C & I block | 2022.06.08 | 2022.09.05 | 50.04 | 55.78 (May'23) | 0.00 (Jul'23) | M. N. Construction Co. |
Detail Report
Graph / Photo |
|
86 | Provision for 1. Construction of front side boundary wall near main gate 2. Complete renovation of toilet blocks of old Building at Sarvodaya (Co-ed) Vidyalaya, Masjid Moth, New Delhi. (School ID: 1925246, Building ID: 19251141 & EOR ID: 20211430. | 2023.09.06 | 2024.02.05 | 49.74 | Shamshad Ahmad |
Detail Report
Graph / Photo |
|||
87 | Providing and fixing three seater stainless steel bench at ACI Block, Karkardooma Court Complex, Delhi | 2022.02.26 | 2022.03.27 | 48.15 | 0.00 (Oct'23) | GEEKEN SEATING COLLECTION PVT LTD |
Detail Report
Graph / Photo |
||
88 | Improvement of the existing bituminous road with granite stone block toward dedicated area from gate no. 1 to DJ parking toward C-Block and upto first face of B-Block toward gate no.1 and Renovation of corridor of court no-1 3rd floor C-Block KKD Court, Delhi | 2022.06.25 | 2022.08.23 | 47.61 | 55.48 (May'23) | 0.00 (Aug'23) | Manish Construction |
Detail Report
Graph / Photo |
|
89 | Stone cleaning of Extension Block, Administrative Block and Outer Boundary Wall, Delhi High Court, New Delhi. | 2023.07.17 | 2023.09.14 | 45.56 | 0.00 (Oct'23) | Jamshed Ali and Sons | Work in progress |
Detail Report
Graph / Photo |
|
90 | A R and M O Jagpravesh Chandra Hospital, Shastri Park, Lal Bahadur Shastri Hospital, Khichripur, Chacha Nehru Bal Chikitsalaya, Geeta Colony, Dr. Hedgewar Arogya Sansthan, Karkardooma, Aam Admi Polyclinic, Kanti Nagar an Delhi Govt. Dispensaries .... | 2019.08.19 | 2020.08.18 | 45.47 | Royal Construction | p |
Detail Report
Graph / Photo |
||
91 | Improvement and renovation works in 06 Nos. Type III/IV Quarters. | 2023.08.06 | 2023.11.05 | 43.58 | Nasimuddin |
Detail Report
Graph / Photo |
|||
92 | SITC of Building Management System | 2020.09.12 | 2021.03.11 | 43.49 | Digital Controls & Automation | Material supplied by the firm. Work is held-up by the agency. Notice under Clause 3 submitted to Competent Authority for approval for determination of contract. |
Detail Report
Graph / Photo |
||
93 | Construction of Oxygen Generator plant Hall at GIPMER, New Delhi. (Electrical works) | 2021.12.06 | 2022.01.19 | 43.31 | 0.11 (Jul'22) | 0.00 (Jul'22) | Jain Electric Works |
Detail Report
Graph / Photo |
|
94 | P/F Vitrified tile flooring, false ceiling, wall paneling and IRC Fabric, Construction of underground R.C.C water tank, installation of 01 no. Borewell and other miscellaneous works at DSEU, Vivek Vihar, Delhi dg. 2022-23). (Civil & Electrical Works). | 2022.06.13 | 2022.09.10 | 41.34 | 51.67 (Jun'23) | 0.00 (Jun'23) | Uma Shankar |
Detail Report
Graph / Photo |
|
95 | Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings incupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) | 2022.07.29 | 2022.09.11 | 41.32 | 40.40 (Mar'23) | 0.00 (Oct'23) | Engineers India Construction Co. |
Detail Report
Graph / Photo |
|
96 | Renovation of toilet blocks at post office and ATM side in Lawyers Chamber Block-I, Delhi High Court, New Delhi. | 2023.07.11 | 2023.10.08 | 41.13 | 0.00 (Nov'23) | SHREE PAL SINGH | Work in progress |
Detail Report
Graph / Photo |
|
97 | Water proofing treatment of Main Court Block A Block podium and basement area at Delhi High Court New Delhi | 2023.01.07 | 2023.05.06 | 40.42 | 14.95 (Jun'23) | 0.00 (Aug'23) | Complete waterproofing system inc. | Work in progress |
Detail Report
Graph / Photo |
98 | Toilets renovation works | 2021.07.09 | 2021.10.06 | 40.06 | 49.76 (Jan'23) | 0.00 (Jan'23) | Saeed Builders | In progress. |
Detail Report
Graph / Photo |
99 | Up gradation of Type V Judges flats No 402 Type IV Judges flats No 205 Type VI Judge s flats No 607 and Servant Qtrs. 402 607 and 102 at Karkardooma Court Complex Delhi Civil and Electrical Works | 2023.01.01 | 2023.03.31 | 38.79 | 0.00 (Oct'23) | Uma Shankar | In progress. |
Detail Report
Graph / Photo |
|
100 | Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings in cupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) | 2022.07.29 | 2022.09.11 | 35.17 | 34.64 (Apr'23) | 0.00 (Oct'23) | Engineers India Construction Co. |
Detail Report
Graph / Photo |
|
101 | CO of Toilet for primary wing support staff visitor and attached toilet to principal room renovation of water tank platform and toilet repairing of b wall and other misc civil works | 2020.08.15 | 2020.12.14 | 34.45 | 80.00 % (Dec'20) | CSM CONSTRUCTION |
Detail Report
Graph / Photo |
||
102 | Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing ductable type air conditioning system | 2019.07.09 | 2019.10.08 | 33.85 | 14.13 (Oct'22) | 0.00 (Oct'22) | SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. | work in Progress 6th RA 18182135 |
Detail Report
Graph / Photo |
103 | Providing, installation, testing, and commissioning of Code Blue System (NCS) for Old and New block at MAIDS, New Delhi | 2019.08.11 | 2019.11.10 | 33.77 | 19.85 (Mar'23) | 0.00 (Mar'23) | Med Freshe Pvt. Ltd. | Work in progress Med Freshe Pvt. Ltd. |
Detail Report
Graph / Photo |
104 | Construction of porta cabins Legal Aid Defence Counsel System office near facilitation centre for Legal Aid Defence Counsel System office Karkardooma Court Delhi. Civil Furniture and Electrical Works 2nd recall | 2022.08.31 | 2022.09.29 | 33.23 | 0.25 (Mar'23) | 0.00 (Mar'23) | MUZAMMIL ALI |
Detail Report
Graph / Photo |
|
105 | Construction of SAKHI- ONE STEP CENTRE at campus of GBSSS, Malviya Nagar, New Delhi. (Civil and Electrical Works) | 2021.12.16 | 2022.04.15 | 32.92 | 29.75 (Jan'23) | 0.00 (Jan'23) | AKSHAY KUMAR DAGAR | Work in Progress 80% |
Detail Report
Graph / Photo |
106 | Strengthening of damaged beams columns slabs during 2021 22 at SKV No 1 Mansarovar Park Shahdara Delhi 32 School ID 11061655 (Balance work) | 2022.04.05 | 2022.07.03 | 32.79 | 30.24 (Nov'22) | 0.00 (Nov'22) | Cembond Construction Pvt. Ltd |
Detail Report
Graph / Photo |
|
107 | C O Police Housing Complex at Mandoli Delhi. (SH Annual Comprehensive Maintenance Contract of Johnson Make lift installed at Police Housing Complex, Mandoli Delhi) | 2023.01.14 | 2024.01.13 | 32.49 | Invalid | Work in progress |
Detail Report
Graph / Photo |
||
108 | Renovation and Modification of 32 Nos Chambers of Honble Judge in A Block Delhi High Court New Delhi | 2022.09.09 | 2022.11.07 | 31.97 | 119.75 (Mar'23) | 0.00 (Aug'23) | R L WADHWA | Work in progress |
Detail Report
Graph / Photo |
109 | C/o Boundary Wall in newly allotted land to Directorate of Education, GNCTD at village Satbari, South District, New Delhi. | 2023.04.03 | 2023.08.02 | 31.15 | 0.25 (Jun'23) | 0.00 (Nov'23) | Kapil Tanwar | Work is in progress |
Detail Report
Graph / Photo |
110 | SITC of additional CCTV and allied equipment at GTB Hospital, Shahdara, Delhi | 2018.10.16 | 2018.12.15 | 30.64 | 15.29 (Feb'19) | 50.00 % (Feb'19) | San Infotech Services | work in progress 2nd RA 1696099 |
Detail Report
Graph / Photo |
111 | Strengthening work in various buildings M N O block in Judges Residential Complex at KKD Court Shahdara Delhi dg 2021 22 | 2021.12.17 | 2022.04.15 | 29.81 | 28.23 (Feb'23) | 0.00 (Oct'23) | Cembond Construction Pvt. Ltd | In Progress. |
Detail Report
Graph / Photo |
112 | Making Accessible approach. Balance Work 1st recall | 2022.09.24 | 2022.12.22 | 27.32 | 20.23 (Apr'23) | 0.00 (Aug'23) | Shobhit Kumar |
Detail Report
Graph / Photo |
|
113 | SITC of WI-FI & AC. | 2023.08.07 | 2023.10.06 | 27.08 | R J P ENTERPRISE |
Detail Report
Graph / Photo |
|||
114 | Renovation of court no 51 & 53 B-Block at Karkardooma Court, Delhi | 2022.06.13 | 2022.08.11 | 26.85 | 27.90 (Jul'23) | 0.00 (Jul'23) | Uma Shankar |
Detail Report
Graph / Photo |
|
115 | Up gradation of AFAS at Basement, G.F. & 1 st floors. | 2023.07.27 | 2023.08.26 | 25.93 | R B SUPER ELECTRICALS |
Detail Report
Graph / Photo |
|||
116 | Civil work, false ceiling, flooring and finishing work at Multilevel Car parking in Delhi High Court, New Delhi. | 2023.03.12 | 2023.06.10 | 25.91 | 0.00 (Nov'23) | Yameen | Work in progress |
Detail Report
Graph / Photo |
|
117 | Construction of 01 Nos. Clinical care centre under School Health Scheme on the vacant piece of land between Babu Ram Govt. SBV Bhola Nath Nagar and DIET Shahdara. (Civil, Furniture & Electrical Works). (4th Recall) | 2022.09.16 | 2022.11.14 | 25.77 | 30.48 (Feb'23) | 0.00 (Nov'23) | SUDHIR KUMAR SHARMA |
Detail Report
Graph / Photo |
|
118 | Renovation of electrical installation for lab no. 403 and 403 A at 4th floor of Forensic Science Laboratory, Rohini, Delhi | 2023.04.13 | 2023.07.02 | 25.26 | R J P ENTERPRISE |
Detail Report
Graph / Photo |
|||
119 | Construction of 5 Nos. Units of Toilets for Male, Female & Transgender, Near OPD, Casualty, Dharamshala Mortuary & MCH Building outside area at GTB Hospital Construction of 03 Nos. sheds with granite benches for patient attendants at Various Locations Near MCH Ground floor and Renovation of Seminar Room of Department of Pediatrics situated at MCH 4rth Floor (Front Wing) at GTB Hospital, Shahdara, Delhi. | 2023.08.10 | 2023.11.07 | 25.20 | 0.00 (Nov'23) | Sanendra Kumar | Work in progress. |
Detail Report
Graph / Photo |
|
120 | Repair and renovation of Veterinary Dispensary, Bankner, Animal Husbandry Unit of GNCT of Delhi-110040 | 2022.08.01 | 2022.10.30 | 24.62 | 31.73 (Jul'23) | 0.00 (Jul'23) | Ankur Bhardwaj | Work in Progress |
Detail Report
Graph / Photo |
121 | Replacement of damaged G.I. Sheets & Covering IRC wire fabric all around Pharmacy for thermal insulation at GTB Hospital, Shahdara, Delhi | 2022.11.26 | 2023.01.24 | 23.91 | 7.93 (Mar'23) | Shamshad Ahmed | Work held up by agency. |
Detail Report
Graph / Photo |
|
122 | SITC of Lifts. | 2023.02.21 | 2023.05.20 | 23.60 | 0.00 (Nov'23) | Techno Industries Limited | First RA Bill RS. 1888099/- dt. 31.05.23 |
Detail Report
Graph / Photo |
|
123 | Replacement of Main Gates No. 1, 2, 3, 5, 6 & 7 with repair of boundary wall for security purpose at GTB Hospital, Shahdara, Delhi. dg. 2023-24. | 2023.08.17 | 2023.11.29 | 23.44 | 0.00 (Nov'23) | AMIR ISRAR | Work in progress. |
Detail Report
Graph / Photo |
|
124 | Construction of some boundary wall after demolition of tilted existing boundary wall behind Principal office & construction of new boundary wall and construction of new stage on ground at Dr. Ambedkar Nagar, Sector-IV, No. 1- SBV (Yogi Arvind), New Delhi. (School ID: 1923005, Building ID: 19231163 & EOR ID: 20221410. | 2023.07.26 | 2023.09.25 | 22.00 | Vision Construction |
Detail Report
Graph / Photo |
|||
125 | Strengthening of Judges Residential Complex Buildings M N and O Block at Karkardooma Court Delhi.(Repair of the external plaster) | 2023.08.05 | 2023.09.03 | 21.94 | Sundriyal Construction - Closed |
Detail Report
Graph / Photo |
|||
126 | Re-layering of Damaged Internal Bituminous Roads at Judges Flat including raising of manhole cover, laying of C.C. pavement, paver block & Kerb stone, at Karkardooma Court, Sahadara, Delhi-110032 | 2022.07.15 | 2022.08.13 | 21.86 | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|||
127 | Construction of Boundary Wall, Vehicle Shed with Porta Cabin near UCMS Building, Repair of Structural Glazing and ACP Sheet Cladding of DEM Building GTB Hospital and Renovation of Aam Aadmi Polyclinic Nand Nagri, Delhi. | 2023.04.14 | 2023.07.13 | 21.65 | Nasir Ali | Work in progress but progress work is very slow. |
Detail Report
Graph / Photo |
||
128 | Renovation of toilet blocks & miscellaneous civil works- Balance work | 2022.06.26 | 2022.09.23 | 21.44 | 6.94 (Mar'23) | 0.00 (Oct'23) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
129 | Expansion of Lawyers Cafeteria in B Block and Shifting of Filing Counter in Administrative Block & Providing and fixing work stations for IT Branch at Lawyers Chambers Block-III of Delhi High Court New Delhi. | 2023.03.07 | 2023.04.05 | 21.18 | 0.00 (Oct'23) | R L WADHWA | Work in progress |
Detail Report
Graph / Photo |
|
130 | Waterproofing treatment and Heat resistant tile work at terrace of J K and L block and replacement cum repairing of door and window of lift rooms at A C I J and L block Karkardooma Court Complex | 2022.06.08 | 2022.09.05 | 20.86 | 22.91 (May'23) | 0.00 (Aug'23) | Karan Walia |
Detail Report
Graph / Photo |
|
131 | Upgradation of existing analog CCTV system to IP based CCTV system in lockup rooms at District Court Dwarka Sector 10 New Delhi | 2022.04.17 | 2022.07.16 | 20.86 | YASH ENTERPRISES |
Detail Report
Graph / Photo |
|||
132 | Repair Renovation of Gents Ladies Staff toilet general girls toilet and CWSN toilet block at Sarvodaya Kanya Vidyalaya Prahladpur Banger Delhi (School ID 1310032) | 2022.10.21 | 2022.12.05 | 19.90 | M/s R M constrution | Work in progress |
Detail Report
Graph / Photo |
||
133 | Providing AC, Fan, Light Fitting, rewiring in Govt. Co-ed. SSS, Sec15, Rohini, Delhi. | 2023.08.19 | 2023.09.18 | 19.57 | 0.00 (Oct'23) | Kuldeep Traders |
Detail Report
Graph / Photo |
||
134 | Operation and maintenance of compost machines installed in various jail at Prison Complex Mandoli Delhi (4th Call) | 2022.09.26 | 2023.09.25 | 19.02 | 10.89 (Jun'23) | 0.00 (Jun'23) | Clean India Ventures Pvt. Ltd. | Work is in progress |
Detail Report
Graph / Photo |
135 | SITC of CCTV in various Mohalla Clinic under sub division M3513 | 2022.04.13 | 2022.05.12 | 18.93 | YASH ENTERPRISES | 100% Work Completed |
Detail Report
Graph / Photo |
||
136 | Provision of chequrred tiles, raising of boundary wall and other misc civil work | 2022.06.26 | 2022.07.25 | 18.67 | 21.25 (Dec'22) | 0.00 (Dec'22) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
137 | SITC of VRV/ VRF Air Condition Plant | 2022.06.12 | 2022.07.11 | 18.55 | 12.64 (Sep'22) | 0.00 (Sep'22) | Airtemp Engineers | 100% Work Completed |
Detail Report
Graph / Photo |
138 | Provision of Basket Ball Court along with development of adjoining area in the Residential Campus GTB Hospital Shahdara Delhi | 2023.06.16 | 2023.07.20 | 18.37 | 0.00 (Oct'23) | Chunesh Bansal | Work is in progress |
Detail Report
Graph / Photo |
|
139 | C/o recreation hall at PTS Wazirabad Delhi. (SH- Providing Electrical Installation) | 2019.02.12 | 2019.06.11 | 18.22 | S K Engineers |
Detail Report
Graph / Photo |
|||
140 | Renovation of toilets gutter fixing and barricading work. 1st recall | 2022.08.21 | 2022.12.18 | 18.07 | 0.24 (Mar'23) | 0.00 (Nov'23) | MOHAMMAD HUSSAIN |
Detail Report
Graph / Photo |
|
141 | Renovation of Ladies Bar Association Room at KKD Courts Delhi. Civil Furniture and Electrical Works 1st recall. | 2023.02.12 | 2023.03.28 | 18.05 | 6.15 (May'23) | 0.00 (Sep'23) |
Detail Report
Graph / Photo |
||
142 | Construction of 2 Nos. DLSA offices and 1 no. E-Sewa Kendra in District Court Complex Rohini, Delhi. (SH: Electrical) work) | 2023.07.20 | 2023.08.29 | 17.73 | 0.00 (Sep'23) | R S ELECTRIC CO. | Ist RA Bill Rs.337930/- dt. 06.09.2023 |
Detail Report
Graph / Photo |
|
143 | Replacing of damaged G.S sheets with G.I profile sheets. (1st recall) | 2022.04.01 | 2022.06.29 | 17.32 | 19.11 (Dec'22) | 0.00 (Dec'22) | SABUR ALAM |
Detail Report
Graph / Photo |
|
144 | Construction of Godown for Horticulture Deptt. at Nursery and Store Room at Fire Station near Delhi Secretariat, Delhi. | 2023.02.06 | 2023.04.05 | 17.18 | RAJU | work in progress. 90% work has been done. |
Detail Report
Graph / Photo |
||
145 | Construction of Crèche in IGDTUW Campus, Kashmere Gate, Delhi. | 2023.03.09 | 2023.05.08 | 17.10 | KAMAAL CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|||
146 | Supply, Installation, Testing and Commissioning of Air Purifiers in Judges Chamber at Rouse Avenue Court Complex DDU Marg, New Delhi. | 2023.10.28 | 2023.11.27 | 16.44 | ABUBAKAR SIDDIQUI | Work in progress |
Detail Report
Graph / Photo |
||
147 | Changing the Windows of Nurse Hostel in Residential Campus at GTB Hospital Shahdara Delhi | 2022.08.26 | 2022.11.23 | 16.17 | 4.02 (May'23) | 0.00 (Nov'23) | Sanendra Kumar | Work is in progress |
Detail Report
Graph / Photo |
148 | A/R & M/O GNEC, New Delhi. dg. 2016-17 (SH: Up-Keeping and maintenance of services of GNEC and providing and service of computer operator, Dak Messenger, plumber, carpenter, mason sewerman etc under HMD (Central) SD-3) | 2017.04.13 | 2017.10.12 | 16.04 | 7.45 (Mar'19) | 46.00 % (Mar'19) | Anup Enterprises |
Detail Report
Graph / Photo |
|
149 | SITC of CCTV Cameras at Place of Safety, Majnu Ka Tila, Delhi | 2022.04.13 | 2022.05.12 | 15.40 | 15.10 (May'23) | 0.00 (May'23) | YASH ENTERPRISES | 100% Work Completed |
Detail Report
Graph / Photo |
150 | Construction of Rain Water Harvesting Pit inside ITI Campus and ITI Staff Quarter, Vivek Vihar, Delhi. | 2022.07.15 | 2022.10.12 | 15.37 | 0.00 (Jul'23) | Shivam Builders |
Detail Report
Graph / Photo |
||
151 | SH- Kota stone flooring, repair to boundary wall including grit plaster and concertina wire fencing, repair and maintenance of toilets, P F steel windows, renewing broken glass panes with polycarbonate sheet etc. | 2018.11.07 | 2019.02.04 | 15.26 | 17.61 (Apr'22) | 0.00 (Jul'23) | MOHAMMAD HUSSAIN | in progress. |
Detail Report
Graph / Photo |
152 | Providing and fixing Glow studs, Median Marker and Delineators at Road No. 64, Road No. 68, Captain Javed Ali Marg, Seemapuri link Road and GTB Hospital Road under Sub Division M-2114 during 2023-24. | 2023.07.08 | 2023.08.06 | 15.25 | VEER SINGH DAHIYA |
Detail Report
Graph / Photo |
|||
153 | Annual comprehensive maintenance of existing Air conditioner and Replacement of fans, fittings, security lights , Distribution Boards along with allied switchgears at Laxmi Bai college, Ashok vihar, Delhi. | 2023.09.14 | 2024.09.13 | 15.18 | SUDHIR KUMAR |
Detail Report
Graph / Photo |
|||
154 | Accessibility works | 2022.08.06 | 2022.10.04 | 15.09 | 12.07 (Nov'22) | 0.00 (Nov'22) | M T Builders | In Progress. |
Detail Report
Graph / Photo |
155 | SITC of 6 passengers Hydraulic lift in Admin Block basement 1 to basement 2 at District Court Sector 10 Dwarka New Delhi | 2022.08.01 | 2022.10.30 | 14.92 | 0.00 (Aug'23) | Techno Industries Pvt Ltd |
Detail Report
Graph / Photo |
||
156 | Providing tactile pathway to Resource centre Separate stainless Steel main gate Providing and placing water storage tanks Distempering painting and finishing work and misc civil work | 2022.05.29 | 2022.08.26 | 14.87 | 18.56 (Dec'22) | 0.00 (Oct'23) | Sushil Kumar | Work not started by agency due to rain |
Detail Report
Graph / Photo |
157 | Aluminium Works at Delhi Secretariat | 2022.07.01 | 2023.03.31 | 14.14 | 9.04 (Feb'23) | 0.00 (Oct'23) | Nasimuddin |
Detail Report
Graph / Photo |
|
158 | Providing facilities for person with disability at CAW CELL Building, Sector-3, Rohini, New Delhi. | 2023.04.27 | 2023.07.26 | 13.86 | ESCON ELEVATORS PVT. LTD |
Detail Report
Graph / Photo |
|||
159 | Repair/ improvement of berm, footpath and drain at Jaipur Golden Hospital, Sector-3, Rohini | 2022.04.27 | 2022.07.26 | 13.86 | 17.21 (Sep'22) | 0.00 (Sep'22) | Dharambir Singh |
Detail Report
Graph / Photo |
|
160 | Replacement of old Air conditioner, providing of main LT panels, Distribution boards i/c providing LED fittings and other miscellaneous electrical work for Board of Technical Education building at Muni Maya Ram Marg, Pitampura, Delhi. | 2023.08.17 | 2023.10.16 | 13.68 | 0.00 (Nov'23) | BAJRANG ELECTRICAL (INDIA) |
Detail Report
Graph / Photo |
||
161 | EOR to Govt. Sarvodaya Kanya Vidyalaya a S.P. Road, Nangloi, New Delhi. SH Providing new gate for main entrance, near activity room, providing and fixing grill in front of primary section providing shed for water through near primary section | 2018.04.02 | 2030.09.15 | 13.58 | L V Enterprises |
Detail Report
Graph / Photo |
|||
162 | Expansion of 8 no. Vulnerable Witness Courts at 5th and 6th floor, B-Block KKD Courts Delhi including Audio-Video System and other electrical installations. (Furniture work) | 2022.05.19 | 2022.06.17 | 13.23 | 19.43 (Dec'22) | 0.00 (Dec'22) | Jain Electric Works |
Detail Report
Graph / Photo |
|
163 | Setting up of Dining Hall at HLTB Complex, Tahirpur, Delhi under KKD Court Divn.. M-231 dg. 18-19. | 2019.02.10 | 2019.05.10 | 12.52 | 13.79 (Jan'20) | 0.00 (Jan'20) | Daya Sagar Sharma | work in progress |
Detail Report
Graph / Photo |
164 | Construction of temporary shed at Community hall Welcome Delhi (Civil and Electrical work) | 2022.02.02 | 2022.03.03 | 12.04 | 0.12 (Mar'23) | 0.00 (Mar'23) | Sanjeev Kumar | In progress. |
Detail Report
Graph / Photo |
165 | Providing new stainless steel gate at entry, internal painting of building, P/F signage board, wooden flooring and wall panelling in principal & conference room & misc. civil works in DIET, J & K pocket, Dilshad Garden, Delhi | 2021.12.26 | 2022.02.23 | 11.65 | 11.10 (Feb'23) | 0.00 (Feb'23) | Sanjeev Kumar | In progress. |
Detail Report
Graph / Photo |
166 | Providing Fans, Light Fitting, Water Cooler at SKV, Sector-1, Avantika, Rohini, Delhi. | 2023.07.11 | 2023.09.10 | 11.63 | Adhiraj Construction |
Detail Report
Graph / Photo |
|||
167 | Civil Work. | 2023.02.12 | 2023.05.12 | 11.21 | 12.63 (Apr'23) | 0.00 (Apr'23) | MOHAMMAD HUSSAIN | In Progress. |
Detail Report
Graph / Photo |
168 | Civil Electrical Works | 2021.12.10 | 2022.02.07 | 11.21 | 11.94 (Oct'22) | 0.00 (Oct'22) | Rainbow Constructions | In Progress. |
Detail Report
Graph / Photo |
169 | Providing and fixing down comer and manually operated electronic FA system | 2019.09.19 | 2019.10.18 | 11.18 | 0.00 (Mar'19) | 98.00 % (Jan'21) | M/s Royale Meridian India Pvt Ltd | Work completed. Final bill yet to be submitted by the agency. |
Detail Report
Graph / Photo |
170 | Repair and replacement of defective accessories of Addressable Fire Alarm System & Down comer Fire fighting system at Mangol Puri, ITI New Delhi. | 2023.04.27 | 2023.06.24 | 11.11 | 0.00 (Oct'23) | R J P ENTERPRISE |
Detail Report
Graph / Photo |
||
171 | Renovation of toilet blocks at G/F (02 nos.), F/F (02 nos.) & S/F (01 no.) | 2022.10.05 | 2022.12.03 | 10.79 | 0.00 (Oct'23) | MOHAMMAD HUSSAIN |
Detail Report
Graph / Photo |
||
172 | Miscellaneous Civil works | 2022.05.10 | 2022.07.08 | 10.73 | 8.62 (Jun'23) | 0.00 (Oct'23) | MOHAMMAD HUSSAIN |
Detail Report
Graph / Photo |
|
173 | Renovation of staff room toilets and pantry and other misc civil work in Chemistry Lab at Vivekanand College Vivek Vihar Delhi | 2022.05.29 | 2022.06.27 | 10.53 | 12.79 (Oct'22) | 0.00 (Aug'23) | Sundriyal Construction - Closed |
Detail Report
Graph / Photo |
|
174 | C/o of Two Nos. of Toilet(One for Handicapped and Other for Transgender) and Water Proofing Treatment of Roof at DDMA and Block-C, P/F Kota stone Slab flooring with Granite strip in front of A block etc at the O/o the D.M(East) dg 2022-23 (Balance work) | 2022.08.15 | 2022.11.14 | 10.47 | Aamir Khan |
Detail Report
Graph / Photo |
|||
175 | Upgradation of Type-II, Type-III and Type-IV Flat No. B-415, 97, 80, 118, 149, 407 ,168, 234, 309, 303, 330, 485, 469, 621, 497, 605 ,85, 387, 33 etc. C-734, 741, 756 etc, D-21, D-7, D-30 DA Flats Timarpur Delhi-- Electrical Work, EI and Fans | 2022.02.28 | 2022.08.27 | 10.14 | Dashmesh Enterprises | 100% Work Completed |
Detail Report
Graph / Photo |
||
176 | Wall paneling wooden flooring and toilet renovation work Civil and Electrical works | 2022.06.11 | 2022.07.10 | 7.36 | 0.25 (Mar'23) | 0.00 (Mar'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
177 | Maintenance of EI & Fans and Operation of Pumps & DG Set | 2022.09.16 | 2023.03.15 | 7.28 | 0.00 (Sep'23) | RJP Enterprises | 2nd RA Bill Rs. 824313/- dt. 31.03.23 |
Detail Report
Graph / Photo |
|
178 | Construction of 10 Nos. Room for faculty of Anesthesia with gypsum partition at 4th floor, B.L. Taneja Block at MAMC New Delhi | 2022.09.12 | 2022.11.11 | 7.11 | 8.76 (Feb'23) | 0.00 (Feb'23) | M/s Bajrang Electrical (India) | Work in progress |
Detail Report
Graph / Photo |
179 | Construction of underground water storage tanks for upcoming Court Rooms with additional storage facility for existing Court Complex and Residential Complex Saket including upgrading of existing water main line feeding Residential Court Complex--- | 2023.02.03 | 2023.03.02 | 6.57 | ARSHAD |
Detail Report
Graph / Photo |
|||
180 | Sweeping of road, development of rain water harvesting system, CO sump tank and other misc repair works | 2022.08.04 | 2023.05.10 | 6.41 | 4.94 (Mar'23) | 0.00 (Sep'23) | Invalid | Work in Progress |
Detail Report
Graph / Photo |
181 | Construction of tin shed near main gate and provision for sitting. | 2023.06.28 | 2023.08.11 | 6.28 | N.M. Construction Co. | WORK YET TO STARTED. |
Detail Report
Graph / Photo |
||
182 | Replacement of wooden sofa chair with new visitor chairs at I/C E.D. Lockup and miscellaneous furniture work at courts of Shahdara District Branch, KKD Court Delhi | 2022.07.09 | 2022.08.07 | 6.07 | 7.32 (Jan'23) | 0.00 (Jan'23) | Ganpati Furniture System Pvt Ltd |
Detail Report
Graph / Photo |
|
183 | Construction of 500 LPM PSA Plant for Covid- 19 at A U Tibbia College Hospital, Karol Bagh, New Delhi. (Electrical Works) | 2021.11.11 | 2022.01.10 | 5.94 | Shyam Electricals & Engineers |
Detail Report
Graph / Photo |
|||
184 | Modificatin and relocation of existing sennheiser make communication system in newly bulit court rooms at Saket.(C/o 144 Nos Temporary Courtroom in the existing court complexes ofSaket (Stilt+G+3), Tis Hazari (Stilt +G+3) and Karkardooma (G+4) | 2023.08.06 | 2023.09.05 | 5.93 | 0.00 (Nov'23) | Ambica Electricals | work completed |
Detail Report
Graph / Photo |
|
185 | Providing and fixing data receiver cum water display unit with multiple transmitter of data signal. | 2023.06.30 | 2023.07.14 | 5.69 | 0.00 (Jul'23) | ALPHA TECH |
Detail Report
Graph / Photo |
||
186 | Electrical work. | 2023.07.04 | 2023.09.03 | 5.68 | RAJA ELECTRICAL ENGINEERING WORKS |
Detail Report
Graph / Photo |
|||
187 | Tentage & sitting arrangement | 2022.07.30 | 2022.08.09 | 5.68 | 6.37 (Mar'23) | 0.00 (Mar'23) | Vishal Tents and Decorators | work in progress |
Detail Report
Graph / Photo |
188 | Providing and fixing dustbin at Karkardooma Court Complex, Delhi | 2022.06.13 | 2022.07.12 | 5.66 | 77.43 (Mar'23) | 0.00 (Mar'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
189 | Supplying, Installation, Testing and Commissioning of SS Body water coolers at various floors of Forensic Science Laboratory Building,Sector - 14, Rohini, Delhi. | 2023.08.21 | 2023.09.20 | 5.64 | Vivek associates |
Detail Report
Graph / Photo |
|||
190 | Civil Works | 2022.09.01 | 2022.09.30 | 5.36 | 0.25 (Mar'23) | 0.00 (Mar'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
191 | Making arrangement for sanitized the Judges residential complex and Lawyers chamber blocks D E F G H preventive measures for Corona Virus COVID 19 in Karkardooma Court Complex Delhi. Sanitization work and providing hand sanitizer | 2022.01.31 | 2022.03.31 | 4.93 | 5.35 (Jun'22) | 0.00 (Jun'22) | PURIFIRES INDIA | In Progress. |
Detail Report
Graph / Photo |
192 | Providing Furnitures at Ladies Bar Association Room at KKD courts, Delhi. | 2023.03.22 | 2023.04.20 | 4.88 | 13.84 (Jun'23) | 0.00 (Sep'23) | Uma Shankar |
Detail Report
Graph / Photo |
|
193 | Major repair work on water supply pipe line tanks. | 2023.02.11 | 2023.04.11 | 4.70 | 7.99 (Jun'23) | 0.00 (Sep'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
194 | Providing and fixing of UPVC Doors and Windows S.S railing Blinds cupboard work. | 2023.05.13 | 2023.06.11 | 4.67 | 0.00 (Sep'23) | Anuj Kumar Singal | In Progress. |
Detail Report
Graph / Photo |
|
195 | Civil Works. 1st Recall | 2023.01.06 | 2023.02.04 | 4.63 | 0.87 (Jun'23) | 0.00 (Jun'23) | Mohd. WAZID |
Detail Report
Graph / Photo |
|
196 | Construction of fire resistant barriers in E and M shafts at Delhi High Court | 2019.09.28 | 2019.10.27 | 4.49 | Naini Electricals |
Detail Report
Graph / Photo |
|||
197 | Replacement of faulty cables, switchgear & street light in School of excellence , Sector 17, Rohini, Delhi. | 2023.07.11 | 2023.08.10 | 4.11 | R S ELECTRIC CO. |
Detail Report
Graph / Photo |
|||
198 | Urgent Repair of boundary wall of Parking between Gate No 1 and 2 and pump house at GTB Hospital Shahdara Delhi | 2022.11.07 | 2023.01.05 | 4.01 | 0.00 (Jul'23) | Nasir Ali | Work in progress. |
Detail Report
Graph / Photo |
|
199 | C/o SPS Structure (4 storey) for ITI at Bakkarwala, Delhi. (SH: Supplying, installation, testing and commissioning of Water coolers with inbuilt UV System alongwith RO System) | 2020.01.10 | 2020.02.08 | 3.99 | 99.00 % (Jan'21) | A TO Z Engineering Works | Work in progress and likely to be completed by the end Dec. 2023 |
Detail Report
Graph / Photo |
|
200 | C/o SPS Structure (4 storey) for ITI at Ranhola, Delhi. (SH: Supplying, installation, testing and commissioning of Water coolers with inbuilt UV System alongwith RO System) | 2020.01.10 | 2020.02.08 | 3.99 | 99.00 % (Jan'21) | A TO Z Engineering Works | Work in progress and likely to be completed by the end Dec. 2023 |
Detail Report
Graph / Photo |
|
201 | Installation of 1 no. borewell at Fire Station Tahirpur Delhi dg. 2022 23. Civil and Electrical Works | 2022.09.21 | 2022.10.20 | 3.93 | 4.37 (Jun'23) | 0.00 (Jun'23) | Lucky Project |
Detail Report
Graph / Photo |
|
202 | RMO of water coolers , Split or Window or Ductable ACs installed at Lawyers block , Utility Block , Lockup building and Main Court Building at District Court Complex saket New delhi -110017. | 2019.02.03 | 2020.02.02 | 3.91 | 17.36 (Jun'23) | 0.00 (Jun'23) | ARORA ELECTRICAL WORKS |
Detail Report
Graph / Photo |
|
203 | Replacement of rusted/outlived Electrical Panel and illumination of common area at Fire Station Sector 16, Rohini, Delhi. | 2023.07.11 | 2023.08.10 | 3.80 | R S ELECTRIC CO. |
Detail Report
Graph / Photo |
|||
204 | Replacement of broken glass and painting of grills of window providing and fixing of signage board and other misc. work at DIET Building Karkardooma Institutional area Delhi 110032 1st Recall | 2022.09.09 | 2022.10.08 | 3.59 | 4.18 (Mar'23) | 0.00 (Mar'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
205 | Construction of 3 Nos. Pucca School Building (G+3) with Ancillary Facilities including internal water supply sanitary installation internal electrical installation and development of site at GGSSS No.2/GBSSS Uttam Nagar, Desu Colony (DTL) Janakpuri and Kohat Enclave New Delhi (Package-4) (SH : Transplantation and plantation of trees). | 2022.03.04 | 2023.04.03 | 3.30 | 101.43 (Nov'22) | 68.00 % (Nov'22) | Rohit Nursery | Tree transplantation done at Pucca School Building GGSSS No. 2/GBSSS Uttam Nagar, New Delhi and 365 days for maintenance of Planted Tree Upkeep of transplanted tree work is in progress. |
Detail Report
Graph / Photo |
206 | Barricading of dangerous portion of old school building, chipping of unsound/weak concrete & demolishing damaged RCC & brick work in Gandhi Memorial School, Shahdara (Near Shyamlal College), Delhi. (1st recall) | 2022.08.17 | 2022.09.15 | 3.26 | 0.00 (Aug'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
||
207 | Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23. 1st Recall | 2023.01.06 | 2023.02.04 | 3.22 | 4.01 (Feb'23) | 0.00 (Sep'23) | Mohd. WAZID |
Detail Report
Graph / Photo |
|
208 | Construction of New Passenger Lift for 13 Persons including connection corridor with existing Building PGC, M-Block, Vikas Bhawan, New Delhi (SH. Electrical Works in Lift Shaft and replacement of existing Light in Connecting Corridors) | 2017.10.17 | 2018.01.16 | 3.14 | Chetan Enterprises |
Detail Report
Graph / Photo |
|||
209 | Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23 | 2022.08.26 | 2022.09.24 | 3.06 | 0.25 (Mar'23) | 0.00 (Mar'23) | PRASHANT BUILDERS |
Detail Report
Graph / Photo |
|
210 | Renovation work | 2023.01.13 | 2023.02.11 | 2.61 | Mohd Azam |
Detail Report
Graph / Photo |
|||
211 | Renovation of office of Secretary in DSSSB Building at Karkardooma Shahdara Delhi dg 2022 23 | 2022.08.03 | 2022.09.01 | 2.56 | 6.31 (Apr'23) | 0.00 (Apr'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
212 | Installation of Stainless Steel Grill on the window for safety and security of Valuable assets | 2022.06.13 | 2022.07.12 | 2.29 | 2.90 (Apr'23) | 0.00 (Apr'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
213 | Construction of security gates near entrance road of Church of Divine Mercy in Shakurbasti Assembly Constituency AC-15 under MLALAD scheme, during 2021-2022. (3rd call) | 2022.03.24 | 2022.05.23 | 2.19 | 1.13 (Sep'22) | 0.00 (Sep'22) | A J & CO. |
Detail Report
Graph / Photo |
|
214 | Stationing of a Porta Cabin in the premises Multilevel Car parking, Delhi High Court, New Delhi. (SH: - Civil Work) | 2023.09.30 | 2023.10.21 | 2.19 | IRFAN KHAN AND CO. | Work in progress |
Detail Report
Graph / Photo |
||
215 | Replacement of 04 Nos. Air conditioners at Land & Estate Branch Lucknow Road, Old Sectt, Delhi-54 | 2022.06.22 | 2022.07.06 | 2.08 | 2.09 (Aug'22) | 0.00 (Aug'22) | CHETAN SHARMA | 100% Work Completed |
Detail Report
Graph / Photo |
216 | SPS type building i/c internal internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system & providing furniture etc. | 2022.03.25 | 2022.04.23 | 1.90 | MKSC Design India Private Limited | Work in Progress |
Detail Report
Graph / Photo |
||
217 | Provision of New gate and laying C.C path at the entrance of VSKV Old Seemapuri | 2021.09.04 | 2021.10.03 | 1.85 | 0.88 (Mar'22) | 0.00 (Mar'22) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
218 | Hiring of New Digital Photocopier Machine Model Sharp AR-6020N New Model on Rental basis with ADE Duplex Printer and Scanner | 2021.09.05 | 2023.09.04 | 1.81 | 0.82 (Dec'22) | 0.00 (Dec'22) | Frank Copier Pvt. Ltd. |
Detail Report
Graph / Photo |
|
219 | Supply Installation Testing and Commissioning of Digital Set Top Box in Special Ward at L N Hospital New Delhi due to COVID 19 | 2021.03.18 | 2021.04.01 | 1.70 | DURGA ENTERPRISES |
Detail Report
Graph / Photo |
|||
220 | Measuring and Mapping of Veterinary Polyclinic and SPCA building of Shahdara District A.H. Unit. | 2022.06.23 | 2022.07.07 | 0.74 | 0.74 (Sep'22) | 0.00 (Sep'22) | Kesari & Associates |
Detail Report
Graph / Photo |
|
221 | Soil investigation and bearing capacity of soil | 2021.08.19 | 2021.08.28 | 0.50 | Allied Engineers |
Detail Report
Graph / Photo |
|||
222 | C/o of Researcher Block and Residential Staff Quarters for Delhi Institute of Hotel Management and Catering Technology at Lajpat Nagar New Delhi under HSD South-III/HD-South/PWD/New Delhi dg. 2020-21. Transplantation of trees | 2021.04.05 | 2021.05.19 | 0.16 | Om Prakash Sharma BEYPS5726N1ZC |
Detail Report
Graph / Photo |
|||
223 | Repairing of aluminium doors & Shutters. | 2014.08.19 | 2014.09.03 |
Detail Report
Graph / Photo |
|||||
224 | Providing and laying RCC drain cover in open surface drain in basement. | 2014.08.16 | 2014.09.15 | 2.58 (Mar'21) | 0.00 (Mar'21) |
Detail Report
Graph / Photo |
|||
225 | Providing calcium silicate false ceiling & HRD fabrication in opening balcony at second floor. | 2014.09.16 | 2014.10.15 |
Detail Report
Graph / Photo |
|||||
226 | Finishing of exterior wall in 20 nos. CBI flats. | 2014.12.08 | 2014.12.26 | Pradeep Kumar Sharma |
Detail Report
Graph / Photo |
||||
227 | P/F Manhole cover & Drain cover. | 2015.01.08 | 2015.02.07 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
228 | Providing Security Guard for watch and ward for Sub Divn. Office & Vacant Flats at Mayur Vihar Ph-II and Division Office. | 2014.08.18 | 2015.01.01 |
Detail Report
Graph / Photo |
|||||
229 | Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kondli Delhi-110091. | 2015.01.08 | 2015.02.04 |
Detail Report
Graph / Photo |
|||||
230 | Providing and fixing PVC doors in bathrooms in qtrs. in place of old damaged ones. | 2014.09.18 | 2014.10.17 |
Detail Report
Graph / Photo |
|||||
231 | Replacement of Damaged roof of Sub Divn. Office M-233. | 2014.11.11 | 2014.12.10 | 35.49 (Aug'21) | 0.00 (Aug'21) |
Detail Report
Graph / Photo |
|||
232 | Cleaning of sewer line, manhole & gully traps etc. | 2014.12.22 | 2015.01.21 |
Detail Report
Graph / Photo |
|||||
233 | Providing and fixing door in toilet at G.G.S.S.S. Vasundhara Enclave Delhi School ID-1002185. | 2015.01.24 | 2015.02.23 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
234 | Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kalyan Puri Delhi. | 2015.01.08 | 2015.02.07 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
235 | Providing and fixing polycarbonate in available. | 2014.12.19 | 2015.01.18 |
Detail Report
Graph / Photo |
|||||
236 | Misc. work at RSKV Mayur Vihar Ph-1 Pkt-IV. | 2015.01.17 | 2015.02.16 | Pradeep Kumar Sharma |
Detail Report
Graph / Photo |
||||
237 | Providing and fixing Acrylic sheet in windows, kerb stone, painting work and misc. civil work. | 2015.02.08 | 2015.03.08 |
Detail Report
Graph / Photo |
|||||
238 | Repair to damaged windows, renewing glass panes with acrylic plastic sheet & signage work. | 2015.02.06 | 2015.03.15 |
Detail Report
Graph / Photo |
|||||
239 | Water proofing treatment of first floor toilet. | 2014.12.15 | 2015.01.14 |
Detail Report
Graph / Photo |
|||||
240 | Providing and fixing door & window shutters in pooling booth centre at GGSSS Kondli Gharoli. | 2015.02.06 | 2015.02.20 |
Detail Report
Graph / Photo |
|||||
241 | Wall tile and other misc. civil work in Sports Complex at East Vinod Nagar. | 2015.02.27 | 2015.03.26 |
Detail Report
Graph / Photo |
|||||
242 | Misc. Civil Works. | 2015.03.16 | 2015.03.30 | Shekhar |
Detail Report
Graph / Photo |
||||
243 | Providing ramps in Schools & miscellenious works. | 2015.02.12 | 2015.02.26 |
Detail Report
Graph / Photo |
|||||
244 | P/F Floor tile & broken tile. | 2015.11.20 | 2015.12.12 |
Detail Report
Graph / Photo |
|||||
245 | Providing and laying cement concrete. | 2015.03.12 | 2015.03.25 | Indal Yadav |
Detail Report
Graph / Photo |
||||
246 | Providing railing for Park. | 2015.11.23 | 2015.12.05 |
Detail Report
Graph / Photo |
|||||
247 | Construction of table top in front of Entry and Exit Gates of Residential Complex, District Court Saket at Birla Vidya Niketan Marg under Subdivision -14/ South Road-1 during 2023-24. | 2023.08.14 | 2023.09.13 | Work in progress |
Detail Report
Graph / Photo |
||||
248 | Construction of Change Room including toilet, Guard Room, Office Room, Coach Room, S.S. fencing on Periphery of Athletic Track & Boundary wall with concertina coil fencing etc. and Renovation of existing block, pump house, entry road and provision of stone cladding on boundary wall at Pooth Kalan Sports Complex, Delhi. (Hiring of inspection vehicle) | 2023.08.12 | 2024.08.11 | 0.00 (Dec'23) | Work in progress. |
Detail Report
Graph / Photo |
|||
249 | Special Repair of Expansion Joints, RCC Chajja, Column for arresting leakage /seepage and misc. work to Rouse Avenue District Court Complex at DDU Marg, New Delhi. | 2023.07.07 | 2023.08.20 | The work is in progress |
Detail Report
Graph / Photo |
||||
250 | Providing and Installation of Compactors for DSLSA Record Room at Basement-2, Rouse Avenue Court Complex, DDU Marg, New Delhi. | 2023.07.06 | 2023.08.04 | 0.00 (Oct'23) | Work is in progress |
Detail Report
Graph / Photo |
|||
251 | Reconstruction of SPS Type Roofing, water proofing and other Misc. repair work in Laundry in M.V. Hospital, Pooth Khurd, Delhi. | 2023.07.10 | 2023.08.24 | 0.00 (Nov'23) | Work in Progress (10% Progress) |
Detail Report
Graph / Photo |
|||
252 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. | 2023.03.24 | 2023.09.19 | 3.99 (Jan'23) | 0.00 (Jan'23) | Demolition of existing Barrack completed. The plinth beam and column upto 2.50 m level for Left hand side portion completed. The excavation of footing and PCC completed for right hand side portion. |
Detail Report
Graph / Photo |
||
253 | Consultancy Services for Comprehensive Architectural and Engineering Planning and Designing for Construction of 100 seated Government Veterinary College/Research Institute at Satbari in South Delh. | 2023.09.04 | 2026.12.04 | Work is in progress |
Detail Report
Graph / Photo |
||||
254 | Construction of 48 Nos G plus 3 SPS Eq. classroom including 3 staircase 1 lift and 1 toilet block in Mustafabad School Delhi Including internal and external water supply sanitary installations electrical installations development of site Boundary W | 2023.03.09 | 2024.02.01 | Pile casting for 80% area is completed and pile cap casting for 50% area is in progress. Balance 25% area could not start due to space constraints, slow progress due to space scarcity at site. |
Detail Report
Graph / Photo |
||||
255 | Filling, Carriage and pouring out of drinking and non drinking water into water tank of Burari Hospital complex | 1900.01.12 | 2023.07.11 | Tender is under process |
Detail Report
Graph / Photo |
||||
256 | C/o Residential Hostel at Chhatrasal Stadium Model Town, Delhi. (SH : comprehensive maintenance of PC’s and associated accessories for O/o PM(HEP), PWD and O/o EE(E), B141, PWD.) | 2023.04.20 | 2026.04.19 | Work in progress. |
Detail Report
Graph / Photo |
||||
257 | Cleaning of sewer line, manholes, road gully chambers and storm water drain | 2023.05.30 | 2024.05.30 | 0.00 (Nov'23) | In-progress |
Detail Report
Graph / Photo |
|||
258 | Renovation/Upgradation of the GST Office i/c A,B and C Wing at 4th Floor, Deptt. of Trade & Taxes Bldg. , IP Estate, New Delhi | 2022.10.06 | 2023.04.05 | Work delayed due to not handing over site / electrical work |
Detail Report
Graph / Photo |
||||
259 | Beautification of gate water proofing of new building block S S railing and other misc works Balance Work | 2022.09.10 | 2023.01.09 | work in progress. 65% work has been done. |
Detail Report
Graph / Photo |
||||
260 | Preventive maintenance for Civil works | 2023.01.20 | 2024.01.19 | 0.00 (Sep'23) | work in progress. 40% work has been done. |
Detail Report
Graph / Photo |
|||
261 | Construction of Spectator Gallery for VIP’s/ Visitors | 2022.12.22 | 2023.03.21 | In-Progress |
Detail Report
Graph / Photo |
||||
262 | Filling, Carriage and pouring out of drinking and non drinking water into water tank of Dr. BSA Hospital complex | 2022.12.30 | 2023.06.29 | 100.00 % (Jul'23) | work in progress |
Detail Report
Graph / Photo |
|||
263 | Repairing works and water proofing of DGHS Dispensary OLD Seemapuri New Delhi | 2023.01.08 | 2023.02.07 | 0.00 (Sep'23) | Work in progress. |
Detail Report
Graph / Photo |
|||
264 | Renovation of Emergency Lab and Blood Storage room at Jag Pravesh Chandra Hospital, Shastri Park, Delhi | 2023.01.01 | 2023.03.01 | 0.00 (Oct'23) | Work could not be started due to site is not handed over by the client department. |
Detail Report
Graph / Photo |
|||
265 | Restoration of service road near Mall and Max hospital of Press Enclave Road cut by DJB under PWD Division South Road-1/ Sub Division SR-14, New Delhi during 2022-23. | 2022.12.30 | 2023.01.29 | Work completed |
Detail Report
Graph / Photo |
||||
266 | Road marking, Thermoplastic paint and Synthetic enamel paint on road under Sub Division SR-15 | 2022.09.21 | 2022.11.04 | 31.06 (Apr'23) | 0.00 (Apr'23) | work in progress |
Detail Report
Graph / Photo |
||
267 | A/R & M/O to Rouse Avenue Court Complex at DDU Marg, New Delhi During 2022-23 & 2023-24. (SH: Operation and Maintenance of STP Plant of 180 KLD). | 2022.09.30 | 2024.09.29 | 4.59 (Mar'23) | 0.00 (Mar'23) | Work is in progress |
Detail Report
Graph / Photo |
||
268 | Annual Maintenance and Networking of Computers Systems UPS Photocopier machines and Printers of Circle office M 22 Divisional office M 221 and Sub Divisional Office M 22 | 2022.09.30 | 2023.09.29 | work in progress. |
Detail Report
Graph / Photo |
||||
269 | Laying of sewerline and connecting with main DJB sewerline in SKV Janki Devi | 2022.11.13 | 2022.12.12 | work in progress and sewerline connection is pending. |
Detail Report
Graph / Photo |
||||
270 | Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24 | 2022.11.05 | 2024.11.04 | 90.27 (Jun'23) | 0.00 (Nov'23) | work in progress, as per complaint received in sub division, the regular day to day compliance is made. |
Detail Report
Graph / Photo |
||
271 | Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. | 2016.01.17 | 2016.04.30 | 80.00 % (Jul'16) | polycarbonate |
Detail Report
Graph / Photo |
|||
272 | providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. | 2016.05.01 | 2016.06.30 | 0.01 % (Jul'16) | work in progress |
Detail Report
Graph / Photo |
|||
273 | E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi | 2016.04.10 | 2016.06.09 | 0.01 % (Jul'16) | Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270 |
Detail Report
Graph / Photo |
|||
274 | Construction of new boundary wall | 2016.04.24 | 2016.07.20 | 21.77 (May'17) | 100.00 % (May'17) |
Detail Report
Graph / Photo |
|||
275 | Repair and renovation of toilets | 2016.06.17 | 2016.08.15 | 91.00 % (Sep'16) | Detailed estimate under process. |
Detail Report
Graph / Photo |
|||
276 | Renovation of Classrooms, Corridor, Principal Room & Staff Room. | 2016.06.16 | 2016.09.13 | 53.00 % (Sep'16) | T.S. under process. |
Detail Report
Graph / Photo |
|||
277 | Acoustic treatment system and renovation of multipurpose hall. | 2017.10.20 | 2018.01.17 | 40.27 (Nov'21) | 0.00 (Nov'21) | 65% (Work is delayed due to ongoing electrical work as well as Covid-19) |
Detail Report
Graph / Photo |
||
278 | Construction Of New 460 Bed Mother & Child Hospital Building At Khichripur , Delhi | 2020.01.08 | 2021.04.01 | 804.24 (Mar'23) | 0.00 (Aug'23) | RCC Structure upto terrace level completed. Block work, conduiting, plastering, civil & electrical services and other finishing works in progress. Samples of flooring, tiles, granite and sanitary fittings approved and work is in progress. Work delayed due to Covid pandemic in 2020 & 2021 & stop of construction activities due to pollution in the month of Nov-Dec 2020 & 2021. Also decision regarding type of foundation (Raft/footings) in basement was delayed in 2020. Work delayed due to Covid pandemic in 2020 & 2021 & stop of construction activities due to pollution in the month of Nov-Dec 2020 & 2021. Also decision regarding type of foundation (Raft/footings) in basement was delayed in 2020. |
Detail Report
Graph / Photo |
||
279 | Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. | 2018.11.02 | 2019.11.01 | 214.77 (Sep'19) | 0.00 (Sep'19) | Work in progress |
Detail Report
Graph / Photo |
||
280 | C/o Trauma Centre and Utility Block at SGMH at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Hiring of Photocopier Machine.) | 2019.09.04 | 2021.03.03 | 632.27 (Mar'23) | 0.00 (Mar'23) | work in progress |
Detail Report
Graph / Photo |
||
281 | C/o Additional SPS type class rooms at various schools under Priority-II Edu.(M) Division (North-West), PWD, Delhi. Regariding Third Party Quality Assurance. | 2019.03.01 | 2019.12.25 | 127.80 (Feb'23) | 0.00 (Feb'23) | Work in progress |
Detail Report
Graph / Photo |
||
282 | Setting up of 1912 bedded semi permanent/temporary ICU Hospital at GTB. | 2021.09.23 | 2022.02.22 | 2714.00 (Mar'23) | 82.00 % (Jul'23) | Work stopped due to non availability of funds. |
Detail Report
Graph / Photo |
||
283 | Setting up of 610 bedded semi permanent/temporary Hospital at CNBC. | 2021.09.23 | 2022.02.22 | 88.00 % (Jun'23) | Work stopped due to non availability of funds. |
Detail Report
Graph / Photo |
|||
284 | Maintenance of P.C. in Division and Sub-Division Office | 2021.07.31 | 2023.07.30 | work in progress |
Detail Report
Graph / Photo |
||||
285 | Construction of Hospital at Hastsal, New Delhi | 2021.06.17 | 2023.06.16 | 1643.90 (Jun'23) | 47.00 % (Nov'23) | Casting of 7th floor slab has been completed. 8th floor centering & shuttering and placing of reinforcement is under progress. The masonry work in 1st, 2nd & 3rd floor are in progress. Granite flooring in upper basement and ground floor is in progress. |
Detail Report
Graph / Photo |
||
286 | C/o East Delhi Campus of Guru Gobind Singh Indrasprastha University at Surajmal Vihar, Shahdara, Delhi. (SH: Supply, Installation, Testing & Commissioning of CCTV). | 2021.03.30 | 2021.07.28 | 222.63 (Jun'23) | 0.00 (Jun'23) | Work completed. Final bill to be paid. |
Detail Report
Graph / Photo |
||
287 | Installation of Rain Water Harvesting System with bore well in GGSSS Roop Nagar No 3 School Delhi | 2019.03.07 | 2019.04.06 | Work In Progress |
Detail Report
Graph / Photo |
||||
288 | Construction of multipurpose court, levelling and preparing the layer of good earth on the play ground in Delhi Police Public School at PTS, Wazirabad, Delhi | 2019.06.30 | 2019.08.29 | 26.71 (Mar'21) | 0.00 (Mar'21) | work in progress |
Detail Report
Graph / Photo |
||
289 | Reconstruction of collapsed boundary wall of CBD plot at Shahdara, Delhi owned by Urban Development Department. | 2019.07.24 | 2021.09.22 | in progress. |
Detail Report
Graph / Photo |
||||
290 | Comprehensive architectural consultancy services for Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Jaffarpur Kalan, Nangli Sakrawati and Qutubapur (Sainik Vihar) New Delhi. (Package-1) | 2021.10.04 | 2022.10.03 | 51.25 (Mar'23) | 60.00 % (Jul'23) | Agmt. No. 04/EE/Edu. (M)/South-west/2021-22 received from EE (Edu.) South West, PWD, Sector-6, Dwarka, New Delhi. Agency yet to submit the terrace floor and other misc. drawings. |
Detail Report
Graph / Photo |
||
291 | Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054 | 2021.12.15 | 2022.06.14 | 274.83 (Mar'23) | 0.00 (Oct'23) | Work In Progress. Site available in Parts. |
Detail Report
Graph / Photo |
||
292 | Strengthening of damaged beams and slabs Beautification of main gates Development of pathways and misc works | 2022.03.03 | 2022.09.02 | work in progress. 92% has been done. |
Detail Report
Graph / Photo |
||||
293 | Construction of cycle stand, toilet room, sport room and development of rain water harvesting and other misc. work at RSBV Jheel Khuranja Delhi-110031 (School ID1003003) | 2022.03.30 | 2022.06.29 | work in progress. 60% work has been done. |
Detail Report
Graph / Photo |
||||
294 | Providing and Fixing Bullet Proof Protective Posts 03 Nos at different locations of Delhi Secretariat | 2022.06.26 | 2022.08.09 | work in progress & testing required. 95% work has been done. |
Detail Report
Graph / Photo |
||||
295 | Running and Maintenance and supply of Fittings for Newly constructed Covid Hospital | 2022.04.14 | 2023.04.07 | 6.88 (Aug'22) | 0.00 (Aug'23) |
Detail Report
Graph / Photo |
|||
296 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24 | 2022.05.01 | 2024.04.30 | 357.33 (Mar'23) | 0.00 (Nov'23) | work in porgress |
Detail Report
Graph / Photo |
||
297 | Providing fencing around the small plants in Central Park of Dr. BSA Residential complex | 2022.06.09 | 2022.08.08 |
Detail Report
Graph / Photo |
|||||
298 | Repairs & maintenance of Resource Center for Children with special needs: 1208014--Partap Nagar-SKV | 2022.06.30 | 2022.08.30 | Work in Progress |
Detail Report
Graph / Photo |
||||
299 | Construction of Toe Wall from Kaya Maya Park to Sports Ground at MB Road under Sub Division SER-24 during 2023-24. | 2023.08.20 | 2023.09.19 | Work in Progress |
Detail Report
Graph / Photo |
||||
300 | C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road Delhi. (SH: C/o Common Mess Building near to the newly constructed Girls Hostel Building at DTU Campus) | 2023.08.14 | 2024.05.09 | 0.00 (Oct'23) | Work in progress |
Detail Report
Graph / Photo |
S. No.क्र. सं. | Description | Details |
---|
S. No.क्र. सं. | Remarks | As On | Revised On |
---|
S. No.क्र. सं. | Upload Date | Description |
---|
S. No. | Date | Location | Remarks | Physical Progress (%) | View | ||
---|---|---|---|---|---|---|---|
Last | Upto | Photo | Doc |
S. No.क्र. सं. | Remarks | Date | Document |
---|
This is the Portal of Public Works Department, Govt. of NCT of Delhi, developed with an objective to enable a single window access to information and services being provided by the different wing of PWD Delhi. It is an initiative towards E-Governance Plan. यह लोक निर्माण विभाग, राष्ट्रीय राजधानी क्षेत्र (दिल्ली सरकार) का पोर्टल है जिसे इस उद्देश्य के साथ विकसित किया गया है जिससे लोक निर्माण विभाग, दिल्ली के विभिन्न स्कन्धों (विंग) द्वारा प्रदान की जा रही सूचनाओं तथा सेवाओं को एकल खिड़की के माध्यम से जाना जा सके | यह ई - गवर्नेंस योजना की दिशा में पहल है |
12th Floor, MSO Building,
I. P. Estate, New Delhi – 110002
Toll Free: 1800 11 00 93
© 2021 All Rights Reserved. Version 35.1.2 / 18-11-2023
This portal is designed, developed and maintained by M/s Calibre Websol Pvt. Ltd.
मैसर्स कैलिबर बेबसोल प्रा० लिमिटेड ने इस पोर्टल का विकास तथा अनुरक्षण / अभिकल्पन डिजाइन किया है
Session expire