Building - Construction Workभवन - रखरखाव का कार्य
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwakra, New Delhi on turn-key basis 27/08/2014 26/02/2017 54511.43 0.00 (Jan'21) 93.00 % (Jan'21) Larson & Toubro Limited Minor finishing works are under progress. Detail Report
Graph / Photo
2 setting up of Semi- permanent / temporary ICU Hospital at shalimar Bagh (G+3) (14530Beds) Kirar (G+4) (458 Beds)and Sultanpuri (G+3) (525Beds) Package-I (Electrical) 23/09/2021 22/02/2022 50680.19 1021.01 (May'22) 0.00 (May'22) SAM India Builtwell Detail Report
Graph / Photo
3 setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) 23/09/2021 22/02/2022 40775.18 1258.28 (Jun'22) 0.00 (Jun'22) SAM India Builtwell GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave. Detail Report
Graph / Photo
4 CONSTRUCTION OF NEW HOSPITAL AT SIRASPUR, NEW DELHI (ON EPC MODE -I) INCLUDING ALL CIVIL, ELECTRICAL, MECHANICAL, HORTICULTURE AND MEDICAL SERVICES. 10/08/2020 09/05/2023 38439.53 4181.35 (Jun'22) 0.00 (Jun'22) Ramacivil India Construction Private Limited Progress slow down due to Covid-19 Epademic. Detail Report
Graph / Photo
5 C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi SH Co Academic Bldg, Auditorium Bldg, Sports Hall, Boys, Girls, Teachers Hostel, Type II III IV and V Qtrs ic Ext Dev. works, Int Elect Inst, Ext Lighting, lifts, fire fighting system, fire alarm with PA System, D.G. Sets, Elect Sub Stn, HVAC works 09/08/2017 09/11/2019 23127.43 2854.01 (Jun'22) 0.00 (Jun'22) NKG Infrastructure Limited Physical Progress of the work is 96%. Detail Report
Graph / Photo
6 C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road, Delhi (SH: C/o Academic Blocks AB-3 & AB-4, Boys Hostel H-5 & Girls Hostels HG-5 & HG-6 and all external and internal services including external development and landscaping, and allied civil and E&M works). 23/09/2019 23/12/2020 22769.91 1391.84 (Jun'22) 0.00 (Jun'22) SAM India Builtwell Work is in progress. Work delayed due to NGT ban and Covid-19 pandamic. The progress of work 98%. Detail Report
Graph / Photo
7 Additional and Remodeling Work for Cancer Block, Maternity Block and Screening OPD At Satyawadi Raja Harish Chandra Hospital, Narela For Delhi Govt. (Delhi) 09/08/2020 08/05/2023 21785.66 492.91 (Jun'22) 0.00 (Jun'22) Parnika Commercial and Estates Pvt. Ltd. Work in progress Detail Report
Graph / Photo
8 Construction of 144 Nos Temporary Courtroom in the existing court complexes of Saket Stilt plus 3 Tis Hazari Stilt plus G plus 3 and Karkardooma G plus 4 04/10/2019 03/07/2020 14316.00 30.29 (Apr'22) 0.00 (Apr'22) Quality Buildcon Pvt. Ltd. Karkardooma (44 Courtrooms G 4): The building at Karkardooma inaugurated on 13th May 2022. Not physically occupied yet. Saket (2 blocks of 23 Courtrooms each G 5): Work of rectification of defects in both blocks is in progress inside the building. Work of external development work is completed. Work for obtaining clearance from Delhi Fire Service is underway. Some addtional work of polishing of consoles and strengthening of wooden long benches is under progress as per instructions of court authorities. Decision regarding 2 rooms at 5th floor of Block-1 is to be given by DHC. Tis Hazari (50 Courtrooms G 6): 1) All Structure work completed. 2) LGSF work is almost complete. 3) Final coat of polishing and painting work is in progress. 4) Work of sanitary installations and CP fittings is almost complete. 5) Development works pertaining to sewerage line, drainage, external lighting etc. mostly completed and work for linking of sewer line to existing line is being taken up. 6) Final RCC of roadwork is in progress. 7) All the external windows and ventilators including Structural Glazing work is almost completed. 8) False Ceiling works almost complete and defect removal is in progress. 9) The furniture items have been made available at site and final placing of furniture is being taken up. Detail Report
Graph / Photo
9 Addition & Remodelling work for Bhagwan Mahavir Hospital at Pitampura Delhi including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 10/12/2019 01/06/2020 13992.80 777.85 (Jun'22) 0.00 (Jun'22) Kamladitya Construction Private Limited Work in progress Detail Report
Graph / Photo
10 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 18/10/2019 10/04/2021 13447.15 261.25 (May'22) 0.00 (May'22) Roshan Real Estate Pvt Ltd. Work is under progress. Detail Report
Graph / Photo
11 Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 04/03/2020 03/09/2021 10708.84 765.44 (Jun'22) 0.00 (Jun'22) Quality Buildcon Pvt. Ltd. work in progress Detail Report
Graph / Photo
12 Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Kohat Enclave, New Delhi (Package - 4). SH : Civil & Electrical work. 15/05/2021 14/05/2022 7689.40 2.13 (Apr'22) 0.00 (Apr'22) B. L. INFRA PROJECTS PRIVATE LIMITED

On dated 26.06.2021, it was directed by Hon'ble Deputy Chief Minister of Delhi and Hon'ble Minister of PWD to hold the work and proposed Sports facility at Kohat Enclave. Now, Chief Engineer (Projects) vide letter No. 23(42)/22/CE(Projects) /PWD/West/292(E) dated 18.04.2022 directed to resume the construction work of school at Kohat Enclave on direction of Education Department. (i) Block-A & B Raft done. Column upto plinth level in progress. Block-C PCC done, raft done, pedestal done. Column & beam upto plinth level done.

Detail Report
Graph / Photo
13 C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 04/09/2019 03/03/2021 7122.09 529.86 (Mar'22) 0.00 (Mar'22) PNSC Infrastructure Pvt. Ltd work in progress. Detail Report
Graph / Photo
14 Construction of (G+3) Pucca School Buildings at Tehkhand 18/07/2021 17/07/2022 7047.98 PNSC Infrastructure Pvt. Ltd (i) Work has been awarded to contractor. (ii) Hon'ble PWD Minister has approved Architectural Drawings in the meeting on 23.08.2021 (iii)Submission drgs for DUAC/Fire/Local body are under preparation. (iv) Structural design : Str. drawing are under preparation. Detail Report
Graph / Photo
15 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 06/08/2019 29/10/2020 6563.40 128.14 (May'22) 0.00 (May'22) PNSC Infrastructure Pvt. Ltd Work is under progress. Detail Report
Graph / Photo
16 Construction of (G+3) Pucca at Jaunapur, Site –II (Aya Nagar) New Delhi 110047 18/07/2021 17/07/2022 6137.90 0.30 (Feb'21) 0.00 (Feb'21) PNSC Infrastructure Pvt. Ltd (i). Work has been awarded to contractor. (ii) Architectural Drawing : Revised drgs are under preparation as per direction of Hon'ble PWD Minister. (iii) Structural design : Str. drawing will be prepared after approval of Architectural drawing by competent authority. (iv). DUAC /Fire approval: Drgs will be uploaded online after approval of Architectural drawing by competent authority. Detail Report
Graph / Photo
17 C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) 14/01/2019 09/11/2019 4874.05 4140.18 (Jun'22) 0.00 (Jun'22) Shri kamal singh Work in progress Detail Report
Graph / Photo
18 C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) 20/01/2019 15/11/2019 4603.38 3517.82 (Jun'22) 0.00 (Jun'22) Sh. Kamal Singh Work in progress Detail Report
Graph / Photo
19 Const 182 Nos. of additional SPS class rooms (Package-C) 17/03/2019 11/12/2019 3699.32 2782.40 (Mar'22) 0.00 (Mar'22) SPS Infrabuild Pvt. Ltd. Work is in Progress. Detail Report
Graph / Photo
20 Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 24/12/2018 19/09/2019 3675.76 2397.91 (Jun'22) 0.00 (Jun'22) RAMA Contractor Development Work is in Progress. Detail Report
Graph / Photo
21 Const 180 Nos. of additional SPS class rooms (Package-B) 17/03/2019 11/12/2019 3636.43 2110.79 (Jul'22) 0.00 (Jul'22) RAMA Contractor Work is in Progress. Detail Report
Graph / Photo
22 Const 174 Nos. of additional SPS class rooms in various schools (Package-E) 17/03/2019 11/12/2019 3553.31 2860.77 (Mar'22) 0.00 (Mar'22) SPS Infrabuild Pvt. Ltd. Finishing & Development Work is in Progress. Detail Report
Graph / Photo
23 Up gradation and Construction of an additional multi- story building in the premise of Forensic Science Laboratory, Rohini, Delhi. 14/11/2019 13/02/2021 3541.69 394.14 (Jun'22) 0.00 (Jun'22) Tewatia Construction Pvt. Ltd. work in progress Detail Report
Graph / Photo
24 Const 184 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 17/03/2019 11/12/2019 3455.84 2767.78 (Mar'22) 0.00 (Mar'22) RAMA Contractor Work is in Progress. Detail Report
Graph / Photo
25 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II.(Package-F) 27/01/2019 23/10/2019 3347.23 3590.52 (May'22) 0.00 (May'22) BCC DEVELOPERS AND PROMOTERS PVT LTD Work in progress. Detail Report
Graph / Photo
26 Civil work and Internal E.I. work 24/04/2007 23/07/2009 3002.21 Globe Civil Project Pvt. Ltd. Detail Report
Graph / Photo
27 SKV Sangam Vihar J Block Sch. ID 1923346 17/03/2019 11/12/2019 3002.10 1990.33 (May'22) 0.00 (May'22) Devinder Singh

Work is in progress

Detail Report
Graph / Photo
28 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Dariyapur Kalan, Delhi 30/05/2020 29/05/2021 2936.58 1617.06 (Jun'22) 0.00 (Jun'22) Tewatia Construction Pvt. Ltd. Structure work completed. Partition work with bricks in progress. Tile, plaster and granite work is in progress. Truss work of MP Hall is in progress. Detail Report
Graph / Photo
29 Construction of Pucca School Building G plus 3 with ancillary facilities including internal water supply sanitary installation, internal electrical installation and development of sites RWHS STP etc at Sector 05 Rohini Delhi 29/05/2020 28/05/2021 2931.78 1816.09 (May'22) 0.00 (May'22) The Krishna Construction Co. Work in progress Detail Report
Graph / Photo
30 Construction of DTC Bus Depot in resettlement colony at Sawada Ghevra, Delhi 05/04/2022 04/12/2022 2915.78 1.58 (Jul'22) 0.00 (Jul'22) SVK Infrastructures Tender for the work invited and work awarded on 04.03.2022. Letter of commencement issued on 05.04.2022. Site clearing, leveling work completed. Foundation work of retaining wall has started. Detail Report
Graph / Photo
31 SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW 17/10/2019 12/07/2020 2849.35 1382.32 (Mar'22) 0.00 (Mar'22) A. K. Builders work in progress. Detail Report
Graph / Photo
32 Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. 28/06/2019 22/06/2020 2806.33 Roshan Real Estate Pvt Ltd. Work in progress Detail Report
Graph / Photo
33 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Libaspur, Delhi 30/05/2020 29/05/2021 2653.59 2197.38 (Jun'22) 0.00 (Jun'22) Tewatia Construction Pvt. Ltd. Work in progress. Detail Report
Graph / Photo
34 Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site, RWHS, STP, Furniture etc at Sector 18, Rohini. (SH: Civil and Electrical Composite Work). 23/05/2020 23/05/2021 2606.13 641.74 (Jun'22) 0.00 (Jun'22) Tewatia Construction Pvt. Ltd. Work in progress Detail Report
Graph / Photo
35 SKV Hari Nagar, Ashram, School ID : 1924043 14/01/2019 10/09/2019 2464.23 1928.29 (May'22) 0.00 (May'22) Reliance Elektrik works Work is in progress Detail Report
Graph / Photo
36 Co 136 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 1 20/01/2019 16/09/2019 2420.66 2768.21 (Mar'22) 0.00 (Mar'22) M C Constructions Company Work in Progress. Detail Report
Graph / Photo
37 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II. SH: C/o 162 Nos. of additional SPS class rooms at G Co.Ed.SS, Sec-16A, Dwarka (School ID-1821242), Shahid Captain Amit Verma Govt. S(Co.Ed)V, Inderpuri (School ID-1720121) & SKV, Rajnagar-I (School ID-1824027) under Education Maintenance South West Division, PWD Delhi including internal & external water supply, sanitary installation, electrical installations, development of site and fire fighting system etc. (Package-H) 19/12/2018 15/08/2019 2420.05 2724.70 (Mar'22) 0.00 (Mar'22) Multi Tech Construction Co. Work in progress. Detail Report
Graph / Photo
38 Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi 23/08/2021 22/05/2022 2373.12 125.00 (Jun'22) 0.00 (Jun'22) M/s PK Gupta & Co.

Earth & foundation work is in progress...

Detail Report
Graph / Photo
39 SBV Jonapur, School ID: 1923359 08/12/2018 04/08/2019 2342.87 552.12 (May'22) 0.00 (May'22) Reliance Elektrik works

Work is in progress

Detail Report
Graph / Photo
40 RPVV Lajpat Nagar, School ID : 1925334 08/12/2018 04/08/2019 2303.62 2228.74 (May'22) 0.00 (May'22) Reliance Elektrik Works, Work is in progress Detail Report
Graph / Photo
41 C o 138 Nos Addl SPS Classrooms in GGSSS Rani Bagh Sch ID 1411043 GGSSS Trinagar Narang Colony Sch ID 1411037 ic Lab staircases toilets and ramps internal water supply sanitary installations internal electrification and fire fighting arrangements 01/03/2019 26/09/2019 2120.02 0.00 (Apr'22) 95.00 % (Apr'22) The Krishna Construction Co. Work in progress Detail Report
Graph / Photo
42 GGSSS Dera Village School ID: 1923023 08/12/2018 04/08/2019 1877.31 1613.97 (Jun'22) 0.00 (Jun'22) Varun Gupta & Co. In progress Detail Report
Graph / Photo
43 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 31/05/2020 30/05/2021 1874.70 0.00 (Apr'22) 10.00 % (Apr'22) SSP Promoters and Builders Private Limited WORK IN PROGRESS Detail Report
Graph / Photo
44 Furniture Work RECALL 04/11/2019 18/12/2019 1858.08 6.26 (Sep'21) 0.00 (Sep'21) Rajdhani Furnitures PVT. LTD. Detail Report
Graph / Photo
45 Renovation / Development work in Building for Education Department at Boulverd Road, Delhi 07/04/2022 04/08/2022 1842.64 230.97 (Jun'22) 0.00 (Jun'22) DND Infra Private Limited Work in progress. Detail Report
Graph / Photo
46 Const. of 112 Nos. addl SPS classrooms GGSS, Mukundpur Village Sch. ID 1207230 - 36 Nos., GBSSS Bakhtawarpur Sch. ID 1309266 -56 Nos. incl. 01 No. M.P Hall Equi. to 08 Nos. Class Rooms and SV Lancer Road Sch. ID 1207032 -20 Nos. under North Edu. Divn 08/06/2019 02/02/2020 1799.01 0.00 (Nov'21) 69.00 % (Nov'21) C. PARKASHAN Co. Work in progress Detail Report
Graph / Photo
47 C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc 01/04/2022 24/02/2023 1798.93 K. L. ARORA & SON Demolition work is in progress. 90% demolition completed and Layout for excavation has done in A C C GSBV at Jhilmil Colony, Delhi. Detail Report
Graph / Photo
48 C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) 29/12/2018 26/07/2019 1743.19 3722.23 (May'22) 0.00 (May'22) AMAR CONSTRUCTION COMPANY Work in progress Detail Report
Graph / Photo
49 Development of Synthetic Athletic Track with Football field and Synthetic Hockey Turf in Rajiv Gandhi Sports Complex Singhu Delhi 08/03/2021 02/11/2021 1583.17 115.52 (May'22) 0.00 (May'22) Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 Hockey field & synthetic Athletic Track is completed. Certificate from FIH has also been received. Certificate from IAAF is awaited. Structure work for change rooms is in progress. Work is suffering due to non-availability of fund in Sports Head. Physical Progress is 82%. Detail Report
Graph / Photo
50 C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc 26/03/2022 19/02/2023 1553.88 K L Arora & Son 100% demolition completed. Temporary room work is in progress. The excavation and footing work in progress Detail Report
Graph / Photo
51 Construction of 80 Nos G plus 3 equivalent SPS Class Rooms at Govt Co Ed Sr Secondary School Gandhi Brahampur Delhi including 8 toilet blocks, 4 nos staircase 1 lift and internal and external water supply sanitary installations, electrical installations, development of site, RWH & UGR fire fighting system etc. 26/03/2022 19/02/2023 1377.43 K. L. ARORA & SON Demolition work & completion delay due to tree cutting permission from forest department. Detail Report
Graph / Photo
52 C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc 02/04/2022 25/02/2023 1359.28 K. L. ARORA & SON Demolition work is in progress. 90% demolition completed. Layout for excavation in progress. Detail Report
Graph / Photo
53 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at GSSS (Co ed) at Rana Pratap Bagh, Delhi 30/05/2020 29/05/2021 1335.04 1023.53 (May'22) 0.00 (May'22) The Krishna Construction Co. Structure work of building completed, Plaster work & brick completed. Water proofing work completed, Granite work and tile work completed. Toilet fittings, C.I. Work, CPVC work, painting work is in progress. False ceiling, SS work and Boundary wall work in progress. Detail Report
Graph / Photo
54 Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) 12/03/2022 04/02/2023 1275.84 0.60 (May'22) 0.00 (May'22) M/s SURENDRA KUMAR Work recently awarded, pile load test is under process. Detail Report
Graph / Photo
55 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and Placing of Medical Furnitures at Indira Gandhi Hospital, Dwarka, New Delhi) 11/07/2021 23/09/2021 1244.16 Godrej & Boyce Mfg. Co. Ltd. Work is under progress. Detail Report
Graph / Photo
56 GGSS No. 3 Sec IV, Ambedkar Nagar 03/03/2016 15/07/2016 1212.87 Devinder Singh completed Detail Report
Graph / Photo
57 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi (SH: Providing and Placing of Non-Medical Furnitures at Indira Gandhi Hospital, Dwarka, New Delhi). 11/07/2021 23/09/2021 1118.83 M/s Rajdhani Furnitures Pvt. Ltd. Work is under progress. Detail Report
Graph / Photo
58 Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi 06/04/2022 05/04/2025 1099.29 SIKKA ASSOCIATES REGD. The work has been awarded to the agency. The presentation of the proposed University has been made with Dy. CM of GNCTD Delhi as on dt. 08.04.2022 & 13.05.2022. Detail Report
Graph / Photo
59 C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) 18/04/2022 13/03/2023 1090.67 K. L. ARORA & SON Demolition work in progress. 72% demolition completed and layout for excavation in progress. Detail Report
Graph / Photo
60 Construction of 55 Nos. Aam Admi Mohalla Clinic at various locations under South-East (M), Circle, New Delhi during 2018-19. 15/12/2018 12/06/2019 827.90 290.07 (Oct'19) 17.00 % (Oct'19) S. P. Construction Work in progress Detail Report
Graph / Photo
61 Construction of 30 Nos. Aam Admi Mohalla Clinic at various places under south building (M) Division/South District. 10/01/2019 08/07/2019 585.53 91.21 (Mar'21) 0.00 (Mar'21) P S ASSOCIATES work in progress Detail Report
Graph / Photo
62 Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work 28/01/2022 27/12/2022 579.95 R.K ENTERPRISES Work is in progress 3% Detail Report
Graph / Photo
63 Providing and Fixing Customized Furniture and Interior works 24/09/2020 22/11/2020 533.13 0.00 (Jan'21) 15.00 % (Jan'21) M/s Rajasthan Decorators Work is in progress Detail Report
Graph / Photo
64 Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 30/09/2014 26/05/2015 474.90 61.36 (May'19) 0.00 (May'19) Work completed on 31/12/2017 final payment yet to be made Detail Report
Graph / Photo
65 Remodeling of Drain with Development of Kuccha Portion along the ESI Hospital Road and Road along B-Block Jhilmil under Sub Division M-2112 during 2021-22 02/04/2022 28/09/2022 462.00 PRATAP SINGH Detail Report
Graph / Photo
66 Construction of Boundary Wall and other basic work for establishing of Driving training Institute in Village Malikpur Dist. South West, Delhi 25/01/2022 24/05/2022 435.79 72.02 (Jun'22) 0.00 (Jun'22) M/s Satish Builders Earth & foundation work is in progress... Detail Report
Graph / Photo
67 C/o classrooms, labs & Toilets i/c Internal & External Water Supply, Sanitary & Electric Installations, Development of SiteAnd Firefighting System etc. at Government Co-ed Secondary School Maidan Garhi, New Delhi (School Id-1923033) 02/03/2022 26/11/2022 382.04 M/s. Satyam Construction Work to be started Detail Report
Graph / Photo
68 Building work i/c Water Supply, Sanitary installation,Development Work and providing EI & Fire fighting system 26/05/2015 25/05/2016 316.66 Sudesh Kumar Work is in progress. Delay due to non-receipt of funds & revised A/A & E/S from Client Department and covid-19 pandemic since March 2020. Balance works in final stage of completion. Detail Report
Graph / Photo
69 Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi 27/12/2018 26/04/2019 296.85 335.77 (Aug'21) 0.00 (Aug'21) Ram Krishan Yudhister Parkash

work completed

Detail Report
Graph / Photo
70 Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). 28/02/2019 27/06/2019 294.21 58.25 (Feb'22) 0.00 (Feb'22) AASRA Martech Pvt.Ltd. Work in progress. Detail Report
Graph / Photo
71 Civil and Electrical work. 05/05/2019 04/03/2020 292.64 Dheeraj Singh & Company Work just awarded Detail Report
Graph / Photo
72 Air Pistol & Rifle 10m Shooting Hall cum all internal finishing fixtures fitting and development of complete setup of electronic type targets, shooting equipment etc. complete 18/03/2022 13/09/2022 290.26 Dev Enterprises Work just awarded Detail Report
Graph / Photo
73 Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi 16/01/2022 15/10/2024 288.00 Arcop Associates Pvt. Ltd. Work has been awarded to the agency. Presentation for the proposed University has been made with the Dy. CM & Minister. Detail Report
Graph / Photo
74 Construction prefab hut for HQ at PTS Wazirabad, Delhi 21/07/2018 20/11/2018 285.56 Aliyan Constaruction Company

work completed

Detail Report
Graph / Photo
75 Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool 23/12/2020 20/06/2021 262.79 Maa Narayan Constuction Co. Structural work almost completed. Work of raising of level of swimming pool under progress. Tensile structure work is in progress. Physical Progress is 48%. Work is also suffering due to non-availability of fund in Sports Head. Detail Report
Graph / Photo
76 Vertical Extension of Teaching Block No.1 of B.R. Ambedkar College, Wazirabad Road, Delhi 16/01/2018 15/07/2018 172.40 127.50 (Jan'22) 0.00 (Jan'22) JABIR HUSSAIN

work completed

Detail Report
Graph / Photo
77 C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi. (SH: Providing & fixing industrial kitchen equipments in Boy's, Girl's & Teacher's Hostel) 02/12/2021 01/03/2022 157.41 Simple Enterprises WORK DOES NOT PERTAIN TO THIS DIVISION Detail Report
Graph / Photo
78 Providing and Installing Fire Fighting, Fire Alarm system and Public Address system 10/08/2014 09/04/2015 155.31 Detail Report
Graph / Photo
79 Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). 25/01/2019 24/05/2019 140.44 216.46 (Oct'21) 0.00 (Oct'21) Uma Shankar work in progress Detail Report
Graph / Photo
80 Construction of prefab hut for HQ of Meghalaya Police along with development work located at PTS Wazirabad, Delhi 15/07/2018 14/11/2018 134.50 138.77 (Jan'22) 0.00 (Jan'22) Aliyan Constaruction Company

work completed

Detail Report
Graph / Photo
81 Construction of Migrant workers support centre at the office joint labour commissioner Vishwakarma Nagar Jhilmil colony Delhi (Civil and Electrical Work) 23/04/2022 22/01/2023 124.05 Dheeraj Singh & Company Detail Report
Graph / Photo
82 Renovation and Interior works for Rouse Avenue Court Complex at DDU Marg, New Delhi. (SH :- Providing and fixing work stations, Cabin partitions, Office furniture and interior finishing and Electrical works for DSLSA.) 06/08/2021 05/10/2021 112.91 Millennium Furniture Work is in progress Detail Report
Graph / Photo
83 Changes in infrastructure of CHB to develop it as OHB Model Home.(Civil and Electrical work) 24/10/2019 23/02/2020 112.72 Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 Detail Report
Graph / Photo
84 Attending Day-to-Day complaint in Mandoli Jail complex and residential area including Supply of Material, Horticulture Operation, STP operation and tank and drain cleaning 08/06/2022 07/06/2023 112.05 M/s Gejwal Construction Company Work is in progress Detail Report
Graph / Photo
85 Making the Building disable friendly under Accessible India campaign at RTRM Hospital Jaffarpur Kalan New Delhi. 01/06/2020 27/11/2020 106.37 0.00 (Jan'21) 30.00 % (Jan'21) Aliyan Constaruction Company Work is under progress. Detail Report
Graph / Photo
86 Providing and supplying tree planters in various places, New Delhi under MLA LAD Fund Scheme 04/11/2019 18/12/2019 91.97 91.97 (Mar'21) 0.00 (Mar'21) Rajeshwar Dayal Pandey Detail Report
Graph / Photo
87 Construction of Shed with Boxing Ring at Sports Complex, East Vinod Nagar, Delhi 08/05/2017 04/09/2017 84.89 19.39 (Jul'20) 0.00 (Jul'20) Anish Ahmed Work in Progress Detail Report
Graph / Photo
88 Providing and Fixing of compactors in Hall No 2 of Original Branch situated in the basement of A Block of Delhi High Court New Delhi 25/05/2021 23/07/2021 83.82 66.62 (Oct'21) 0.00 (Oct'21) Rajdhani Furnitures PVT. LTD. work in progress Detail Report
Graph / Photo
89 Up-gradation of swimming pool and other misc. civil works including electrical work 11/08/2021 08/12/2021 83.39 48.02 (Mar'22) 0.00 (Mar'22) M/s Tanishq Ions In Progress. Detail Report
Graph / Photo
90 Renovation of gate no. 1 & 3 with GRC mouldings/cornices). (Civil & Electrical Works) 25/06/2022 23/08/2022 78.59 15.43 (Jun'22) 0.00 (Jun'22) Uma Shankar Detail Report
Graph / Photo
91 Construction of 04 Nos Aam Aadmi Mohalla Clinic Primary Health Centres at various Places in the jurisdiction of Shahdara Circle PWD Delhi Civil Furniture Electrical Works Ist Recall 23/12/2021 20/02/2022 77.72 20.18 (Mar'22) 0.00 (Mar'22) Gee Internationals In Progress. Detail Report
Graph / Photo
92 Repair and Renovation of toilets of Hon ble Judges Chambers and Public ladies toilet in A Block G plus 3 and staff toilet G plus 6 near to copying agency in J block at KKD Court Delhi Civil and Electrical works 13/03/2022 19/08/2022 76.84 31.46 (Apr'22) 0.00 (Apr'22) Uma Shankar Detail Report
Graph / Photo
93 Renovation of Library Block of IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, New Delhi.(SH-Civil and Electrical works). 09/07/2018 08/01/2019 75.80 77.23 (Jan'22) 0.00 (Jan'22) Kamal Construction Co. Work in progress Detail Report
Graph / Photo
94 Changes in Infrastructure of Model Home to convert it as CHB and JJB in front of Building (Civil and Electrical work). 24/10/2019 23/01/2020 71.13 AJAY CONSTRUCTION CO. Detail Report
Graph / Photo
95 Providing and laying RMC in the campus of N, J1, J2, J3, K, L and M Block at Sujan Singh Park, New Delhi under MLA LAD Fund Scheme. 27/10/2019 07/12/2019 70.87 79.44 (May'21) 0.00 (May'21) Gyanchand Detail Report
Graph / Photo
96 Augmentation of Old and Outlived Sub-Station equipments at LBSH, Khichripur, Delhi Sub Head S.I. T.C. of Substation Equipments 13/10/2018 12/04/2019 69.44 35.42 (Mar'19) 50.00 % (Mar'19) Ajay M/c Tools work in progress ( 2nd RA ) Detail Report
Graph / Photo
97 Construction of 10 Nos FRP Gazebo rubens and 06 Nos of porta cabin Chaupal at various places of New Delhi Constituency AC40, under MLA LAD Fund Scheme 26/11/2019 24/01/2020 68.77 34.44 (Dec'21) 0.00 (Dec'21) Tripurari Prasad Singh Detail Report
Graph / Photo
98 Construction of boundary wall at Tikri Khurd (Narela Project) for Delhi District Courts, New Delhi 19/12/2021 18/04/2022 68.04 Durga Construction Co. Work is in progress Detail Report
Graph / Photo
99 Construction of Recreation Hall at PTS, Wazirabad, Delhi 16/02/2019 15/06/2019 63.80 81.48 (Mar'21) 0.00 (Mar'21) Shekhar

work completed

Detail Report
Graph / Photo
100 Comprehensive maintenance of 310 DA staff qtrs. Supply of materials and providing services of manpower for day to day maintenance work of 310 DA staff qtrs. KKD Court Divn. under SD M-2313 Karkardooma Delhi dg. 2021 22 07/02/2022 06/02/2023 63.52 21.66 (Jun'22) 0.00 (Jun'22) N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
101 Comprehensive maintenance, Supply of material and providing services of manpower for day to day maintenance work of lawyer’s chamber blocks (ie. D,E,F,G& H- Blocks) Under SubDivision M-2311, KKD Court, PWD, Delhi 22/01/2022 21/01/2023 62.58 25.68 (May'22) 0.00 (May'22) N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
102 Construction of rain water harwasting system in Main Court Buildings i e in A B C I J K L Blocks and Lawyers Chamber Blocks D E F G H at KKD Court Shahdara Delhi Balance Work 18/12/2021 17/03/2022 59.22 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 In Progress. Detail Report
Graph / Photo
103 Making casting of factory made modular cupboard with fire retardant and boiling water proof Boilo Board in Alhmad rooms of C Block of KKD Court Complex Delhi 2nd Recall 14/03/2022 11/06/2022 59.19 Srishti Assosiates Detail Report
Graph / Photo
104 Maintenance and repair work in Mandoli Jail complex, Delhi-110093 during year 2022-23. SH: External and Internal finishing work of Non- Residential Buildings and Residential quarters.2nd call 10/06/2022 09/03/2023 57.65 Aamir Khan The work is awarded to the agency but PG not submitted by the agency Detail Report
Graph / Photo
105 Misc repair work under SRD Project Division I Sub Division III PWD New Delhi Recall 23/09/2019 22/03/2020 56.09 70.01 (Feb'21) 0.00 (Feb'21) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
106 AA to SKV No. 01 Gandhi Nagar Delhi dg 2018 19 17/03/2019 16/07/2019 55.57 32.21 (Jun'20) 0.00 (Jun'20) Arif 90% work in progress Detail Report
Graph / Photo
107 Construction of New boundary wall (with State of Art) of Govt. Boys Sr. Sec. School, Varun Marg, Defence Colony, New Delhi-24 (School ID- 1924014) 15/03/2022 17/07/2022 55.34 R N Construction

Work is in progress

Detail Report
Graph / Photo
108 Making casting of factory made modular cupboard with fire retardant and boiling water proof Board in Court rooms North East District of KKD Court Complex Delhi 21/11/2021 18/02/2022 54.92 Millennium Furniture Detail Report
Graph / Photo
109 Expansion of 8 no Vulnerable Witness Courts at 5th and 6th floor B Block KKD Courts Delhi and other electrical installations 19/03/2022 17/05/2022 53.14 28.31 (May'22) 0.00 (May'22) SABUR ALAM Detail Report
Graph / Photo
110 Civil and Electrical Works. 13/06/2019 12/09/2019 51.83 15.96 (Nov'20) 0.00 (Nov'20) Abhikalp Constructions Syndicate

work in progress

Detail Report
Graph / Photo
111 Construction of 5 nos arch shaped FRP pergola, 4 nos FRP porta cabin and 25 nos FRP Security Cabin at various places of New Delhi constituency AC 40 under MLA LAD Scheme 26/11/2019 24/01/2020 51.22 5.64 (May'22) 0.00 (May'22) Tripurari Prasad Singh Detail Report
Graph / Photo
112 Replacement of Carpets in Courts of A block Extension block and wooden texture laminated flooring in Chambers of Extension block at Delhi High Court New Delh 27/06/2017 26/07/2017 50.20 Bansal Builder Agreement closed PG forfeited Detail Report
Graph / Photo
113 Waterproofing treatment and Heat resistant tile work at terrace of A, C & I block 08/06/2022 05/09/2022 50.04 M. N. Construction Co. Detail Report
Graph / Photo
114 C o Boundary wall finished with GRC Tile MS grills Concertina coil MS Gate and security guard room for proposed Govt Sr Sec School at PSP 10 Industrial area Phase V Kirari Rohini Delhi 29/07/2021 28/10/2021 49.75 48.44 (May'22) 0.00 (May'22) Deepa Engineering Co. WORK IN PROGRESS Detail Report
Graph / Photo
115 Renovation of 10 Nos faculty rooms of Anatomy at MAMC 22/05/2021 22/05/2023 49.64 14.10 (Jun'22) 0.00 (Jun'22) SABUR ALAM

work completed

Detail Report
Graph / Photo
116 Providing and fixing three seater stainless steel bench at ACI Block, Karkardooma Court Complex, Delhi 26/02/2022 27/03/2022 48.15 GEEKEN SEATING COLLECTION PVT LTD Detail Report
Graph / Photo
117 Improvement of the existing bituminous road with granite stone block toward dedicated area from gate no. 1 to DJ parking toward C-Block and upto first face of B-Block toward gate no.1 and Renovation of corridor of court no-1 3rd floor C-Block KKD Court, Delhi 25/06/2022 23/08/2022 47.61 Manish construction and co Detail Report
Graph / Photo
118 Upgradation of Type V Judges flats No. 401 601 701 and 702 and Servant Qtrs. 401 601 701 and 702 at Karkardooma Court Complex Delhi. (Civil and Electrical Work) 05/10/2021 02/04/2022 46.05 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
119 Providing and fixing Fire Check door fitting in SVBPGH 20/03/2021 19/04/2021 45.28 Amodh Construction Work is Progress Detail Report
Graph / Photo
120 Construction of RCC Lift Duct and external development in the front of proposed Lift area 17/04/2022 14/08/2022 43.84 TKN Developers Detail Report
Graph / Photo
121 Providing mandatory fire provisions including fire check doors and repair of fire fighting system at Pt.M.M.M. Hospital, Malviya Nagar, New Delhi. (Civil works)z 07/03/2021 10/04/2021 43.62 Sohan Lal Chhitoria and Sons Work in progress Detail Report
Graph / Photo
122 SITC of Building Management System 12/09/2020 11/03/2021 43.49 130.52 (Jan'21) 50.00 % (Jan'21) Digital Controls & Automation Material supplied by the firm. Installation work in progress. Detail Report
Graph / Photo
123 P/F Vitrified tile flooring, false ceiling, wall paneling and IRC Fabric, Construction of underground R.C.C water tank, installation of 01 no. Borewell and other miscellaneous works at DSEU, Vivek Vihar, Delhi dg. 2022-23). (Civil & Electrical Works). 13/06/2022 10/09/2022 41.34 Uma Shankar Detail Report
Graph / Photo
124 A/R and M/O Delhi High Court, New Delhi dg. 2021-22 (SH: Providing services of plumbing, carpentry jobs etc.) 01/08/2021 31/07/2022 40.87 32.98 (Jun'22) 0.00 (Jun'22) TRENDY SECURITY SERVICES Work in progress Detail Report
Graph / Photo
125 Improvement of lighting in various OTs at GTB Hospital Complex, Shahdara, Delhi. 03/03/2019 02/05/2019 40.46 19.10 (May'19) 0.00 (May'19) CARONA ELECTRICALS Work completed Detail Report
Graph / Photo
126 Toilets renovation works 09/07/2021 06/10/2021 40.06 15.36 (Mar'22) 0.00 (Mar'22) Saeed Builders In progress. Detail Report
Graph / Photo
127 Improvement Multi Model intigration System at Karkardooma Court Metro Station under M-2111 dg. 2022-23. 03/07/2022 30/09/2022 38.77 Ram Kirpal Singh Detail Report
Graph / Photo
128 EOR in Sanjay Gandhi Memorial Hospital, Delhi. (SH Construction of Badminton Court, Fixing of grill gate, rain water harvesting well to recharge ground water and other misc. works). 28/08/2019 27/11/2019 37.39 SUSHIL KUMAR work is in slow progress Detail Report
Graph / Photo
129 Up-gradation and enhancement of aesthetic view of Swimming pool premises located at Captain Hanifuddin G.G.S.S.S. Mayur Vihar Phase-1, Pocket-4, Delhi. 03/06/2022 31/08/2022 35.06 Dheeraj Singh & Company Work just awarded. Detail Report
Graph / Photo
130 CO of Toilet for primary wing support staff visitor and attached toilet to principal room renovation of water tank platform and toilet repairing of b wall and other misc civil works 15/08/2020 14/12/2020 34.45 CSM CONSTRUCTION Detail Report
Graph / Photo
131 Providing and laying interlocking paver block and RMC in the campus of Police Colony at Tilak Marg, New Delhi under MLA LAD Fund Scheme. 27/10/2019 25/12/2019 33.92 42.37 (Apr'22) 0.00 (Apr'22) Gyanchand Detail Report
Graph / Photo
132 Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing ductable type air conditioning system 09/07/2019 08/10/2019 33.85 SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. work in Progress 6th RA 18182135 Detail Report
Graph / Photo
133 Providing, installation, testing, and commissioning of Code Blue System (NCS) for Old and New block at MAIDS, New Delhi 11/08/2019 10/11/2019 33.77 Med Freshe Pvt. Ltd. Work in progress Med Freshe Pvt. Ltd. Detail Report
Graph / Photo
134 Construction of SAKHI- ONE STEP CENTRE at campus of GBSSS, Malviya Nagar, New Delhi. (Civil and Electrical Works) 16/12/2021 15/04/2022 32.92 14.29 (Jun'22) 0.00 (Jun'22) AKSHAY KUMAR DAGAR Detail Report
Graph / Photo
135 Strengthening of damaged beams columns slabs during 2021 22 at SKV No 1 Mansarovar Park Shahdara Delhi 32 School ID 11061655 (Balance work) 05/04/2022 03/07/2022 32.79 22.88 (Jun'22) 0.00 (Jun'22) Cembond Construction Pvt. Ltd Detail Report
Graph / Photo
136 Construction of Rain Water Harvesting Pit inside HLTB Complex Tahirpur Delhi 21/11/2021 18/02/2022 32.74 26.42 (Jun'22) 0.00 (Jun'22) Sushil Kumar Detail Report
Graph / Photo
137 Providing and fixing retro reflective informatory sign boards at various location of New Delhi constituency AC40 under MLA LAD Fund Scheme 25/10/2019 22/01/2020 32.70 12.66 (Mar'21) 0.00 (Mar'21) Rajesh Kumar Gupta Detail Report
Graph / Photo
138 Construction of Porta Cabin for PWD Sub Divn. Office of Civil and Electrical including enquiries of both and Development of lab collection centre and shed covering 06/01/2021 05/04/2021 31.62 0.00 (Jan'21) 5.00 % (Jan'21) Nation Star Enterprises Work is under progress. Detail Report
Graph / Photo
139 Installation of hard drawn wire fabric at D Block and B Block residential quarters for monkey protection in Fire Station Connaught Place New Delhi. 08/02/2019 07/03/2019 31.58 39.47 (Jul'19) 90.00 % (Jul'19) Vasdev Work in progress Detail Report
Graph / Photo
140 C/o 144 Nos. temporary court room in the existing court complexes of Saket (stilt +G+3), Tis Hazari (Stilt + G +3) and Karkardooma (G+4). SH: SITC of 1250 KVA dry Type Transformer at Saket Court. 09/06/2022 06/09/2022 31.45 Ramesh Electric Works Tender Called Opening Date 09.05.2022 Detail Report
Graph / Photo
141 Renovation of Kotwali Building at Chandni Chowk, Police Station under SRD Division-I, Sub-Division-III, PWD, New Delhi. 25/06/2018 24/10/2018 31.39 0.00 (Feb'19) 39.16 % (Feb'19) Kamal Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
142 Providing and fixing modular partition panel and supplying furniture for extension of administrative block at RTRM Hospital, Jaffarpur Kalan, New Delhi 22/10/2021 20/12/2021 31.27 GEEKEN SEATING COLLECTION PVT. LTD. Work is under progress. Detail Report
Graph / Photo
143 AR and MO Delhi High Court New Delhi dg 2021 22 SH Providing services of plumbing carpentry jobs etc 09/07/2021 08/07/2022 31.07 Krishna Kumar Work in progress Detail Report
Graph / Photo
144 SITC of additional CCTV and allied equipment at GTB Hospital, Shahdara, Delhi 16/10/2018 15/12/2018 30.64 15.29 (Feb'19) 50.00 % (Feb'19) San Infotech Services work in progress 2nd RA 1696099 Detail Report
Graph / Photo
145 Providing and fixing furniture at Ground Floor and 1st Floor 15/08/2021 29/08/2021 30.45 33.54 (Mar'22) 0.00 (Mar'22) DURIAN INDUSTRIES LIMITED In progress. Detail Report
Graph / Photo
146 Renovation of toilets in J, K & L Block at Karkardooma Court, Delhi (Balance work) (IstRecall) 30/12/2021 29/03/2022 30.36 Ravinder Kumar Gupta In Progress. Detail Report
Graph / Photo
147 Making through way from Barrack to Toilet in all Ward of CJ- 11, 12, 13, 14 and 16 in Prison Complex Mandoli, Delhi 28/07/2021 24/11/2021 30.00 M/s Gejwal Construction Company Work is in progress Detail Report
Graph / Photo
148 Strengthening work in various buildings M N O block in Judges Residential Complex at KKD Court Shahdara Delhi dg 2021 22 17/12/2021 15/04/2022 29.81 Cembond Construction Pvt. Ltd In Progress. Detail Report
Graph / Photo
149 Upgradation of General store, Quality Cell, Old Doctors Hostel, Kitchen and Misc. work 09/02/2022 08/07/2022 29.38 22.59 (May'22) 0.00 (May'22) SATYA RAM Work is under progress. Detail Report
Graph / Photo
150 Comprehensive Maintenance of Old Saint Stephens College Building Kashmere Gate, CPO Building, Old Court Building, NCC Offices Buildings, Novelty Fire Station, Fire Station Jama Masjid, Disability Commissioner Office, Lok Nayak Setu Office Compl 17/11/2019 16/11/2020 29.01 36.24 (Feb'21) 0.00 (Feb'21) K.P. Singh & Co. Detail Report
Graph / Photo
151 False ceiling work in Ward Area 23/05/2021 22/07/2021 28.86 Royal Construction Co. work is progress Detail Report
Graph / Photo
152 Supplying, installation, testing and commissioning of X Ray baggage machine system at Rouse Avenue Court Complex, New Delhi. 29/03/2022 27/04/2022 28.67 Vehant Technologies. Pvt. Ltd. Work in progress Detail Report
Graph / Photo
153 Rehabilitation work in Police Station at Chandni Mahal, Asaf Ali Road, Delhi. 29/09/2019 26/03/2020 27.08 33.83 (Mar'21) 0.00 (Mar'21) Shah Pandya & Shot Crete Detail Report
Graph / Photo
154 Renovation of court no 51 & 53 B-Block at Karkardooma Court, Delhi 13/06/2022 11/08/2022 26.85 Uma Shankar Detail Report
Graph / Photo
155 Construction of yard for Malkhana of Police Station Chandni Mahal, Darya Ganj under SRD Division-I, Sub-Division-III, New Delhi. 30/07/2018 29/10/2018 25.67 23.27 (Sep'19) 0.00 (Sep'19) Krishan Kumar Work in progress Detail Report
Graph / Photo
156 Providing and laying Flushing and water supply line al-round at Police housing campus Delhi-110093 (Balance work) 5th call 29/03/2022 27/05/2022 23.94 PUSHPENDER SINGH YADAV Work is in progress Detail Report
Graph / Photo
157 Providing and Fixing Net to stop the reach of items thrown from outside Periphery of Jail to inmates in Prison Complex Mandoli, Delhi 19/04/2022 17/07/2022 23.37 M/s Gejwal Construction Company Work is in progress Detail Report
Graph / Photo
158 Providing and laying bituminous concrete surface at BR Campus, Race course, New Delhi under MLA LAD fund Scheme. 3rd CALL 26/11/2019 25/12/2019 22.88 25.04 (Nov'21) 0.00 (Nov'21) Rajesh Kumar Gupta Detail Report
Graph / Photo
159 Development Cricket ground football field and chain link fencing at newly taken over plot for sports complex at village kair in the Assembly constituency Najafgarh, Delhi. (SH: Comprehensive maintenance of cricket ground for one year) 01/04/2021 31/03/2022 22.80 Devender Pal Singh work Completed. Final bill under preparation. Detail Report
Graph / Photo
160 Providing and fixing of overhead water tank in LCB I II A Block Medical Health Centre and Administrative Block Delhi High Court New Delhi 24/09/2021 22/12/2021 22.29 KRISHAN KUMAR MISHRA Work in progress Detail Report
Graph / Photo
161 Renovation of B Voc Labs 20/05/2019 19/08/2019 22.14 M.Y Construction 40% Work could not start due to electrical tender not in force. Detail Report
Graph / Photo
162 Supplying and replacement of Outlived Air Handling Units at JPCH Shastri Park, Delhi 22/07/2019 21/09/2019 21.72 US Engineers

Tender is in process

Detail Report
Graph / Photo
163 Providing and Fixing of MS tubular Window with Acrylic plastic Sheet 14/11/2019 12/03/2020 21.53 26.89 (Mar'21) 0.00 (Mar'21) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
164 Renovation of toilet blocks & miscellaneous civil works- Balance work 26/06/2022 23/09/2022 21.44 Sanjeev Kumar Detail Report
Graph / Photo
165 Supply, Installation, Testing and Commissioning of IP based CCTV systems along with integration with existing Pelco Make systems at Basement Parking of Rouse avenue court, DDU Marg, New Delhi. 29/03/2022 27/04/2022 21.25 Sonal Enterpries Pvt. Ltd. Work in Progress Detail Report
Graph / Photo
166 Up-gradation of Type-V Judge’s flats No- G-1 Type-VI Judge’s flats No-507 and Servant Qtrs. G-1 & 507 at Karkardooma Court Complex, Delhi. (SH:- Civil Work). 02/05/2022 30/06/2022 21.17 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
167 Supply, Installation, testing and commissioning of LED Light diode display board for Temporary Court block at Karkardooma Court Complex, New Delhi 05/03/2022 03/04/2022 20.91 Neelam Elevator Care Work in progress Detail Report
Graph / Photo
168 Waterproofing treatment and Heat resistant tile work at terrace of J K and L block and replacement cum repairing of door and window of lift rooms at A C I J and L block Karkardooma Court Complex 08/06/2022 05/09/2022 20.86 Karan Walia Detail Report
Graph / Photo
169 Providing and fixing of shade at 3rd floor Arbitration Centre Delhi High Court New Delhi 18/12/2021 16/01/2022 19.23 51.47 (Mar'22) 0.00 (Mar'22) R L WADHWA Work in progress Detail Report
Graph / Photo
170 SITC of CCTV in various Mohalla Clinic under sub division M3513 13/04/2022 12/05/2022 18.93 YASH ENTERPRISES Detail Report
Graph / Photo
171 Renovation of toilets in J K and L Block at Karkardooma Court Delhi Balance work 06/11/2021 03/02/2022 18.82 Phoenix Constructions In Progress. Detail Report
Graph / Photo
172 Provision of chequrred tiles, raising of boundary wall and other misc civil work 26/06/2022 25/07/2022 18.67 Sanjeev Kumar Detail Report
Graph / Photo
173 SITC of VRV/ VRF Air Condition Plant 12/06/2022 11/07/2022 18.55 Airtemp Engineers Detail Report
Graph / Photo
174 Supply and fixing of energy efficient LED fittings in order to replace the existing and obsolete conventional MH and T 5 fittings in CJ 11 and CJ 12 at Prison Complex Mandoli, DelhiDelhi 29/05/2022 27/06/2022 17.89 Modern Enterprises Tender Recall Detail Report
Graph / Photo
175 Replacing of damaged G.S sheets with G.I profile sheets. (1st recall) 01/04/2022 29/06/2022 17.32 13.14 (Jun'22) 0.00 (Jun'22) SABUR ALAM Detail Report
Graph / Photo
176 Const. of office building for Sub Division III SRD Project Divn I at Road No. 47 near Metro Pillar No. 29, Kashmere Gate, Delhi 23/09/2019 21/12/2019 17.04 21.26 (Jul'20) 0.00 (Jul'20) K.P. Singh & Co. Detail Report
Graph / Photo
177 Supplying, installation, testing and commissioning of DFMD and HHMD at Rouse Avenue Court Complex, New Delhi 05/03/2022 03/04/2022 16.82 Smiths Detection Systems Pvt. Ltd. Work in Progress Detail Report
Graph / Photo
178 Construction of Conference Hall and Waiting/Reception Hall in Office of Commissioner for Persons with Disabilities at Mata Sundari Road under SRD Division-I, Sub-Division-III, PWD, New Delhi. (SH-Civil Renovation Work). 09/08/2018 08/11/2018 16.72 15.33 (Oct'19) 5.60 % (Oct'19) Intkhab Alam Work in progress Detail Report
Graph / Photo
179 A/R & M/O GNEC, New Delhi. dg. 2016-17 (SH: Up-Keeping and maintenance of services of GNEC and providing and service of computer operator, Dak Messenger, plumber, carpenter, mason sewerman etc under HMD (Central) SD-3) 13/04/2017 12/10/2017 16.04 7.45 (Mar'19) 46.00 % (Mar'19) Anup Enterprises Detail Report
Graph / Photo
180 Miscellaneous requisite work in Central Jail No 11, 12, 13, 14, 15 and 16 in Prison Complex Mandoli, Delhi- 110093 15/10/2020 11/02/2021 15.37 0.00 (Dec'20) 22.00 % (Dec'20) M/s Manomay Work is progress Detail Report
Graph / Photo
181 SH- Kota stone flooring, repair to boundary wall including grit plaster and concertina wire fencing, repair and maintenance of toilets, P F steel windows, renewing broken glass panes with polycarbonate sheet etc. 07/11/2018 04/02/2019 15.26 17.61 (Apr'22) 0.00 (Apr'22) Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 in progress. Detail Report
Graph / Photo
182 Providing and supplying plastic moulded table in porta cabins reading room at various places of New Delhi Constituency AC40 under MLA LAD Fund Scheme. 25/10/2019 08/12/2019 15.17 DECOR MODULAR SYSTEM PVT LTD Detail Report
Graph / Photo
183 Upkeep Service 05/10/2019 04/10/2020 15.15 18.80 (Feb'21) 0.00 (Feb'21) Ashish Gupta Detail Report
Graph / Photo
184 Providing tactile pathway to Resource centre Separate stainless Steel main gate Providing and placing water storage tanks Distempering painting and finishing work and misc civil work 29/05/2022 26/08/2022 14.87 Sushil Kumar Detail Report
Graph / Photo
185 Providing and fixing sufficient light in basement and other low light/ dark area for security purpose at Rouse Avenue Court Complex, DDU Marg, New Delhi 11/06/2022 10/07/2022 14.87 BHAGWAT ASSOCIATES Tender Opened PG Letter issued Detail Report
Graph / Photo
186 Construction of porta cabin for camp office of Honble Minister at DJB (BPS/UGR) at C-6, Vasant Kunj, New Delhi 04/01/2022 03/02/2022 14.34 4.87 (Jun'22) 0.00 (Jun'22) SHRI DATTA KRUPA ENTER PRISES Detail Report
Graph / Photo
187 Construction of Underground sump at ITI Jija Bai for Women, Sirifort, New Delhi (Civil and Electrical work) 23/10/2021 22/12/2021 13.91 11.75 (Apr'22) 0.00 (Apr'22) SHRI DATTA KRUPA ENTER PRISES Detail Report
Graph / Photo
188 Repair/ improvement of berm, footpath and drain at Jaipur Golden Hospital, Sector-3, Rohini 27/04/2022 26/07/2022 13.86 Dharambir Singh Detail Report
Graph / Photo
189 Construction of permanent shed on pavement near Gyne OPD registration 18/08/2020 17/10/2020 13.73 SS Enterprises work in progress. Detail Report
Graph / Photo
190 Providing and fixing PU Tactile tiles for visually impaired persons in Saket and Tis Hazari Temporary Court sites (PU tiles peel and stick type to be fixed over existing flooring) 22/03/2022 19/06/2022 13.69 M/S DEVDUTT SHARMA Work is in progress Detail Report
Graph / Photo
191 Providing and installation of 10 Nos. passenger lift in Four Storey Building at DIPSAR, M.B. Road New Delhi. 25/06/2019 24/08/2019 13.59 Sanjeev Kumar Goel work in progress Detail Report
Graph / Photo
192 EOR to Govt. Sarvodaya Kanya Vidyalaya a S.P. Road, Nangloi, New Delhi. SH Providing new gate for main entrance, near activity room, providing and fixing grill in front of primary section providing shed for water through near primary section 02/04/2018 15/09/2030 13.58 L V Enterprises Detail Report
Graph / Photo
193 Shifting of X Ray machine at Gate No 6 and provision of porta cabin at gate No 6 and covering of vehicle session at gate No 03 20/05/2019 03/07/2019 13.40 13.90 (Jan'20) 0.00 (Jan'20) Rajeev Kumar site not available for work 60% Detail Report
Graph / Photo
194 Renovation of gents and ladies toilet and guniting of ceiling of ground, 1st, 4th, 5th and 6th floor of I block, College of Art at Tilak Marg, New Delhi 14/11/2019 11/02/2020 13.30 14.80 (Mar'21) 0.00 (Mar'21) Amiruddin Detail Report
Graph / Photo
195 Expansion of 8 no. Vulnerable Witness Courts at 5th and 6th floor, B-Block KKD Courts Delhi including Audio-Video System and other electrical installations. (Furniture work) 19/05/2022 17/06/2022 13.23 4.42 (Jun'22) 0.00 (Jun'22) Jain Electric Works Detail Report
Graph / Photo
196 Construction of Porta Cabin for storage purpose on Terrace of Family Court, Saket, New Delhi. 26/06/2019 25/07/2019 13.07 8.01 (Mar'21) 0.00 (Mar'21) P S ASSOCIATES work in progress Detail Report
Graph / Photo
197 Repair Renovation of old damaged porta cabins at I block and other miscellaneous work 08/03/2022 06/05/2022 12.65 AMIR ISRAR Detail Report
Graph / Photo
198 Rehabilitation of distress open staircase at Admn. Block. (ii) Conversion of Existing class room into PGs Accommodation. Balance 17/09/2020 05/12/2020 12.59 sabur alam Work in progress. Detail Report
Graph / Photo
199 Rehabilitation of distress open staircase at Admn. Block. Conversion of Existing class room into PG s Accommodation. Balance work of PG s Accommodation. 17/09/2020 05/12/2020 12.59 4.16 (May'22) 0.00 (May'22) sabur alam Work is Progress Detail Report
Graph / Photo
200 Setting up of Dining Hall at HLTB Complex, Tahirpur, Delhi under KKD Court Divn.. M-231 dg. 18-19. 10/02/2019 10/05/2019 12.52 13.79 (Jan'20) 0.00 (Jan'20) Daya Sagar Sharma work in progress Detail Report
Graph / Photo
201 Installation of Rain Water Harvesting system at Sarvodaya bal vidyalaya, Fatehpur Beri, New Delhi (School ID 1923014, Building ID 19231036, EOR ID 20172367). 03/03/2019 02/05/2019 12.15 10.84 (Nov'20) 0.00 (Nov'20) RECKONN work in progress Detail Report
Graph / Photo
202 Construction of temporary shed at Community hall Welcome Delhi (Civil and Electrical work) 02/02/2022 03/03/2022 12.04 Sanjeev Kumar In progress. Detail Report
Graph / Photo
203 Providing new stainless steel gate at entry, internal painting of building, P/F signage board, wooden flooring and wall panelling in principal & conference room & misc. civil works in DIET, J & K pocket, Dilshad Garden, Delhi 26/12/2021 23/02/2022 11.65 Sanjeev Kumar In progress. Detail Report
Graph / Photo
204 Civil Electrical Works 10/12/2021 07/02/2022 11.21 Rainbow Constructions In Progress. Detail Report
Graph / Photo
205 Urgent Security related works in CJ- 15 (High Security Prison) in Prison Complex Mandoli, Delhi 20/01/2022 20/03/2022 11.19 M/s Gejwal Construction Company Work is in progress Detail Report
Graph / Photo
206 Providing and fixing down comer and manually operated electronic FA system 19/09/2019 18/10/2019 11.18 0.00 (Jan'21) 98.00 % (Jan'21) M/s Royale Meridian India Pvt Ltd Work completed. Detail Report
Graph / Photo
207 Provision for Rain Water Harvesting Systems in Govt. Girls Sec. School (Urdu Medium) Lambi Gali, Hauz Qazi under SRD Division-I, Sub-Division-III, PWD, New Delhi dg. 2018-19. 11/07/2019 10/09/2019 11.10 1.62 (Mar'21) 0.00 (Mar'21) Shakur Ahmed & Sons Detail Report
Graph / Photo
208 Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 1 (Hindi Medium) at Jama Masjid, Delhi dg. 18-19 (School ID-2127024.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 11/03/2019 10/05/2019 11.09 13.85 (Mar'20) 0.00 (Mar'20) Mohd. Asad work in progress Detail Report
Graph / Photo
209 Construction of Rouse Avenue Court Complex at DDU Marg, New Delhi. (SH :- Providing office cabins for Branches ). 13/01/2022 13/04/2022 11.08 R L WADHWA work is in progress Detail Report
Graph / Photo
210 Miscellaneous Civil works 10/05/2022 08/07/2022 10.73 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 Detail Report
Graph / Photo
211 Renovation of staff room toilets and pantry and other misc civil work in Chemistry Lab at Vivekanand College Vivek Vihar Delhi 29/05/2022 27/06/2022 10.53 Sundriyal Construction Detail Report
Graph / Photo
212 Construction of Old Age Home at Kanti Nagar Installation of fire doors in the building 04/03/2021 02/04/2021 10.22 11.71 (Aug'21) 0.00 (Aug'21) A. V. ENTERPRISES In progress. Detail Report
Graph / Photo
213 Upgradation of Type-II, Type-III and Type-IV Flat No. B-415, 97, 80, 118, 149, 407 ,168, 234, 309, 303, 330, 485, 469, 621, 497, 605 ,85, 387, 33 etc. C-734, 741, 756 etc, D-21, D-7, D-30 DA Flats Timarpur Delhi-- Electrical Work, EI and Fans 28/02/2022 27/08/2022 10.14 Dashmesh Enterprises Detail Report
Graph / Photo
214 Construction one no additional toilet at 14/2 Tilak Marg and Renovation of kitchen, toilets and other civil miscellaneous repair works at 36 Ashoka Road under SRD Project Division-I, Sub-Division-IV, PWD, New Delhi 11/08/2019 10/10/2019 9.97 11.78 (Nov'20) 0.00 (Nov'20) Sher Singh Detail Report
Graph / Photo
215 Earth filling and making play ground in vacant land behind shopping center in residential complex of Prison Complex Mandoli, Delhi 06/10/2021 04/12/2021 9.18 RAM KUMAR SHARMA Work is in progress Detail Report
Graph / Photo
216 Construction of Two Store Room and renovation of Voter Centre Building Deoli (AC-47), Sector-IV, Pushp Vihar, New Delhi-110017. (Civil and Electrical work) 27/01/2022 26/03/2022 9.07 11.06 (Jun'22) 0.00 (Jun'22) Vision Constructions Detail Report
Graph / Photo
217 Provision for Rain Water Harvesting System in Govt Girls Sr Sec School at Gali Baraf Wali Kinari Bazar Delhi during 2018 19 School ID-1208023 under SRD Division I Sub-Division III PWD New Delhi 11/07/2019 10/09/2019 8.86 9.64 (May'22) 0.00 (May'22) Shakur Ahmed & Sons Detail Report
Graph / Photo
218 Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 2 at Zeenat Mahal, Lal Kuan, Delhi (School ID-2127179) under SRD Division-I, Sub-Division-III, PWD, New Delhi 14/07/2019 13/09/2019 8.76 Shakur Ahmed & Sons Detail Report
Graph / Photo
219 Providing services of plumbing, carpentry jobs etc RECALL 04/11/2019 03/11/2020 8.68 8.68 (Mar'21) 0.00 (Mar'21) Good Luck Enterprises Detail Report
Graph / Photo
220 Distempering painting and Finishing works of various Schools under sub divn M 2313 of KKD Court Division M 231 during 2021 22 (Balance work) 16/12/2021 15/03/2022 8.33 7.20 (Jun'22) 0.00 (Jun'22) M T Builders In Progress. Detail Report
Graph / Photo
221 A R and M O to 405 DA Flats Kalyanvas Delhi 91 dg 2018 19 18/06/2018 14/06/2019 8.03 5.04 (Nov'20) 0.00 (Nov'20) SABUR ALAM work in progress 40% Detail Report
Graph / Photo
222 A/R and M/O to I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Upkeep Service). 25/09/2018 24/09/2019 8.01 1.56 (Jan'20) 0.00 (Jan'20) Ashish Gupta Work in progress Detail Report
Graph / Photo
223 Provision for Rain Water Harvesting System in Sarvodaya Bal Vidyalaya at Pataudi House, Darya Ganj, Delhi (School ID-2127003.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 25/06/2019 24/08/2019 7.90 6.08 (Nov'19) 0.00 (Nov'19) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
224 Furniture work 25/10/2019 08/12/2019 7.84 7.84 (Mar'21) 0.00 (Mar'21) DURIAN INDUSTRIES LIMITED Detail Report
Graph / Photo
225 Construction of public toilet near mortuary, providing shed for blood bank and other misc. works. 18/03/2020 17/05/2020 7.80 Sudhakar Samal work in progress Detail Report
Graph / Photo
226 Provision for Rain Water Harvesting System in Govt. Boys Sr. Sec. School No. 2 (Hindi Medium) at Jama Msjid, Delhi (School ID-2127006.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 25/06/2019 24/08/2019 7.66 6.42 (Jan'20) 0.00 (Jan'20) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
227 Wall paneling wooden flooring and toilet renovation work Civil and Electrical works 11/06/2022 10/07/2022 7.36 N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
228 Preparation of one room of 2nd and 3rd floor in front of lift gallery and replacement of gallery window of I Block, College of Art at Tilak Marg, New Delhi 14/11/2019 12/01/2020 7.35 9.10 (Feb'21) 0.00 (Feb'21) Amiruddin Detail Report
Graph / Photo
229 Installation of rain water harvesting system 02/06/2018 01/08/2018 7.23 6.04 (Jul'19) 0.00 (Jul'19) Mohd Akram work in progress 70% Detail Report
Graph / Photo
230 Installation of Open Gym and Joy Rides in the grounds of Mandoli Prison Residential Complex and for Creche in CJ- 16 in Mandoli Prison Complex Delhi. (2nd Call) 23/03/2022 06/05/2022 7.08 Abhishek Enterprises Work is in progress Detail Report
Graph / Photo
231 A/R and M/O I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Repair and Renovation work of University Staff Quarters at IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, PWD, New Delhi). 29/03/2019 28/06/2019 7.01 Prithvi creation work in progress Detail Report
Graph / Photo
232 Renovation of D Block 1st Floor MP Hall 28/11/2019 26/01/2020 6.80 6.89 (Sep'20) 0.00 (Sep'20) Mohd Amjad Detail Report
Graph / Photo
233 Operation and Maintenance of 3x110 TR Capacity HVAC System and Servicing Overhauling and Comprehensive running maintenance of WTAC, Water coolers and Split AC units 01/04/2019 31/12/2019 6.53 7.48 (May'20) 0.00 (May'20) M/s Naj Refrigeration & Air Conditioning Works Detail Report
Graph / Photo
234 Distempering, painting and Finishing works at Various Schools under sub division M-2313 of KKD Court Division (M-231) during 2022-23 29/06/2022 27/08/2022 5.83 M/S FAIZAN ALI Detail Report
Graph / Photo
235 Providing and fixing dustbin at Karkardooma Court Complex, Delhi 13/06/2022 12/07/2022 5.66 N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
236 Raising of boundary wall of Lal quarter Kidwai Nagar residential area under MLA LAD Fund Scheme RECALL 04/11/2019 18/12/2019 5.60 4.89 (Sep'20) 0.00 (Sep'20) B P Rai and Sons Detail Report
Graph / Photo
237 Anti termite treatment of Hostel building and P F commercial ply and Mattress on beds of Hostel block Ist recall 21/11/2021 19/01/2022 5.42 6.18 (Mar'22) 0.00 (Mar'22) Verma Pesticides & Pest Control Services Pvt. Ltd. In progress. Detail Report
Graph / Photo
238 Providing infrastructure to Rouse Avenue Court Complex at DDU Marg, New Delhi during 2020-21. (SH :- Providing internal furnishing for De-Stress Room and Automatic Hand Sanitizer). 25/10/2020 24/11/2020 5.41 0.00 (Jan'21) 30.00 % (Jan'21) R L WADHWA work is in progress Detail Report
Graph / Photo
239 Construction of Rain water Harvesting System at Govt Boys Sr Secondary School Dev Nagar New Delhi Building ID 21281284 30/05/2019 13/07/2019 5.19 4.90 (Jan'20) 0.00 (Jan'20) Prem Sagar Work completed final bill paid Detail Report
Graph / Photo
240 Maintenance of PCs and their accessories in Health Maintenance Division Office (S-W) and all Sub Divisions under this Division office. 27/01/2020 26/01/2021 5.04 STAR COMPUTER SYSTEMS The Tender has been Cancel. Detail Report
Graph / Photo
241 Construction of Rain water Harvesting System in Sarovodya Kanya Vidyalaya Baba Ram Dev at Prasad Nagar New Delhi Building ID 21281295 30/05/2019 13/07/2019 4.97 5.56 (Nov'19) 0.00 (Nov'19) Prem Sagar Bill paid Detail Report
Graph / Photo
242 Making arrangement for sanitized the Judges residential complex and Lawyers chamber blocks D E F G H preventive measures for Corona Virus COVID 19 in Karkardooma Court Complex Delhi. Sanitization work and providing hand sanitizer 31/01/2022 31/03/2022 4.93 5.35 (Jun'22) 0.00 (Jun'22) PURIFIRES INDIA In Progress. Detail Report
Graph / Photo
243 Providing and fixing work stations for PSA Branch at VIIth floor Admin Block of Delhi High Court New Delhi 18/04/2022 17/05/2022 4.83 R L WADHWA Work in progress Detail Report
Graph / Photo
244 E.O.R. to repair and replacement of sewer line, rain water disposal line and other misc. repair work in Police Station, Darya Ganj, Delhi dg. 2018-19 (SH- Improvement of drainage system under SRD Division-I, Sub-Division-III, PWD, New Delhi). 26/02/2019 25/04/2019 4.59 5.27 (Jun'19) 0.00 (Jun'19) Prashant Gupta work in progress Detail Report
Graph / Photo
245 Anti termite treatment of Hostel building and PF commercial ply and Mattress on beds of Hostel block 29/09/2021 27/11/2021 4.41 Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 Detail Report
Graph / Photo
246 EOR to Police Colony, Rajinder Nagar, New Delhi during 2018-19.(SH- Covering of open drain in Police Colony). 30/05/2018 28/07/2018 4.37 5.48 (Aug'19) 0.00 (Aug'19) G.S construction wip Detail Report
Graph / Photo
247 Misc. civil repair work 15/09/2019 14/12/2019 4.36 5.44 (Oct'21) 0.00 (Oct'21) Shabbi Abbas Detail Report
Graph / Photo
248 Cons. of toilet in front of SCP Canteen and Requirement of bathroom and toilet in Community Centre. 23/03/2020 22/05/2020 4.12 5.14 (Mar'21) 0.00 (Mar'21) Panchu ram Detail Report
Graph / Photo
249 RMO of water coolers , Split or Window or Ductable ACs installed at Lawyers block , Utility Block , Lockup building and Main Court Building at District Court Complex saket New delhi -110017. 03/02/2019 02/02/2020 3.91 1.61 (Jul'19) 0.00 (Jul'19) ARORA ELECTRICAL WORKS Detail Report
Graph / Photo
250 EOR to National Law University, Sec-14, under Sub Div-III, SWBMD, New Delhi during 2018-19.(SH- Cleaning of sewerline by using super sucker machine). 05/06/2018 02/09/2018 3.81 3.81 (Dec'18) 70.00 % (Dec'18) Surender Singh Chahal work in progress Detail Report
Graph / Photo
251 Replacement of broken kota stone flooring and wooden racks, false ceiling and white washing of MFA final year Sculpture Studio, College of Art at Tilak Marg, New Delhi 15/11/2019 14/12/2019 3.73 4.31 (Apr'21) 0.00 (Apr'21) Sher Singh Detail Report
Graph / Photo
252 A R and M O L N Hospital, New Delhi dg 2017 18 (SH Misc day to day Work for Pediatric Ward Surgical Block Skin Ward Administrative Block Burn Ward, Medical Ward Ward No. 19 and Gynae Ward at Lok Nayak Hospital, New Delhi 07/02/2021 06/02/2022 3.47 T. S. Enterprises

work completed

Detail Report
Graph / Photo
253 Providing and fixing dustbin at Karkardooma Court Complex Delhi 10/12/2021 08/01/2022 3.10 Saman Mehboob In Progress. Detail Report
Graph / Photo
254 Provision of Security Guard for Watch and ward at Old Age Home, Chattarpur under Sub Division-II, PTS Malviya Nagar, New Delhi during 2019-20. 21/06/2019 20/06/2020 3.05 3.05 (Mar'21) 0.00 (Mar'21) Universal Security & Placement Services (Regd.) work in progress Detail Report
Graph / Photo
255 A/R and M/O to I.G.D.T.U.W. at Kashmere Gate under Sub-Division-III, SRD Division-I, PWD, New Delhi During 2017-18 (SH-Specialized waterproofing treatment in the profile sheet gutter of workshop behind MAE Block). 21/04/2018 20/05/2018 2.62 0.00 (Jul'18) 2.90 % (Jul'18) Garg Waterproofing Company Work Completed and final bill paid Detail Report
Graph / Photo
256 Installation of 1 no bore well at Fire Station Tahirpur Delhi dg 2021 22 Civil and Electrical Works (2nd Recall) 19/03/2022 17/04/2022 2.62 Mohd. WAZID Detail Report
Graph / Photo
257 Providing and erecting permanent barricading around dangerous building in Kasturba Kustha Ashram Tahirpur Delhi 1st recall 11/12/2021 09/01/2022 2.50 Akhil Okharwal In Progress. Detail Report
Graph / Photo
258 Installation of Stainless Steel Grill on the window for safety and security of Valuable assets 13/06/2022 12/07/2022 2.29 2.84 (Jun'22) 0.00 (Jun'22) Mohd Azam Detail Report
Graph / Photo
259 Installation of 1 no bore well at Fire Station Tahirpur Delhi dg 2021 22 Civil Electrical Works Ist Recall 08/01/2022 06/02/2022 2.25 MUZAMMIL ALI Detail Report
Graph / Photo
260 Construction of security gates near entrance road of Church of Divine Mercy in Shakurbasti Assembly Constituency AC-15 under MLALAD scheme, during 2021-2022. (3rd call) 24/03/2022 23/05/2022 2.19 A J & CO. Detail Report
Graph / Photo
261 Installation of 1 no. bore well at Fire Station, Tahirpur Delhi dg. 2021 22. Civil and Electrical Works 21/11/2021 20/12/2021 2.16 Sudesh Jain Detail Report
Graph / Photo
262 Replacement of 04 Nos. Air conditioners at Land & Estate Branch Lucknow Road, Old Sectt, Delhi-54 22/06/2022 06/07/2022 2.08 CHETAN SHARMA Detail Report
Graph / Photo
263 A/R and M/O other PWD Roads under SRD Division -I, PWD, New Delhi during 2019-20. (SH- Painting of Kerb Stones on various roads for Independence Day under Sub Division-II.) 13/08/2019 27/08/2019 2.06 2.27 (Nov'19) 0.00 (Nov'19) MOHD AFTAB Detail Report
Graph / Photo
264 A/A to RCL Tahirpur Sunder Nagri, Delhi during 2021-22.SH:- Providing and erecting permanent barricading around the dangerous buildings in Kasturba Kustha Ashram Tahirpur Delhi 03/09/2021 02/10/2021 1.95 Sanjeev Kumar In progress. Detail Report
Graph / Photo
265 SPS type building i/c internal internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system & providing furniture etc. 25/03/2022 23/04/2022 1.90 MKSC Design India Private Limited Work in Progress Detail Report
Graph / Photo
266 Provision of New gate and laying C.C path at the entrance of VSKV Old Seemapuri 04/09/2021 03/10/2021 1.85 0.88 (Mar'22) 0.00 (Mar'22) Sanjeev Kumar Detail Report
Graph / Photo
267 Hiring of New Digital Photocopier Machine Model Sharp AR-6020N New Model on Rental basis with ADE Duplex Printer and Scanner 05/09/2021 04/09/2023 1.81 0.45 (Jun'22) 0.00 (Jun'22) Frank Copier Pvt. Ltd. Detail Report
Graph / Photo
268 Measuring and Mapping of Veterinary Polyclinic and SPCA building of Shahdara District A.H. Unit. 23/06/2022 07/07/2022 0.74 Kesari & Associates Detail Report
Graph / Photo
269 Soil investigation and bearing capacity of soil 19/08/2021 28/08/2021 0.50 Allied Engineers Detail Report
Graph / Photo
270 Providing and fixing fire Check door in DDU Hospital 11/03/2021 10/04/2021 R U Enterprise Work is Progress Detail Report
Graph / Photo
271 Repairing of aluminium doors & Shutters. 19/08/2014 03/09/2014 Detail Report
Graph / Photo
272 Providing and laying RCC drain cover in open surface drain in basement. 16/08/2014 15/09/2014 2.58 (Mar'21) 0.00 (Mar'21) Detail Report
Graph / Photo
273 Providing calcium silicate false ceiling & HRD fabrication in opening balcony at second floor. 16/09/2014 15/10/2014 Detail Report
Graph / Photo
274 Finishing of exterior wall in 20 nos. CBI flats. 08/12/2014 26/12/2014 Pradeep Kumar Sharma Detail Report
Graph / Photo
275 P/F Manhole cover & Drain cover. 08/01/2015 07/02/2015 M. N. Construction Co. Detail Report
Graph / Photo
276 Providing Security Guard for watch and ward for Sub Divn. Office & Vacant Flats at Mayur Vihar Ph-II and Division Office. 18/08/2014 01/01/2015 Detail Report
Graph / Photo
277 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kondli Delhi-110091. 08/01/2015 04/02/2015 Detail Report
Graph / Photo
278 Providing services of labour for day to day maintenance under Sub-Division M-2334. 31/05/2014 -- Detail Report
Graph / Photo
279 Providing and fixing PVC doors in bathrooms in qtrs. in place of old damaged ones. 18/09/2014 17/10/2014 Detail Report
Graph / Photo
280 Replacement of Damaged roof of Sub Divn. Office M-233. 11/11/2014 10/12/2014 35.49 (Aug'21) 0.00 (Aug'21) Detail Report
Graph / Photo
281 Cleaning of sewer line, manhole & gully traps etc. 22/12/2014 21/01/2015 Detail Report
Graph / Photo
282 Providing and fixing door in toilet at G.G.S.S.S. Vasundhara Enclave Delhi School ID-1002185. 24/01/2015 23/02/2015 M. N. Construction Co. Detail Report
Graph / Photo
283 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kalyan Puri Delhi. 08/01/2015 07/02/2015 M. N. Construction Co. Detail Report
Graph / Photo
284 Providing and fixing polycarbonate in available. 19/12/2014 18/01/2015 Detail Report
Graph / Photo
285 Improvement of Open Space in Circle Office & Division Office. 06/02/2015 -- Rajeev Sharma Detail Report
Graph / Photo
286 Misc. work at RSKV Mayur Vihar Ph-1 Pkt-IV. 17/01/2015 16/02/2015 Pradeep Kumar Sharma Detail Report
Graph / Photo
287 Providing and fixing FRP door shutters in place of old damaged flush door shutters. 18/09/2014 17/10/2014 Detail Report
Graph / Photo
288 Providing and fixing Acrylic sheet in windows, kerb stone, painting work and misc. civil work. 08/02/2015 08/03/2015 Detail Report
Graph / Photo
289 Repair to damaged windows, renewing glass panes with acrylic plastic sheet & signage work. 06/02/2015 15/03/2015 Detail Report
Graph / Photo
290 Water proofing treatment of first floor toilet. 15/12/2014 14/01/2015 Detail Report
Graph / Photo
291 Providing and fixing door & window shutters in pooling booth centre at GGSSS Kondli Gharoli. 06/02/2015 20/02/2015 Detail Report
Graph / Photo
292 Wall tile and other misc. civil work in Sports Complex at East Vinod Nagar. 27/02/2015 26/03/2015 Detail Report
Graph / Photo
293 Providing & fixing door and installation of PVC overhead tank for fire safety. 17/01/2015 -- Detail Report
Graph / Photo
294 Misc. Civil Works. 16/03/2015 30/03/2015 Shekhar Detail Report
Graph / Photo
295 Providing ramps in Schools & miscellenious works. 12/02/2015 26/02/2015 Detail Report
Graph / Photo
296 P/F Floor tile & broken tile. 20/11/2015 12/12/2015 Detail Report
Graph / Photo
297 Providing and laying cement concrete. 12/03/2015 25/03/2015 Indal Yadav Detail Report
Graph / Photo
298 Providing railing for Park. 23/11/2015 05/12/2015 Detail Report
Graph / Photo
299 Renovation of D.D.E. office by changing sanitary & plumbing fixtures in office toilet and internal finishing works 04/07/2016 03/09/2016 0.00 (Aug'16) 40.00 % (Aug'16) Work completed Detail Report
Graph / Photo
300 Construction of Double storeyed SPS type rooms for Cal lab,Library,Science labs,toilet for HOS & staff at Govt. Co.Ed.Edn.Dichaon Kalan,New Delhi. 18/12/2017 15/06/2019 34.21 (Jun'19) 100.00 % (Jun'19) work in progress. Detail Report
Graph / Photo
301 Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. 25/06/2016 24/07/2016 WORK RESCIENED. Detail Report
Graph / Photo
302 C/o Boundary wall on the newly taken over plot at village Dera Mandi, New Delhi. 25/03/2016 24/07/2016 0.00 (Aug'16) 75.00 % (Aug'16) DOSE PERTAIN TO THIS DIVISION Detail Report
Graph / Photo
303 Arrangement of Drinking water facility by bore well at GBSSS No. 1, Khanpur, New Delhi. (School ID : 1923020) 10/05/2016 09/06/2016 0.00 (Jul'16) 50.00 % (Jul'16) Tender re-call and date of opening 24-09-2016 Detail Report
Graph / Photo
304 EOR to Raja Ram Mohan Rai, Hauz Rani, New Delhi. (SH: laying of one borewell & installation of 1 Nos. R.O. System 23/05/2016 23/06/2016 0.00 (Jul'16) 70.00 % (Jul'16) Dose not pertain to this Division Detail Report
Graph / Photo
305 EOR to Govt.Sarvodaya Vidyalaya Gokhle Marg School,No.2,Mori Gate,Delhi. 15/04/2016 14/10/2016 0.00 (Jul'16) 10.00 % (Jul'16) Completed Detail Report
Graph / Photo
306 EOR to slabs beams, coloums chajjas by short creting replacement of old & damaged roof treatment and other misc repair work at Sarvodaya Kanya Vidyala,Ahataa Kedara Idgah road Delhi. 15/04/2016 14/07/2016 0.00 (Jul'16) 15.00 % (Jul'16) Completed Detail Report
Graph / Photo
307 Improvement of ground with drainage system and providing paver blocks, kota stone flooring in classroom & varandah, repair to boundary wall & other Misc. work at Idhgh road-GGSS 05/04/2016 04/06/2016 0.00 (Jul'16) 80.00 % (Jul'16) Completed Detail Report
Graph / Photo
308 Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. 17/01/2016 30/04/2016 0.00 (Jul'16) 80.00 % (Jul'16) polycarbonate Detail Report
Graph / Photo
309 providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. 01/05/2016 30/06/2016 0.00 (Jul'16) 0.01 % (Jul'16)

work in progress

Detail Report
Graph / Photo
310 E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi 10/04/2016 09/06/2016 0.00 (Jul'16) 0.01 % (Jul'16)

Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270

Detail Report
Graph / Photo
311 Construction of new boundary wall 24/04/2016 20/07/2016 21.77 (May'17) 100.00 % (May'17) Detail Report
Graph / Photo
312 Repair and renovation of toilets 17/06/2016 15/08/2016 0.00 (Sep'16) 91.00 % (Sep'16)

Detailed estimate under process.

Detail Report
Graph / Photo
313 Renovation of Classrooms, Corridor, Principal Room & Staff Room. 16/06/2016 13/09/2016 0.00 (Sep'16) 53.00 % (Sep'16)

T.S. under process.

Detail Report
Graph / Photo
314 Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. 16/10/2016 15/11/2016 forfeited Detail Report
Graph / Photo
315 Installation of R.O System at Dr. Ambedkar Nagar ,Sector-V , No-2-GGSSS-1923050. 20/08/2016 15/09/2016 0.00 (Aug'16) 0.01 % (Aug'16) work completed Detail Report
Graph / Photo
316 C/o 20 Nos. SPS type class rooms including toilet blocks, staircase and electrical installations, fan etc. at Sarvodaya (Co-ed) Sr. Sec. School, Netaji Nagar, (School I.D.) 1719102, Building I.D. 17191327). New Delhi 04/11/2014 30/09/2015 85% Work is in Progress Detail Report
Graph / Photo
317 Up gradation to Delhi Govt. D-II Flats, Vasant Kunj, New Delhi. 05/02/2017 04/08/2017 100.57 (Jul'18) 100.00 % (Jul'18) completed Detail Report
Graph / Photo
318 Providing Services of Security Guard at T.V. Branch Enquiry Office 10/04/2017 09/04/2018 2.52 (Apr'18) 90.00 % (Apr'18) Work completed Detail Report
Graph / Photo
319 Acoustic treatment system and renovation of multipurpose hall. 20/10/2017 17/01/2018 40.27 (Nov'21) 0.00 (Nov'21) 65% (Work is delayed due to ongoing electrical work as well as Covid-19) Detail Report
Graph / Photo
320 Acoustic work. 02/02/2018 01/04/2018 67.40 (Jul'18) 100.00 % (Jul'18) work in progress Detail Report
Graph / Photo
321 Repair of toilet blocks, Finishing of offices and other misc.works at beggar home Lamur Delhi-36 28/05/2021 27/05/2022 Work in Progress Detail Report
Graph / Photo
322 A/R and M/O to Residential and Non Residential building under Building Maintenance Sub Division (SW) - 4, PWD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19.(SH Engaging labour for Day to Day Maintenance). 17/05/2018 16/05/2019 94.01 (Mar'20) 0.00 (Mar'20) WORK IN PROGRESS Detail Report
Graph / Photo
323 Construction of New block Forensic Science Laboratory, Rohini, New Delhi 06/03/2020 05/09/2021 212.87 (Aug'21) 0.00 (Aug'21) work in progress Detail Report
Graph / Photo
324 A/R and M/O to residential and Non residential Building under Sub Div-II of SWBMD at ITI Campus, Pusa, New Delhi during 2018-19.(Sh- Misc repair work and finishing work in quarters). 23/05/2018 21/11/2018 14.29 (Jul'19) 0.00 (Jul'19) work in progress. Detail Report
Graph / Photo
325 AR and MO to District Court Resid. Complex Saket, ND-18-19 (SH Cleaning, mopping of common area, like lift lobby, staircase, basement, community centre, footpath area, terrace, servant qtr. etc. by mopping machine at Resid. Complex Saket Court, ND). 25/09/2018 24/09/2019 0.49 (Nov'18) 25.00 % (Nov'18) work in progress Detail Report
Graph / Photo
326 Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. 02/11/2018 01/11/2019 214.77 (Sep'19) 0.00 (Sep'19) Work in progress Detail Report
Graph / Photo
327 Construction of Boundary wall at Sayurpur Village, New Delhi. (SH- Providing fixing grills and concertina coil at boundary wall). 10/07/2018 09/09/2018 work in progress Detail Report
Graph / Photo
328 A/R and M/O to Educational Building under SWBMD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19. (Sh -Internal and external finishing and other misc works). 03/08/2018 01/10/2018 0.25 (May'22) 0.00 (May'22) WORK IN PROGRESS Detail Report
Graph / Photo
329 REMODELLING AND UPGRADING OF EXISTING DEEP CHAND BANDHU HOSPITAL AT KOKIWALA BAGH, ASHOK VIHAR, PH-IV, DELHI. 28/06/2019 22/06/2020 0.00 (Mar'19) 0.01 % (Mar'19) Agency has gone in the arbitration. work in progress Detail Report
Graph / Photo
330 EOR to Govt. Co-ed. Sr. Sec. School at Daulatpur and Govt. Co-ed. Sr. Sec. School at Malikpur, New Delhi. (Sh- C/o Rain Water Harvesting System). 04/03/2019 02/05/2019 69.90 (Aug'19) 0.00 (Aug'19) WORK IN PROGRESS Detail Report
Graph / Photo
331 GGSSS DDA Flat, Kalkaji, Phase-II, School ID: 1925041 14/01/2019 10/10/2019 0.00 (Sep'21) 65.00 % (Sep'21) Work is in progress Detail Report
Graph / Photo
332 GGSSS No. 3, Kalkaji School ID : 1925039 14/01/2019 10/10/2019 10365.03 (Nov'21) 0.00 (Nov'21) Work is in progress Detail Report
Graph / Photo
333 SKV Mandi Village, School ID : 1923064 14/01/2019 10/10/2019 5342.69 (Dec'21) 0.00 (Dec'21) Work is in progress Detail Report
Graph / Photo
334 GBSSS, No. 2, Kalkaji, , School ID: 1925011 23/01/2019 19/10/2019 4661.03 (Feb'22) 0.00 (Feb'22) Work is in progress Detail Report
Graph / Photo
335 GBSS, Garhi, Jharia Maria School ID : 1924042 23/01/2019 19/10/2019 4662.60 (Mar'22) 0.00 (Mar'22)

Work is in progress

Detail Report
Graph / Photo
336 GBSSS Dera Village School ID: 1923360 08/12/2018 04/08/2019 0.00 (Feb'21) 63.00 % (Feb'21) In progress Detail Report
Graph / Photo
337 Co-Ed. SSS Lajpat Nagar, School ID: 1925335 08/12/2018 04/08/2019 0.00 (Sep'21) 60.00 % (Sep'21) Work is in progress Detail Report
Graph / Photo
338 GBSSS Jungpura, School ID : 1924004 08/12/2018 04/08/2019 2754.99 (Dec'21) 0.00 (Dec'21)

Work is in progress

Detail Report
Graph / Photo
339 GGSSS, DDA Flats, Phase II, Kalkaji, School ID: 1925045 14/01/2019 10/09/2019 0.00 (Sep'21) 56.00 % (Sep'21)

Work is in progress

Detail Report
Graph / Photo
340 Govt. Co.-Ed., Middle School, Sarai Kale Khan, Vidut Nagar, School ID: 1925418 14/01/2019 10/09/2019 1983.32 (Mar'22) 0.00 (Mar'22) Work is in progress Detail Report
Graph / Photo
341 SKV,, Jonapur- BNK, School ID: 1923003 08/12/2018 04/08/2019 0.00 (Sep'21) 65.00 % (Sep'21)

Work is in progress

Detail Report
Graph / Photo
342 EOR to GBSSS Bijwasan, Govt. Sarvodaya Co-ed Sr. Sec. School Kitchner Road (Malcha Marg), DIET Sec-07 R.K. Puram etc New Delhi.(Sh- Construction of Rain Water Harvesting System). 22/02/2019 24/04/2019 47.84 (Jul'19) 80.00 % (Jul'19) WORK IN PROGRESS. Detail Report
Graph / Photo
343 AR and MO to Delhi Sachivalaya at IG Stadium Complex New Delhi dg 2018 19 10/11/2018 09/05/2019 1.02 (Jul'19) 0.00 (Jul'19) Work in Progress 95% Detail Report
Graph / Photo
344 Construction of 30 Nos. Porta Cabin Aam Admi Mohalla Clinics under Sub division- I,II,III and IV under South West Building Maintenance Division New Delhi. (SH Civil works and Electrical works). 06/12/2018 02/08/2019 308.01 (May'22) 0.00 (May'22) WORK IN PROGRESS Detail Report
Graph / Photo
345 SKV Surajmal Vihar (School Id- 1001102) 24/12/2018 19/09/2019 Handed over to HOS. Detail Report
Graph / Photo
346 SKV, Kiran Vihar (School Id- 1001106) 24/12/2018 19/09/2019 Building work completed. Development work in progress. Detail Report
Graph / Photo
347 Govt. Co-ed SSS Preet Vihar (School Id- 1002351) 24/12/2018 19/09/2019 0.00 (Apr'19) 1.50 % (Apr'19) Inventory submitted to HOS. 28 rooms handed over on 30.10.2021 balance class rooms will be hand over 10.05.2022 Detail Report
Graph / Photo
348 SKV Radhey Shyam Park (School Id- 1003153) 17/03/2019 11/12/2019 Structure work completed. Finishing work is in progress. Flooring, plastering and other miscellaneous work are under progress. Detail Report
Graph / Photo
349 RPVV Gandhi Nagar (School Id- 1003261) 17/03/2019 11/12/2019 12491.60 (Nov'20) 0.00 (Nov'20) 48 rooms handed over to HOS on 25.03.2022. In 42 Additional Rooms In Block-C structure work completed. Flooring work including corridor are completed & other miscellaneous works are under progress. In Block-D, structure work is completed and misc. work is under progress. Detail Report
Graph / Photo
350 SBV, Rajgarh Colony (School Id- 1001110) 17/03/2019 11/12/2019 0.00 (Apr'19) 0.50 % (Apr'19) External development work is in progress. In MP Hall, stage flooring & wall paneling works completed. In Block-C, Grinding work of Kota flooring, finishing & misc. works are in progress. External GRC tile work is under progress. Detail Report
Graph / Photo
351 GGSSS Mayur Vihar Ph-3 (Kondali Gharauli) (School Id- 1002352) 17/03/2019 11/12/2019 0.00 (Jan'21) 1.00 % (Jan'21) Building work completed and development is in progress. Detail Report
Graph / Photo
352 SKV Patparganj (School Id- 1002031) 17/03/2019 11/12/2019 12491.60 (Nov'20) 0.00 (Nov'20) Structure work completed. GRC, Flooring, Plastering and development work in progress. Detail Report
Graph / Photo
353 GGSSS Khichripur (School Id- 1002037) 17/03/2019 11/12/2019 0.00 (Jan'21) 30.00 % (Jan'21) Block-A : (20 rooms) : Structure work complete and internal finishing is in progress. Block-B : (24 Rooms) : Structure work complete and internal finishing is in progress. Block-C : (28 Rooms) : Structure work complete and internal finishing is in progress. Block-D : (4 Rooms) : Development work under progress. Work delay due to late handover of the site of Block D. Detail Report
Graph / Photo
354 Raising of main gate, C/o guard room, repair of ground water tank, providing and fixing IRC fabric jali inside the Class rooms etc. 30/06/2019 29/08/2019 1.60 (Mar'21) 0.00 (Mar'21)

work completed

Detail Report
Graph / Photo
355 Construction of Recreation Room, Coys room, Officers Quarters and Shed. 30/06/2019 29/08/2019 51.12 (Jul'20) 0.00 (Jul'20)

work completed

Detail Report
Graph / Photo
356 Construction of 2 nos.Viewers stand in Parade ground at PTS, Wazirabad, Delhi 30/06/2019 19/07/2019 8.39 (Jan'20) 0.00 (Jan'20)

work completed

Detail Report
Graph / Photo
357 Attending complaints of routine maintenance of service centre PTS, Wazirabad, Delhi. 30/06/2019 29/06/2020 7.20 (Mar'20) 0.00 (Mar'20)

work completed

Detail Report
Graph / Photo
358 Renovation of 10 Nos toilet blocks, Construction of 3 nos. R.C.C. tank of size 8 x 5 mtr. and 6 nos. M.S. grill gates. 30/06/2019 29/08/2019 52.31 (Aug'20) 0.00 (Aug'20)

work completed

Detail Report
Graph / Photo
359 External plaster work of Judges Flats Including tile work in over head water storage tank of block D AND E, Steel works and other Misc. work 24/10/2019 23/01/2020 work in progress Detail Report
Graph / Photo
360 External plaster work including painting. 16/06/2019 15/09/2019 work in progress Detail Report
Graph / Photo
361 Redevelopment of rain water harvesting pits and cleaning of storm water lines at Residential and Non-Residential Complex, Saket Court, New Delhi. 25/07/2019 24/09/2019 work in progress Detail Report
Graph / Photo
362 Reconstruction of collapsed boundary wall of CBD plot at Shahdara, Delhi owned by Urban Development Department. 24/07/2019 22/09/2021 in progress. Detail Report
Graph / Photo
363 Repairing of Fire Door and Replacement of Damaged Door/Fittings and Other Misc Works 30/03/2021 29/04/2021 27.50 (Aug'21) 0.00 (Aug'21) work in progress. Detail Report
Graph / Photo
364 construction of oxygen gas plant room and car parking shed for staff 05/05/2021 03/06/2021 Work is progress Detail Report
Graph / Photo
365 False ceiling work in Ward Area. (2nd CALL) 25/03/2021 23/05/2021 Work is progress Detail Report
Graph / Photo
366 Making Building and Campus Barrier free for accessibility of disabled persons at Dr. BR Sur Homeopathic, Hospital, Nanakpura, New Delhi 18/06/2021 15/09/2021 Work is in progress Detail Report
Graph / Photo
367 A Finishing Work. B Cleaning of Sewer line Water Storage Tank. C Providing and Supplying building material for day to day maintenance 02/09/2021 01/04/2022 Work in progress Detail Report
Graph / Photo
368 Replacement of existing water closet with single piece water closet set, P/F floor and wall tile in toilets, replacement of damaged window and misc. civil works 18/11/2020 28/11/2020 In Progress. Detail Report
Graph / Photo
369 Furnishing of new lecture theatre over OT at Dr. BSA Medical College and Hospital Sector-6, Rohini Delhi. 06/03/2021 05/05/2021 work in progress Detail Report
Graph / Photo
370 Construction of Hospital at Hastsal, New Delhi 17/06/2021 16/06/2023 Work is in progress Detail Report
Graph / Photo
371 AR and MO Pt. Madan Mohan Malviya Hospital Malviya Nagar, New Delhi dg. 2020-21 Comprehensive maintenance of automatic stainless steel scrub station (07 Unit) installed at O.T. area. 07/01/2021 16/01/2022 2.08 (Jun'22) 0.00 (Jun'22) work in progress Detail Report
Graph / Photo
372 Providing and Fixing Cubical Curtain in OPD Erection of shed for waiting area of COVID-19 suspected Patients and other Misc. work at NHMC and Hospital 02/02/2021 02/04/2021 Work is Progress Detail Report
Graph / Photo
373 Renovation of Labour room, Public toilet at 5th floor in MCH block and other misc. works 17/03/2021 16/07/2021 9.25 (May'22) 0.00 (May'22) work in progres Detail Report
Graph / Photo
374 Renovation of Department of Surgery and Department of Gyne and Obs 20/02/2021 20/04/2021 Work is progress Detail Report
Graph / Photo
375 C/o Staircase (Structural steel) for fire Exist in College Building and PG Accommodation Block and providing fixing mandatory fire check doors at NHMC Hospital 07/03/2021 21/04/2021 Work is Progress Detail Report
Graph / Photo
376 Providing and fixing Fire Check doors and fittings in ASBGH 11/03/2020 10/04/2021 Work is Progress Detail Report
Graph / Photo
377 Repair of damaged parapet wall, ceiling plaster of residential staff Quarters and other Misc. work.0 15/03/2021 15/04/2021 5.64 (May'22) 0.00 (May'22) Work is Progress Detail Report
Graph / Photo
378 Misc Civil repairing work in Lift pit, lift shaft and machine room in OBH and GH at residential campus GTBH 04/09/2021 03/10/2021 Site is not being provided by Electrical Department. Detail Report
Graph / Photo
379 Construction of (G+3) Pucca at SKV, Sultanpur, New Delhi 110030 18/07/2021 17/07/2022 (i) Work has been awarded to contractor. (ii) Hon'ble PWD Minister has approved Architectural Drawings in the meeting on 23.08.2021 (iii) Fire approval received and Submission drg. has been submitted in South MCD for approval from Local Body (iv) Structural design : Str. drawing are under preparation. Detail Report
Graph / Photo
380 Construction of (G+3) Pucca School Buildings at Sarita Vihar 18/07/2021 17/07/2022 (i) Work has been awarded to contractor. (ii) Hon'ble PWD Minister has approved Architectural Drawings in the meeting on 23.08.2021 (iii)Submission drgs for DUAC/Fire/Local body are under preparation. (iv) Structural design : Str. drawing are under preparation. Detail Report
Graph / Photo
381 Construction of (G+3) Pucca School Buildings at Satbari 18/07/2021 17/07/2022 (i) Work has been awarded to contractor. (ii) Hon'ble PWD Minister has approved Architectural Drawings in the meeting on 23.08.2021 (iii)Submission drgs for DUAC/Fire/Local body are under preparation. (iv) Structural design : Str. drawing are under preparation. Detail Report
Graph / Photo
382 Construction of Boundary wall at Plot No. FA 6 for District office and bataliyan, Women training college, Police line and Advanced research and Training Institute of Delhi Police Officers Narela, Delhi 110040 20/01/2022 20/05/2022 Work in Progress Detail Report
Graph / Photo
383 Development of play ground and construction of boundary wall. (Balance Work) 20/01/2022 20/05/2022 Work in Progress Detail Report
Graph / Photo
384 Provision of Iron Steel Gate in the Residential Campus, GTB Hospital, Shahdara, Delhi 27/11/2021 26/01/2022 Work is in progress Detail Report
Graph / Photo
385 Renovation of Various Rooms (Room No. 417 to 439) in the department of Pathology 4th floor of the UCMS college Block, GTB Hospital, Shahdara, Delhi 28/12/2021 26/06/2022 Major work could be not started due the Electrical work not started till date. Detail Report
Graph / Photo
386 Renovation of Various Rooms and laboratories (Room No. 324 to 341) in the department of Forensic Medicine 3rd floor of the UCMS college Block, GTB Hospital, Shahdara, Delhi 28/12/2021 27/04/2022 Work could be not started due the Electrical work not started till date. Detail Report
Graph / Photo
387 Construction of additional SPS type classrooms in Govt Schools Directorate of Education under Priority II 05/09/2019 04/09/2020 0.11 (Nov'19) 0.00 (Nov'19) work in progress Detail Report
Graph / Photo
388 Construction of 460 Beds Mother and Child Hospital Block at LBS Hospital Khichripur, Delhi 23/09/2019 23/09/2019 658.28 (Jun'22) 0.00 (Jun'22) Work is in progress. Detail Report
Graph / Photo
389 Construction of Mother and Child Block and Screening OPD Block at Dr. BSA Hospital at Rohini, Delhi, i/c Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Supply of Furniture). 06/03/2020 05/09/2021 221.89 (Mar'22) 0.00 (Mar'22) work in progress Detail Report
Graph / Photo
390 Providing the services of Security Guard for day to day maintenance at D-II flats. 02/08/2019 01/08/2020 work in progress Detail Report
Graph / Photo
391 Providing security guards at Division Office M-222 (NE), Sub Division M-2222, Sub Division M-2221, Sub Division Office Loni Road and Division M-222 30/06/2019 29/05/2020 23.93 (Mar'21) 0.00 (Mar'21)

work completed

Detail Report
Graph / Photo
392 Attending day to day complaints 24/06/2019 23/06/2020 10.22 (Oct'20) 0.00 (Oct'20)

work completed

Detail Report
Graph / Photo
393 Construction of multipurpose court, levelling and preparing the layer of good earth on the play ground in Delhi Police Public School at PTS, Wazirabad, Delhi 30/06/2019 29/08/2019 26.71 (Mar'21) 0.00 (Mar'21)

work in progress

Detail Report
Graph / Photo
394 Pumping out rainwater to avoid water logging at DC office complex,Weavers Complex Nand Nagri and SDM Court Seelampur Delhi. 30/06/2019 29/10/2019 5.86 (Jan'20) 0.00 (Jan'20)

work completed

Detail Report
Graph / Photo
395 A/A in Sanjay Gandhi Memorial Hospital, Mangolpuri, Delhi. (SH Renovation of ENT OPD, OST Centre, CMO room in main casualty, patient toilet in ward-4, change of floor tiles in digital X-ray room and change of windows in physiotherapy department etc. 12/09/2019 09/01/2020 16.74 (May'22) 0.00 (May'22) work is in slow progress Detail Report
Graph / Photo
396 C/o Trauma Centre and Utility Block at SGMH at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Hiring of Photocopier Machine.) 04/09/2019 03/03/2021 work in progress Detail Report
Graph / Photo
397 C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Libaspur, Delhi. 30/05/2020 29/05/2021 0.00 (Nov'21) 34.00 % (Nov'21) Structure work completed. Brick work and plastering work completed in Part-A, B, C, D and in Part -E is in progress. Boundary wall work, granite work, tile works are in progress. Detail Report
Graph / Photo
398 C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Daryapur kalan, Delhi. 30/05/2020 29/05/2021 0.00 (Nov'21) 30.00 % (Nov'21) Structure work completed. Partition work with bricks in progress. Tile, plaster and granite work is in progress. Truss work of MP Hall is in progress. Detail Report
Graph / Photo
399 C/O Pucca School Building (G+3) of Govt. Sr Sec. School (Co-Ed) at Rana Pratap Bagh (School ID: 13091907), Delhi.(SH: Main Civil Work). 02/09/2020 29/05/2021 0.00 (Nov'21) 39.00 % (Nov'21) Structure work of building completed, Plaster work & brick completed. Water proofing work completed, Granite work and tile work completed. Toilet fittings, C.I. Work, CPVC work, painting work is in progress. False ceiling, SS work and Boundary wall work in progress. Detail Report
Graph / Photo
400 Bhola Nath Nagar, No.3-GGSSS (ID : 1001023) (DIET BUILDING) 17/03/2019 11/12/2019 0.00 (Jan'21) 1.00 % (Jan'21) Cleaning in progress. Inventory submitted to HOS to 20.05.2022 Detail Report
Graph / Photo
401 Jhilmil Colony-SBV Avinash Chadda (ID: 1001105 ) (Addl. Rooms) 01/04/2022 24/02/2023 Demolition work is in progress. 90% demolition completed and Layout for excavation has done in A C C GSBV at Jhilmil Colony, Delhi. Detail Report
Graph / Photo
402 Consultancy Services for Construction (on EPC mode) of New Block for expansion of Deen Dayal Upadhyay Govt. Hospital of Hari Nagar, Delhi. 28/05/2020 27/11/2022 WORK IN PROGRESS Detail Report
Graph / Photo
403 Providing vehicle on hire charge basis for official purpose 25/02/2022 24/02/2023 Work in progress. Detail Report
Graph / Photo
404 Construction of 16 Nos. additional SPS class rooms (G+3) in GGSSS, Qadipur, Delhi ( Sch Id 1309265) (SH: C/o main SPS type building including internal & external water supply, sanitary installation, electrical installations, development of site i/c Fire fighting system etc. at GGSSS Qadipur Delhi -110036. (Sch. ID: 1309265) 14/04/2022 11/10/2022 Work in progress. Detail Report
Graph / Photo
405 Constn. of Peripheral wall around the A, B ,C and D Type in the residential campus, GTB Hospital, Shahdara, Delhi 20/03/2022 19/07/2022 Work not started yet. Detail Report
Graph / Photo
406 Renovation of Girls common Room, Boys common Room and Drivers Room ground Floor of UCMS College GTB Hospital, Shahdara, Delhi 20/03/2022 05/05/2022 Work is in progress Detail Report
Graph / Photo
407 Mechanized cleaning of Underground and Overhead RCC/ PVC water storage tanks at Rajiv Gandhi Super Specialty Hospital, Tahirpur, Delhi. 26/04/2022 25/04/2023 Work in progress. Detail Report
Graph / Photo
408 Urgent Misc Civil repairing work in CMO Room No. 56 and 56A at GTB Hospital, Shahdara, Delhi for preparation of 3rd wave of COVID-19 02/03/2022 02/04/2022 Work is in progress Detail Report
Graph / Photo
409 Construction of Additional 17 nos Class room with Light Gauge Steel Framed structure including electrical installations & Providing and erecting 2.00 metre high temporary wall with precoated galvanised iron profile sheets at SBBM, SV Shankaracharya Marg , Delhi 14/04/2022 13/07/2022 Work could not be started due to pending decision of DDE for partition wall between two schools. Detail Report
Graph / Photo
410 Repair of IHBAS side Impaired Wall From start of Girls hostel to end of Nurse hostel in residential campus, GTB Hospital, Shahdara, Delhi 22/05/2022 11/06/2022 Work in progress. Detail Report
Graph / Photo
411 Waterproofing and urgent repairing of damaged deteriorated RCC OH tank on roof of Block-5 and Block-3 in Rajiv Gandhi Super Specialty Hospital Tahirpur, Delhi. 03/05/2022 30/06/2022 Not started yet. Detail Report
Graph / Photo
412 Refurbishment of damaged RCC Beam, Projections, Vertical fins and Chajja at External face of Old Boys Hostel block in residential campus at Guru Teg Bahadur Hospital, Shahdara, Delhi. 22/05/2022 21/08/2022 Work is in progress Detail Report
Graph / Photo
413 Renovation of damage toilet block of Ground Floor 1st floor and 2nd floor toilet of ITI Narela with other misc Works at ITI Narela Delhi 08/03/2022 06/05/2022 Work in progress Detail Report
Graph / Photo
414 Providing Security and Disaster Management Arrangement at Rouse Avenue Court Complex, DDU Marg, New Delhi. (SH: Providing Steel Wire Fabric, Barbed Wire Fencing with Concertina Coil, MS Barricading and Emergency Evacuation Plan). 10/01/2022 10/04/2022 Work is in progress Detail Report
Graph / Photo
415 Providing and Fixing of MS Gate at Main Entrances of Hospital, Low Height Gate at Entrance of RRC Centre and Gate for PSA Rajiv Gandhi Super Specialty Hospital, Tahirpur, Delhi 05/01/2022 19/02/2022 Work in progress. Detail Report
Graph / Photo
416 Renovation of FNA OPD (Room No. 130) 1st floor at GTB Hospital, Shahdara, Delhi 04/01/2022 03/02/2022 Work is in progress Detail Report
Graph / Photo
417 Hiring of Inspection Vehicle along with Driver in the office of Executive Engineer Health Project Division (East), PWD, Tahirpur, Delhi during 2021-22 10/02/2022 09/11/2022 Work is in progress. Detail Report
Graph / Photo
418 Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site , RWHS, STP , Furniture etc at Ladpur Village . (SH:- Civil & Electrical composite work). 18/07/2021 17/07/2022 Work could not be started due to change in Architectural drawing by the then Hon'ble PWD Minister. Fire NOC issued on dt. 13.05.2022. Local body approval is awaited. Detail Report
Graph / Photo
419 Hiring of Inspection Vehicle along with Driver for LBS Hospital Project work in the office of Assistant Engineer Health Project Sub-Division (East)-III, PWD, Khichripur, Delhi-110091 during 2021-22 29/01/2022 28/10/2022 Work is in progress. Detail Report
Graph / Photo
420 Construction of Peripheral wall around the A, B ,C and D Type in the residential campus, GTB Hospital, Shahdara, Delhi 20/03/2022 19/07/2022 Work not started yet. Detail Report
Graph / Photo
421 Provision of Wiremess door, flush door, SS Grills, Aluminum work and others misc civil work of the Nurse Hostel of Residential Campus, GTB Hospital, Shahdara, Delhi 21/02/2022 04/04/2022 Work is in progress Detail Report
Graph / Photo
422 Providing Services of Computer Operator, MTS etc. under various PWD Offices of North Building Division and office of SA North 01/02/2022 26/01/2023 Work in progress Detail Report
Graph / Photo