Building - Construction Workभवन - रखरखाव का कार्य
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 Civil work and Internal E.I. work 24/04/2007 23/07/2009 300221271.00 Globe Civil Project Pvt. Ltd. Detail Report
Graph / Photo
2 C/o 700 Beds Indira Gandhi Hospital at Sector-9, Dwakra, New Delhi on turn-key basis 27/08/2014 26/02/2017 54511.43 0.00 (Jan'21) 93.00 % (Jan'21) Larson & Toubro Limited Internal finishing work like Granite flooring, Granite dado, Cement plaster, Ceramic wall tile, Vitrified flooring tile, False ceiling, underdeck insulation, Door frame & shutter is in progress. External finishes work like M.S. Backup structure, Dry stone Cladding work, Structural Glazing work is in progress. Apart from above S.S. Railing work, vinyl flooring base preparation, Mortuary block fabrication & erection work in progress. Various medical & non-medical services are required for completion. R.P.E. submitted for accord of A/A & E/S. Detail Report
Graph / Photo
3 Construction of New Block For Medicine, Maternity And Advanced Pediatric Centre ( Composite Steel plus RCC framed 2B plus G plus 22 Storyed building At LN Hospital including internal water supply, Sanitary installation, External Development works, Dr 04/11/2020 03/05/2023 46552.58 Swadeshi Civil Infrastructure Pvt. Ltd., 302, DLF Tower B Jasola, New Delhi-110025 Execution of D-wall is under progress. Detail Report
Graph / Photo
4 CONSTRUCTION OF NEW HOSPITAL AT SIRASPUR, NEW DELHI (ON EPC MODE -I) INCLUDING ALL CIVIL, ELECTRICAL, MECHANICAL, HORTICULTURE AND MEDICAL SERVICES. 10/08/2020 09/05/2023 38439.53 Ramacivil India Construction Private Limited work in progress Detail Report
Graph / Photo
5 Construction of Hospital at Madipur, New Delhi 11/11/2020 10/11/2022 26970.58 Ramacivil India Construction Private Limited Excavation, PCC & water proofing membrane work in progress. Detail Report
Graph / Photo
6 Construction of Hospital at Jwalapuri, New Delhi 07/08/2020 06/08/2022 26950.37 0.00 (Nov'20) 3.00 % (Nov'20) Parnika Commercial and Estates Pvt. Ltd. Cutting binding & RCC for raft and colomn. Laying of water proofing membrane. Detail Report
Graph / Photo
7 C/o East Delhi Campus of Guru Gobind Singh Indraprastha University at Surajmal Vihar, Shahdara, Delhi SH Co Academic Bldg, Auditorium Bldg, Sports Hall, Boys, Girls, Teachers Hostel, Type II III IV and V Qtrs ic Ext Dev. works, Int Elect Inst, Ext Lighting, lifts, fire fighting system, fire alarm with PA System, D.G. Sets, Elect Sub Stn, HVAC works 09/08/2017 09/11/2019 23127.43 0.00 (Jan'21) 78.00 % (Jan'21) NKG Infrastructure Limited Physical Progress of the work is 82%. Detail Report
Graph / Photo
8 C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road, Delhi (SH: C/o Academic Blocks AB-3 & AB-4, Boys Hostel H-5 & Girls Hostels HG-5 & HG-6 and all external and internal services including external development and landscaping, and allied civil and E&M works). 23/09/2019 23/12/2020 22769.91 0.00 (Jan'21) 5.00 % (Jan'21) SAM India Builtwell Progress of work is 55% Detail Report
Graph / Photo
9 Additional and Remodeling Work for Cancer Block, Maternity Block and Screening OPD At Satyawadi Raja Harish Chandra Hospital, Narela For Delhi Govt. (Delhi) 09/08/2020 08/05/2023 21785.66 Parnika Commercial and Estates Pvt. Ltd. Work in progress Detail Report
Graph / Photo
10 Construction of 144 Nos Temporary Courtroom in the existing court complexes of Saket Stilt plus 3 Tis Hazari Stilt plus G plus 3 and Karkardooma G plus 4 04/10/2019 03/07/2020 14316.00 0.00 (Jan'21) 62.00 % (Jan'21) Quality Buildcon Pvt. Ltd. Work is in progress at all the three sites. In Karkardooma, the structure work upto 3rd floor level completed and part 4th level slab also casted. Activities pertaining to providing of internal walls, electrical conduits, fire fighting lines, fire paint, HVAC and other related activities in progress. The work of creating sample rooms for Court room, Judges chamber, PA room and Alhmad room etc. also taken up. The columns for 4th floor & terrace level also erected and fixing of deck sheet at remaining portion of 4th floor level in progress. In Saket, Bolck-1: Casting of Grade slab, 1st floor & 2nd floor slab completed. Erection of 3rd stage columns in progress. Fabrication and erection of beams and columns from 3rd to 5th floor also in progress. Block-2 (near lockup block): Casting of Grade slab, 1st floor & 2nd floor slab completed. Erection of 3rd stage columns in progress. Fabrication and erection of beams and columns from 3rd to 5th floor also in progress. In Tis Hazari, the casting of slab upto X-- 7 grade completed and now placing of reinforcement at 2nd floor level in progress. The fixing of beams at 2nd & 3rd floor level completed and is in progress at 1st floor level. Casting of Grade slab and plinth beams at ground floor level complete except toilet block and pump room area. All the beams upto 3rd floor level fabricated and available at site. Fabrication of 4th stage columns (upto floor 5 level) also started and erection work to be taken up shortly. Detail Report
Graph / Photo
11 Addition & Remodelling work for Bhagwan Mahavir Hospital at Pitampura Delhi including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 10/12/2019 01/06/2020 13992.80 Kamladitya Construction Private Limited Work in progress Detail Report
Graph / Photo
12 Construction of New Building S Block for Delhi High Court on 2.74 acre land at Bapa Nagar Zakir Hussein Marg New Delhi SH C o RCC framed structure Building including water supply sanitary Electrical installation and E&M Services 02/03/2017 01/09/2019 13770.69 12311.35 (Mar'21) 0.00 (Mar'21) Swadeshi Civil Infrastructure Pvt. Ltd., 302, DLF Tower B Jasola, New Delhi-110025 Work in progress Detail Report
Graph / Photo
13 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 18/10/2019 10/04/2021 13447.15 0.00 (Jan'21) 18.00 % (Jan'21) Roshan Real Estate Pvt Ltd. Work is under progress. Detail Report
Graph / Photo
14 Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 04/03/2020 03/09/2021 10708.84 Quality Buildcon Pvt. Ltd. work in progress Detail Report
Graph / Photo
15 SKV Madanpur Khadar, School ID: 1925062 14/01/2019 10/10/2019 7836.66 0.00 (Mar'21) 75.00 % (Mar'21) BCC DEVELOPERS AND PROMOTERS PVT LTD Work is in progress Detail Report
Graph / Photo
16 C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 04/09/2019 03/03/2021 7122.09 PNSC Infrastructure Pvt. Ltd work in progress. Detail Report
Graph / Photo
17 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 06/08/2019 29/10/2020 6563.40 0.00 (Jan'21) 15.00 % (Jan'21) PNSC Infrastructure Pvt. Ltd Work is under progress. Detail Report
Graph / Photo
18 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 324 nos. SPS type class rooms, Libraries, Toilets, Labs & 2 Nos. M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. under Edu. M. Division (West) at GGSSS No. 1 Khyala, SKV No. 2 Khyala, SBV Chand Nagar, Govt. (Co-Ed) S. S. J. J. Colony Raghubir Nagar & GGSSS J.J. Colony Raghubir Nagar New Delhi [Package-A]. 13/01/2019 23/12/2019 6019.45 7180.66 (Jan'21) 81.00 % (Jan'21) SPG Infraprojects Private Limited Work is in progress. Detail Report
Graph / Photo
19 C/o of 316 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, development of site and fire fighting arrangements etc. at GBSSS E Block Sultanpuri (School ID 1412086), SKV H Block Sultanpuri (School ID 1412029), Govt. (Co-ed) Sec. School Sultanpur Majra (School ID 1412016), SKV Block-Q, Mangolpuri (School ID 141208). (Package-VIII). 14/01/2019 09/11/2019 5752.21 0.00 (Mar'21) 87.00 % (Mar'21) SPG Infraprojects Private Limited Work in progress Detail Report
Graph / Photo
20 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 288 nos. SPS type class rooms, Libraries, Toilets, Labs & 4 Nos. M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. under Education M. Division (West) at GBSSS Shadi Khampur, SKV Shadi Khampur, GBSSS West Patel Nagar, GGSSS West Patel Nagar & SBV West Patel Nagar New Delhi [Package-I]. 13/01/2019 23/12/2019 5688.38 1535.90 (Jan'21) 61.00 % (Jan'21) Winner Construction Pvt. Ltd. Work is in progress. Detail Report
Graph / Photo
21 C/o 316 Nos Additional SPS Classrooms Labs, M.P. Hall, Toilets and Staircases, internal water supply, sanitary installations, drainage, electrical installation, development of site and fire-fighting arrangements etc. in SV- Kailash Enclave(School ID 1411005), GGSSS-Anandvas (School ID 1411038),GGSSS A-Block Saraswati Vihar (School ID 1411042) and GGSSS, Kohat Enclave, Anandvas (School ID 1411046). (Package-4) 14/01/2019 09/11/2019 5653.04 3954.15 (Mar'21) 82.00 % (Mar'21) SPG Infraprojects Private Limited Work in progress Detail Report
Graph / Photo
22 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 304 nos. SPS type class rooms, Libraries, Toilets, Labs & 2 Nos. M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. under Education M. Division (West) at SKV Ranhaula, Govt. (Co-Ed) SS Hiran Kudna, SKV Nilothi, SKV Jwalapuri Amalwas, Govt. (Co-ed) SS Ranhaula Kunwar Singh Nagar & GSKV Shiv Ram Park Nangloi at New Delhi [Package-D]. 13/01/2019 23/12/2019 5561.05 0.00 (Jan'21) 97.00 % (Jan'21) B. L. Infra Projects Pvt. Ltd. Work is in progress. Detail Report
Graph / Photo
23 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 296 nos. SPS type class rooms, Libraries, Toilets, Labs & 3 Nos. M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. under Education M. Division (West) at SBV Ashok Nagar, GGSSS Ashok Nagar, SBV Subhash Nagar, GBSSS Rajouri Garden Extn., SKV Rajouri Garden Extn., SKV Rajouri Garden Main., SKV-No.2 Tagore Garden, GBSSS Tagore Garden New Delhi [Package-L] 13/01/2019 23/12/2019 5485.49 4611.46 (Jan'21) 74.00 % (Jan'21) A. K. Mehta & Co. Work is in progress. Detail Report
Graph / Photo
24 GGSSS No. 1, Molarband School ID : 1925401 14/01/2019 10/10/2019 5268.41 0.00 (Mar'21) 48.00 % (Mar'21) Subham Builders Work is in progress Detail Report
Graph / Photo
25 GGSSS Tajpur Pahari, School ID : 1925359 14/01/2019 10/10/2019 5139.81 0.00 (Mar'21) 53.00 % (Mar'21) Subham Builders Work is in progress Detail Report
Graph / Photo
26 C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) 14/01/2019 09/11/2019 4874.05 2114.44 (Mar'21) 60.00 % (Mar'21) Shri kamal singh Work in progress Detail Report
Graph / Photo
27 C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) 20/01/2019 15/11/2019 4603.38 1495.28 (Mar'21) 56.00 % (Mar'21) Sh. Kamal Singh Work in progress Detail Report
Graph / Photo
28 GGSSS No. 1, East of Kailash, School ID: 1924032 23/01/2019 19/10/2019 4586.20 0.00 (Mar'21) 88.00 % (Mar'21) IQBAL CONSTRUCTION CO. Work is in progress Detail Report
Graph / Photo
29 SKV New Friends Colony, School ID 1925033 23/01/2019 19/10/2019 4224.32 0.00 (Mar'21) 94.00 % (Mar'21) Subham Builders Work is in progress Detail Report
Graph / Photo
30 Co 232 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 12 13/01/2019 09/10/2019 4150.23 0.00 (Mar'21) 92.00 % (Mar'21) K.B.G. Engineers

Work in progress.

Detail Report
Graph / Photo
31 C/o of 236 Nos. Additional SPS Class rooms, MP Hall, Labs, Toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at Rani Khera S (Co-ed) ( School ID 1412095), SBV Sawada Ghevra (School ID 1413323 ) and SV Ghevra (School ID 1413003) (Package -10) 20/01/2019 16/10/2019 4125.76 2605.23 (Mar'21) 84.00 % (Mar'21) M/s K.B.G. Engineers Work in progress Detail Report
Graph / Photo
32 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 208 nos. SPS type class rooms, Libraries, Toilets, Labs & 2 No. M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. under Education M. Division (West) at GGSSS No-2 Uttam Nagar, SKV Uttam Nagar, G(Co-Ed)SS Vikas Nagar & GBSSS KG-I/III Vikaspuri New Delhi [Package-E]. 18/01/2019 13/12/2019 3891.02 0.00 (Jan'21) 76.00 % (Jan'21) Aadhar Stumbh Township Pvt. Ltd. Work is in progress. Detail Report
Graph / Photo
33 C/o 204 Nos. Additional SPS Class rooms including Labs, M.P. Hall, Toilets and Staircases, internal water supply, sanitary installations, drainage, electrical installation, development of site and fire fighting arrangements etc. at GBSSS, Prashant Vihar (ID- 1413016) and Govt. Co-ed Sr. Sec. School Sector -08 Rohini Delhi (ID- 1413027) (Package -V). 20/01/2019 16/10/2019 3731.99 0.00 (Mar'21) 89.00 % (Mar'21) M/s K.B.G. Engineers Work in progress Detail Report
Graph / Photo
34 Co 212 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 3 16/03/2019 10/12/2019 3708.98 2321.34 (Mar'21) 65.00 % (Mar'21) M/s K B G Engineers

Work in progress.

Detail Report
Graph / Photo
35 Const 182 Nos. of additional SPS class rooms (Package-C) 17/03/2019 11/12/2019 3699.32 2205.21 (Feb'21) 0.00 (Feb'21) SPS Infrabuild Pvt. Ltd. Work is in Progress. Detail Report
Graph / Photo
36 Const 190 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 24/12/2018 19/09/2019 3675.76 13098.31 (Feb'21) 0.00 (Feb'21) RAMA Contractor Work is in Progress. Detail Report
Graph / Photo
37 Const 180 Nos. of additional SPS class rooms (Package-B) 17/03/2019 11/12/2019 3636.43 1146.09 (Nov'20) 0.00 (Nov'20) RAMA Contractor Work is in Progress. Detail Report
Graph / Photo
38 SKV Begumpur, School ID: 1923057 23/01/2019 19/10/2019 3607.51 0.00 (Mar'21) 53.00 % (Mar'21) Subham Builders Work is in progress Detail Report
Graph / Photo
39 Const 174 Nos. of additional SPS class rooms in various schools (Package-E) 17/03/2019 11/12/2019 3553.31 12491.60 (Nov'20) 0.00 (Nov'20) SPS Infrabuild Pvt. Ltd. Work is in Progress. Detail Report
Graph / Photo
40 Up gradation and Construction of an additional multi- story building in the premise of Forensic Science Laboratory, Rohini, Delhi. 14/11/2019 13/02/2021 3541.69 Tewatia Construction Pvt. Ltd. work in progress Detail Report
Graph / Photo
41 C/o 232 Nos. of additional SPS class rooms in various schools under North Education Division, PWD Delhi including internal & external water supply, sanitary installation, electrical installations, development of site and fire fighting system etc. (Package - 9) 17/03/2019 11/12/2019 3526.08 2096.20 (Mar'21) 86.00 % (Mar'21) Satish Chand & Rajesh Kumar Pvt. Ltd.

Work in progress.

Detail Report
Graph / Photo
42 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 192 nos. SPS type class rooms, Libraries, Toilets, Labs & 2 Nos. M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc, under Education M. Division (West) at SBV No.1 Tilak Nagar, SBV No.2 Tilak Nagar, GGSSS No.1 Tilak Nagar, SKV No. 3 Tilak Nagar & SBV Block-A Vikaspuri New Delhi [Package-J]. 13/01/2019 09/10/2019 3522.95 0.00 (Jan'21) 94.00 % (Jan'21) Tewatia Construction Pvt. Ltd. Work is in progress. Detail Report
Graph / Photo
43 Const 184 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW 17/03/2019 11/12/2019 3455.84 12491.60 (Nov'20) 0.00 (Nov'20) RAMA Contractor Work is in Progress. Detail Report
Graph / Photo
44 C/o of 196 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases including internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Nithari (School ID 1412093) and GGSSS Mubarakpur Dabas (School ID 1412133 ).(Package VI) 20/01/2019 16/10/2019 3448.67 3578.03 (Mar'21) 97.00 % (Mar'21) K.B.G.Engineers Work in progress Detail Report
Graph / Photo
45 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II.(Package-F) 27/01/2019 23/10/2019 3347.23 1995.62 (Feb'21) 64.00 % (Feb'21) BCC DEVELOPERS AND PROMOTERS PVT LTD Work in progress. Detail Report
Graph / Photo
46 Co 180 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 10 17/03/2019 11/12/2019 3304.27 2521.33 (Mar'21) 72.00 % (Mar'21) Tewatia Construction Pvt. Ltd.

Work in Progress.

Detail Report
Graph / Photo
47 Co 196 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 2 20/01/2019 16/10/2019 3303.39 3466.89 (Mar'21) 0.00 (Mar'21) Tewatia Construction Pvt. Ltd. Work in progress. Detail Report
Graph / Photo
48 C/o of 172 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases including internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Sector 20, Rohini Ext. Pooth Kalan (School ID 1412084) GGSSS Block D Sultanpuri (School ID 1412088 ) and GGSSS P- Block Sultanpuri (School ID 1412019). (Package-VII) 14/01/2019 10/10/2019 3101.08 2186.81 (Mar'21) 91.00 % (Mar'21) The Krishna Construction Co. Work in progress Detail Report
Graph / Photo
49 Co 180 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 6 20/01/2019 16/10/2019 3051.32 2017.73 (Mar'21) 89.00 % (Mar'21) M/s K B G Engineers

Work in progress.

Detail Report
Graph / Photo
50 SKV Sangam Vihar J Block Sch. ID 1923346 17/03/2019 11/12/2019 3002.10 0.00 (Mar'21) 28.00 % (Mar'21) Devinder Singh In progress Detail Report
Graph / Photo
51 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Dariyapur Kalan, Delhi 30/05/2020 29/05/2021 2936.58 0.00 (Mar'21) 13.00 % (Mar'21) Tewatia Construction Pvt. Ltd.

Casting of footing in progress.

Detail Report
Graph / Photo
52 Construction of Pucca School Building G plus 3 with ancillary facilities including internal water supply sanitary installation, internal electrical installation and development of sites RWHS STP etc at Sector 05 Rohini Delhi 29/05/2020 28/05/2021 2931.78 0.00 (Mar'21) 7.00 % (Mar'21) The Krishna Construction Co. Work in progress Detail Report
Graph / Photo
53 SH Co 169 Nos. of additional SPS class rooms at Sarvodaya Co.Ed SSS Munirka Sch. ID 1719125 G Co.ed MS C4 Vasant Vihar Sch. ID 1720174 SV Vasant Vihar Sch. ID 1720024 and G Co.Ed SV, Sector 13 R.K.Puram Sch. ID 1719130 under Education Maint. SW 17/10/2019 12/07/2020 2849.35 2.19 (Feb'21) 1.13 % (Feb'21) A. K. Builders work in progress. Detail Report
Graph / Photo
54 SBV Yogi Arvind, School ID: 1923005 14/01/2019 10/10/2019 2844.79 0.00 (Mar'21) 65.00 % (Mar'21) Devinder Singh Work is in progress Detail Report
Graph / Photo
55 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 148 nos. SPS type class rooms, Libraries, Toilets, Labs & 2 Nos. M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. under Education M. Division (West) at SKV No. 2 Madipur, GGSSS No. 1 Madipur, SV(Co.Ed.) A-2 Paschim vihar, SV(Co-Ed) New Multan Nagar New Delhi [Package-C]. 13/01/2019 09/10/2019 2816.66 0.00 (Jan'21) 81.00 % (Jan'21) Tewatia Construction Pvt. Ltd. Work is in progress. Detail Report
Graph / Photo
56 Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. 28/06/2019 22/06/2020 2806.33 Roshan Real Estate Pvt Ltd. Work started Detail Report
Graph / Photo
57 C/o 168 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, STP, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV No.-2 Shakurpur (ID-1411030) (Package-2) 15/01/2019 11/10/2019 2788.70 1129.07 (Mar'21) 51.00 % (Mar'21) RAMA Contractor Work in progress Detail Report
Graph / Photo
58 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Libaspur, Delhi 30/05/2020 29/05/2021 2653.59 0.00 (Mar'21) 18.00 % (Mar'21) Tewatia Construction Pvt. Ltd.

Work in progress.

Detail Report
Graph / Photo
59 Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site, RWHS, STP, Furniture etc at Sector 18, Rohini. (SH: Civil and Electrical Composite Work). 23/05/2020 23/05/2021 2606.13 0.00 (Feb'21) 4.00 % (Feb'21) Tewatia Construction Pvt. Ltd. Work in progress Detail Report
Graph / Photo
60 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II. SH: C/o 148 Nos. of additional SPS class rooms at GBSSS, J.J Camp, Naraina (School ID-1720015) & SBV, Nairana (School ID-1720002) & SBV under Education Maintenance South West Division, PWD Delhi including internal & external water supply, sanitary installation, electrical installations, development of site and fire fighting system etc. (Package-E). 15/01/2019 11/09/2019 2578.40 2008.49 (Feb'21) 90.00 % (Feb'21) Raghav Engineers Work in progress. Detail Report
Graph / Photo
61 Construction of two Cluster Bus Depots including boundary wall at Sector-37, Rohini, Delhi. 06/10/2018 31/08/2019 2553.10 0.00 (Mar'21) 94.00 % (Mar'21) Ramacivil India Construction Private Limited Boundary wall, Admn. block, Restroom, Toilet block & Workshop block and Hard standing works are in progress. Detail Report
Graph / Photo
62 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II. 15/01/2019 11/09/2019 2524.95 2553.99 (Feb'21) 99.00 % (Feb'21) ARIHANTBUILDERS Work in progress Detail Report
Graph / Photo
63 Co 148 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 13 13/01/2019 09/09/2019 2518.71 1375.08 (Mar'21) 70.00 % (Mar'21) Pawan Kumar

Work in progress.

Detail Report
Graph / Photo
64 SKV Hari Nagar, Ashram, School ID : 1924043 14/01/2019 10/09/2019 2464.23 0.00 (Mar'21) 38.00 % (Mar'21) Reliance Elektrik works Work is in progress Detail Report
Graph / Photo
65 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 144 nos. SPS type class rooms, Libraries, Toilets, Labs & 1 no M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at Govt. Schools SKV Basai Darapur, Govt. Co-Ed SSS Industrial Area Karampura & SKV Ranjit Nagar New Delhi [Package-H]. 09/01/2019 05/09/2019 2458.51 0.00 (Jan'21) 86.00 % (Jan'21) ARIHANTBUILDERS Work is in progress. Detail Report
Graph / Photo
66 Co 136 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 1 20/01/2019 16/09/2019 2420.66 0.00 (Mar'21) 67.00 % (Mar'21) M C Constructions Company

Work in Progress.

Detail Report
Graph / Photo
67 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II. SH: C/o 162 Nos. of additional SPS class rooms at G Co.Ed.SS, Sec-16A, Dwarka (School ID-1821242), Shahid Captain Amit Verma Govt. S(Co.Ed)V, Inderpuri (School ID-1720121) & SKV, Rajnagar-I (School ID-1824027) under Education Maintenance South West Division, PWD Delhi including internal & external water supply, sanitary installation, electrical installations, development of site and fire fighting system etc. (Package-H) 19/12/2018 15/08/2019 2420.05 1828.68 (Feb'21) 90.50 % (Feb'21) Multi Tech Construction Co. Work in progress. Detail Report
Graph / Photo
68 Co 152 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 5 08/12/2018 04/08/2019 2395.22 1980.93 (Mar'21) 92.00 % (Mar'21) RAJIV AGGARWAL

Work in progress.

Detail Report
Graph / Photo
69 Co 124 Nos of additional SPS classrooms at various schools under North Education Division PWD Delhi including internal external water supply....... Package-11 17/01/2019 13/09/2019 2349.00 2119.64 (Mar'21) 82.00 % (Mar'21) M/s Munshi Ram Kharbanda

Work in progress.

Detail Report
Graph / Photo
70 SBV Jonapur, School ID: 1923359 08/12/2018 04/08/2019 2342.87 0.00 (Feb'21) 62.00 % (Feb'21) Reliance Elektrik works In progress Detail Report
Graph / Photo
71 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 136 nos. SPS type class rooms, Libraries, Toilets, Labs & 1 no M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at S.V. East Punjabi Bagh, GBSSS No. 1 Punjabi Bagh, SKV No-2 Punjabi Bagh New Delhi [Package-B]. 09/01/2019 06/09/2019 2337.95 1952.54 (Feb'21) 0.00 (Feb'21) Satya Narain Work is in progress. Detail Report
Graph / Photo
72 SKV (Gargi) Green Park Extension, School ID: 1925032 08/12/2018 04/08/2019 2319.71 0.00 (Mar'21) 89.00 % (Mar'21) Devinder Singh Work is in progress Detail Report
Graph / Photo
73 RPVV Lajpat Nagar, School ID : 1925334 08/12/2018 04/08/2019 2303.62 0.00 (Mar'21) 68.00 % (Mar'21) Reliance Elektrik Works, Work is in progress Detail Report
Graph / Photo
74 C/o 143 Nos. of additional SPS class rooms at G(co.ed)SSS, Pochanpur (School ID-1821037) , SBV Bijwasan (Bharthal) (School ID-1821032)& GGSSS Bijwasan Bharthal Road, (School ID-1821035) under Education Maintenance SouthWest Division, PWD Delhi. (Package-G) 15/01/2019 11/09/2019 2237.55 2238.31 (Feb'21) 90.00 % (Feb'21) JAP BUILDCON PRIVATE LIMITED Work in Progress Detail Report
Graph / Photo
75 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 148 nos. SPS type class rooms, Libraries, Toilets & Labs etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at Govt. Schools SKV No. 2 C-Block Janakpuri, GGSSS No. 2 A-Block Janakpuri, SV(Co. Ed.) L-Block Hari Nagar, GBSSS Site-2 Clock Tower Hari Nagar New Delhi [Package-K]. 07/12/2018 04/08/2019 2234.81 0.00 (Jan'21) 90.00 % (Jan'21) Multi Tech Construction Co. Work is in progress. Detail Report
Graph / Photo
76 Construction of DTC Bus Depot at Ghumanhera 18/05/2018 17/11/2018 2161.87 790.60 (Feb'21) 0.00 (Feb'21) Satya Narain nearly completed. Detail Report
Graph / Photo
77 C o 138 Nos Addl SPS Classrooms in GGSSS Rani Bagh Sch ID 1411043 GGSSS Trinagar Narang Colony Sch ID 1411037 ic Lab staircases toilets and ramps internal water supply sanitary installations internal electrification and fire fighting arrangements 01/03/2019 26/09/2019 2120.02 1239.34 (Mar'21) 72.00 % (Mar'21) The Krishna Construction Co. Work in progress Detail Report
Graph / Photo
78 Co 132 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 4 08/12/2018 04/08/2019 2115.52 2041.98 (Mar'21) 91.00 % (Mar'21) Rajiv Aggarwal

Work in progress.

Detail Report
Graph / Photo
79 S.K.V. Andrews Ganj, School ID : 1924033 08/12/2018 04/08/2019 2112.37 0.00 (Mar'21) 99.00 % (Mar'21) Devinder Singh Work is in progress Detail Report
Graph / Photo
80 Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site , RWHS, STP etc at Ladpur Village (SH:- Civil & Electrical composite work). 29/05/2020 28/05/2021 2053.72 Shree construction Co Foreclosed vide this office letter no. 1374-H dated 31.12.2020 Detail Report
Graph / Photo
81 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II. 15/01/2019 11/09/2019 2001.74 1123.58 (Feb'21) 66.00 % (Feb'21) M/S Sunehari Bagh Builders Pvt. Ltd. Work in progress. Detail Report
Graph / Photo
82 GGSSS Dera Village School ID: 1923023 08/12/2018 04/08/2019 1877.31 844.70 (Feb'21) 63.00 % (Feb'21) Varun Gupta & Co. In progress Detail Report
Graph / Photo
83 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 31/05/2020 30/05/2021 1874.70 0.00 (Feb'21) 2.00 % (Feb'21) SSP Promoters and Builders Private Limited Work in progress Detail Report
Graph / Photo
84 Furniture Work RECALL 04/11/2019 18/12/2019 1858.08 Rajdhani Furnitures PVT. LTD. Detail Report
Graph / Photo
85 Co. 104 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi incl int. and external water supply fire fighting system etc. Pkg 7 14/01/2019 10/09/2019 1812.55 0.00 (Mar'21) 86.00 % (Mar'21) Raghav Engineers

Work in progress

Detail Report
Graph / Photo
86 Const. of 112 Nos. addl SPS classrooms GGSS, Mukundpur Village Sch. ID 1207230 - 36 Nos., GBSSS Bakhtawarpur Sch. ID 1309266 -56 Nos. incl. 01 No. M.P Hall Equi. to 08 Nos. Class Rooms and SV Lancer Road Sch. ID 1207032 -20 Nos. under North Edu. Divn 08/06/2019 02/02/2020 1799.01 1269.55 (Mar'21) 63.00 % (Mar'21) C. PARKASHAN Co.

Work in progress

Detail Report
Graph / Photo
87 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 104 nos. SPS type class rooms, Libraries, Toilets, Labs & 1 no M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at SKV Sultan Puri Road, Nangloi, SKV B-3 Paschim Vihar New Delhi [Package-F]. 09/01/2019 06/09/2019 1782.55 0.00 (Jan'21) 98.00 % (Jan'21) Satya Narain Work is in progress. Detail Report
Graph / Photo
88 C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) 29/12/2018 26/07/2019 1743.19 1398.76 (Mar'21) 61.00 % (Mar'21) AMAR CONSTRUCTION COMPANY Work in progress Detail Report
Graph / Photo
89 C/o Additional SPS Class rooms in various schools under Priority-II. SH : C/o 88 nos. SPS type class rooms, Libraries, Toilets, Labs & 1 no M.P. Hall etc. including internal & external water supply, sanitary installation, electrical installation, firefighting system and development of site etc. at SV Jaidev Park, SBV Moti Nagar & SKV Moti Nagar New Delhi [Package-G]. 09/01/2019 06/08/2019 1637.88 0.00 (Jan'21) 89.00 % (Jan'21) Y D Builders and hotels pvt. ltd Work is in progress. Detail Report
Graph / Photo
90 Development of Synthetic Athletic Track with Football field and Synthetic Hockey Turf in Rajiv Gandhi Sports Complex Singhu Delhi 08/03/2021 02/11/2021 1583.17 Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 Financial bids openend & approved. PG letter issued to the agency on 27.02.2021, PG in form of Bank Guarantee submitted by the agency on 03.03.2021 & same is under verification from Bank. Detail Report
Graph / Photo
91 Construction of 92 Nos Additional SPS Classrooms in SV Co ed Sector 7 Rohini School ID 1411074 including Laboratory staircases toilets and ramps internal water supply sanitary installations Internal electrification and fire fighting arrangements 30/12/2019 24/10/2020 1502.95 770.67 (Mar'21) 55.00 % (Mar'21) S.D.CONSTRUCTION COMPANY Work in progress Detail Report
Graph / Photo
92 Construction of Residential Hostel at Chhatrasal Stadium, Model Town, Delhi. (SH: Const. of Hostel Building inc. Ext. Dev. works Internal Elect. Installation External Lighting lifts firefighting system fire alarm with PASystem CCTV Audio video system HVAC works 24/02/2021 23/05/2022 1374.16 M.C. Construction Tender Under scrutiny Detail Report
Graph / Photo
93 C/o 80 Nos. of additional SPS class rooms at SKV Banger, Prahalad Pur (Sch. Id-1310032) under North Education Division, PWD Delhi including internal & external water supply, sanitary installation, electrical installations, development of site and fire fighting system etc. (Package -8) 13/01/2019 10/08/2019 1354.81 1724.01 (Mar'21) 99.00 % (Mar'21) Shree construction Co Work in progress. Detail Report
Graph / Photo
94 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at GSSS (Co ed) at Rana Pratap Bagh, Delhi 30/05/2020 29/05/2021 1335.04 176.01 (Mar'21) 25.00 % (Mar'21) The Krishna Construction Co.

Foundation work & Plinth beam completed, column to 1st floor completed, reinforcement of 1st floor beam, 1st floor slab work in progress.

Detail Report
Graph / Photo
95 GGSS No. 3 Sec IV, Ambedkar Nagar 03/03/2016 15/07/2016 1212.87 Devinder Singh completed Detail Report
Graph / Photo
96 Construction of 60 Nos G plus 3 SPS class rooms including internal and external water supply sanitary installations electrical installations development of site fire fighting system at Veer Sawarkar Arogya Sansthan, Karawal Nagar in District North 31/12/2019 25/10/2020 1112.81 149.62 (Nov'20) 0.00 (Nov'20) Mathra Dass Ahuja & Sons "Block-A : (16 Rooms) : Structure completed, finishing works are in progress. Block-B :(12 Rooms) : Structure completed, finishing works are in progress. Block-C : (20 Rooms) : Terrace floor is in progress. Block-D : (12 Rooms): 3rd floor beam is in progress. Kota stone flooring, Granite flooring, internal / External finishing and GRC tile work is in progress. Detail Report
Graph / Photo
97 Construction of 60 Nos Addl SPS Classrooms in Govt Co Ed MS Punjab Khore School ID 1413075 GGSSS including Laboratory staircases toilets and ramps internal water supply sanitary installations internal electrification and fire fighting arrangements 05/01/2020 30/10/2020 991.24 778.71 (Mar'21) 78.00 % (Mar'21) M/s Satish Builders Work in progress Detail Report
Graph / Photo
98 "Up-gradation/EOR of 802 Nos. Type-B, C & D at Timarpur Delhi. (SH:- Package-II of 410 Nos. Flats consisting of 320 Nos. Type-B, from 361 to 680 and 90 Nos. Type-C Flats) Civil Work. " 04/04/2013 03/10/2014 908.74 Devinder Singh Work Completed. Final bill yet to be submitted by agency. Detail Report
Graph / Photo
99 "Upgradation / EOR of 802 Nos. Type-B, C & D at Timarpur, Delhi. (SH:- Package-I of 392 Nos. Flats consisting of 360 Nos. Type-B, from 1 to 360 and 32 Nos. Type-D Flats) Civil Work " 04/04/2013 03/10/2014 903.01 Devinder Singh Work Completed. Final bill yet to be submitted by agency. Detail Report
Graph / Photo
100 Conversion of existing Cinder Athletic Track into 400 metres 8 lane Synthetic Athletic Track at Sports Complex located within the premises of Government Boys Sarvodaya Vidyalaya Pehladpur Delhi 04/01/2020 30/08/2020 895.64 0.00 (Jan'21) 85.00 % (Jan'21) Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 Synthetic track including marking of lane has been got completed. All accessories related with work has also been installed. Road work has also been got completed. Finishing of stonework on compound wall is yet to be done. Certificate from IAAF authorities is awaited. Physical progress is 99%. Detail Report
Graph / Photo
101 Construction of SPS Engineering office block, Girls and Boys Hostel for Foreign Students including internal electrification in NSUT Campus, Sector-3, Dwarka, New Delhi. 23/12/2019 19/06/2020 890.74 0.00 (Sep'20) 5.00 % (Sep'20) MANISH BUILDWELL Work in progress 85% Detail Report
Graph / Photo
102 Construction of 55 Nos. Aam Admi Mohalla Clinic at various locations under South-East (M), Circle, New Delhi during 2018-19. 15/12/2018 12/06/2019 827.90 290.07 (Oct'19) 17.00 % (Oct'19) S. P. Construction Work in progress Detail Report
Graph / Photo
103 Construction of Blind Hostel 96 Seated at Bal Sadan Timarpur Delhi SH Civil and Electrical work 11/01/2019 10/01/2020 786.44 989.84 (Mar'21) 0.00 (Mar'21) MANISH BUILDWELL Detail Report
Graph / Photo
104 Construction of Girls Hostel at Kalindi College, East Patel Nagar, New Delhi during 2017-18. SH Civil Works Electrical Works 16/01/2018 15/01/2019 731.25 216.46 (Mar'20) 0.00 (Mar'20) PRAGATI ENTERPRISES Detail Report
Graph / Photo
105 Co 44 Nos Addl SPS Classrooms in GGMS at Sec 24 Rohini Sch ID 1413316 in lieu of SV Wazirpur Village ic Lab. staircases toilets and ramps internal water supply sanitary installations internal electrification and fire fighting arrangements Recall 31/05/2020 03/03/2021 597.86 556.72 (Mar'21) 76.00 % (Mar'21) SUSHIL BUILDWELL PRIVATE LIMITED Work in progress Detail Report
Graph / Photo
106 Construction of 30 Nos. Aam Admi Mohalla Clinic at various places under south building (M) Division/South District. 10/01/2019 08/07/2019 585.53 91.21 (Mar'21) 0.00 (Mar'21) P S ASSOCIATES work in progress Detail Report
Graph / Photo
107 Providing and Fixing Customized Furniture and Interior works 24/09/2020 22/11/2020 533.13 0.00 (Jan'21) 15.00 % (Jan'21) M/s Rajasthan Decorators Work is in progress Detail Report
Graph / Photo
108 Construction of 30 Nos. Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under West Building Division-1, West Maintenance Circle in Assembly Constituency Mundka (AC-08), Nangloi( Full Name of work mention in NIT) 19/12/2018 18/04/2019 505.78 183.84 (Mar'20) 0.00 (Mar'20) Gee Internationals Detail Report
Graph / Photo
109 Construction of Synthetic Hockey Court at Vivekanand College, Vivek Vihar, Delhi 03/01/2020 30/06/2020 490.76 0.00 (Mar'21) 69.00 % (Mar'21) Chadha Sports (Regd.), 109, Bhagat Singh Market, New Delhi-110001 Physical Progress of the work is 90%. Detail Report
Graph / Photo
110 Co New Teaching block in DIET at Daryaganj New Delhi Sh Phase I having Lab, Library faculty room etc ic connecting staircase Civil and Electrical Work 06/06/2019 05/03/2020 485.59 232.38 (Mar'21) 0.00 (Mar'21) KALYAN CHANDRA GOYAL & CO. Detail Report
Graph / Photo
111 Construction of 30 Nos Aam Aadmi Mohalla Clinic Primary Health Centre at various places under North Building Division North Maintenance Circle in Assembly Constituency Narela Badli Adarsh Nagar and Bawana Civil Electrical 29/12/2018 27/04/2019 482.18 0.00 (Sep'20) 90.00 % (Sep'20) Jasvir Singh Shokeen Work in progress (90%) Detail Report
Graph / Photo
112 Construction of Old Age Home including Electrical Work at BG–6, Paschim Vihar, Delhi. (Composite Work). 28/06/2018 27/06/2019 479.58 424.28 (Mar'21) 0.00 (Mar'21) KALYAN CHANDRA GOYAL & CO. Work in progress 75%, Work is slow in Progress due to Covid-19 Detail Report
Graph / Photo
113 Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 30/09/2014 26/05/2015 474.90 61.36 (May'19) 0.00 (May'19) Work completed on 31/12/2017 final payment yet to be made Detail Report
Graph / Photo
114 Up gradation of one staff room, each at 951 School under Delhi Govt. (SH: - 123 Nos. of staff rooms under West Maintenance Circle). 30/03/2019 29/06/2019 433.89 171.66 (Feb'20) 0.00 (Feb'20) Sham Lal Gupta & Sons Detail Report
Graph / Photo
115 Construction of Wrestling Hall at Village Mitraon Delhi 29/12/2019 25/06/2020 363.93 0.00 (Jan'21) 26.00 % (Jan'21) SAHIL GOYAL Casting of all footings has been completed. Work is suffered for shifting of electric pole which is in the alignment of the building. The same has been shifted by BSES. Now, plinth beam, Top beam column & steel built up columns completed. Earth work in filling erection & Fabricationof tublar truss and brick work in super structure is in progress. Physical Progress is 35% Detail Report
Graph / Photo
116 Building work i/c Water Supply, Sanitary installation,Development Work and providing EI & Fire fighting system 26/05/2015 25/05/2016 316.66 Sudesh Kumar Work Suspended due to non-receipt of funds from Client Department. Detail Report
Graph / Photo
117 Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi 27/12/2018 26/04/2019 296.85 332.69 (Mar'21) 0.00 (Mar'21) Ram Krishan Yudhister Parkash

work completed

Detail Report
Graph / Photo
118 Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). 28/02/2019 27/06/2019 294.21 42.34 (Mar'21) 0.00 (Mar'21) AASRA Martech Pvt.Ltd. Work in progress. Detail Report
Graph / Photo
119 Civil and Electrical work. 05/05/2019 04/03/2020 292.64 Dheeraj Singh & Company Work just awarded Detail Report
Graph / Photo
120 Construction of Police post at Bharola Village Delhi 15/11/2019 15/07/2020 289.91 Sham Lal Gupta & Sons work is in progress (0%) Detail Report
Graph / Photo
121 Construction of G4 storey Police Post including Rain Water Harvesting Tank Underground water tank and development work at Sanjay Gandhi Transport Nagar Delhi Civil and Electrical 08/11/2019 07/07/2020 289.50 33.28 (Jan'21) 0.00 (Jan'21) Sagar Construction work is in progress (22%) Detail Report
Graph / Photo
122 Construction of 200 mtrs. Athletic Track normal size Swimming Pool, Basket ball, Volley Ball & Kabaddi Court, Toilet Block/Change room (for Boys & Girls) including E & M Services with in the Premises of Govt. Boys Sr. Sec School, Bakhtawarpur, Delhi.( SH: Package-B : C/o 200 metre Athletic Track Basket Ball Volley Ball Kabaddi Court and Boundary wall etc including E and M works. 17/09/2020 16/03/2021 286.80 0.00 (Jan'21) 10.00 % (Jan'21) Shiv Naresh Sports Pvt. Ltd., E-23, Karampura. New Delhi-110015 Track, Volleyball ground GSB & WMM completed. Kabbaddi Ground Flooring PCC & footpath work is in progress. Tree cutting charges deposited. Tree cutting permission expected in first week of April. Physical process is 25% Detail Report
Graph / Photo
123 Construction prefab hut for HQ at PTS Wazirabad, Delhi 21/07/2018 20/11/2018 285.56 Aliyan Constaruction Company

work completed

Detail Report
Graph / Photo
124 Conversion of existing normal size swimming pool within the premises of Shaheed Amir Chand Sarvodaya Vidyalaya Ludlow Castle No 2 Sham Nath Marg, Delhi into all weather swimming pool 23/12/2020 20/06/2021 262.79 Maa Narayan Constuction Co. Work awarded Detail Report
Graph / Photo
125 EOR/REPAIR OF BUILDING OF PS, M, N, O, P, Q and R BLOCK QTRS. AND REPLACEMENT OF DAMAGED G.I./C.I. PIPE LINE, ALL/FLOOR TILES OF P, Q and R BLOCKS IN PC MODEL TOWN, DELHI. (SH CIVIL and ELECTRICAL WORK). 01/11/2018 01/07/2019 201.92 158.30 (Mar'20) 0.00 (Mar'20) Pooja Construction

ok

Detail Report
Graph / Photo
126 Construction of Normal Size Swimming Pool within the Premises of Shaheed Captain Haniffuddin Sarvodaya Kanya Vidyalaya Mayur Vihar Phase 1, Pocket 4, Delhi 110091 16/03/2019 15/09/2019 182.18 0.00 (Dec'20) 72.00 % (Dec'20) Anish Ahmed RPE under scrutiny. Detail Report
Graph / Photo
127 Vertical Extension of Teaching Block No.1 of B.R. Ambedkar College, Wazirabad Road, Delhi 16/01/2018 15/07/2018 172.40 114.27 (Oct'20) 0.00 (Oct'20) JABIR HUSSAIN

work completed

Detail Report
Graph / Photo
128 Providing and Installing Fire Fighting, Fire Alarm system and Public Address system 10/08/2014 09/04/2015 155.31 Detail Report
Graph / Photo
129 Construction of Gymnastic Hall at SBV Moti Nagar Delhi 11/01/2020 09/07/2020 147.53 0.00 (Aug'20) 2.00 % (Aug'20) Aniket Enterprises Physical progress of the work is 15%. Detail Report
Graph / Photo
130 Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). 25/01/2019 24/05/2019 140.44 208.86 (Mar'21) 0.00 (Mar'21) Uma Shankar work in progress Detail Report
Graph / Photo
131 Construction and setup the Nursery Pre-School in 15 No. FIFTEEN NOS. Sarvodaya Vidyalayas, Delhi Govt. School under Division West Building-I, PWD, New Delhi during 2018-19. SH Civil and Electrical Work.PWD, New Delhi during 2017-18. SH Civil and El 12/09/2018 11/01/2019 140.01 Satyam Construction Co. Detail Report
Graph / Photo
132 Construction of SPS building and boundary wall for Training cum Production Centre at Indira Nagar Azadpur Delhi 33 Civil and Electrical Work 08/03/2020 04/09/2020 137.37 A R Construction Co. Work in progress. (The agency has submitted structural drawings for proof check by SE, NMC) SE, NMC suggested the modification and agency has bee asked to submit vetted drawing from 3rd party incorporating the modification. Detail Report
Graph / Photo
133 Construction of prefab hut for HQ of Meghalaya Police along with development work located at PTS Wazirabad, Delhi 15/07/2018 14/11/2018 134.50 110.06 (Oct'19) 0.00 (Oct'19) Aliyan Constaruction Company

work completed

Detail Report
Graph / Photo
134 Extension and Renovation of office space at the 1st Floor of LG s Secretariat, Raj Niwas, Delhi-54. (SH Civil and Electrical Work ). 14/10/2018 10/02/2019 133.59 179.19 (Feb'21) 0.00 (Feb'21) Munzareen Ahmd

ok

Detail Report
Graph / Photo
135 Construction and setup the Nursery Pre-School in 13 No.THIRTEEN NOS. Sarvodaya Vidyalayas Delhi Govt. School under West Building-I, PWD, New Delhi during 2018-19. SH Civil and Electrical Work. 28/02/2019 28/06/2019 117.55 77.24 (Jan'20) 0.00 (Jan'20) krishna construction co Detail Report
Graph / Photo
136 Changes in infrastructure of CHB to develop it as OHB Model Home.(Civil and Electrical work) 24/10/2019 23/02/2020 112.72 Vashistha and Sons Construction Co PAN Number: ANFV6477F 9 Methapur , New Delhi - 110044 Detail Report
Graph / Photo
137 Making the Building disable friendly under Accessible India campaign at RTRM Hospital Jaffarpur Kalan New Delhi. 01/06/2020 27/11/2020 106.37 0.00 (Jan'21) 30.00 % (Jan'21) Aliyan Constaruction Company Work is under progress. Detail Report
Graph / Photo
138 Construction of SPS Type Main Store and demolition of old PWD enquiry office. 04/02/2019 03/08/2019 103.91 55.03 (Mar'20) 0.00 (Mar'20) ASHOK MALIK Detail Report
Graph / Photo
139 Construction of boundary wall, main gates, guard rooms etc. for vacant land at K Block Jahangir puri, Delhi. 21/12/2019 18/05/2020 102.07 54.12 (Mar'21) 75.00 % (Mar'21) Saeed Builders

Work in progress.

Detail Report
Graph / Photo
140 Providing and supplying tree planters in various places, New Delhi under MLA LAD Fund Scheme 04/11/2019 18/12/2019 91.97 91.97 (Mar'21) 0.00 (Mar'21) Rajeshwar Dayal Pandey Detail Report
Graph / Photo
141 Providing and replacement, up-gradation and comprehensive maintenance of UPS and TVSS system at LBS Hospital, Khichripur, Delhi. 31/05/2019 30/07/2019 86.23 POWER HOUSE work completed Detail Report
Graph / Photo
142 Construction of Shed with Boxing Ring at Sports Complex, East Vinod Nagar, Delhi 08/05/2017 04/09/2017 84.89 19.39 (Jul'20) 0.00 (Jul'20) Anish Ahmed Work in Progress Detail Report
Graph / Photo
143 AR and MO to Various Delhi Govt. Buildings under Division West Building-1, Tihar, New Delhi. During 2019-20. SH Providing services of Computer Operator, Clerk, Peon, Dak Messenger 28/08/2019 27/08/2020 77.50 10.35 (Mar'20) 0.00 (Mar'20) Good Luck Enterprises Detail Report
Graph / Photo
144 Development of sports facilities at Govt. Girls Sr. Sec School, Jhilmil Colony, Delhi. (SH: C/o Table Tennis Room, Gymnastic Room and other miscellaneous works). 23/09/2019 22/01/2020 77.45 0.00 (Dec'20) 97.00 % (Dec'20) K.P. Singh & Co. Work completed. Detail Report
Graph / Photo
145 Renovation of Library Block of IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, New Delhi.(SH-Civil and Electrical works). 09/07/2018 08/01/2019 75.80 61.12 (Jan'20) 0.00 (Jan'20) Kamal Construction Co. Work in progress Detail Report
Graph / Photo
146 Changes in Infrastructure of Model Home to convert it as CHB and JJB in front of Building (Civil and Electrical work). 24/10/2019 23/01/2020 71.13 AJAY CONSTRUCTION CO. Detail Report
Graph / Photo
147 Providing and laying RMC in the campus of N, J1, J2, J3, K, L and M Block at Sujan Singh Park, New Delhi under MLA LAD Fund Scheme. 27/10/2019 07/12/2019 70.87 44.70 (Mar'20) 0.00 (Mar'20) Gyanchand Detail Report
Graph / Photo
148 Augmentation of Old and Outlived Sub-Station equipments at LBSH, Khichripur, Delhi Sub Head S.I. T.C. of Substation Equipments 13/10/2018 12/04/2019 69.44 35.42 (Mar'19) 50.00 % (Mar'19) Ajay M/c Tools work in progress ( 2nd RA ) Detail Report
Graph / Photo
149 Replacement of existing 3 Nos 26 Passenger cum bed lift at CNBC, Geeta Colony, Delhi. 01/08/2018 30/04/2019 69.00 18.02 (Nov'18) 35.00 % (Nov'18) Johnson Lift Pvt Ltd Work in progress (3RD RA 600525 Detail Report
Graph / Photo
150 Construction of 10 Nos FRP Gazebo rubens and 06 Nos of porta cabin Chaupal at various places of New Delhi Constituency AC40, under MLA LAD Fund Scheme 26/11/2019 24/01/2020 68.77 34.11 (Nov'20) 0.00 (Nov'20) Tripurari Prasad Singh Detail Report
Graph / Photo
151 C/o SPS Type New M.P. Hall at SBV, Subhash Nagar, New Delhi. 07/03/2019 06/07/2019 68.63 Vinay Shanker Detail Report
Graph / Photo
152 SH Repairing to plaster and water proofing treatment of roofs to prevent seepage i c re-strengthened to roof of barracks in various wards 21/12/2018 20/04/2019 66.46 53.94 (Mar'20) 0.00 (Mar'20) Ashok Kumar Detail Report
Graph / Photo
153 Construction of Recreation Hall at PTS, Wazirabad, Delhi 16/02/2019 15/06/2019 63.80 81.48 (Mar'21) 0.00 (Mar'21) Shekhar

work completed

Detail Report
Graph / Photo
154 SITC of ETP (Effluent Treatment Plant) 28/04/2015 27/07/2015 59.53 Mgrow Techno System Pvt. Ltd. Detail Report
Graph / Photo
155 Misc repair work under SRD Project Division I Sub Division III PWD New Delhi Recall 23/09/2019 22/03/2020 56.09 70.01 (Feb'21) 0.00 (Feb'21) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
156 EOR to Police Station, Vikas puri, New Delhi. SH Water proofing treatment of roofs, Renovation of toilets, Replacement of damaged C.I and G.I pipe lines. Tile flooring in rooms and corridors, raising of boundary wall and other misc repair works 15/10/2018 14/02/2019 56.04 51.27 (Sep'19) 0.00 (Sep'19) Tubya Construction Detail Report
Graph / Photo
157 AA to SKV No. 01 Gandhi Nagar Delhi dg 2018 19 17/03/2019 16/07/2019 55.57 32.21 (Jun'20) 0.00 (Jun'20) Arif 90% work in progress Detail Report
Graph / Photo
158 EOR to DAP Line, Vikas Puri, New Delhi. SH Construction replacement of damaged sewer lines of Vikas Puri, Police Lines and residential Complex 3rd battalion, Delhi Armed Police Delhi 20/07/2018 19/11/2018 55.08 12.19 (Dec'19) 0.00 (Dec'19) Tubya Construction Detail Report
Graph / Photo
159 A EOR to Co of toilet block septic tank parking shed renovation of principal rooms GBSSS Katewara B Repair renovation toilet block at GSBV Prahladpur Banger C PF wall tiles false ceiling MS gate railing flush door misc work at RSGSKV Bawana Delhi 16/11/2019 15/03/2020 54.51 Batra Constructions work is in progress (35%) Detail Report
Graph / Photo
160 Providing and fixing door, window, Floor tile, kota stone flooring, wall tile, chajja etc except toilet portion. 02/07/2020 20/10/2020 54.33 52.89 (Jan'21) 0.00 (Jan'21) Dharambir Singh work in progress (80%) Detail Report
Graph / Photo
161 Re construction of collapsed boundary wall of school of about 28 metres length in North west side at Govt Co ed SSS Barwala Delhi 110039 School Id1310161 Bldg Id13101377 EOR Id20182296 25/11/2019 23/01/2020 54.06 50.20 (Nov'20) 0.00 (Nov'20) HARI RAM VERMA work is in progress (88%) Detail Report
Graph / Photo
162 Raising of boundary wall on back side of the school, Grit wash on boundary wall renovation of multipurpose hall and misc work 23/12/2019 20/04/2020 53.77 43.28 (Nov'20) 0.00 (Nov'20) Jeetender Kumar Verma work is in progress (80%) Detail Report
Graph / Photo
163 Re-Construction of 8 nos. Servants Quarters (Type-I) including development at Session House,2 North End Road, Delhi (SH Civil and Electrical Works) 02/08/2019 02/04/2020 53.74 D.S. Construction Co

ok

Detail Report
Graph / Photo
164 Civil and Electrical Works. 13/06/2019 12/09/2019 51.83 15.96 (Nov'20) 0.00 (Nov'20) Abhikalp Constructions Syndicate

work in progress

Detail Report
Graph / Photo
165 Construction of 5 nos arch shaped FRP pergola, 4 nos FRP porta cabin and 25 nos FRP Security Cabin at various places of New Delhi constituency AC 40 under MLA LAD Scheme 26/11/2019 24/01/2020 51.22 5.46 (Mar'20) 0.00 (Mar'20) Tripurari Prasad Singh Detail Report
Graph / Photo
166 Construction of SPS Structure 4 Storey for ITI at Ranhola Delhi. (SH: Erection of MS fire escape stair fire resistant doors cement concrete pavement and other miscellaneous works 15/02/2021 15/05/2021 51.05 BHUPESH KUMAR Tender uploaded. Detail Report
Graph / Photo
167 Repair of old building wall, roof and floor, Grit wash plaster, sewerline, repair of stair case, replacement of windows. 18/11/2019 16/04/2020 50.60 51.80 (Nov'20) 0.00 (Nov'20) Saeed Builders No works since previous month Detail Report
Graph / Photo
168 Replacement of Carpets in Courts of A block Extension block and wooden texture laminated flooring in Chambers of Extension block at Delhi High Court New Delh 27/06/2017 26/07/2017 50.20 Bansal Builder Agreement closed PG forfeited Detail Report
Graph / Photo
169 Grit Wash and Internal Finishing for ABIT main building and exterior and internal finishing of workshop 02/11/2020 01/05/2021 49.46 Irshad Ahmed Work in progress 1% Detail Report
Graph / Photo
170 Providing Creche at Multi Level Car Parking Ground Floor Delhi High Court New Delhi SH Composite Work 08/01/2021 08/03/2021 48.59 14.96 (Mar'21) 0.00 (Mar'21) SHREE PAL SINGH Work in progress Detail Report
Graph / Photo
171 Providing Services of labour for day to day maintenance of colony. 15/09/2020 14/07/2021 45.28 Mazid Hussain Work in progress Detail Report
Graph / Photo
172 SITC of Building Management System 12/09/2020 11/03/2021 43.49 130.52 (Jan'21) 50.00 % (Jan'21) Digital Controls & Automation Work in progress Detail Report
Graph / Photo
173 Solar water heating system 14/02/2015 14/05/2015 43.42 M.S. Associates . Detail Report
Graph / Photo
174 Miscellaneous Civil Works 13/08/2020 11/09/2020 42.87 0.00 (Jan'21) 95.00 % (Jan'21) M/s Gejwal Construction Company Work is in progress Detail Report
Graph / Photo
175 EOR to Govt. Boys Senior Secondary School, Tagore garden, New Delhi. SH Kota flooring in rooms, sheet doors, guniting works, RMC in approach area and other misc. works 21/07/2018 19/10/2018 42.01 Bagga Enterprises Detail Report
Graph / Photo
176 (1) Renovation of Surgery Emergency ward at room no. 149 and supporting rooms at Accidental & Emergency Block at GTB Hospital, Shahdara, Delhi (2) Renovation of Room No. 331, 332 & 338 in Administratvei Block 3rd Floor at GTB Hospital, Shahdara, Delhi. (SH: Providing Electrical and Civil Works) 07/07/2017 02/01/2018 41.98 12.42 (Mar'19) 30.00 % (Mar'19) RCC Enterprises Work completed Detail Report
Graph / Photo
177 Construction of parking shed for students and staff and fixing new aluminium windows in corridor of ground floor 1st floor 2nd floor 3rd floor and rooms along with vension blinds at ITI Narela Delhi 40 03/07/2020 02/11/2020 41.45 17.43 (Nov'20) 0.00 (Nov'20) Aayan Construction Co. Work in progress Detail Report
Graph / Photo
178 AR and MO to 252 DA Flats and 72 DA Flats, I.T.I Jail Road, Fire Stations Dy. Labour Commissioner Office and other Govt. Bldgs, under Sub Division WB-14 dg 2018-19. SH Providing services of labour for day to day maintenance 12/09/2018 12/09/2019 40.82 19.05 (Feb'20) 0.00 (Feb'20) Pristine management and allied services Detail Report
Graph / Photo
179 Improvement of lighting in various OTs at GTB Hospital Complex, Shahdara, Delhi. 03/03/2019 02/05/2019 40.46 19.10 (May'19) 0.00 (May'19) CARONA ELECTRICALS Work completed Detail Report
Graph / Photo
180 Supplying and replacement of 2 Nos. outlive water cooled 115 TR reciprocating type Chiller Unit with 120 TR Capacity screw type chiller unit at JPCH Shastri Park, Delhi 26/11/2018 25/03/2019 40.39 32.21 (May'19) 0.00 (May'19) Blue Star Limited Work completed Detail Report
Graph / Photo
181 Repairing of 4x420 TR and 1x150 TR capacity central AC plant installed at RGSS Hospital, Tahirpur, Delhi 16/09/2018 15/11/2018 37.82 45.88 (May'19) 0.00 (May'19) SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. Work In Progress (2ND RA 2445663) Detail Report
Graph / Photo
182 Connecting of corridors, flooring in main building, widening of path, widening of gate, door on staircases, repair of rain water harvesting system and other miscellaneous work at SKV, Moti Nagar. 10/10/2018 09/01/2019 36.52 8.53 (Mar'20) 0.00 (Mar'20) ASH NARAYAN SINGH Detail Report
Graph / Photo
183 CO of Toilet for primary wing support staff visitor and attached toilet to principal room renovation of water tank platform and toilet repairing of b wall and other misc civil works 15/08/2020 14/12/2020 34.45 CSM CONSTRUCTION Detail Report
Graph / Photo
184 EOR to Central Jail No. 1, 2, 3, 6, 8 & 9, Tihar, New Delhi. (SH:- Mechanized cleaning of underground & overhead RCC / PVC water storage tanks). Tender ID 188903 02/04/2020 01/04/2021 34.01 Royal Construction Detail Report
Graph / Photo
185 Construction of Resource Centre for Children with Disabilities at A-2 Sarvodaya Vidyalaya (Co-Ed), Paschim Vihar, New Delhi (Civil Work) 09/01/2021 08/05/2021 33.98 6.58 (Mar'21) 0.00 (Mar'21) IKRAMUDDIN Work in progress 25% Detail Report
Graph / Photo
186 Construction work including internal Electrical installation in Akhara at NPL,Kingsway Camp, Delhi. 30/10/2018 28/01/2019 33.95 8.52 (Oct'19) 0.00 (Oct'19) Saeed Builders

ok

Detail Report
Graph / Photo
187 Providing and laying interlocking paver block and RMC in the campus of Police Colony at Tilak Marg, New Delhi under MLA LAD Fund Scheme. 27/10/2019 25/12/2019 33.92 22.42 (Jan'21) 0.00 (Jan'21) Gyanchand Detail Report
Graph / Photo
188 Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing ductable type air conditioning system 09/07/2019 08/10/2019 33.85 SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. work in Progress 6th RA 18182135 Detail Report
Graph / Photo
189 Providing, installation, testing, and commissioning of Code Blue System (NCS) for Old and New block at MAIDS, New Delhi 11/08/2019 10/11/2019 33.77 Med Freshe Pvt. Ltd. Work in progress Med Freshe Pvt. Ltd. Detail Report
Graph / Photo
190 Addition/Alteration works in DII/1, DII/2, DII/3, DII/5, DII/6, DII/7 & DII/8 at Court Lane, Delhi during 2014-15. (SH:- Misc. Civil work in flats No. DII/1, DII/3 & DII/8) & Providing & fixing Kitchen Cabinets DII/1, DII/2, DII/3, DII/5, DII/6, DII/7 & DII/8. 11/08/2014 06/02/2015 32.94 Aslam Builders Final Bill Submitted in Division office Detail Report
Graph / Photo
191 Providing and fixing retro reflective informatory sign boards at various location of New Delhi constituency AC40 under MLA LAD Fund Scheme 25/10/2019 22/01/2020 32.70 12.66 (Mar'21) 0.00 (Mar'21) Rajesh Kumar Gupta Detail Report
Graph / Photo
192 Attending Day-to-Day complaint in Mandoli Jail complex and resi. area including Supply of Material Horti Operation cleaning of water tank and Operation and maint of 850 KLD STP 05/02/2021 05/04/2021 32.04 0.00 (Jan'21) 10.00 % (Jan'21) M/s Gejwal Construction Company Work is in progress Detail Report
Graph / Photo
193 Construction of Porta Cabin for PWD Sub Divn. Office of Civil and Electrical including enquiries of both and Development of lab collection centre and shed covering 06/01/2021 05/04/2021 31.62 0.00 (Jan'21) 5.00 % (Jan'21) Nation Star Enterprises Work is under progress. Detail Report
Graph / Photo
194 Installation of hard drawn wire fabric at D Block and B Block residential quarters for monkey protection in Fire Station Connaught Place New Delhi. 08/02/2019 07/03/2019 31.58 39.47 (Jul'19) 90.00 % (Jul'19) Vasdev Work in progress Detail Report
Graph / Photo
195 Renovation of Kotwali Building at Chandni Chowk, Police Station under SRD Division-I, Sub-Division-III, PWD, New Delhi. 25/06/2018 24/10/2018 31.39 0.00 (Feb'19) 39.16 % (Feb'19) Kamal Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
196 Providing & fixing electrical panel and cabling for VRV system in 4th, 5th & 6th block at RGSS Hospital at Tahirpur, Delhi 27/03/2015 26/04/2015 31.02 Perfect Air Conditioning & Electricals Detail Report
Graph / Photo
197 Providing and fixing door, window, Floor tile, kota stone flooring, wall tile, chajja etc i/c toilet portion. 30/07/2020 02/11/2020 30.96 0.00 (Oct'20) 85.00 % (Oct'20) Laxmi Narayan work in progress (60%) Detail Report
Graph / Photo
198 SITC of additional CCTV and allied equipment at GTB Hospital, Shahdara, Delhi 16/10/2018 15/12/2018 30.64 15.29 (Feb'19) 50.00 % (Feb'19) San Infotech Services work in progress 2nd RA 1696099 Detail Report
Graph / Photo
199 C/o approach road. Phase-II. 01/11/2019 30/12/2019 30.03 28.70 (Mar'20) 0.00 (Mar'20) Asif work is in progress (95%) Detail Report
Graph / Photo
200 Comprehensive Maintenance of Old Saint Stephens College Building Kashmere Gate, CPO Building, Old Court Building, NCC Offices Buildings, Novelty Fire Station, Fire Station Jama Masjid, Disability Commissioner Office, Lok Nayak Setu Office Compl 17/11/2019 16/11/2020 29.01 36.24 (Feb'21) 0.00 (Feb'21) K.P. Singh & Co. Detail Report
Graph / Photo
201 (A) Replacement of damaged C.I and G.I Pipes. (B) Supply of Material. (C) Providing for services of Day to Day maintenance. 29/05/2020 23/01/2021 27.31 13.96 (Jan'21) 0.00 (Jan'21) Mazid Hussain Work in progress (90%) Detail Report
Graph / Photo
202 Rehabilitation work in Police Station at Chandni Mahal, Asaf Ali Road, Delhi. 29/09/2019 26/03/2020 27.08 33.83 (Mar'21) 0.00 (Mar'21) Shah Pandya & Shot Crete Detail Report
Graph / Photo
203 Up gradation of toilets and guniting work in ITC lab and class rooms. Phase III 28/12/2019 26/04/2020 26.66 7.74 (Mar'20) 0.00 (Mar'20) HARI RAM VERMA Work In progress (85%) Detail Report
Graph / Photo
204 Running and maintenance of UPS at GTB Hospital, Complex, Shahdara, Delhi. Sub Head Comprehensive maintenance of Emerson make 2x200KVA UPS systems 25/02/2019 24/02/2022 26.03 POWER HOUSE Work In Progress (2ND RA 618590 ).. Detail Report
Graph / Photo
205 Construction of yard for Malkhana of Police Station Chandni Mahal, Darya Ganj under SRD Division-I, Sub-Division-III, New Delhi. 30/07/2018 29/10/2018 25.67 23.27 (Sep'19) 0.00 (Sep'19) Krishan Kumar Work in progress Detail Report
Graph / Photo
206 Providing Materials and Manpower for day to day maintenance including miscellaneous repair works in the building 26/05/2020 24/05/2021 24.70 0.00 (Jan'21) 70.00 % (Jan'21) KRISHAN KUMAR MISHRA Work is in progress Detail Report
Graph / Photo
207 EOR to Police Colony, Tilak Nagar, New Delhi. SH Renovation of existing rooms and provision of multipurpose hall 27/06/2018 26/09/2018 23.05 12.24 (Dec'19) 0.00 (Dec'19) Adorn associates Detail Report
Graph / Photo
208 Providing and laying bituminous concrete surface at BR Campus, Race course, New Delhi under MLA LAD fund Scheme. 3rd CALL 26/11/2019 25/12/2019 22.88 10.29 (Aug'20) 0.00 (Aug'20) Rajesh Kumar Gupta Detail Report
Graph / Photo
209 Development Cricket ground football field and chain link fencing at newly taken over plot for sports complex at village kair in the Assembly constituency Najafgarh, Delhi. (SH: Comprehensive maintenance of cricket ground for one year) 01/04/2021 31/03/2023 22.80 Devender Pal Singh

Tender uploaded

Detail Report
Graph / Photo
210 S.I.T.C of air conditioning system for Medicine and ENT OPD Section at JPC Hospital, Shastri Park, Delhi. 21/07/2018 20/09/2018 22.52 M/s Pneumatic Engineering Services Work completed Detail Report
Graph / Photo
211 Construction of Portacabin for additional space of camp office over the Garrage at Bunglow No 2, 8 Raj Niwas Marg Delhi 04/04/2019 03/06/2019 22.38 26.50 (Feb'20) 0.00 (Feb'20) Mohd Arshad Detail Report
Graph / Photo
212 Renovation of B Voc Labs 20/05/2019 19/08/2019 22.14 M.Y Construction 40% Work could not start due to electrical tender not in force. Detail Report
Graph / Photo
213 Supplying and replacement of Outlived Air Handling Units at JPCH Shastri Park, Delhi 22/07/2019 21/09/2019 21.72 US Engineers

Tender is in process

Detail Report
Graph / Photo
214 Providing and Fixing of MS tubular Window with Acrylic plastic Sheet 14/11/2019 12/03/2020 21.53 26.89 (Mar'21) 0.00 (Mar'21) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
215 "Addition / Alteration of Roop Nagar fire station Delhi. (SH:- Ready Mix concrete, Renovation of Toilet and other Misc. work.) " 08/10/2015 07/01/2016 19.71 Jabir Husain Final Bill not submitted by the Agency Detail Report
Graph / Photo
216 SITC of Water softerner and treatment equipment 27/01/2015 26/07/2015 18.59 Passim Water Services .. Detail Report
Graph / Photo
217 Renovation of Reporter Branch and Legislation Branch at Delhi Vidhan Sabha 01/05/2020 31/07/2020 18.20 HPS Enterprises

Work in Progress

Detail Report
Graph / Photo
218 Const. of office building for Sub Division III SRD Project Divn I at Road No. 47 near Metro Pillar No. 29, Kashmere Gate, Delhi 23/09/2019 21/12/2019 17.04 21.26 (Jul'20) 0.00 (Jul'20) K.P. Singh & Co. Detail Report
Graph / Photo
219 Construction of New Shed over main stage of Control Room in Central Jail No. 2, Tihar, New Delhi. 15/07/2017 20/07/2017 16.86 Bagga Enterprises Detail Report
Graph / Photo
220 Repair/Renovation of the garage at H-Block of Delhi Commission for Women, Vikas Bhawan, I.P. Estate, New Delhi. 01/08/2016 30/09/2016 16.80 0.00 (Aug'16) 10.00 % (Aug'16) Sanendra Kumar Work in progress Detail Report
Graph / Photo
221 Repair and Renovation of Auditorium in Shahed Bhai Bal Mukand Govt. Sarvodaya Vidyalaya at Shankaracharya Marg, Delhi, during 2015-16 23/10/2015 22/01/2016 16.78 Munzareen Ahmed Final Bill not submitted by the Agency Detail Report
Graph / Photo
222 EOR to Sarvodaya Kanya Vidyalaya, Hari Nagar, Clock Tower, New Delhi. SH Provision of Rain Water Harvesting System 06/09/2018 05/11/2018 16.77 23.50 (Mar'20) 0.00 (Mar'20) Kishan singhal Detail Report
Graph / Photo
223 Construction of Conference Hall and Waiting/Reception Hall in Office of Commissioner for Persons with Disabilities at Mata Sundari Road under SRD Division-I, Sub-Division-III, PWD, New Delhi. (SH-Civil Renovation Work). 09/08/2018 08/11/2018 16.72 15.33 (Oct'19) 5.60 % (Oct'19) Intkhab Alam Work in progress Detail Report
Graph / Photo
224 EOR to Central Jail No. 4, Tihar, New Delhi. SH Improvement of covering of stage at chakkar. 01/02/2019 30/04/2019 16.39 20.64 (Mar'20) 0.00 (Mar'20) SUSHIL ENGINEERING WORKS Detail Report
Graph / Photo
225 A/R & M/O GNEC, New Delhi. dg. 2016-17 (SH: Up-Keeping and maintenance of services of GNEC and providing and service of computer operator, Dak Messenger, plumber, carpenter, mason sewerman etc under HMD (Central) SD-3) 13/04/2017 12/10/2017 16.04 7.45 (Mar'19) 46.00 % (Mar'19) Anup Enterprises Detail Report
Graph / Photo
226 Miscellaneous requisite work in Central Jail No 11, 12, 13, 14, 15 and 16 in Prison Complex Mandoli, Delhi- 110093 15/10/2020 11/02/2021 15.37 0.00 (Dec'20) 22.00 % (Dec'20) M/s Manomay Work is in progress Detail Report
Graph / Photo
227 Providing and laying Flushing and water supply line al-round at Police housing campus Delhi-110093 (Balance work) 05/02/2021 05/04/2021 15.34 Himanshu Saini The contractor forfeited the PG and work is 2nd call. Detail Report
Graph / Photo
228 SH- Kota stone flooring, repair to boundary wall including grit plaster and concertina wire fencing, repair and maintenance of toilets, P F steel windows, renewing broken glass panes with polycarbonate sheet etc. 07/11/2018 04/02/2019 15.26 Prashant Construction Co. , PAN: AIDPA3845Q, Address: C-4/5,KABIR NAGAR, DELHI-110094 in progress. Detail Report
Graph / Photo
229 Providing and supplying plastic moulded table in porta cabins reading room at various places of New Delhi Constituency AC40 under MLA LAD Fund Scheme. 25/10/2019 08/12/2019 15.17 DECOR MODULAR SYSTEM PVT LTD Detail Report
Graph / Photo
230 Upkeep Service 05/10/2019 04/10/2020 15.15 18.80 (Feb'21) 0.00 (Feb'21) Ashish Gupta Detail Report
Graph / Photo
231 AR and MO Various Buildings under Sub Division WB-15, Sunder Apartment, New Delhi. During 2018-19. SH Providing labour for day to day maintenance and watch and ward in 32 Nos. Type IV and 32 Nos.Type V, Fire Station at Paschim Vihar, JawalaPuri, Jwal 06/10/2018 05/08/2019 14.64 8.96 (Aug'19) 0.00 (Aug'19) Universal Security & Placement Services (Regd.) Detail Report
Graph / Photo
232 Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing Electrical Installation work 22/07/2019 21/09/2019 14.54 Sangeeta Electricals 1st RA 729827 Detail Report
Graph / Photo
233 Providing barrier free environment for disable persons. 21/09/2020 20/03/2021 14.49 ARIF, Jahangirpuri, Delhi Work in progress 10% Detail Report
Graph / Photo
234 Construction of 2 Nos Rain water harvesting system 25/11/2019 22/02/2020 14.36 8.89 (Jul'20) 0.00 (Jul'20) Shamshad Ahmed work is in progress (70%) Detail Report
Graph / Photo
235 Renovation work of kitchen area, Stage work, interlocking tile work, misc repair work in Old community centre and Shri Ram Park 25/11/2019 23/01/2020 14.35 12.82 (Aug'20) 0.00 (Aug'20) Sageer Ahmad work is in progress (60%) Detail Report
Graph / Photo
236 SITC of Emergency Call Bell System in CJ 13 and CJ 15 Mandoli Prisons Delhi 13/03/2021 11/05/2021 14.10 M/s TOPAZ SERVICES CORPORATION award letter issued Detail Report
Graph / Photo
237 P/F of Kota stone PVC tank sitting platform near statue and other major misc works 25/11/2019 22/02/2020 14.03 7.90 (Sep'20) 0.00 (Sep'20) M H Builders work is in progress (75%) Detail Report
Graph / Photo
238 Construction of steel staircase with passage for making approach to library, lift and second floor room, renovation of college canteen, water proofing treatment on roof with APP and broken tile, false ceiling and aluminium partition work in library a 13/01/2020 12/03/2020 13.98 17.43 (Sep'20) 0.00 (Sep'20) Saeed Builders work in progress 60%. Work heldup due to lockdown Detail Report
Graph / Photo
239 Special repair to EI work in Mandoli Prison Complex, Delhi 15/03/2021 13/05/2021 13.93 Neeraj Kumar PG ISSUED Detail Report
Graph / Photo
240 Construction of permanent shed on pavement near Gyne OPD registration 18/08/2020 17/10/2020 13.73 SS Enterprises work in progress. Detail Report
Graph / Photo
241 Providing renovation repair of toilet, ramps, railing, tactile tiles, signage etc. to make school building and environment barrier free and accessible. EOR ID 20191350. 02/07/2020 17/08/2020 13.62 Laxmi Narayan Work in progress (40%) Detail Report
Graph / Photo
242 Providing and installation of 10 Nos. passenger lift in Four Storey Building at DIPSAR, M.B. Road New Delhi. 25/06/2019 24/08/2019 13.59 Sanjeev Kumar Goel work in progress Detail Report
Graph / Photo
243 EOR to Govt. Sarvodaya Kanya Vidyalaya a S.P. Road, Nangloi, New Delhi. SH Providing new gate for main entrance, near activity room, providing and fixing grill in front of primary section providing shed for water through near primary section 02/04/2018 15/09/2030 13.58 L V Enterprises Detail Report
Graph / Photo
244 "EOR to Sarvodaya Bal Vidyalaya, Timarpur, Delhi-54, dg. 2014-15 (SH:- Repairing of roof and toilets ( SSH:- Repair and Renovation of staircase and other misc repair) " 23/10/2015 22/12/2015 13.57 Jabir Husain Final Bill not submitted by the Agency Detail Report
Graph / Photo
245 Providing UPS supply in DGHS (HQ) for computer Network (LAN) at Karkardooma, Delhi. (SH: EI works). 06/04/2018 05/06/2018 13.57 6.60 (Jan'19) 40.00 % (Jan'19) Aas Electric Co. Work in Progress ( 1st RA 659060 Detail Report
Graph / Photo
246 P/L of Bituminous concrete of 40/50 mm compacted thickness with bitumen of grade VG-30. (Through MLA Fund) 16/11/2019 16/12/2019 13.56 Laxmi Narayan Work yet not started. Tender is to be foreclosed & re invited bid new TS. Detail Report
Graph / Photo
247 Repairing work to already installed Rain Water Harvesting Systems to make them functional in 7 Nos. Schools of NB-11, Delhi. 03/01/2020 03/04/2020 13.50 Shyam Sunder, PAN: CHLPS5692A Work In progress (30%) Detail Report
Graph / Photo
248 Shifting of X Ray machine at Gate No 6 and provision of porta cabin at gate No 6 and covering of vehicle session at gate No 03 20/05/2019 03/07/2019 13.40 13.90 (Jan'20) 0.00 (Jan'20) Rajeev Kumar site not available for work 60% Detail Report
Graph / Photo
249 Renovation of gents and ladies toilet and guniting of ceiling of ground, 1st, 4th, 5th and 6th floor of I block, College of Art at Tilak Marg, New Delhi 14/11/2019 11/02/2020 13.30 14.80 (Mar'21) 0.00 (Mar'21) Amiruddin Detail Report
Graph / Photo
250 Miscellaneous EI work in various Jails of Mandoli Prison Complex, Delhi 31/03/2021 30/06/2021 13.30 BHS Pump Specialist tender called Detail Report
Graph / Photo
251 Construction of Porta Cabin for storage purpose on Terrace of Family Court, Saket, New Delhi. 26/06/2019 25/07/2019 13.07 8.01 (Mar'21) 0.00 (Mar'21) P S ASSOCIATES work in progress Detail Report
Graph / Photo
252 Rehabilitation of distress open staircase at Admn. Block. (ii) Conversion of Existing class room into PGs Accommodation. Balance 17/09/2020 05/12/2020 12.59 sabur alam Work in progress. Detail Report
Graph / Photo
253 Rehabilitation of distress open staircase at Admn. Block. Conversion of Existing class room into PG s Accommodation. Balance work of PG s Accommodation. 17/09/2020 05/12/2020 12.59 sabur alam Work is Progress Detail Report
Graph / Photo
254 Setting up of Dining Hall at HLTB Complex, Tahirpur, Delhi under KKD Court Divn.. M-231 dg. 18-19. 10/02/2019 10/05/2019 12.52 13.79 (Jan'20) 0.00 (Jan'20) Daya Sagar Sharma work in progress Detail Report
Graph / Photo
255 Construction of Rain Water Harvesting Structure at GBSS Mukherjee Nagar under Sub division M-3211(N), Delhi. 09/02/2019 10/05/2019 12.31 Hare Ram Singh

ok

Detail Report
Graph / Photo
256 Installation of Rain Water Harvesting system at Sarvodaya bal vidyalaya, Fatehpur Beri, New Delhi (School ID 1923014, Building ID 19231036, EOR ID 20172367). 03/03/2019 02/05/2019 12.15 10.84 (Nov'20) 0.00 (Nov'20) RECKONN work in progress Detail Report
Graph / Photo
257 AR and MO Fire Stations, Hari Nagar, Janak Puri under Sub Division WB-14. During 2018-19. SH Repair misc. civil works 10/09/2018 02/09/2019 11.82 Arif Detail Report
Graph / Photo
258 Replacement of existing damaged carpet of Assembly hall, MLA lounge I and II at Vidhan Sabha, Delhi. 17/07/2017 15/08/2017 11.77 14.00 (Oct'20) 0.00 (Oct'20) Vijay Furnitures

ok

Detail Report
Graph / Photo
259 Providing and fixing down comer and manually operated electronic FA system 19/09/2019 18/10/2019 11.18 0.00 (Jan'21) 98.00 % (Jan'21) M/s Royale Meridian India Pvt Ltd Work in progress Detail Report
Graph / Photo
260 EOR to SKV Bakhtawarpur, Delhi 110036. (A) Construction of parking shed and toe wall around gardening area.) (B) Dismantling Over Head Water tank platform. 06/01/2020 06/03/2020 11.13 VAKIL AHMAD Work In progress (80%) Detail Report
Graph / Photo
261 Provision for Rain Water Harvesting Systems in Govt. Girls Sec. School (Urdu Medium) Lambi Gali, Hauz Qazi under SRD Division-I, Sub-Division-III, PWD, New Delhi dg. 2018-19. 11/07/2019 10/09/2019 11.10 1.62 (Mar'21) 0.00 (Mar'21) Shakur Ahmed & Sons Detail Report
Graph / Photo
262 Construction of room at 1st floor on existing store room and misc. renovation work at JJB-I, Sewa Kutir Complex, Kingsway Camp, Delhi. 09/06/2016 08/08/2016 11.10 0.00 (Apr'17) 85.00 % (Apr'17) Nafees Ahamed Work in progress Detail Report
Graph / Photo
263 Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 1 (Hindi Medium) at Jama Masjid, Delhi dg. 18-19 (School ID-2127024.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 11/03/2019 10/05/2019 11.09 13.85 (Mar'20) 0.00 (Mar'20) Mohd. Asad work in progress Detail Report
Graph / Photo
264 Repair and Renovation works 21/11/2018 19/01/2019 11.00 6.86 (May'19) 0.00 (May'19) Daya Sagar Sharma Work in progress Detail Report
Graph / Photo
265 Operation and Maintenance of STP Plant of 180 KLD 27/07/2020 26/07/2022 10.91 0.00 (Jan'21) 25.00 % (Jan'21) M/s Parasar Electricals & Refrigeration Work is in progress Detail Report
Graph / Photo
266 Construction of Old Age Home at Kanti Nagar Installation of fire doors in the building 04/03/2021 02/04/2021 10.22 A. V. ENTERPRISES just awarded. Detail Report
Graph / Photo
267 Construction of office Rooms 2 Nos for Junior Engineer Electrical and Horticulture Staff and walking track at the park 10/12/2019 08/02/2020 10.02 8.95 (Feb'21) 0.00 (Feb'21) Mateen Ahmad work is in progress (80%) Detail Report
Graph / Photo
268 Upgradation/Renovation of Two rooms of HQ branch, Directorate of Education at Ground Floor of Old Patrachar Building, Timarpur Delhi-54. 24/04/2016 22/06/2016 10.01 Krishan Kumar Site not made available by the Client Detail Report
Graph / Photo
269 Construction one no additional toilet at 14/2 Tilak Marg and Renovation of kitchen, toilets and other civil miscellaneous repair works at 36 Ashoka Road under SRD Project Division-I, Sub-Division-IV, PWD, New Delhi 11/08/2019 10/10/2019 9.97 11.78 (Nov'20) 0.00 (Nov'20) Sher Singh Detail Report
Graph / Photo
270 Provision for Rain Water Harvesting System in Govt Girls Sr Sec School at Gali Baraf Wali Kinari Bazar Delhi during 2018 19 School ID-1208023 under SRD Division I Sub-Division III PWD New Delhi 11/07/2019 10/09/2019 8.86 8.84 (Mar'20) 0.00 (Mar'20) Shakur Ahmed & Sons Detail Report
Graph / Photo
271 Provision for Rain Water Harvesting System in Sarvodaya Kanya Vidyalaya No. 2 at Zeenat Mahal, Lal Kuan, Delhi (School ID-2127179) under SRD Division-I, Sub-Division-III, PWD, New Delhi 14/07/2019 13/09/2019 8.76 Shakur Ahmed & Sons Detail Report
Graph / Photo
272 Providing Services of Inspection Vehicle for Chief Engineer Other Projects Zone and Division office 08/08/2020 07/08/2021 8.73 0.00 (Jan'21) 50.00 % (Jan'21) Nisha Travels Work is in progress Detail Report
Graph / Photo
273 Providing services of plumbing, carpentry jobs etc RECALL 04/11/2019 03/11/2020 8.68 8.68 (Mar'21) 0.00 (Mar'21) Good Luck Enterprises Detail Report
Graph / Photo
274 AR and MO to ITI for women Tilak Nagar, ITI Hari Nagar Jail Road Labour Commissioner Office, Hari Nagar, New Delhi. During 2018-19. SH Repair and finishing work 04/06/2018 03/06/2019 8.35 KAILASH CHANDRA AND SONS Detail Report
Graph / Photo
275 A R and M O to 405 DA Flats Kalyanvas Delhi 91 dg 2018 19 18/06/2018 14/06/2019 8.03 5.04 (Nov'20) 0.00 (Nov'20) SABUR ALAM work in progress 90% Detail Report
Graph / Photo
276 A/R and M/O to I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Upkeep Service). 25/09/2018 24/09/2019 8.01 1.56 (Jan'20) 0.00 (Jan'20) Ashish Gupta Work in progress Detail Report
Graph / Photo
277 Provision for Rain Water Harvesting System in Sarvodaya Bal Vidyalaya at Pataudi House, Darya Ganj, Delhi (School ID-2127003.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 25/06/2019 24/08/2019 7.90 6.08 (Nov'19) 0.00 (Nov'19) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
278 Furniture work 25/10/2019 08/12/2019 7.84 7.84 (Mar'21) 0.00 (Mar'21) DURIAN INDUSTRIES LIMITED Detail Report
Graph / Photo
279 Provision for Rain Water Harvesting System in Govt. Boys Sr. Sec. School No. 2 (Hindi Medium) at Jama Msjid, Delhi (School ID-2127006.) under SRD Division-I, Sub-Division-III, PWD, New Delhi 25/06/2019 24/08/2019 7.66 6.42 (Jan'20) 0.00 (Jan'20) SUDHIR KUMAR SHARMA Detail Report
Graph / Photo
280 Providing and fixing Signage board in various place at L.N. Hospital, New Delhi. 10/09/2020 06/06/2021 7.57 Shrayash Enterprises

Work in progress.

Detail Report
Graph / Photo
281 Preparation of one room of 2nd and 3rd floor in front of lift gallery and replacement of gallery window of I Block, College of Art at Tilak Marg, New Delhi 14/11/2019 12/01/2020 7.35 9.10 (Feb'21) 0.00 (Feb'21) Amiruddin Detail Report
Graph / Photo
282 Installation of rain water harvesting system 02/06/2018 01/08/2018 7.23 6.04 (Jul'19) 0.00 (Jul'19) Mohd Akram p.g. forfeited and being tender recall Detail Report
Graph / Photo
283 A/R and M/O I.G.D.T.U.W. at Kashmere Gate, Delhi During 2018-19. (SH-Repair and Renovation work of University Staff Quarters at IGDTUW, Kashmere Gate under SRD Division-I, Sub-Division-III, PWD, New Delhi). 29/03/2019 28/06/2019 7.01 Prithvi creation work in progress Detail Report
Graph / Photo
284 Providing and renovation /repair of ramps, railing, tactile tiles signage etc. to make school building and environment barrier free and accessible for CWSN. 03/07/2020 02/10/2020 6.87 ARIF, Jahangirpuri, Delhi Work in progress (40%) Detail Report
Graph / Photo
285 ARMO of E & M Services in Children Home at Alipur, Delhi (SH: Operation of Sub-Station and DG Set 30/05/2017 29/05/2018 6.87 Parmar Electrical

Completed/In Progress

Detail Report
Graph / Photo
286 Renovation of D Block 1st Floor MP Hall 28/11/2019 26/01/2020 6.80 6.89 (Sep'20) 0.00 (Sep'20) Mohd Amjad Detail Report
Graph / Photo
287 Operation and Maintenance of 3x110 TR Capacity HVAC System and Servicing Overhauling and Comprehensive running maintenance of WTAC, Water coolers and Split AC units 01/04/2019 31/12/2019 6.53 7.48 (May'20) 0.00 (May'20) M/s Naj Refrigeration & Air Conditioning Works Detail Report
Graph / Photo
288 Renovation of DDE Office and Staff Room. 05/01/2020 06/03/2020 6.24 ARIF, Jahangirpuri, Delhi Work not allowed by Principal Date. Detail Report
Graph / Photo
289 "EOR to SKV Magazine Road, Majnu ka Tila, Delhi dg. 2014-15 (SH:- Changing of Asbestos sheet and other misc works at Primary wing) " 18/10/2015 17/11/2015 5.90 K.P. Singh & Co. Final Bill not submitted by the Agency Detail Report
Graph / Photo
290 Raising of boundary wall of Lal quarter Kidwai Nagar residential area under MLA LAD Fund Scheme RECALL 04/11/2019 18/12/2019 5.60 4.89 (Sep'20) 0.00 (Sep'20) B P Rai and Sons Detail Report
Graph / Photo
291 AR MO to DAP Line, Vikas Puri, New Delhi. During 2018-19. SH Cleaning and opening of blocked chocked sewerage system inside the campus by Super Sucker Machine and disilting of storm water pipe drains. 13/10/2018 12/02/2019 5.46 RichCon Engineering Company Detail Report
Graph / Photo
292 C/o District Court Complex at Plot No. 8, Shastri Park, Delhi During 2020-21 9 (SH:Deploying Persons for Safety of Government Properties). 03/10/2020 02/10/2021 5.41 0.00 (Jan'21) 33.00 % (Jan'21) Star security & Placement Services Work is in progress Detail Report
Graph / Photo
293 Providing inspection vehicles on hire charge basis One no. inspection vehicle for use in the office of Executive Engineer OPD-II and Two nos. inspection vehicles 04/01/2021 03/07/2021 5.39 0.00 (Feb'21) 20.00 % (Feb'21) SKIEZS Work is in progress Detail Report
Graph / Photo
294 Barrier free and accessible building for disabled persons. 31/07/2020 30/09/2020 5.38 Laxmi Narayan Work in progress 40% Detail Report
Graph / Photo
295 Construction of Rain water Harvesting System at Govt Boys Sr Secondary School Dev Nagar New Delhi Building ID 21281284 30/05/2019 13/07/2019 5.19 4.90 (Jan'20) 0.00 (Jan'20) Prem Sagar Work completed final bill paid Detail Report
Graph / Photo
296 Providing renovation repairof ramps railing tactile tiles signage etc to make school building and environment barrier free and accessible EOR ID 20182544 29/05/2020 28/07/2020 5.08 Suresh Ray work in progress (5%) Detail Report
Graph / Photo
297 Maintenance of PCs and their accessories in Health Maintenance Division Office (S-W) and all Sub Divisions under this Division office. 27/01/2020 26/01/2021 5.04 STAR COMPUTER SYSTEMS The Tender has been Cancel. Detail Report
Graph / Photo
298 Construction of Rain water Harvesting System in Sarovodya Kanya Vidyalaya Baba Ram Dev at Prasad Nagar New Delhi Building ID 21281295 30/05/2019 13/07/2019 4.97 5.56 (Nov'19) 0.00 (Nov'19) Prem Sagar Bill paid Detail Report
Graph / Photo
299 Renovation work at Session House, 2 North End Road, Delhi, SH Providing doors, cup boards, false ceiling and other misc. works. 08/06/2019 07/08/2019 4.97 6.25 (Sep'19) 0.00 (Sep'19) Mool Chand

ok

Detail Report
Graph / Photo
300 Construction of additional SPS type classrooms in Govt Schools Directorate of Education under Priority II SH Providing inspection vehicle for the office of Executive Engineer Edu M Division C and ND at Vikas Bhawan II Civil Lines New Delhi 110054 05/09/2019 04/09/2020 4.82 0.00 (Jan'20) 100.00 % (Jan'20) Surender Singh Chahal

work in progress

Detail Report
Graph / Photo
301 Construction of 9981 Class Roooms 106 MP Halls, 328 Labs 204 Librarie Principal and Vice principal rooms Staffrooms and 1067 Toilet block including stair cases etc 12748 No equivalent classrooms in existing premises of Govt Schools in Govt 22/01/2021 05/02/2021 4.81 Kesari & Associates work in progress Detail Report
Graph / Photo
302 E.O.R. to repair and replacement of sewer line, rain water disposal line and other misc. repair work in Police Station, Darya Ganj, Delhi dg. 2018-19 (SH- Improvement of drainage system under SRD Division-I, Sub-Division-III, PWD, New Delhi). 26/02/2019 25/04/2019 4.59 5.27 (Jun'19) 0.00 (Jun'19) Prashant Gupta work in progress Detail Report
Graph / Photo
303 Construction of tubewell at Govt. Girls Senior Secondary School, West Patel Nagar, New Delhi. 14/03/2019 13/06/2019 4.50 ATUL SHARMA Detail Report
Graph / Photo
304 Making barrier free for accessibility of disabled persons at PCR Colony, Model Town II, Delhi 03/07/2020 02/08/2020 4.39 2.85 (Dec'20) 0.00 (Dec'20) Anshikha Enterprises work in progress (65%) Detail Report
Graph / Photo
305 EOR to Police Colony, Rajinder Nagar, New Delhi during 2018-19.(SH- Covering of open drain in Police Colony). 30/05/2018 28/07/2018 4.37 5.48 (Aug'19) 0.00 (Aug'19) G.S construction wip Detail Report
Graph / Photo
306 Misc. civil repair work 15/09/2019 14/12/2019 4.36 Shabbi Abbas Detail Report
Graph / Photo
307 Rain Water Harvesting structure at Rajokari Institute of Technology Rajokari New Delhi 04/02/2021 20/03/2021 4.33 BANSIWAL CONSTRUCTION COMPANY 100% work completed. Detail Report
Graph / Photo
308 Cons. of toilet in front of SCP Canteen and Requirement of bathroom and toilet in Community Centre. 23/03/2020 22/05/2020 4.12 5.14 (Mar'21) 0.00 (Mar'21) Panchu ram Detail Report
Graph / Photo
309 RMO of water coolers , Split or Window or Ductable ACs installed at Lawyers block , Utility Block , Lockup building and Main Court Building at District Court Complex saket New delhi -110017. 03/02/2019 02/02/2020 3.91 1.61 (Jul'19) 0.00 (Jul'19) ARORA ELECTRICAL WORKS Detail Report
Graph / Photo
310 EOR to National Law University, Sec-14, under Sub Div-III, SWBMD, New Delhi during 2018-19.(SH- Cleaning of sewerline by using super sucker machine). 05/06/2018 02/09/2018 3.81 3.81 (Dec'18) 70.00 % (Dec'18) Surender Singh Chahal work in progress Detail Report
Graph / Photo
311 Misc. civil repair works. 25/02/2019 25/04/2019 3.73 4.73 (Mar'21) 0.00 (Mar'21) Harsh Heights Pvt Ltd Work in progress. Detail Report
Graph / Photo
312 Replacement of broken kota stone flooring and wooden racks, false ceiling and white washing of MFA final year Sculpture Studio, College of Art at Tilak Marg, New Delhi 15/11/2019 14/12/2019 3.73 3.53 (Sep'20) 0.00 (Sep'20) Sher Singh Detail Report
Graph / Photo
313 Conversion of Garrage No 4 for Staff Accommodation at Bunglow No 3, 8 Raj Niwas Marg, Delhi dg. 2016-17. (SH:- Civil Work). 13/08/2016 01/09/2016 3.49 0.00 (Aug'16) 90.00 % (Aug'16) Work Completed Detail Report
Graph / Photo
314 Cleaning of Sewerline of Residential Building and Non Residential Building and repair in AAMC 14/11/2020 13/01/2021 3.47 UR Construction Work in Progress 10% Detail Report
Graph / Photo
315 A/R and M/O to AUD, Kashmere Gate, Delhi dg - 2015 -16( Finishing work) 26/11/2015 15/12/2015 3.19 Mohd Israil & Sons final bill and labour licence etc. Not submitted by the agency. Detail Report
Graph / Photo
316 Construction of boundary wall at Shastri Park court complex New Delhi (SH EI Work at the main gates and Guard Rooms) 06/08/2019 05/11/2019 3.17 0.00 (Dec'20) 99.00 % (Dec'20) M/S RAKESH KUMAR ARYA Work pending due to civil wing Detail Report
Graph / Photo
317 AMC of Computers,printer, UPS and Networking systems installed in the in Education Maint. Circle Unit 1, Unit 2, Division North PWD and its Sub-divisions 11/07/2020 10/07/2021 3.07 0.42 (Mar'21) 60.00 % (Mar'21) Silicate Technologies Private Limited

Work in progress.

Detail Report
Graph / Photo
318 Provision of Security Guard for Watch and ward at Old Age Home, Chattarpur under Sub Division-II, PTS Malviya Nagar, New Delhi during 2019-20. 21/06/2019 20/06/2020 3.05 3.05 (Mar'21) 0.00 (Mar'21) Universal Security & Placement Services (Regd.) work in progress Detail Report
Graph / Photo
319 Providing of work stations and file racks in the office of the Financial Commissioner at 5- Sham Nath Marg. Delhi. 30/06/2016 13/08/2016 2.73 0.00 (Apr'17) 50.00 % (Apr'17) work in progress Detail Report
Graph / Photo
320 A/R and M/O to I.G.D.T.U.W. at Kashmere Gate under Sub-Division-III, SRD Division-I, PWD, New Delhi During 2017-18 (SH-Specialized waterproofing treatment in the profile sheet gutter of workshop behind MAE Block). 21/04/2018 20/05/2018 2.62 0.00 (Jul'18) 2.90 % (Jul'18) Garg Waterproofing Company Work Completed and final bill paid Detail Report
Graph / Photo
321 Miscellaneous electrical work at Rouse Avenue District Court Complex New Delhi 26/03/2021 25/06/2021 2.60 R. Diamond Enterprises tender work in process Detail Report
Graph / Photo
322 A/R and M/O other PWD Roads under SRD Division -I, PWD, New Delhi during 2019-20. (SH- Painting of Kerb Stones on various roads for Independence Day under Sub Division-II.) 13/08/2019 27/08/2019 2.06 2.27 (Nov'19) 0.00 (Nov'19) MOHD AFTAB Detail Report
Graph / Photo
323 A/R & M/O to residensial building type -IV flats (duplex) at Maharaja lane. Dg.2015-16.( SH: Internal and External finishing of type-IV flats). 26/11/2015 25/12/2015 1.99 Mohd Israil & Sons final bill and labour licence etc. Not submitted by the agency. Detail Report
Graph / Photo
324 Soil Investigation. 02/06/2018 17/06/2018 1.43 M/S GEO Technical Consultants work is in progress. Detail Report
Graph / Photo
325 Photocopy, Scanning/ Digital Color Printing Job 21/02/2019 20/02/2020 1.02 0.00 (Jan'21) 87.20 % (Jan'21) Durga Electro State work is in progress Detail Report
Graph / Photo
326 Providing service of Photocopier Machine on rental basis in the office ofExecutive Engineer, Health Project Division (Central), PWD, Lok Nayak Hospital, New Delhi 24/10/2020 23/10/2021 0.37 Continental Copier Co. work in progress. Detail Report
Graph / Photo
327 Remodeling of Existing Casualty Block at L.N Hospital Block, New Delhi. 15/12/2019 14/03/2021 MIA Construction Pvt. Ltd. work in progress Detail Report
Graph / Photo
328 Providing and fixing PVC doors in bathrooms in qtrs. in place of old damaged ones. 18/09/2014 17/10/2014 Detail Report
Graph / Photo
329 Replacement of Damaged roof of Sub Divn. Office M-233. 11/11/2014 10/12/2014 Detail Report
Graph / Photo
330 Cleaning of sewer line, manhole & gully traps etc. 22/12/2014 21/01/2015 Detail Report
Graph / Photo
331 Providing and fixing door in toilet at G.G.S.S.S. Vasundhara Enclave Delhi School ID-1002185. 24/01/2015 23/02/2015 M. N. Construction Co. Detail Report
Graph / Photo
332 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kalyan Puri Delhi. 08/01/2015 07/02/2015 M. N. Construction Co. Detail Report
Graph / Photo
333 Providing and fixing polycarbonate in available. 19/12/2014 18/01/2015 Detail Report
Graph / Photo
334 Providing and fixing door & window shutters in pooling booth centre at GGSSS Kondli Gharoli. 06/02/2015 20/02/2015 Detail Report
Graph / Photo
335 Wall tile and other misc. civil work in Sports Complex at East Vinod Nagar. 27/02/2015 26/03/2015 Detail Report
Graph / Photo
336 Providing & fixing door and installation of PVC overhead tank for fire safety. 17/01/2015 -- Detail Report
Graph / Photo
337 Misc. Civil Works. 16/03/2015 30/03/2015 Shekhar Detail Report
Graph / Photo
338 Providing ramps in Schools & miscellenious works. 12/02/2015 26/02/2015 Detail Report
Graph / Photo
339 P/F Floor tile & broken tile. 20/11/2015 12/12/2015 Detail Report
Graph / Photo
340 Providing and laying cement concrete. 12/03/2015 25/03/2015 Indal Yadav Detail Report
Graph / Photo
341 Providing railing for Park. 23/11/2015 05/12/2015 Detail Report
Graph / Photo
342 Providing calcium silicate false ceiling & HRD fabrication in opening balcony at second floor. 16/09/2014 15/10/2014 Detail Report
Graph / Photo
343 Finishing of exterior wall in 20 nos. CBI flats. 08/12/2014 26/12/2014 Pradeep Kumar Sharma Detail Report
Graph / Photo
344 P/F Manhole cover & Drain cover. 08/01/2015 07/02/2015 M. N. Construction Co. Detail Report
Graph / Photo
345 Providing Security Guard for watch and ward for Sub Divn. Office & Vacant Flats at Mayur Vihar Ph-II and Division Office. 18/08/2014 01/01/2015 Detail Report
Graph / Photo
346 Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kondli Delhi-110091. 08/01/2015 04/02/2015 Detail Report
Graph / Photo
347 Providing services of labour for day to day maintenance under Sub-Division M-2334. 31/05/2014 -- Detail Report
Graph / Photo
348 Repairing of aluminium doors & Shutters. 19/08/2014 03/09/2014 Detail Report
Graph / Photo
349 Providing and laying RCC drain cover in open surface drain in basement. 16/08/2014 15/09/2014 2.58 (Mar'21) 0.00 (Mar'21) Detail Report
Graph / Photo
350 Improvement of Open Space in Circle Office & Division Office. 06/02/2015 -- Rajeev Sharma Detail Report
Graph / Photo
351 Misc. work at RSKV Mayur Vihar Ph-1 Pkt-IV. 17/01/2015 16/02/2015 Pradeep Kumar Sharma Detail Report
Graph / Photo
352 Providing and fixing FRP door shutters in place of old damaged flush door shutters. 18/09/2014 17/10/2014 Detail Report
Graph / Photo
353 Providing and fixing Acrylic sheet in windows, kerb stone, painting work and misc. civil work. 08/02/2015 08/03/2015 Detail Report
Graph / Photo
354 Repair to damaged windows, renewing glass panes with acrylic plastic sheet & signage work. 06/02/2015 15/03/2015 Detail Report
Graph / Photo
355 Water proofing treatment of first floor toilet. 15/12/2014 14/01/2015 Detail Report
Graph / Photo
356 D G Set 30/01/2015 29/07/2015 16.61 (May'19) 0.00 (May'19) Supernova Engineers Limited Detail Report
Graph / Photo
357 Lift work 20/12/2014 27/11/2015 Johnson Lifts Pvt. Ltd. work in progress Detail Report
Graph / Photo
358 Sub-station work 02/02/2015 01/08/2015 S.L. Electromech Pvt. Ltd. Detail Report
Graph / Photo
359 UPS System 23/01/2015 22/06/2015 Labotech completed Detail Report
Graph / Photo
360 200 Kwp Solar PV Plant 13/05/2015 12/10/2015 progress Detail Report
Graph / Photo
361 Fire fighting and Water supply pumps 13/01/2015 30/07/2015 Royale Meridian (India ) Pvt. Ltd. . Detail Report
Graph / Photo
362 Fire Alarm system 06/12/2014 07/10/2015 Electroquip Ltd. . Detail Report
Graph / Photo
363 Energy Management System 26/04/2015 25/07/2015 . Detail Report
Graph / Photo
364 Modular OT 25/05/2015 24/11/2015 . Detail Report
Graph / Photo
365 IP Based CCTV 27/03/2015 26/08/2015 . Detail Report
Graph / Photo
366 ETP System 27/01/2015 26/07/2015 Texol Engineers . Detail Report
Graph / Photo
367 IP based LAN & voice communication system 21/03/2015 20/08/2015 Tacker Technologies Pvt. Ltd. . Detail Report
Graph / Photo
368 EOR to SSA Building at DIET, Darya Ganj, Delhi. (SH:- False Ceiling, Kota Flooring, Wall tiles etc.) 09/06/2016 08/08/2016 K.P. Singh & Co. Site not handed over by DIET Detail Report
Graph / Photo
369 Renovation of D.D.E. office by changing sanitary & plumbing fixtures in office toilet and internal finishing works 04/07/2016 03/09/2016 0.00 (Aug'16) 40.00 % (Aug'16) Work completed Detail Report
Graph / Photo
370 Construction of Double storeyed SPS type rooms for Cal lab,Library,Science labs,toilet for HOS & staff at Govt. Co.Ed.Edn.Dichaon Kalan,New Delhi. 18/12/2017 15/06/2019 34.21 (Jun'19) 100.00 % (Jun'19) work in progress. Detail Report
Graph / Photo
371 Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. 25/06/2016 24/07/2016

NA

Detail Report
Graph / Photo
372 C/o Boundary wall on the newly taken over plot at village Dera Mandi, New Delhi. 25/03/2016 24/07/2016 0.00 (Aug'16) 75.00 % (Aug'16) DOSE PERTAIN TO THIS DIVISION Detail Report
Graph / Photo
373 Arrangement of Drinking water facility by bore well at GBSSS No. 1, Khanpur, New Delhi. (School ID : 1923020) 10/05/2016 09/06/2016 0.00 (Jul'16) 50.00 % (Jul'16) Tender re-call and date of opening 24-09-2016 Detail Report
Graph / Photo
374 EOR to Raja Ram Mohan Rai, Hauz Rani, New Delhi. (SH: laying of one borewell & installation of 1 Nos. R.O. System 23/05/2016 23/06/2016 0.00 (Jul'16) 70.00 % (Jul'16) Dose not pertain to this Division Detail Report
Graph / Photo
375 EOR to Govt.Sarvodaya Vidyalaya Gokhle Marg School,No.2,Mori Gate,Delhi. 15/04/2016 14/10/2016 0.00 (Jul'16) 10.00 % (Jul'16) Completed Detail Report
Graph / Photo
376 EOR to slabs beams, coloums chajjas by short creting replacement of old & damaged roof treatment and other misc repair work at Sarvodaya Kanya Vidyala,Ahataa Kedara Idgah road Delhi. 15/04/2016 14/07/2016 0.00 (Jul'16) 15.00 % (Jul'16) Completed Detail Report
Graph / Photo
377 Improvement of ground with drainage system and providing paver blocks, kota stone flooring in classroom & varandah, repair to boundary wall & other Misc. work at Idhgh road-GGSS 05/04/2016 04/06/2016 0.00 (Jul'16) 80.00 % (Jul'16) Completed Detail Report
Graph / Photo
378 Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. 17/01/2016 30/04/2016 0.00 (Jul'16) 80.00 % (Jul'16) polycarbonate Detail Report
Graph / Photo
379 Renovation of MP Hall. 26/04/2016 24/06/2016 16.37 (Feb'21) 0.00 (Feb'21) Work recently awarded. Detail Report
Graph / Photo
380 Construction of water module. 22/04/2016 20/06/2016 0.00 (Jul'16) 0.01 % (Jul'16) Work recently awarded. Detail Report
Graph / Photo
381 providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. 01/05/2016 30/06/2016 0.00 (Jul'16) 0.01 % (Jul'16)

work in progress

Detail Report
Graph / Photo
382 E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi 10/04/2016 09/06/2016 0.00 (Jul'16) 0.01 % (Jul'16)

Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270

Detail Report
Graph / Photo
383 const. of New cycle stand, Dismantling of tin shed and rovision of free path from toilet to first gate. 13/06/2016 12/07/2016 0.00 (Sep'16) 11.00 % (Sep'16) Work in porgress Detail Report
Graph / Photo
384 Renovation of M.P. Hall 26/04/2016 04/06/2016 0.00 (Sep'16) 66.00 % (Sep'16) work in progress Detail Report
Graph / Photo
385 Construction of new boundary wall 24/04/2016 20/07/2016 21.77 (May'17) 100.00 % (May'17) Detail Report
Graph / Photo
386 Renovation of M.P. Hall with Toilet Block of G.S.K.V at E Block, Nand Nagri, Delhi 29/01/2016 28/05/2016 6.64 (Jan'18) 100.00 % (Jan'18) work in progress Detail Report
Graph / Photo
387 Development of ground and construction of stage at G.G.S.S. F-1, F-2 Block, Nand Nagri,Delhi School ID-1106026 14/04/2016 12/06/2016 5.75 (Feb'17) 100.00 % (Feb'17)

Work in progress

Detail Report
Graph / Photo
388 Renovation of Classrooms. 07/05/2016 05/07/2016 0.00 (Sep'16) 66.00 % (Sep'16) Work in progress Detail Report
Graph / Photo
389 Repair of Basketball Court Flooring. 06/05/2016 19/06/2016 0.00 (Sep'15) 25.00 % (Sep'15) site is not handed over to contractor since in the working areathe work of SPS Detail Report
Graph / Photo
390 Repair of boundary wall and toilets. 06/05/2016 03/08/2016 0.00 (Sep'16) 86.00 % (Sep'16) Work in progress Detail Report
Graph / Photo
391 Providing Rain Water Harvesting pit, laying interlocking paver block in the ground and raising of boundary wall at Govt. Girls Sr. Sec. School at A Block, Nand Nagri, Delhi Building ID-11061019 10/06/2016 09/10/2016 0.00 (Sep'16) 76.00 % (Sep'16) work in progress Detail Report
Graph / Photo
392 Renovation of Principal Room, Staff Room and Laboratories. 20/06/2016 18/08/2016 0.00 (Sep'16) 71.00 % (Sep'16) Work in progress Detail Report
Graph / Photo
393 Repair and renovation of toilets 17/06/2016 15/08/2016 0.00 (Sep'16) 91.00 % (Sep'16)

Detailed estimate under process.

Detail Report
Graph / Photo
394 Renovation of Classrooms, Corridor, Principal Room & Staff Room. 16/06/2016 13/09/2016 0.00 (Sep'16) 53.00 % (Sep'16)

T.S. under process.

Detail Report
Graph / Photo
395 Construction of SPS type 01 No M.P. Hall, 01 No. Dining Hall with Kitchen, 2 Nos.Guest room, garrage for two vehicle and 2 Nos. Dormitory at 1st floor on under construction single storied dormitories and construction of approach road for Nehru Yuva Kendra, Alipur, Delhi 12/09/2016 11/05/2017 Work stopped by client deptt vide their letter No-NYKS/Construction work/Admin/2016-17/693 dated 09.03.2017. No response from client about restart of work. The contractor is approaching for closure of agmt. Now the clint has permitted to re-start the work and work has been re-started on 25.07.2018. but progress is slow. Detail Report
Graph / Photo
396 A/R and M/O to residential and Non residential Building under Sub Div-II of SWBMD at ITI Campus, Pusa, New Delhi during 2018-19.(Sh- Misc repair work and finishing work in quarters). 23/05/2018 21/11/2018 14.29 (Jul'19) 0.00 (Jul'19) work in progress. Detail Report
Graph / Photo
397 A/R and M/O to Residential and Non Residential building under Building Maintenance Sub Division (SW) - 4, PWD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19.(SH Engaging labour for Day to Day Maintenance). 17/05/2018 16/05/2019 94.01 (Mar'20) 0.00 (Mar'20) WORK IN PROGRESS Detail Report
Graph / Photo
398 Acoustic work. 02/02/2018 01/04/2018 67.40 (Jul'18) 100.00 % (Jul'18)

Work in progress

Detail Report
Graph / Photo
399 C/o New Block for Medicaine, Maternity and advance pediatric centre at L.N.Hospital 04/11/2020 03/05/2023 Execution of D-wall is under progress. Detail Report
Graph / Photo
400 Construction of new building (‘S’ Block) for Delhi High Court on 2.74 Acre Land at Bapa Nagar, Zakir Hussain Marg, New Delhi. (SH: Providing consultancy services for obtaining Green Building rating including day light simulation, Energy simulation, GRIHA rating certification and facilitation) 01/01/2016 31/01/2016 work in progress Detail Report
Graph / Photo
401 Acoustic treatment system and renovation of multipurpose hall. 20/10/2017 17/01/2018 9.27 (Jun'20) 0.00 (Jun'20) work in progress Detail Report
Graph / Photo
402 Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. 16/10/2016 15/11/2016 forfeited Detail Report
Graph / Photo
403 Installation of R.O System at Dr. Ambedkar Nagar ,Sector-V , No-2-GGSSS-1923050. 20/08/2016 15/09/2016 0.00 (Aug'16) 0.01 % (Aug'16) work completed Detail Report
Graph / Photo
404 C/o toilet attached to office & providing safety cage for water tank at Kothi No. 115 (Dy. Chairman Dialouge Commissioner) Daryaganj, Delhi. 03/06/2017 02/07/2017 Work In Progress. Detail Report
Graph / Photo
405 Renvoation of CCTV Camera PWD office at 13th Floor, MSO Building New Delhi 18/07/2016 17/09/2016 Work In Progress Detail Report
Graph / Photo
406 Mechanized housekeeping services for Internal and external areas of MSO Building, Delhi, dg, 2016-17 02/04/2017 01/03/2019 31.08 (Feb'20) 0.00 (Feb'20) Work In Progress Detail Report
Graph / Photo
407 Repair and renovation work in Bomb Disposal squad & summon warrant Cell building, crime & railways at Yamuna Bazar, Delhi . 10/06/2016 09/08/2016 Work In Progress Detail Report
Graph / Photo
408 C/o 20 Nos. SPS type class rooms including toilet blocks, staircase and electrical installations, fan etc. at Sarvodaya (Co-ed) Sr. Sec. School, Netaji Nagar, (School I.D.) 1719102, Building I.D. 17191327). New Delhi 04/11/2014 30/09/2015 85% Work is in Progress Detail Report
Graph / Photo
409 Up gradation to Delhi Govt. D-II Flats, Vasant Kunj, New Delhi. 05/02/2017 04/08/2017 100.57 (Jul'18) 100.00 % (Jul'18)

Work in progress

Detail Report
Graph / Photo
410 Providing Services of Security Guard at T.V. Branch Enquiry Office 10/04/2017 09/04/2018 2.52 (Apr'18) 90.00 % (Apr'18) Work completed Detail Report
Graph / Photo
411 RMO Eand M Services at GNEC, New Delhi SH Comprehensive Maintenance of Aquaguard Water Dispenser with Inbuilt RO and UV Purifier 19/03/2017 18/03/2019 Work in Progress Detail Report
Graph / Photo
412 Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. 02/11/2018 01/11/2019 214.77 (Sep'19) 0.00 (Sep'19) Work in progress Detail Report
Graph / Photo
413 Construction of Boundary wall at Sayurpur Village, New Delhi. (SH- Providing fixing grills and concertina coil at boundary wall). 10/07/2018 09/09/2018 work in progress Detail Report
Graph / Photo
414 A/R and M/O to Educational Building under SWBMD, B-6, NCC Building, Safdarjung Enclave, New Delhi during 2018-19. (Sh -Internal and external finishing and other misc works). 03/08/2018 01/10/2018 WORK IN PROGRESS Detail Report
Graph / Photo
415 AR and MO to District Court Resid. Complex Saket, ND-18-19 (SH Cleaning, mopping of common area, like lift lobby, staircase, basement, community centre, footpath area, terrace, servant qtr. etc. by mopping machine at Resid. Complex Saket Court, ND). 25/09/2018 24/09/2019 0.49 (Nov'18) 25.00 % (Nov'18) work in progress Detail Report
Graph / Photo
416 REMODELLING AND UPGRADING OF EXISTING DEEP CHAND BANDHU HOSPITAL AT KOKIWALA BAGH, ASHOK VIHAR, PH-IV, DELHI. 28/06/2019 22/06/2020 0.00 (Mar'19) 0.01 % (Mar'19) Agency has gone in the arbitration. work in progress Detail Report
Graph / Photo
417 SKV Vishwas Nagar (School Id- 1001196) 24/12/2018 19/09/2019 0.00 (Apr'19) 2.00 % (Apr'19) Structure work of 44 Rooms completed and internal & external finishing in toilets which is in progress, Lift work footing cast. Work of MP hall yet to start. Detail Report
Graph / Photo
418 SKV Surajmal Vihar (School Id- 1001102) 24/12/2018 19/09/2019 Structure work completed & mumty is in progress. Internal & external finishing in progress in Block A & B. Dismantling work not started for Block-C Detail Report
Graph / Photo
419 SKV, Kiran Vihar (School Id- 1001106) 24/12/2018 19/09/2019 Terrace floor roof is in progress for both blocks A & B. Brick work in progress Detail Report
Graph / Photo
420 Govt. Co-ed SSS Preet Vihar (School Id- 1002351) 24/12/2018 19/09/2019 0.00 (Apr'19) 1.50 % (Apr'19) Structure work of 48 Rooms completed and internal & external finishing in progress. Work of MP hall yet to start. The site of MP Hall shall be made available for dismantling the single storied class rooms after handing over the 48 class rooms. Detail Report
Graph / Photo
421 S(Co. Ed.) Hiran Kundna (School ID - 1617006). 13/01/2019 23/12/2019 0.00 (Jan'21) 98.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
422 G(Co. Ed.)SS Kunwar Singh Nagar Ranhaula (School ID - 1617214). 13/01/2019 23/12/2019 0.00 (Jan'21) 97.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
423 SKV Uttam Nagar (School ID - 1618057). 18/01/2019 13/12/2019 0.00 (Jan'21) 72.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
424 G(Co.Ed.)SS Vikas Nagar (School ID - 1618057). 18/01/2019 13/12/2019 0.00 (Jan'21) 40.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
425 GBSSS KG-I/II Vikaspuri (School ID - 1618015). 18/01/2019 13/12/2019 0.00 (Jan'21) 78.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
426 SBV Moti Nagar (School ID - 1516010). 09/01/2019 06/08/2019 0.00 (Jan'21) 87.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
427 SKV Moti Nagar (School ID - 1516018). 09/01/2019 06/08/2019 0.00 (Jan'21) 92.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
428 GBSSS West Patel Nagar (School ID - 1516140). 13/01/2019 23/12/2019 0.00 (Oct'20) 37.00 % (Oct'20) Work is in progress. Detail Report
Graph / Photo
429 SBV West Patel Nagar (School ID - 1516143). 13/01/2019 23/12/2019 1536.19 (Feb'21) 0.00 (Feb'21) Work is in progress. Detail Report
Graph / Photo
430 GGSSSS No. I Tilak Nagar (School ID - 1514014). 13/01/2019 09/10/2019 0.00 (Jan'21) 89.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
431 GGSSS No. 2 A-Block Janakpuri (School ID - 1618064). 07/12/2018 04/08/2019 0.00 (Jan'21) 93.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
432 S(Co. Ed.) Block-L Hari Nagar (School ID - 1514022). 07/12/2018 04/08/2019 0.00 (Jan'21) 87.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
433 GBSSS Site-2 Clock Tower, Hari Nagar (School ID - 1514112). 07/12/2018 04/08/2019 0.00 (Jan'21) 85.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
434 GGSSS Ashok Nagar (School ID - 1514018). 13/01/2019 23/12/2019 0.00 (Oct'20) 64.00 % (Oct'20) Work is in progress. Detail Report
Graph / Photo
435 SBV Subhash Nagar (School ID - 1515003). 13/01/2019 23/12/2019 4611.46 (Jan'21) 85.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
436 GBSSS Rajouri Garden Extn. (School ID - 1515018). 13/01/2019 23/12/2019 4611.46 (Jan'21) 70.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
437 SKV Rajouri Garden Extn. (School ID - 1515021). 13/01/2019 23/12/2019 4611.46 (Jan'21) 78.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
438 SKV Rajouri Garden Main (School ID - 1515022). 13/01/2019 23/12/2019 4611.46 (Jan'21) 81.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
439 SKV No. 2 Tarogre Garden (School ID - 1515025). 13/01/2019 23/12/2019 4611.46 (Jan'21) 66.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
440 GBSSS Tagore Garden (School ID - 1515139). 13/01/2019 23/12/2019 4611.46 (Jan'21) 63.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
441 EOR to Govt. Co-ed. Sr. Sec. School at Daulatpur and Govt. Co-ed. Sr. Sec. School at Malikpur, New Delhi. (Sh- C/o Rain Water Harvesting System). 04/03/2019 02/05/2019 69.90 (Aug'19) 0.00 (Aug'19) WORK IN PROGRESS Detail Report
Graph / Photo
442 GGSSS No. 2, Molarband School ID : 1925053 14/01/2019 10/10/2019 0.00 (Mar'21) 73.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
443 GGSSS No. 4, Molarband School ID : 1925400 14/01/2019 10/10/2019 0.00 (Mar'21) 65.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
444 S.K.V., Molarband School ID : 1925037 14/01/2019 10/10/2019 0.00 (Mar'21) 62.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
445 GGSSS DDA Flat, Kalkaji, Phase-II, School ID: 1925041 14/01/2019 10/10/2019 0.00 (Mar'21) 51.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
446 GGSSS No. 3, Badarpur, School ID : 1925248 14/01/2019 10/10/2019 0.00 (Mar'21) 75.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
447 GGSSS No. 3, Kalkaji School ID : 1925039 14/01/2019 10/10/2019 0.00 (Mar'21) 26.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
448 SKV Mandi Village, School ID : 1923064 14/01/2019 10/10/2019 0.00 (Apr'21) 42.00 % (Apr'21) Work is in progress Detail Report
Graph / Photo
449 SPM Sarvodaya Vidyalya Chittaranjan park, School ID: 1925060 14/01/2019 10/10/2019 0.00 (Mar'21) 80.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
450 SKV No. 2, East of Kailash, School ID: 1924027 23/01/2019 19/10/2019 0.00 (Mar'21) 90.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
451 GBSSS, No. 2, Kalkaji, , School ID: 1925011 23/01/2019 19/10/2019 0.00 (Mar'21) 38.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
452 GBSS, Garhi, Jharia Maria School ID : 1924042 23/01/2019 19/10/2019 0.00 (Mar'21) 72.00 % (Mar'21)

Work is in progress

Detail Report
Graph / Photo
453 SKV No. 2 Khyala (School ID - 1514013). 13/01/2019 23/12/2019 7696.54 (Feb'21) 0.00 (Feb'21) Work is in progress. Detail Report
Graph / Photo
454 SBV Chand Nagar (School ID - 1514110) 13/01/2019 23/12/2019 0.00 (Oct'20) 75.00 % (Oct'20) Work is in progress. Detail Report
Graph / Photo
455 GGSSS J. J. Colony Raghubir Nagar (School ID - 1515030). 13/01/2019 23/12/2019 0.00 (Oct'20) 65.00 % (Oct'20) Work is in progress. Detail Report
Graph / Photo
456 SV(Co. Ed.) A-2, Paschim Vihar (School ID - 1617003). 13/01/2019 09/10/2019 0.00 (Jan'21) 81.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
457 SV (Co. Ed.) B-4 New Multan Nagar (School ID - 1617007). 13/01/2019 09/10/2019 0.00 (Jan'21) 75.00 % (Jan'21) Work is in progress. Detail Report
Graph / Photo
458 SV Shahpur Jat, School ID: 1925333 08/12/2018 04/08/2019 0.00 (Mar'21) 93.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
459 S.B.V., Sadiq Nagar, School ID: 1924009 08/12/2018 04/08/2019 0.00 (Mar'21) 93.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
460 SV Safdarjung Enclave, School ID: 1719106 08/12/2018 04/08/2019 0.00 (Mar'21) 98.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
461 SKV Hauzrani, School ID: 1923041 08/12/2018 04/08/2019 0.00 (Mar'21) 90.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
462 GBSSS Dera Village School ID: 1923360 08/12/2018 04/08/2019 0.00 (Feb'21) 63.00 % (Feb'21) In progress Detail Report
Graph / Photo
463 Co-Ed. SSS Lajpat Nagar, School ID: 1925335 08/12/2018 04/08/2019 0.00 (Mar'21) 42.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
464 GBSSS Jungpura, School ID : 1924004 08/12/2018 04/08/2019 0.00 (Mar'21) 50.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
465 GGSSS, DDA Flats, Phase II, Kalkaji, School ID: 1925045 14/01/2019 10/09/2019 0.00 (Mar'21) 42.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
466 Govt. Co.-Ed., Middle School, Sarai Kale Khan, Vidut Nagar, School ID: 1925418 14/01/2019 10/09/2019 0.00 (Mar'21) 25.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
467 SKV,, Jonapur- BNK, School ID: 1923003 08/12/2018 04/08/2019 0.00 (Feb'21) 62.00 % (Feb'21) In progress Detail Report
Graph / Photo
468 GGSS, Begumpur, School ID: 1923072 23/01/2019 19/10/2019 0.00 (Mar'21) 1.00 % (Mar'21) Building has been demolished and malba disposal is in progress Detail Report
Graph / Photo
469 Sarvodaya Co-ed Vidyalaya Sec-2, R K Puram, New delhi, School ID: 1719013 23/01/2019 19/10/2019 0.00 (Mar'21) 57.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
470 GBSSS Sec-3, R K Puram, School ID: 1719103 23/01/2019 19/10/2019 0.00 (Mar'21) 1.00 % (Mar'21) Site not handed over by the Education Department. Detail Report
Graph / Photo
471 SKV Noor Nagar, School ID 1925035 23/01/2019 19/10/2019 0.00 (Mar'21) 13.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
472 GGSSS Jogabai, New Delhi School ID : 1925049 23/01/2019 19/10/2019 0.00 (Mar'21) 45.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
473 EOR to GBSSS Bijwasan, Govt. Sarvodaya Co-ed Sr. Sec. School Kitchner Road (Malcha Marg), DIET Sec-07 R.K. Puram etc New Delhi.(Sh- Construction of Rain Water Harvesting System). 22/02/2019 24/04/2019 47.84 (Jul'19) 80.00 % (Jul'19) WORK IN PROGRESS. Detail Report
Graph / Photo
474 S.K.V. A-Block, School ID : 1924025 14/01/2019 10/10/2019 0.00 (Mar'21) 84.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
475 S.K.V. C-Block, Defence Colony, School ID : 1924023 14/01/2019 10/10/2019 0.00 (Mar'21) 78.00 % (Mar'21) in progress Detail Report
Graph / Photo
476 S.V. Jorbagh, School ID 2026005 14/01/2019 10/10/2019 0.00 (Mar'21) 72.00 % (Mar'21) work is in progress Detail Report
Graph / Photo
477 S.K.V. Rani Jhansi, School ID 1925031 14/01/2019 10/10/2019 0.00 (Mar'21) 98.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
478 GGSSS No. 2, Tughlakabad, Railway Colony, School ID 1925046 14/01/2019 10/10/2019 0.00 (Mar'21) 83.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
479 GGSSS Tigri, School ID 1923080 14/01/2019 10/10/2019 0.00 (Mar'21) 82.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
480 Ishani G- Block Saket, School ID 1923036 14/01/2019 10/10/2019 0.00 (Mar'21) 88.00 % (Mar'21)

Work is in progress

Detail Report
Graph / Photo
481 SKV MB Road Pushp Vihar, School ID 1923071 14/01/2019 10/10/2019 0.00 (Mar'21) 87.00 % (Mar'21) Work is in progress Detail Report
Graph / Photo
482 AR and MO to Delhi Sachivalaya at IG Stadium Complex New Delhi dg 2018 19 10/11/2018 09/05/2019 1.02 (Jul'19) 0.00 (Jul'19) Work in Progress 95% Detail Report
Graph / Photo
483 Construction of 30 Nos. Porta Cabin Aam Admi Mohalla Clinics under Sub division- I,II,III and IV under South West Building Maintenance Division New Delhi. (SH Civil works and Electrical works). 06/12/2018 02/08/2019 285.83 (Nov'20) 0.00 (Nov'20) WORK IN PROGRESS Detail Report
Graph / Photo
484 Construction of additional SPS type classrooms in Govt Schools Directorate of Education under Priority II 05/09/2019 04/09/2020 0.11 (Nov'19) 0.00 (Nov'19)

work in progress

Detail Report
Graph / Photo
485 A PL paver block repair and renovation of room No 41 at SKV Khera Kalan BNN B PL APP treatment at roof of SBV Auchandi Delhi 05/11/2019 02/02/2020 0.00 (Sep'20) 50.00 % (Sep'20) work is in progress (60%) Detail Report
Graph / Photo
486 Pumping out rainwater to avoid water logging at DC office complex,Weavers Complex Nand Nagri and SDM Court Seelampur Delhi. 30/06/2019 29/10/2019 5.86 (Jan'20) 0.00 (Jan'20)

work completed

Detail Report
Graph / Photo
487 Providing the services of Security Guard for day to day maintenance at D-II flats. 02/08/2019 01/08/2020 work in progress Detail Report
Graph / Photo
488 Providing security guards at Division Office M-222 (NE), Sub Division M-2222, Sub Division M-2221, Sub Division Office Loni Road and Division M-222 30/06/2019 29/05/2020 23.93 (Mar'21) 0.00 (Mar'21)

work completed

Detail Report
Graph / Photo
489 Attending day to day complaints 24/06/2019 23/06/2020 10.22 (Oct'20) 0.00 (Oct'20)

work completed

Detail Report
Graph / Photo
490 Construction of multipurpose court, levelling and preparing the layer of good earth on the play ground in Delhi Police Public School at PTS, Wazirabad, Delhi 30/06/2019 29/08/2019 26.71 (Mar'21) 0.00 (Mar'21)

work in progress

Detail Report
Graph / Photo
491 Raising of main gate, C/o guard room, repair of ground water tank, providing and fixing IRC fabric jali inside the Class rooms etc. 30/06/2019 29/08/2019 1.60 (Mar'21) 0.00 (Mar'21)

work completed

Detail Report
Graph / Photo
492 Construction of Recreation Room, Coys room, Officers Quarters and Shed. 30/06/2019 29/08/2019 51.12 (Jul'20) 0.00 (Jul'20)

work completed

Detail Report
Graph / Photo
493 Construction of 2 nos.Viewers stand in Parade ground at PTS, Wazirabad, Delhi 30/06/2019 19/07/2019 8.39 (Jan'20) 0.00 (Jan'20)

work completed

Detail Report
Graph / Photo
494 Attending complaints of routine maintenance of service centre PTS, Wazirabad, Delhi. 30/06/2019 29/06/2020 7.20 (Mar'20) 0.00 (Mar'20)

work completed

Detail Report
Graph / Photo
495 Renovation of 10 Nos toilet blocks, Construction of 3 nos. R.C.C. tank of size 8 x 5 mtr. and 6 nos. M.S. grill gates. 30/06/2019 29/08/2019 52.31 (Aug'20) 0.00 (Aug'20)

work completed

Detail Report
Graph / Photo
496 External plaster work of Judges Flats Including tile work in over head water storage tank of block D AND E, Steel works and other Misc. work 24/10/2019 23/01/2020 work in progress Detail Report
Graph / Photo
497 External plaster work including painting. 16/06/2019 15/09/2019 work in progress Detail Report
Graph / Photo
498 Redevelopment of rain water harvesting pits and cleaning of storm water lines at Residential and Non-Residential Complex, Saket Court, New Delhi. 25/07/2019 24/09/2019 work in progress Detail Report
Graph / Photo
499 Reconstruction of collapsed boundary wall of CBD plot at Shahdara, Delhi owned by Urban Development Department. 24/07/2019 22/09/2021 in progress. Detail Report
Graph / Photo
500 SKV Radhey Shyam Park (School Id- 1003153) 17/03/2019 11/12/2019 In Block A Part-I of 16 rooms structure complete and finishing in progress, Part-II, Terrace roof of 16 room has been cast and column of Mumty above is in progress. In Block B Part-I of 16 rooms structure complete and finishing in progress, Part-II, Mumty has been cast. MP hall earth work has started. Koba work is in progress. External GRC Tile work is in progress. Detail Report
Graph / Photo
501 SKV Shanker Nagar (School Id- 1003026) 17/03/2019 11/12/2019 0.00 (Jan'21) 25.00 % (Jan'21) Structure of 24 rooms complete. Plastering, Kota, Koba, Stair Case Granite & other miscellaneous work are under progress. Detail Report
Graph / Photo
502 RPVV Gandhi Nagar (School Id- 1003261) 17/03/2019 11/12/2019 12491.60 (Nov'20) 0.00 (Nov'20) Structure of 48 rooms complete. Stair case granite, cladding, brick koba work and other miscellaneous works are under progress. 1st floor beam of 4 rooms and 1 lift has been cast. Detail Report
Graph / Photo
503 SBV, Rajgarh Colony (School Id- 1001110) 17/03/2019 11/12/2019 0.00 (Apr'19) 0.50 % (Apr'19) RCC Structure is completed. Painting inside building is under progress and other miscellaneous work has been taken up. Ground floor column of MP hall has been cast. Raft of Block-C has been cast. Detail Report
Graph / Photo
504 SKV Kondali (Jija Bai) (School Id- 1002026) 17/03/2019 11/12/2019 0.00 (Jan'21) 81.00 % (Jan'21) Polishing of Kota/Marble Stone is under progress. GRC Tile completed. Fixing of Poly Carbonate Sheet in Window completed. Painting inside classrooms is under progress. Plumbing work in toilets and sanitary fittings work completed. External development work is under progress. Laying of SW Pipe, construction of chamber completed. Construction of RCC Road work completed. Laying of Interlocking Paver Block and other development activities completed. Detail Report
Graph / Photo
505 GGSSS Mayur Vihar Ph-3 (Kondali Gharauli) (School Id- 1002352) 17/03/2019 11/12/2019 0.00 (Jan'21) 1.00 % (Jan'21) Brick work at 2nd floor level is under progress. Cement Plaster at 1st floor is under progress. Flooring work is under progress at 2nd floor level. Fixing of Window & T-iron frame at 2nd floor level is under progress. Tiles have been procured for fixing in cladding. Reinforcement in columns from 3rd floor to terrace in Block-B is in progress. Casting of terrace floor beam in Block-A (RHS) under progress. Detail Report
Graph / Photo
506 SKV Patparganj (School Id- 1002031) 17/03/2019 11/12/2019 12491.60 (Nov'20) 0.00 (Nov'20) RCC in columns from Ground Floor to 1st Floor is completed. Casting of Beam at 1st floor level completed. Reinforcement work in Column from 1st floor to 2nd floor is in progress. Detail Report
Graph / Photo
507 GGSSS Khichripur (School Id- 1002037) 17/03/2019 11/12/2019 0.00 (Jan'21) 30.00 % (Jan'21) "Block-A : (20 rooms) : Terrace beam is in progress. Block-B : (24 Rooms) : Terrace beam is in progress. Block-C : (28 Rooms) : Column from third floor to terrace beam is in progress. Block-D : (4 Rooms) : Demolition of old structure in progress. Brick work, AAC block masonry, Plaster and fixing of door frame & windows work are in progress. " Detail Report
Graph / Photo
508 Bhola Nath Nagar, No.3-GGSSS (ID : 1001023) (DIET BUILDING) 17/03/2019 11/12/2019 0.00 (Jan'21) 1.00 % (Jan'21) Second floor roof is in progress. Detail Report
Graph / Photo
509 Jhilmil Colony-SBV Avinash Chadda (ID: 1001105 ) (Addl. Rooms) 17/03/2019 11/12/2019 Preliminary Estimate amounting to Rs. 17,16,56,000/- for C/o 64 Nos. Additional SPS Class rooms in ACC SBV/GGSSS, Jhilmil colony, Delhi (ID : 1001105/1001111) was submitted to the Director of Education vide letter no. 23(49)/20/CE (Proj.)/PWD/Estimate/316 dt. 13.07.2020 (Copy enclosed), whose sanction is still awaited. Any action to call the tenders can only be started after receipt of the A/A & E/S or on any request made by Directorate of Education in anticipation of the same. The survey report for demolition of SPS Structure in the same school was also submitted vide this office letter no. 20(Survey report)/Edu M(E&NE)/PWD/DS/973 dt. 02.11.2020, which is also still awaited. Regarding taking up of the 64 Additional Class rooms in the ACC SBV/GGSSS, Jhilmil colony, Delhi, clear instructions may please be issued by the competent authority for calling the tenders in anticipation of A/A & E/S against the Preliminary estimate submitted. Detail Report
Graph / Photo
510 Construction of G4 storey Police Post including Rain Water Harvesting Tank Underground water tank and development work at Sanjay Gandhi Transport Nagar Delhi Civil and Electrical 08/11/2019 07/07/2020 work is started Detail Report
Graph / Photo
511 Consultancy Services for Construction (on EPC mode) of New Block for expansion of Deen Dayal Upadhyay Govt. Hospital of Hari Nagar, Delhi. 28/05/2020 27/11/2022 1st RA Bill Detail Report
Graph / Photo
512 C/o boundary wall of vacant land piece at Aya Nagar, New Delhi. 18/05/2018 17/11/2018 63.30 (Feb'21) 0.00 (Feb'21) In progress Detail Report
Graph / Photo
513 C/o Additional 176 SPS class rooms in existing premises including Labs, Library, Toilet blocks etc. under jurisdiction EO Zone 27 of DDE, Bulbuli Khana SKV (school ID: 2127021) and Kamla Market Zeenat Mahal- SKV No.1 (School IS: 2127014) Central & New Delhi. (Priority-2) 16/03/2019 10/12/2019 25159.43 (Feb'21) 0.00 (Feb'21)

work in progress

Detail Report
Graph / Photo
514 C/o 138 Nos. of additional SPS class rooms in various schools under Central and New Delhi, Education (M) Division, PWD including internal & external water supply, sanitary installation, electrical installations, development of site and fire fighting system etc. (Package - 2). 18/01/2019 14/09/2019 25159.43 (Feb'21) 0.00 (Feb'21)

work in progress

Detail Report
Graph / Photo
515 Construction of 28 Nos. Additional SPS classrooms in Govt. Girls. Sr. Sec. School, Urdu Medium (School ID:- 2127025) at Chasma Building , Ballimaran, Delhi- 29/09/2018 26/06/2019 267.49 (Mar'21) 0.00 (Mar'21)

work in progress

Detail Report
Graph / Photo
516 Construction of 28 Nos. Additional SPS classrooms in Govt. Girls. Sr. Sec. School, Urdu Medium (School ID:- 2127025) at Chasma Building , Ballimaran, Delhi- (SH:- SPS type building i/c Internal & External water supply, sanitary installation, ramp, electrical installation, development of site, fire fighting system & providing furniture etc. 29/09/2018 26/06/2019 0.00 (Feb'20) 100.00 % (Feb'20)

work in progress

Detail Report
Graph / Photo
517 Hiring of Inspection Vehicle along with Driver in the office of Executive Engineer Health Project Division (East), PWD, Tahirpur, Delhi-110093 dg. 2019-20 02/03/2020 01/09/2020 Work completed. Detail Report
Graph / Photo
518 C/o Trauma Centre and Utility Block at SGMH at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Hiring of Photocopier Machine.) 04/09/2019 03/03/2021 work in progress Detail Report
Graph / Photo
519 C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Libaspur, Delhi. 30/05/2020 29/05/2021 0.00 (Mar'21) 18.00 % (Mar'21)

Foundation/footing of 30% portion completed and remaining portion in progress.

Detail Report
Graph / Photo
520 C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Daryapur kalan, Delhi. 30/05/2020 29/05/2021 0.25 (Mar'21) 13.00 % (Mar'21)

Casting of footing in progress.

Detail Report
Graph / Photo
521 C/O Pucca School Building (G+3) of Govt. Sr Sec. School (Co-Ed) at Rana Pratap Bagh (School ID: 13091907), Delhi.(SH: Main Civil Work). 02/09/2020 29/05/2021 0.00 (Mar'21) 25.00 % (Mar'21)

Foundaton work completed. Plinth beam, column work in progress.

Detail Report
Graph / Photo
522 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priority II. 05/09/2019 04/09/2020 612.63 (Mar'21) 0.00 (Mar'21)

work in progress

Detail Report
Graph / Photo
523 C/o SPS type additional class rooms under Priority II. 16/03/2019 10/12/2019 25159.43 (Feb'21) 0.00 (Feb'21)

work in progress

Detail Report
Graph / Photo
524 Construction of boundary wall and Guard Room and Main Gate of site on vacant land at Salempur Majra, Delhi 29/10/2020 26/01/2021 0.00 (Feb'21) 20.00 % (Feb'21) Work in progress. Detail Report
Graph / Photo
525 Watch and Ward of vacant land 08/12/2020 11/07/2021 work in progress Detail Report
Graph / Photo
526 Replacement of existing water closet with single piece water closet set, P/F floor and wall tile in toilets, replacement of damaged window and misc. civil works 18/11/2020 28/11/2020