Road - Construction Work
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 2015.04.18 2017.10.17 96400.00 74832.97 (Oct'23) 0.00 (Jul'24) Larson & Toubro Limited RMP 31D - 31E G1 girder reinforcement checking in progress Detail Report
Graph / Photo
2 Underground Tunnel, Underpass, FOB, Loops, Ramps, Footpath, Road Work including Road Signage, Road/Street Lighting works, Tunnel furnishing (FF& FA system, PA system, Automated drainage, integrated tunnel management system etc.), landscaping/horticulture work & allied works 2017.11.08 2019.08.29 77700.00 56196.25 (Jun'23) 0.00 (May'24) M/s L&T Ltd. Work in progress, transformer already installed Detail Report
Graph / Photo
3 Construction of Flyover at Nand Nagri and Gagan Cinema Junction of Mangal Paney Marg including Elevated Corridor Footpath Road Work and Road Signages Electrical Works Drainage Rain Water Harvesting and Allied works on EPC mode 2023.02.03 2024.07.31 15785.00 32.55 (Jul'23) 0.00 (Sep'24) Ram Kumar Contractor Piling completed / pier cap / PSC girder is in progress. 88 Nos. of PSC girders have been erected out of 132 Nos. 12 No. of deck slab has been casted. BSES shifting in progress. Tree cutting permission awaited. Work getting delayed due to non availability of tree cutting permission. Detail Report
Graph / Photo
4 Construction of Bridge on Najafgarh Drain at Tri Nagar/Inderlok, Karampura and Rampura, Delhi to cover the complete Right of Way (ROW) excluding area of already constructed bridge alongwith road improvement on either side of bridge including making. 2019.03.16 2021.09.30 5388.53 5809.90 (Mar'23) 0.00 (Mar'24) Ram Kumar Contractor Final bill is yet to be paid. Detail Report
Graph / Photo
5 Construction of underpass by jack pushing of pre-cast RCC boxes at outer ring road near Mukarba Chowk including construction of approach road from Badli Junction to Haiderpur Metro Station. 2022.10.14 2023.10.13 4329.32 0.00 (Aug'24) Dharamraj Contracts (I) Pvt. Ltd. Shifting of IGL gas pipeline has been completed on 28.11.2023. Payment of Rs. 5.15 Cr has been made to TPDDL on 22.12.2023. The casting of the thrust bed has been completed.  Machinery is being mobilized for box pushing. The casting of the four boxes has been completed. Pushing of the boxes will commence soon. Acquisition of land from IFCD is to be expedited. Detail Report
Graph / Photo
6 Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi 2021.11.22 2022.10.17 1773.27 2049.22 (Mar'23) 0.00 (Mar'24) Harbel Singh & Sons - Work slow down due to shortage of funds. - 4 Nos of slab casted out of 5. - 5th span girder launched. -RPE submitted to higher office after compliance of observations. Proposal for foreclosure is being initited due to want of sanction. Detail Report
Graph / Photo
7 Strengthening of Sri Aurobindo Marg (ID - 96), Ch. Harsukh Marg (ID - 19), and Ch. Jhandu Singh Marg (ID - 13) by cold milling and recycling process under SubDivision-II of Division South Road-II PWD, New Delhi during 2022-23. 2023.06.19 2023.09.16 1489.16 0.00 (Oct'24) SBG INFRACON PRIVATE LIMITED Work in Progress. Detail Report
Graph / Photo
8 Strengthening of S.A. Road under the jurisdiction of Division SER-2/21, New Delhi (Road ID: 946). 2023.04.14 2023.07.12 1291.28 0.00 (Dec'24) MAHAVIR PRASAD GUPTA AND SONS 95% Detail Report
Graph / Photo
9 Strengthening of various roads such as Najafgarh Road, Punjab Garden Road, Smt. Ginni Devi Road, Bhagwan Das Road, Hemwati Nandan Bahuguna Marg, road from Milan Cinema to H. No. 19/289 , Road from House no. H-1 to I-47 near Milan Cinema Karampura and Road from House HIL to bus terminal of 234, HIL Karampura, Lal Sai Mandir Marg D story, Pankaj Batra Marg under PWD Maintenance Division WR-2 / Sub Division WR-21, New Delhi during 2022-23. 2023.04.28 2023.08.27 1124.92 0.00 (Oct'24) MIA Construction Pvt. Ltd. Detail Report
Graph / Photo
10 Strengthening of road from Western Yamuna Canal to Bawana under Sub-Division NR-15, North Roads Division, PWD, Delhi(Second Call) 2023.07.04 2023.12.03 1087.55 0.00 (Oct'24) MIA Construction Pvt. Ltd. Work in progress Detail Report
Graph / Photo
11 Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) 2022.09.17 2022.12.15 861.04 653.41 (May'23) 0.00 (Oct'24) Invalid Detail Report
Graph / Photo
12 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). 2022.09.30 2023.03.29 818.33 711.49 (Jun'23) 0.00 (Mar'24) SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
13 Strengthening of roads from (i) Ramdev Chowk Narela to Singhu Border, NH44 (ii) Ramdev Chowk Narela to Piao Maniyari border (iii) Y-Section railway crossing to CRPF camp, under Sub-Division NR-13, PWD Division North Roads, Delhi 2023.07.08 2024.01.03 789.25 MIA Construction Pvt. Ltd. Work yet to be started Detail Report
Graph / Photo
14 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi 2022.07.14 2022.10.13 751.50 Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
15 Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi 2022.04.28 2022.10.24 643.92 552.30 (Jun'23) 0.00 (Oct'24) Kundu Nirma work Detail Report
Graph / Photo
16 Strengthening of Ring Road from I.P. Flyover to Raj Ghat Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi during 2022-23. 2023.06.02 2023.08.01 579.40 0.00 (Oct'24) MAHAVIR PRASAD GUPTA AND SONS Work in Progress. Detail Report
Graph / Photo
17 Strengthening of various roads such as prof. Joginder Singh Marg Major Deepak Tyagi Marg Lal Sai Marg 60 Futa Road Possangi Pur Road A 1 Block Main Road Opp A 1 Block Main Road and Asalat Pur Road 1 under Sub Division WR 12 Division WR-1 PWD New Delh 2022.09.25 2023.01.24 578.76 467.80 (May'23) 0.00 (Mar'24) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
18 Construction of Inter-connecting RCC box type storm water drain between JhaitkaraMorh via Chhawla Village to IandFC Najafgarh drain, NajafgarhBijwasan Road (ID 1173) under PWD Division SWR-II, New Delhi. 2023.03.17 2023.09.12 564.26 0.00 (Jul'24) Rajan Builders Detail Report
Graph / Photo
19 Strengthening / Resurfacing of (1) Road No. 70, (2) Road 62, (3) Road from Seemapuri Bus depot Road no. 70 to GTB Hospital Road (Gurudwara road), (4) Road from Labour chowk (Seemapuri link road) to General Hospital Road no. 64 (Divider Road), (5) Road from Rajiv Gandhi Super Specialty Hospital to GTB Hospital Road. 2023.01.26 2023.05.25 554.25 50.00 (Jun'23) 0.00 (Oct'24) Kundu Nirman Detail Report
Graph / Photo
20 Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW 2022.02.27 2022.06.26 548.07 550.78 (Feb'23) 0.00 (Mar'24) RK Brothers Detail Report
Graph / Photo
21 Strengthening of various road under North Roads, Division, Sub-Division NR-14, Shaheed Captain Vikram Batra Chowk PWD, New Delhi. 1. Mam Chand Dhaniya Marg from Old GTK Road to Siraspur Village 2. ITI Road at Jahangirpuri from Main Road to Metro Apartment & K-Block from Metro Apartment to dividing road K-Block.3. C-D Park Road from Main Road Jahangirpuri to Kushal Cinema Road. 4. I-Block Road & JBlock Road from Main Road Jahangirpuri to G.T. Road at Jahangirpuri. 2023.04.21 2023.07.19 538.44 0.00 (Oct'24) Karambir Rana Builders work in progress Detail Report
Graph / Photo
22 Strengthening of Mall Road Extension from Azadpur H Point to Sanjay Enclave (GTK Depot) under Sub Division NR-12, North Roads Division, PWD, Delhi. 2023.02.17 2023.04.17 507.62 0.00 (Oct'24) M.C.CONSTRUCTION CO. 60% Detail Report
Graph / Photo
23 C/o Common Mess Building near to the newly constructed Girls Hostel Building at DTU Campus. 2023.08.14 2024.05.09 498.97 Satish Chand RaJesh Kumar Pvt. Ltd. Work awarded on 14.08.2023. Preparation of Structural drawings & their approval is in progress. Detail Report
Graph / Photo
24 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 2022.08.06 2022.12.03 484.07 232.87 (May'23) 0.00 (Oct'24) Invalid work in progress Detail Report
Graph / Photo
25 Strengthening / resurfacing of PWD roads by cold milling and recycling process of various roads of Sub Division East Road-II under Division East Road /(M-212), Delhi during 2023-24. 1. Road No. 109 from Sapera Basti to Khora Chowk. 2. Dallupura Road from Timber Market to Noida Border. 3. Budh Singh Marg from Manav Ashray Cut to Dallupura T-point 2024.03.20 2024.05.18 456.73 0.00 (Oct'24) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
26 Strengthening of various roads (Ahinsha Marg sector-9, Rohini, Babosachowk to Tulsi Aptt., Ring road to Maheswari Aptt., ORR to Road No. B-5 sector-14, Rohini, Internal road of sector-9, Rohini, Pkt.-14 to Pkt.C-1, Pkt.-10 to Pkt.D-4, sector-20, Rohini, Pkt. 8 to Pkt. 9, Pkt. B-2 to Park, Pkt. 13 to pkt. 9, Pkt. 5 to Pkt. 6 sector-21, Rohini) having ROW < 30 mtr. under Sub Division NWR-23, PWD Division NWR-2, Sainik Vihar Delhi under PWD North Zone by cold milling method with recycled material, dg. 2022-23 & 2023-24. 2023.08.16 2024.02.15 415.97 0.00 (Jun'24) R K Brothers & Company Detail Report
Graph / Photo
27 Strengthening of Ring Road from Shantivan to Hanuman Setu under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 2023.06.02 2023.08.01 413.71 0.00 (Oct'24) MAHAVIR PRASAD GUPTA AND SONS Work in progress Detail Report
Graph / Photo
28 Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain 2022.09.25 2022.12.24 386.35 150.00 (Jun'23) 0.00 (Mar'24) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
29 Strengthening of Amar Shaheed Bismil Marg, Police Line road Parwana Road under Sub Division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW. 2023.08.20 2023.12.19 381.30 0.00 (Jul'24) SBG INFRACON PRIVATE LIMITED Detail Report
Graph / Photo
30 Street Scaping of Nelson Mandela Road, New Delhi. 2023.07.01 2023.08.29 377.15 0.00 (Feb'24) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
31 Road Resurfacing of Savitri Cinema (Road ID-601) Road from Guru Ravi Dass Marg to Outer Ring Road under Sub Division SER-24. 2023.04.15 2023.06.14 372.52 0.00 (Mar'24) Kundu Nirman work in progress Detail Report
Graph / Photo
32 Strengthening of Ring Road from Raj Ghat to Shanti Van Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 2023.06.02 2023.08.01 364.49 0.00 (Oct'24) MAHAVIR PRASAD GUPTA AND SONS Work in progress Detail Report
Graph / Photo
33 Construction of Back to back U-turn near Aali Village Red-light and Single U-Turn for Sarita Vihar Colony to facilitate signal free and congestion free movement of traffic on Mathura Road under SER-2/22.(Road ID-961) 2022.03.19 2022.06.18 331.52 10.15 (May'23) 0.00 (Mar'24) Satyam Construction Company 50% Detail Report
Graph / Photo
34 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021-22 2022.12.26 2023.02.25 282.98 380.05 (Jul'23) 0.00 (Jul'23) RUDRA CONSTRUCTIONS Detail Report
Graph / Photo
35 Strengthening of Road No. 30 under sub division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling. 2023.07.01 2023.10.30 279.38 0.00 (Oct'24) A S INFRATECH Detail Report
Graph / Photo
36 Construction of Foot over bridge with Staircase & lifts for Pedestrians across road at Ganesh Chowk ROB-36 Road. 2023.02.23 2023.06.22 258.65 SS Chauhan & Sons Work in Progress Detail Report
Graph / Photo
37 Strengthening of Hans Raj Sethi Marg (Road ID 1235), Baba Fateh Singh Marg (Road ID 600), Maharaja Agarsen Marg (Road ID 599) and Kanshi Ram Takkar Marg (Road ID 952) under the jurisdiction of Division SER-2, New Delhi. 2022.10.11 2022.12.10 255.06 100.56 (May'23) 0.00 (Sep'24) Karambir Rana Builders 98% Detail Report
Graph / Photo
38 Remodelling of drain at Porta Cabin road from Kondli Bridge to Porta Cabin, MCD under PWD Sub-Division East Road-II during 2022-23. 2023.03.29 2023.07.26 226.79 0.00 (Mar'24) Vinod Kumar

Work in progress

Detail Report
Graph / Photo
39 Rehabilitation/ Strengthening of PWD roads by cold milling and recycling process of various roads under Sub Division East Road-IV of Division East Road/(M-212), Delhi during 2023-24. 1. Road no 57 A - (Road ID:- 1731. 2. Agarsain Apartment Road. (Road ID:- 1491). 3. NH-24 to Link road No .01 (Road ID:- 178). 4. NH-24 to Link road No .02 (Road ID:- 131). 2024.03.19 2024.05.17 222.88 0.00 (Oct'24) R K Brothers & Company Detail Report
Graph / Photo
40 Providing LED Screens at different locations. 2023.03.13 2023.04.12 215.30 0.00 (Mar'24) labotek Detail Report
Graph / Photo
41 Remodelling of drain along road No. 102 (Pragati Marg) from Khora Chowk towards Road No. 108 under PWD Sub-Division East Road-II during 2022-23. 2023.03.29 2023.07.26 214.13 0.00 (Nov'24) BASAU CONSTRUCTION (INDIA)

Work in Progress

Detail Report
Graph / Photo
42 Construction of RCC drain from Road no. 64 to Road no. 62 at Mother dairy Road in Dilshad Garden, New Delhi. (Recall). 2023.04.06 2023.12.31 202.76 0.00 (Oct'24) Singh Construction Co. Detail Report
Graph / Photo
43 Providing and fixing Foot Over Bridge including electrical installation etc. 2023.01.30 2023.05.29 196.02 0.00 (Oct'24) Dilshad Khan work in progress Detail Report
Graph / Photo
44 Strengthening of Road No. 42 under sub division NWR-24, Division NWR-2,Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling. 2023.07.01 2023.10.30 183.50 0.00 (Oct'24) A S INFRATECH Detail Report
Graph / Photo
45 Road between Block No. 11-15 from Block-15 to LBS Hospital Through jalebi Chowk, Kalyanpuri.(SH:- Construction of RCC drain from Jalebi Chowk to LBS Hospital) 2023.08.24 2023.12.21 179.62 0.00 (Oct'24) Dinesh Chand Sharma Work in progress Detail Report
Graph / Photo
46 Remodelling of RCC Drain from Shekhar Apartment to UP Link Road via Chilla Sai Mandir Mayur Vihar Phase-1 Delhi 2023.09.29 2024.04.25 162.48 0.00 (Oct'24) Chaudhary Construction Company Pvt. Ltd. work in progress Detail Report
Graph / Photo
47 Construction of RCC drain at Shahbad Dairy village in place of existing Brick drain under Sub Division NR-15, North road Division, PWD, Delhi, During-2022-23. 2023.02.04 2023.08.02 158.58 0.00 (Mar'24) Kundu Nirman Work in progress Detail Report
Graph / Photo
48 Providing and Laying stone matrix Asphalt (SMA) on B-Avenue and Africa Avenue Flyover at Ring Road through cold milling and recycling process under Sub Division-2 of Division South Road-2, PWD, New Delhi during 2023-24 2024.03.15 2024.06.14 154.51 R K Brothers & Company Work In Progress. Detail Report
Graph / Photo
49 Providing and laying waste water pipe line from Arvind Nagar pump house Gamri Road to Drain no. 1 at road no. 66 via Maujpur Road Delhi. 2019.02.26 2019.06.25 149.77 182.60 (Nov'20) 0.00 (Nov'20) K. CONSTRUCTION COMPANY work in progress Detail Report
Graph / Photo
50 Providing and laying Stone Matrix Asphalt on Raja Garden Flyover at Ring Road during 2022-23 under Sub-Division WR21 2022.10.28 2022.12.27 136.70 0.00 (Mar'24) Sethi Construction Detail Report
Graph / Photo
51 Construction of footpath & drain at Block No.1 to 8 Khicharipur (Dhobighat road),Delhi Dg. 2023-24. 2023.09.08 2024.02.04 122.55 Ravinder Kumar Work in progress Detail Report
Graph / Photo
52 Construction of Toe wall for Plantation with Drip irrigation system and fixing of M.S grill , Kerb ston. 2023.03.22 2023.04.20 120.16 0.00 (Feb'24) Puneet Sehrawat Detail Report
Graph / Photo
53 Providing and laying of paver block in berm portion of Palla road from Tiggipur mor to Palla village under Sub Division NR-13, North roads Division, PWD, Delhi. 2023.02.17 2023.05.17 89.62 0.00 (Mar'24) Aditya Construction Work in progress Detail Report
Graph / Photo
54 Providing and laying Stone Matrix Asphalt on Punjabi Bagh Flyover at Ring Road during 2022-23 under Sub-Division WR-21. 2023.02.08 2023.04.08 83.65 0.00 (Nov'23) M C CONSTRUCTION CO Detail Report
Graph / Photo
55 Restoration of outer ring road (Keshopur Mandi to Janakpuri) cut by BSES for Laying of 04 Nos Cables under sub division WR-13, Division West Road-1 PWD during 2022-23 via ID 202112311521139. 2022.07.15 2022.08.28 82.92 100.37 (Jan'23) 0.00 (Jan'23) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
56 Construction of Central Verge with R.C.C. Crash Barriers at Pankha Road (From Uttam Nagar T-Point to C-2 Red Light Under Sub Division WR-12 & Division WR-1. 2023.06.10 2023.08.09 78.34 Sanjay Kaura Detail Report
Graph / Photo
57 Construction of drain and footpath from NG drain towards Zakhira r/a and near Rampura Subway on Rohtak road under Sub-division WR-21, New Delhi, dg. 2021-22 2022.08.31 2022.11.28 68.72 0.00 (Nov'23) Sanjay Kaura Detail Report
Graph / Photo
58 Construction of Lift well with painting including New lift installation at Outer Ring Road near Subroto Park under Sub Division-I, SWR-I/PWD, New Delhi 2024.01.11 2024.04.10 67.17 Samridhi Construction Detail Report
Graph / Photo
59 Comprehensive Development of Corridor (Outer Ring Road) between Mukarba Chowk to Wazirabad. SH. Providing and laying stone pitching and chute drain on embankment slope and construction of cycle track. 2017.04.10 2017.04.09 55.56 AANISHA COMMUNICATION PVT.LTD. Detail Report
Graph / Photo
60 AR Mo to various roads under PWD SWR II dg 2018 19 SH Improvement of Drain from Golak Dham to Bijwasan flyover RHS and providing footpath from IOC Morh to Bijwasan Flyover Sub Division 24 2019.03.22 2019.07.19 54.67 1.37 (May'22) 0.00 (May'22) Bishwa Mohan Jha work in progress Detail Report
Graph / Photo
61 Construction of RCC drain & footpath at road from Sunday Chowk to DDA road in Sector-20, Rohini under Sub Division NWR-25, PWD Division NWR-2, during 2023-24. 2023.11.15 2024.03.13 53.16 Sanjay Kaura Detail Report
Graph / Photo
62 Remodeling of drain from LIC Road to Gurudwara Road (Seemapuri Thana Road) , Dilshad Garden, Delhi-110095 during 2023-24. 2023.09.09 2023.12.07 53.03 0.00 (Mar'24) Aayan Construction Co. Detail Report
Graph / Photo
63 AR and Mo to various roads under Sub Division 21 SWR-II PWD dg 2018 19. SH Repair of drain and footpath on Peer Baba Road ID 1218 Bindapur New Delhi. 2019.02.11 2019.05.11 52.63 BLG Innovations work in progress Detail Report
Graph / Photo
64 Construction of Central Verge with R.C.C. crash barriers at Dharam Marg under Sub Division WR-11, Division WR-1 during 2022-23 2022.10.08 2022.12.06 52.49 0.00 (Mar'24) Kulwant Singh Detail Report
Graph / Photo
65 Construction of RCC drain slab and Improvement of footpath at Prince apartment road under Sub-Division East Road-IV of East Road Division, PWD during 2023-24. 2023.06.01 2023.08.29 49.35 0.00 (Nov'24) Sandeep Kumar

Work in Progress

Detail Report
Graph / Photo
66 SITC of Antique Decorative Fancy Poles on both sides of the footpath at Sultanpur Majra (AC-10). 2024.02.20 2024.05.19 48.42 0.00 (Sep'24) R S ELECTRIC CO. Detail Report
Graph / Photo
67 Beautification work PWD road From Dhaula KUan, New Delhi. (SH : Supplying, installation, testing & commissioning of flood light for Art work Façade illumination Metro Pillar at Airport Line). 2023.07.21 2023.09.20 45.17 0.00 (Mar'24) M/s Shaka Electrical (India) Detail Report
Graph / Photo
68 SITC of Water Features from T-1 Terminal to Technical area gate road. 2023.08.13 2023.09.12 43.86 0.00 (Mar'24) COLORDESIGN INDIA Detail Report
Graph / Photo
69 AR and Mo to various roads under PWD Division South West Road II New Delhi during 2019-20 SH Providing services of Clerk Computer Operators and MTS for Division Office 2019.08.01 2020.07.30 38.51 15.79 (Aug'20) 0.00 (Aug'20) M/s Trendy Security Services WORK IN PROGRESS Detail Report
Graph / Photo
70 AR and MO various roads under Division SWR-II, PWD Delhi during 2019-20. SH Improvement of drain by laying 600 mm dia NP3 pipe Hospital and BSES side from Rawta Morh to Jafferpur Engineering College in Prithvi Singh Dagar Marg 2019.09.03 2019.12.01 36.30 Ashok Kumar Rathi work not started Detail Report
Graph / Photo
71 Construction of RCC drain at Lancer School Road Sector-14, Rohini form Mehta Jewelers to Agarwal Dharamshala under sub Division NWR23. 2023.04.21 2023.06.19 36.21 0.00 (Oct'24) Invalid Detail Report
Graph / Photo
72 Uplifting of Central Verge on Main Road from Cambridge School to CTC at Sri Niwas Puri under Sub Div. R- 11 of Division South East Road -1. 2022.07.06 2022.10.03 35.65 35.00 (Mar'23) 0.00 (Nov'23) AMOCON Detail Report
Graph / Photo
73 AR Mo various roads under PWD Division SWR II during 2018 19 SH Miscellaneous Repair work of drain path of Section II under Sub Division II New Delhi. 2019.03.12 2019.07.09 35.27 H.P Builders Pvt Ltd WORK foreclosed Detail Report
Graph / Photo
74 AR and Mo various roads under Division South West Road II PWD dg 2018-19 SH Providing and Installation of Sewerage Pump at Different Vulnerable Location under Sub Division III. 2019.02.07 2020.02.02 33.55 24.99 (Aug'19) 0.00 (Aug'19) Tripurari Prasad Singh work complted Detail Report
Graph / Photo
75 SITC of decorative pole, LED lights, Feeder Panels with accessories and cable. 2023.06.26 2023.08.25 30.77 0.00 (Jan'24) M/s Shaka Electrical (India) Detail Report
Graph / Photo
76 Construction of CC pavement and improvement of drainage system from Yusuf Sarai to IIT Flyover and service lane Green Park at Sri Aurobindo Marg (ID-96) under Sub Division-II of Division south Road-II, PWD, New Delhi during 2023-24. 2024.02.20 2024.04.21 27.14 Nagendra and Company Work In Progress. Detail Report
Graph / Photo
77 Construction of kerb channel and berm portion at various roads under Section-I, Sub Division NWR-23, PWD Division NWR-2 during 2022-23. 2023.05.06 2023.06.04 26.96 Dinesh Kumar Buildwell Detail Report
Graph / Photo
78 Remodeling of Drain on Road No. 236 towards Samaj Kalyan Society under Sub Division WR-14 Division WR-1 during 2021-22.(Revised) 2022.04.22 2022.06.20 26.90 33.52 (May'23) 0.00 (May'23) Jeetender Kumar Verma Detail Report
Graph / Photo
79 AR and Mo various roads under Division South West Road II PWD dg 2018 19 SH Providing of Maintenance Van with required labours T and P for day to day upkeeping maintenance of roads under Sub Div III Jaffarpur Section. 2019.02.13 2020.02.12 24.14 23.98 (May'22) 0.00 (May'22) Bishwa Mohan Jha work in progress Detail Report
Graph / Photo
80 Construction of 02 nos of M S Stair and repairing of G S Sheet roofing and aluminium composite panel for prevention of water seepage at D M East Delhi During 2022 23 2022.08.17 2022.12.16 23.71 26.87 (Mar'23) 0.00 (Mar'23) Aamir Khan Detail Report
Graph / Photo
81 Construction of RCC wall along MCD Khatta Gazipur at Road No.56 under Sub-division M-2111 dg. 2023-24.(2nd Call) 2023.08.10 2023.11.07 18.92 0.00 (Oct'24) Dinesh Chand Sharma Detail Report
Graph / Photo
82 Installation of Passenger Lift in the office of PAO 18 and 19 3rd floor DFS Building Prasad Nagar New Delhi 2022.09.13 2022.12.12 17.24 0.00 (Jan'24) M B ENTERPRISES Detail Report
Graph / Photo
83 P/L RMC at deepressed berm portions and laying of kerb stone at centre verge of Vedic Marg 2022.04.28 2022.06.26 17.13 0.00 (Mar'24) SHRI KRISHNA CONSTRUCTION COMPANY Detail Report
Graph / Photo
84 SITC of Ornamental Pole & Bollard light. 2023.07.29 2023.09.28 14.84 0.00 (May'24) M/s Shaka Electrical (India)

100% Work Completed

Detail Report
Graph / Photo
85 Construction of Drain at ROB-36 road near Truck Market (Towards NH24) under Sub-Division East Road-I of Division East Road, PWD during 2023-24. 2023.09.18 2023.12.16 13.10 0.00 (Nov'24) Nation Star Enterprises work in progress Detail Report
Graph / Photo
86 Construction of Drain from YC Electrical Vehicle Shop to Subhash Nagar Drain on 100’ Road Patel Chowk Road under Sub-Div. WR-15, Division West-Road -1. dg. 2022-23 2022.05.27 2022.09.23 9.05 3.51 (May'23) 0.00 (May'23) Sanjay Enterprises Detail Report
Graph / Photo
87 Construction of rain water harvesting in the DM Office and SDM Office Saket and SDM office Mehrauli, M.B. Road, Saket. 2023.05.10 2023.06.09 8.22 Mohan Lal Detail Report
Graph / Photo
88 Improvement of drainage system and laying crossing pipe by Horizontal Directional drilling method at Apollo Hospital Red Light on Mathura Road under SER-2/22 2024.06.27 2024.08.26 7.88 0.00 (Dec'24) SABUR ALAM Detail Report
Graph / Photo
89 Desilting of Sump well of Shakti Nagar, Sawan Park, Roshanara Bagh i/c Repairing of Pump, all around the year 2022.06.12 2023.06.11 5.89 4.15 (Mar'23) 0.00 (Jan'24) Kuldeep Traders 100% Work Completed Detail Report
Graph / Photo
90 Construction of Foot Over Bridge on Ring Road at Sanyas Ashram, Bela Road, Sanskrit Mahavidhyalaya Near ISBT, Kashmere Gate, Delhi (SH. Electrical Works) 2017.09.17 2017.11.16 3.07 SUGANDHA ELECTRICALS Detail Report
Graph / Photo
91 AR and MO various roads under PWD Sub Divn I SWR II during 2016-17 SH Desilting of Drains under Section-I Pankha Road Area New Delhi 2017.06.09 2017.12.05 Work foreclosed on 18/10/2017 Detail Report
Graph / Photo
92 Providing and fixing M. S. Grill at central verge from Chhawla Village to BDO office, at Najafgarh Bijwasan Road (ID 1173) under PWD division SWR-II, New Delhi. 2020.09.14 2020.10.13 WORK not started Detail Report
Graph / Photo
93 Providing and fixing Retro-Reflective Double Sided Place identification Signboards on various roads under Sub-Division NWR-24 2021.10.02 2022.02.01 34.96 (Sep'22) 0.00 (Sep'22) work in progress Detail Report
Graph / Photo
94 Construction of Flyover with Ramps, Footpath, Road Work including Road Signage, Street Light works, Drainage, Horticulture, Mural Works & allied works at Road No. 56 between Anand Vihar ROB and Apsara Border ROB, New Delhi (EPC Mode 2022.09.10 2023.12.08 10047.97 (Jun'23) 0.00 (Sep'24) finishing work under progress Detail Report
Graph / Photo
95 Providing and laying tactile and making footpath accessible for differently abled persons on Pramod Mahajan Marg and J Block Road, New Delhi 2022.03.18 2022.05.01 0.00 (Mar'24) running Detail Report
Graph / Photo
96 Construction of new RCC Box Drains at Bhalla Factory Road (from Nangloi Road to F-7/36 near Friends Enclave Ward No.40) with precast RCC, replacing old damaged brick masonry drains at Sultanpuri, Delhi. (Re-call) 2022.12.21 2023.08.20 work in progress Detail Report
Graph / Photo
97 Construction of Shed with seating block Changing room Pump room and UGT tank at East Vinod Nagar sports complex Delhi 2022.12.14 2023.05.12 0.00 (Mar'24) Work in progress. 45% work has been done. Detail Report
Graph / Photo
98 Providing services of Maintenance Vans for day to day repair work 2022.07.30 2024.07.29 35.07 (May'23) 0.00 (Mar'24) Work in progress Detail Report
Graph / Photo
99 Providing services of Maintenance Vans for day to day repair work 2022.07.30 2024.07.29 17.52 (May'23) 0.00 (Oct'24) work in progres Detail Report
Graph / Photo
100 Maintenance and services of Computers Printers installed at Sub Divisions and Division SR-1 2022.07.25 2024.07.24 0.00 (Nov'23) work in progress Detail Report
Graph / Photo
101 Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24 2022.09.29 2023.09.27 work completed Detail Report
Graph / Photo
102 Construction of Officers, Public Toilet (Gents and Ladies) and roof treatment of Enforcement Branch HQ at Transport Authority, 5/9 under Hill Road , Delhi -54. 2023.03.16 2023.05.15 In-porgress Detail Report
Graph / Photo
103 Construction of new footpath, Repairing of existing footpath on Pankaj Juyal Marg & Birla Vidya Niketan Marg, Repair of boundary wall in front of Saket Court on Pankaj Juyal Marg and providing and placing jersey barrier on Press Enclave Road and Mandir Marg. 2023.02.04 2023.03.03 0.00 (Nov'23) work in progress Detail Report
Graph / Photo
104 General repair and maintenance work 2022.09.27 2023.06.26 0.00 (Jun'24) Work in progress Detail Report
Graph / Photo
105 Improvement and reconstruction of footpath on various roads (Mathura Road, Bhairon Marg and Ring Road under Division M-321, Delhi on urgent basis in view of G-20 SUMMIT 2023. 2023.02.12 2023.04.14 0.00 (Nov'23) In-progress Detail Report
Graph / Photo
106 Construction of Shed with seating block, Changing room, Pump room and UGT tank at East Vinod Nagar sports complex, Delhi. 2022.12.14 2023.05.12 0.00 (Nov'23) work in 40 % progress. Detail Report
Graph / Photo
107 Providing additional staircase from Skywalk towards Moti Bagh, MS staircase for underground sump, provision for additional railing over skywalk, Covering of Skywalk with CGI sheet roofing & C/o wall with MS Grill towards Moti bagh at FOB Durgabai Deshmukh Metro Station, Ring Road New Delhi. 2023.06.29 2023.10.28 0.00 (Mar'24) Work in Progress Detail Report
Graph / Photo