Road - Construction Work
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 2015.04.18 2017.10.17 96400.00 74832.97 (Oct'23) 0.00 (Nov'23) Larson & Toubro Limited lower pylon 1st lift in progress Detail Report
Graph / Photo
2 Underground Tunnel, Underpass, FOB, Loops, Ramps, Footpath, Road Work including Road Signage, Road/Street Lighting works, Tunnel furnishing (FF& FA system, PA system, Automated drainage, integrated tunnel management system etc.), landscaping/horticulture work & allied works 2017.11.08 2019.08.29 77700.00 56196.25 (Jun'23) 0.00 (Nov'23) M/s L&T Ltd. work is in progress Detail Report
Graph / Photo
3 Construction of Flyover at Nand Nagri and Gagan Cinema Junction of Mangal Paney Marg including Elevated Corridor Footpath Road Work and Road Signages Electrical Works Drainage Rain Water Harvesting and Allied works on EPC mode 2023.02.03 2024.07.31 15785.00 32.55 (Jul'23) 0.00 (Nov'23) Ram Kumar Contractor Piling work, pile cap, pier, girder casting and pier reinforcement work in progress. Utilities of BSES, TPDDL, DJB etc are to be shifted. Tree cutting permission awaited. Detail Report
Graph / Photo
4 Extension of Ashram Flyover to DND Flyover. 2020.06.19 2021.06.18 12879.00 15278.65 (May'23) 0.00 (Nov'23) KCC Buildcon Pvt. LTD The extended Ashram Flyover has been inaugurated by the Hon'ble CM, Delhi on 06.03.2023. Horticulatuer and development Art work is in progress. RE has been submitted and approval of EFC is awaited. Payment of the final bill can not be made without the same. Detail Report
Graph / Photo
5 Construction of underpass by jack pushing of pre-cast RCC boxes at outer ring road near Mukarba Chowk including construction of approach road from Badli Junction to Haiderpur Metro Station. 2022.10.14 2023.10.13 4329.32 0.00 (Nov'23) Dharamraj Contracts (I) Pvt. Ltd. Work affected due to non-shifting of utilities like IGL, TPDDL etc. Inspite of continuous effort IGL is taking more time than expected. The casting of thrust bed completed. 90 % of shifting of IGL gas pipe line has been completed. During the last ETC meeting in the month of September, the expenditure with respect to the shifting of HT lines was finalized. Detail Report
Graph / Photo
6 C/o Three Lane Flyover, Road Work, Footpath, Drainage System, Landscaping, Railing, Road Signages, Street Light & Allied works. 2022.07.15 2023.07.14 4199.50 2065.77 (Jul'23) 0.00 (Oct'23) Gawar Construction Ltd., Work completed and inaugurated by Hon’ble Chief Minister, Delhi on 22.10.2023 Detail Report
Graph / Photo
7 W/O Mahrauli Mahipalpur Road. SH: from 4 lanes to 8 lanes and Service Road from Andheria More to Masoodpur Village. 2012.10.30 2013.04.29 3812.11 KCC Buildcon Pvt. LTD . Detail Report
Graph / Photo
8 Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi 2021.11.22 2022.10.17 1773.27 2049.22 (Mar'23) 0.00 (Sep'23) Harbel Singh & Sons - Work in progress. - Girder launched of 4 slabs out of 5 - 4 Nos of slab out of 5 casted. --RE has to be submitted and approval of competent authority is required. Payment of the RA bills can not be made without the same. Detail Report
Graph / Photo
9 Strengthening of Sri Aurobindo Marg (ID - 96), Ch. Harsukh Marg (ID - 19), and Ch. Jhandu Singh Marg (ID - 13) by cold milling and recycling process under SubDivision-II of Division South Road-II PWD, New Delhi during 2022-23. 2023.06.19 2023.09.16 1489.16 0.00 (Nov'23) SBG INFRACON PRIVATE LIMITED Work in Progress Detail Report
Graph / Photo
10 Strengthening of S.A. Road under the jurisdiction of Division SER-2/21, New Delhi (Road ID: 946). 2023.04.14 2023.07.12 1291.28 0.00 (Nov'23) MAHAVIR PRASAD GUPTA AND SONS 12% Detail Report
Graph / Photo
11 Strengthening of various roads such as Najafgarh Road, Punjab Garden Road, Smt. Ginni Devi Road, Bhagwan Das Road, Hemwati Nandan Bahuguna Marg, road from Milan Cinema to H. No. 19/289 , Road from House no. H-1 to I-47 near Milan Cinema Karampura and Road from House HIL to bus terminal of 234, HIL Karampura, Lal Sai Mandir Marg D story, Pankaj Batra Marg under PWD Maintenance Division WR-2 / Sub Division WR-21, New Delhi during 2022-23. 2023.04.28 2023.08.27 1124.92 0.00 (Nov'23) MIA Construction Pvt. Ltd. Detail Report
Graph / Photo
12 Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) 2022.09.17 2022.12.15 861.04 653.41 (May'23) 0.00 (May'23) Invalid Detail Report
Graph / Photo
13 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). 2022.09.30 2023.03.29 818.33 711.49 (Jun'23) 0.00 (Nov'23) SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
14 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi 2022.07.14 2022.10.13 751.50 Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
15 Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi 2022.04.28 2022.10.24 643.92 552.30 (Jun'23) 0.00 (Jun'23) Kundu Nirma

work is in progress

Detail Report
Graph / Photo
16 Remodelling of drain from PTS to IIT Both Side of Road on Sri Aurobindo Marg (ID -96) under Sub Division-II of Division South Road-II, New Delhi during 2022-23. (2nd Call). 2023.03.25 2023.07.24 631.30 0.00 (Nov'23) Mangat Ram Gupta work is in progress Detail Report
Graph / Photo
17 Resurfacing of roads from (i) Lampur Mor to Lampur Border, (ii) Ramdev Chowk to Railway crossing Narela, (iii) Y-section Narela to Shahpur Garhi Turn, under Sub-Division NR-13, North Roads Division, PWD, Delhi 2022.03.20 2022.07.17 617.72 316.83 (Apr'23) 0.00 (Aug'23) Sethi Construction

work is in progress

Detail Report
Graph / Photo
18 Strengthening of Ring Road from I.P. Flyover to Raj Ghat Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi during 2022-23. 2023.06.02 2023.08.01 579.40 0.00 (Nov'23) MAHAVIR PRASAD GUPTA AND SONS Work in Progress. Detail Report
Graph / Photo
19 Strengthening of various roads such as prof. Joginder Singh Marg Major Deepak Tyagi Marg Lal Sai Marg 60 Futa Road Possangi Pur Road A 1 Block Main Road Opp A 1 Block Main Road and Asalat Pur Road 1 under Sub Division WR 12 Division WR-1 PWD New Delh 2022.09.25 2023.01.24 578.76 467.80 (May'23) 0.00 (Nov'23) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
20 Construction of Inter-connecting RCC box type storm water drain between JhaitkaraMorh via Chhawla Village to IandFC Najafgarh drain, NajafgarhBijwasan Road (ID 1173) under PWD Division SWR-II, New Delhi. 2023.03.17 2023.09.12 564.26 0.00 (Nov'23) Rajan Builders Detail Report
Graph / Photo
21 Strengthening / Resurfacing of (1) Road No. 70, (2) Road 62, (3) Road from Seemapuri Bus depot Road no. 70 to GTB Hospital Road (Gurudwara road), (4) Road from Labour chowk (Seemapuri link road) to General Hospital Road no. 64 (Divider Road), (5) Road from Rajiv Gandhi Super Specialty Hospital to GTB Hospital Road. 2023.01.26 2023.05.25 554.25 50.00 (Jun'23) 0.00 (Jun'23) Kundu Nirman Detail Report
Graph / Photo
22 Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW 2022.02.27 2022.06.26 548.07 550.78 (Feb'23) 0.00 (Nov'23) RK Brothers Detail Report
Graph / Photo
23 Strengthening of Anuvrat Marg (ID-1198) through cold milling and recycling process under Sub-Division-3 of Division South Road-2 PWD, New Delhi. 2023.04.19 2023.08.18 536.44 0.00 (Nov'23) R K Brothers & Company Work in progress. ( Delayed due to unexpected rain in May and traffic police permission also received on dated 25.05.2023.) Detail Report
Graph / Photo
24 Construction of Two No. Foot Over Bridge across Sri Aurobindo Marg (ID-96) at (i) PTS Bus Stop (ii) T.B. Hospital with staircase and lift including Electrical Installations under Sub Division-II of Division South Road-II, PWD New Delhi. 2020.03.21 2020.09.20 489.85 255.38 (Nov'22) 0.00 (Nov'22) S S Chauhan & Sons Work in Progress. Detail Report
Graph / Photo
25 Construction of Two No Foot Over Bridge across (i)Sri Aurobindo Marg (ID-96) at Adhchini Village (ii) Hauz Khas Enclave (Near Padmini Enclave) with staircase and lift including Electrical Installation under Sub Division-II of Division South Road-II 2020.03.21 2020.09.20 489.30 335.56 (Nov'22) 0.00 (Nov'22) S S Chauhan & Sons Work in Progress. Detail Report
Graph / Photo
26 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 2022.08.06 2022.12.03 484.07 232.87 (May'23) 0.00 (Nov'23) Invalid

work is in progress

Detail Report
Graph / Photo
27 Strengthening of various roads (Ahinsha Marg sector-9, Rohini, Babosachowk to Tulsi Aptt., Ring road to Maheswari Aptt., ORR to Road No. B-5 sector-14, Rohini, Internal road of sector-9, Rohini, Pkt.-14 to Pkt.C-1, Pkt.-10 to Pkt.D-4, sector-20, Rohini, Pkt. 8 to Pkt. 9, Pkt. B-2 to Park, Pkt. 13 to pkt. 9, Pkt. 5 to Pkt. 6 sector-21, Rohini) having ROW < 30 mtr. under Sub Division NWR-23, PWD Division NWR-2, Sainik Vihar Delhi under PWD North Zone by cold milling method with recycled material, dg. 2022-23 & 2023-24. 2023.08.16 2024.02.15 415.97 R K Brothers & Company Detail Report
Graph / Photo
28 Strengthening of Ring Road from Shantivan to Hanuman Setu under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 2023.06.02 2023.08.01 413.71 MAHAVIR PRASAD GUPTA AND SONS Work in progress Detail Report
Graph / Photo
29 Strengthening of MB Road (ID-390) Road through cold milling and recycling process under Sub-Division-1 of Division South Road-1 PWD, New Delhi. 2023.06.20 2023.08.19 388.26 0.00 (Nov'23) Pawan Kumar Work completed Detail Report
Graph / Photo
30 Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain 2022.09.25 2022.12.24 386.35 150.00 (Jun'23) 0.00 (Nov'23) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
31 Strengthening of Amar Shaheed Bismil Marg, Police Line road Parwana Road under Sub Division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW. 2023.08.20 2023.12.19 381.30 SBG INFRACON PRIVATE LIMITED Detail Report
Graph / Photo
32 Road Resurfacing of Savitri Cinema (Road ID-601) Road from Guru Ravi Dass Marg to Outer Ring Road under Sub Division SER-24. 2023.04.15 2023.06.14 372.52 0.00 (Nov'23) Kundu Nirman 80% Detail Report
Graph / Photo
33 Strengthening of Ring Road from Raj Ghat to Shanti Van Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 2023.06.02 2023.08.01 364.49 MAHAVIR PRASAD GUPTA AND SONS Work in progress Detail Report
Graph / Photo
34 Strengthening of various roads by cold milling of sub-Div. East road-III under East road/(M-212) Delhi during 2022-23. 1. Sadhabhawna Marg (Road No. 111) 2. Club Avenue Marg (Road No. 112) 3. Sekarita Marg (Road No. 113) 4. Ambedkar Marg. 5. Subhash Market road. 6. Block No. 1 to 11 Trilokpuri. 7. Khudiram Bose Marg 2022.08.29 2023.02.24 342.13 0.00 (Jul'23) SATYA PARKASH AND BROS PVT LTD

Workin Progress

Detail Report
Graph / Photo
35 Construction of Back to back U-turn near Aali Village Red-light and Single U-Turn for Sarita Vihar Colony to facilitate signal free and congestion free movement of traffic on Mathura Road under SER-2/22.(Road ID-961) 2022.03.19 2022.06.18 331.52 10.15 (May'23) 0.00 (May'23) Satyam Construction Company 45% Detail Report
Graph / Photo
36 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021-22 2022.12.26 2023.02.25 282.98 380.05 (Jul'23) 0.00 (Jul'23) RUDRA CONSTRUCTIONS Detail Report
Graph / Photo
37 Strengthening of Road No. 30 under sub division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling. 2023.07.01 2023.10.30 279.38 A S INFRATECH Detail Report
Graph / Photo
38 Strengthening of Hans Raj Sethi Marg (Road ID 1235), Baba Fateh Singh Marg (Road ID 600), Maharaja Agarsen Marg (Road ID 599) and Kanshi Ram Takkar Marg (Road ID 952) under the jurisdiction of Division SER-2, New Delhi. 2022.10.11 2022.12.10 255.06 100.56 (May'23) 0.00 (May'23) Karambir Rana Builders 60% Detail Report
Graph / Photo
39 Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub Division-1, C&ND-Road Division. 2nd RECALL 2022.07.20 2022.11.19 243.86 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
40 Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub. Division-1, C and ND-Road Division. (1st RECALL) 2022.03.09 2022.07.08 225.35 Sethi Construction Detail Report
Graph / Photo
41 Providing LED Screens at different locations. 2023.03.13 2023.04.12 215.30 labotek Detail Report
Graph / Photo
42 Construction of RCC drain from Road no. 64 to Road no. 62 at Mother dairy Road in Dilshad Garden, New Delhi. (Recall). 2023.04.06 2023.12.31 202.76 Singh Construction Co. Detail Report
Graph / Photo
43 Providing and fixing Foot Over Bridge including electrical installation etc. 2023.01.30 2023.05.29 196.02 0.00 (Nov'23) Dilshad Khan work in progress Detail Report
Graph / Photo
44 Strengthening of Road No. 42 under sub division NWR-24, Division NWR-2,Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling. 2023.07.01 2023.10.30 183.50 0.00 (Nov'23) A S INFRATECH Detail Report
Graph / Photo
45 Providing and laying waste water pipe line from Arvind Nagar pump house Gamri Road to Drain no. 1 at road no. 66 via Maujpur Road Delhi. 2019.02.26 2019.06.25 149.77 182.60 (Nov'20) 0.00 (Nov'20) K. CONSTRUCTION COMPANY work in progress Detail Report
Graph / Photo
46 Providing and laying Stone Matrix Asphalt on Raja Garden Flyover at Ring Road during 2022-23 under Sub-Division WR21 2022.10.28 2022.12.27 136.70 0.00 (Nov'23) Sethi Construction Detail Report
Graph / Photo
47 Construction of footpath & drain at Block No.1 to 8 Khicharipur (Dhobighat road),Delhi Dg. 2023-24. 2023.09.08 2024.02.04 122.55 Ravinder Kumar Detail Report
Graph / Photo
48 Construction of Toe wall for Plantation with Drip irrigation system and fixing of M.S grill , Kerb ston. 2023.03.22 2023.04.20 120.16 0.00 (Nov'23) Puneet Sehrawat Detail Report
Graph / Photo
49 Providing and laying Stone Matrix Asphalt on Punjabi Bagh Flyover at Ring Road during 2022-23 under Sub-Division WR-21. 2023.02.08 2023.04.08 83.65 0.00 (Nov'23) M C CONSTRUCTION CO Detail Report
Graph / Photo
50 Restoration of outer ring road (Keshopur Mandi to Janakpuri) cut by BSES for Laying of 04 Nos Cables under sub division WR-13, Division West Road-1 PWD during 2022-23 via ID 202112311521139. 2022.07.15 2022.08.28 82.92 100.37 (Jan'23) 0.00 (Jan'23) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
51 Providing and laying microsurfacing of B-4 road under Sub Division NWR-23, PWD Division NWR-2 during 2021-22 2022.05.30 2022.07.13 78.40 98.31 (Jan'23) 0.00 (Jan'23) Invalid Detail Report
Graph / Photo
52 Construction of Central Verge with R.C.C. Crash Barriers at Pankha Road (From Uttam Nagar T-Point to C-2 Red Light Under Sub Division WR-12 & Division WR-1. 2023.06.10 2023.08.09 78.34 Sanjay Kaura Detail Report
Graph / Photo
53 Providing and laying microsurfacing of various roads (B-6 Road, Coln. Sarna Marg, N.K. Bagrodia School to Vinobha Kunj, Chetak Appt. to New Modern Appt., Vidya Vihar to Neelgiri Appt. and Pragatisheel Appt. to Green View Appt.under Sub Division NWR-23, PWD Division NWR-2 dg. 2022-23. 2022.09.09 2022.10.22 75.51 83.10 (May'23) 0.00 (May'23) M C CONSTRUCTION CO Detail Report
Graph / Photo
54 Construction of drain in West Parmanand Colony (MCD area) towards I and FC drain under Sub. Division-I, PWD Division (C and ND)-R, New Delhi 2022.04.20 2022.06.19 69.24 Ram Singh Detail Report
Graph / Photo
55 Construction of drain and footpath from NG drain towards Zakhira r/a and near Rampura Subway on Rohtak road under Sub-division WR-21, New Delhi, dg. 2021-22 2022.08.31 2022.11.28 68.72 0.00 (Nov'23) Sanjay Kaura Detail Report
Graph / Photo
56 Construction, Fabrication and Installation of G-20 Backlit Wall / Unipole Mounted Signages Hording in Delhi under Sub Division-IV of Division South Road-II, PWD, Delhi during 2023-24. 2023.08.30 2023.09.08 67.75 JYOTI TRADING CO. Work In Progress. Detail Report
Graph / Photo
57 Construction of Drain from I.P. Estate DTC Depot to SDMC Drain & Making Slip Road near New Railway Bridge at Ring Road between Bhairon Marg T-Junction and Entry Tunnel Ring Road under Division C&ND- Roads, New Delhi. 2022.04.25 2022.05.24 66.21 Gee Internationals Detail Report
Graph / Photo
58 Providing main LT panels, Distribution boards i/c providing LED fittings, Ceiling Fans, & replacement of Air Conditioners, DG set with suitable AMF panel and other miscellaneous electrical work for Department of Training & Technical Building at Muni Maya Ram Marg, Pitampura, Delhi 2022.04.08 2022.10.07 64.45 42.27 (Mar'23) 0.00 (Mar'23) Invalid 4th RA Bill rs. 4226715/- dt, 28.06.2023 Detail Report
Graph / Photo
59 Comprehensive Development of Corridor (Outer Ring Road) between Mukarba Chowk to Wazirabad. SH. Providing and laying stone pitching and chute drain on embankment slope and construction of cycle track. 2017.04.10 2017.04.09 55.56 AANISHA COMMUNICATION PVT.LTD. Detail Report
Graph / Photo
60 Strengthening of M.G. Road to Ghitorni Village Road and Improvement of Footpath for accessibility of disable persons of M.G.Road to Ghitorni Village Road and Provision of Jersey barrier at Aaya Nagar Road under Sub-Division SR-15, Division South Road-1 at New Delhi 2023.02.17 2023.03.16 54.75 8.70 (Oct'22) 0.00 (Oct'22) completed Detail Report
Graph / Photo
61 AR Mo to various roads under PWD SWR II dg 2018 19 SH Improvement of Drain from Golak Dham to Bijwasan flyover RHS and providing footpath from IOC Morh to Bijwasan Flyover Sub Division 24 2019.03.22 2019.07.19 54.67 1.37 (May'22) 0.00 (May'22) Bishwa Mohan Jha work in progress Detail Report
Graph / Photo
62 Construction of Slip Road in front of Gurudwara Majnu Ka Tila at Road No. 45 under Sub. Division-1 of Division C&ND-Roads, New Delhi. 2nd CALL 2022.05.03 2022.08.02 54.58 Aditya Construction Detail Report
Graph / Photo
63 Remodeling of drain from LIC Road to Gurudwara Road (Seemapuri Thana Road) , Dilshad Garden, Delhi-110095 during 2023-24. 2023.09.09 2023.12.07 53.03 Aayan Construction Co. Detail Report
Graph / Photo
64 AR and Mo to various roads under Sub Division 21 SWR-II PWD dg 2018 19. SH Repair of drain and footpath on Peer Baba Road ID 1218 Bindapur New Delhi. 2019.02.11 2019.05.11 52.63 BLG Innovations work in progress Detail Report
Graph / Photo
65 Construction of Central Verge with R.C.C. crash barriers at Dharam Marg under Sub Division WR-11, Division WR-1 during 2022-23 2022.10.08 2022.12.06 52.49 Kulwant Singh Detail Report
Graph / Photo
66 Construction of R.C.C. central verge on August Kranti Marg (ID-16) from Sirifort Red Light to Panchsheel Flyover under Sub Division-I of Division South Road-II, PWD Delhi, during 2022-23. 2023.03.07 2023.05.06 49.40 0.00 (Jul'23) Pawan Kumar Jha Work in Progress Detail Report
Graph / Photo
67 Construction of missing drain behind cluster bus depot on Gurudwara Road under Sub-Division M-2114 of Shahdara Road Division (M-211) during 2023-24. 2023.09.09 2023.12.07 48.95 Aayan Construction Co. Detail Report
Graph / Photo
68 Beautification work PWD road From Dhaula KUan, New Delhi. (SH : Supplying, installation, testing & commissioning of flood light for Art work Façade illumination Metro Pillar at Airport Line). 2023.07.21 2023.09.20 45.17 M/s Shaka Electrical (India) Detail Report
Graph / Photo
69 SITC of Water Features from T-1 Terminal to Technical area gate road. 2023.08.13 2023.09.12 43.86 COLORDESIGN INDIA Detail Report
Graph / Photo
70 Construction of CC Pavement of main carriageway on SA Road under SER-2/21 during 2022-23 2022.09.24 2022.10.23 40.00 39.45 (Apr'23) 0.00 (Apr'23) Buland Constructions Detail Report
Graph / Photo
71 Construction of RCC drain & footpath at road from Sunday Chowk to DDA road in Sector-20, Rohini under Sub Division NWR-23, PWD Division NWR-2 during 2022-23. 2023.04.22 2023.07.20 39.08 Sohan Lal Chhitoria and Sons Detail Report
Graph / Photo
72 AR and Mo to various roads under PWD Division South West Road II New Delhi during 2019-20 SH Providing services of Clerk Computer Operators and MTS for Division Office 2019.08.01 2020.07.30 38.51 15.79 (Aug'20) 0.00 (Aug'20) M/s Trendy Security Services WORK IN PROGRESS Detail Report
Graph / Photo
73 Road Restoration on various roads under Sub Division NWR-22, Division NWR-2, PWD, Delhi dg. 2022-23 2022.06.13 2022.12.09 36.66 45.31 (Dec'22) 0.00 (Aug'23) Jitender Singh Detail Report
Graph / Photo
74 AR and MO various roads under Division SWR-II, PWD Delhi during 2019-20. SH Improvement of drain by laying 600 mm dia NP3 pipe Hospital and BSES side from Rawta Morh to Jafferpur Engineering College in Prithvi Singh Dagar Marg 2019.09.03 2019.12.01 36.30 Ashok Kumar Rathi work not started Detail Report
Graph / Photo
75 Construction of RCC drain at Lancer School Road Sector-14, Rohini form Mehta Jewelers to Agarwal Dharamshala under sub Division NWR23. 2023.04.21 2023.06.19 36.21 Invalid Detail Report
Graph / Photo
76 Modification of berm portion at various roads in Sultanpuri Majra under Sub-Division NWR-21, Division NWR-2, New Delhi 2022.09.04 2022.11.03 36.09 15.51 (Mar'23) 0.00 (Nov'23) Jitendra Singh Detail Report
Graph / Photo
77 Uplifting of Central Verge on Main Road from Cambridge School to CTC at Sri Niwas Puri under Sub Div. R- 11 of Division South East Road -1. 2022.07.06 2022.10.03 35.65 35.00 (Mar'23) 0.00 (Nov'23) AMOCON Detail Report
Graph / Photo
78 AR Mo various roads under PWD Division SWR II during 2018 19 SH Miscellaneous Repair work of drain path of Section II under Sub Division II New Delhi. 2019.03.12 2019.07.09 35.27 H.P Builders Pvt Ltd WORK foreclosed Detail Report
Graph / Photo
79 Providing and Placing Jersey type barrier at Captain javed Ali Marg and Road No.70 under sub div M-2114, New Delhi dg 2021-22. (Modified and 1st Call) 2022.03.20 2022.05.18 35.11 Anmol Infratech Private Limited Detail Report
Graph / Photo
80 AR and Mo various roads under Division South West Road II PWD dg 2018-19 SH Providing and Installation of Sewerage Pump at Different Vulnerable Location under Sub Division III. 2019.02.07 2020.02.02 33.55 24.99 (Aug'19) 0.00 (Aug'19) Tripurari Prasad Singh work complted Detail Report
Graph / Photo
81 SITC of decorative pole, LED lights, Feeder Panels with accessories and cable. 2023.06.26 2023.08.25 30.77 0.00 (Nov'23) M/s Shaka Electrical (India) Detail Report
Graph / Photo
82 Improvement of Inner roads of Shiva Apartment at Road No.30, Paschim Vihar, Delhi. (Balance Work) 2022.05.16 2022.08.15 27.54 18.56 (Sep'22) 0.00 (Sep'22) Jitender Singh Detail Report
Graph / Photo
83 Construction of kerb channel and berm portion at various roads under Section-I, Sub Division NWR-23, PWD Division NWR-2 during 2022-23. 2023.05.06 2023.06.04 26.96 Dinesh Kumar Buildwell Detail Report
Graph / Photo
84 Remodeling of Drain on Road No. 236 towards Samaj Kalyan Society under Sub Division WR-14 Division WR-1 during 2021-22.(Revised) 2022.04.22 2022.06.20 26.90 33.52 (May'23) 0.00 (May'23) Jeetender Kumar Verma Detail Report
Graph / Photo
85 AR and Mo various roads under Division South West Road II PWD dg 2018 19 SH Providing of Maintenance Van with required labours T and P for day to day upkeeping maintenance of roads under Sub Div III Jaffarpur Section. 2019.02.13 2020.02.12 24.14 23.98 (May'22) 0.00 (May'22) Bishwa Mohan Jha work in progress Detail Report
Graph / Photo
86 Construction of 02 nos of M S Stair and repairing of G S Sheet roofing and aluminium composite panel for prevention of water seepage at D M East Delhi During 2022 23 2022.08.17 2022.12.16 23.71 26.87 (Mar'23) 0.00 (Mar'23) Aamir Khan Detail Report
Graph / Photo
87 Road Restoration of various roads cut by TPDDL, BSES, Airtel, Jio and DJB under Sub Division NWR-24 (Section-II), PWD Division NWR-2 dg. 2021-22. (Re-call) 2022.05.02 2022.06.15 19.26 24.66 (Sep'22) 0.00 (Sep'22) J.S. Construction Co. Detail Report
Graph / Photo
88 Construction of damaged drains at Delhi Fire Station and Ekta Apartment on Road No.30, Paschim Vihar under sub- Division NWR-24 during 2021-22 2022.03.26 2022.06.25 18.94 22.93 (Aug'22) 0.00 (Aug'22) Pawan Kumar Gupta & Sons Detail Report
Graph / Photo
89 Construction of RCC wall along MCD Khatta Gazipur at Road No.56 under Sub-division M-2111 dg. 2023-24.(2nd Call) 2023.08.10 2023.11.07 18.92 Dinesh Chand Sharma Detail Report
Graph / Photo
90 Improvement of drain and footpath near Bhikaji Cama Place and Kerb Channel on Ring Road (ID - 1291) (from Safdarjung Hospital to Hyatt Hotel) and Sri Aurobindo Marg (ID - 96) under Sub Division -II of Division South Road-II, PWD during 2022-23. 2023.05.14 2023.06.27 18.08 Samridhi Construction Work in Progress Detail Report
Graph / Photo
91 P/L RMC at deepressed berm portions and laying of kerb stone at centre verge of Vedic Marg 2022.04.28 2022.06.26 17.13 SHRI KRISHNA CONSTRUCTION COMPANY Detail Report
Graph / Photo
92 Construction of new planters from Vidya Vihar to Police Line at ORR-26 and C/o brick drain near B-Block Mangolpuri Delhi under Sub Division NWR-25, PWD Division NWR-2 dg. 2022-23. 2022.07.16 2022.09.15 14.96 25.71 (Mar'23) 0.00 (Mar'23) Sanjay Kaura Detail Report
Graph / Photo
93 SITC of Ornamental Pole & Bollard light. 2023.07.29 2023.09.28 14.84 0.00 (Sep'23) M/s Shaka Electrical (India)

100% Work Completed

Detail Report
Graph / Photo
94 Construction of footpath at road from Chetak Appt. to New modern Appt. Rohini, Sector-2 under PWD Division NWR-2, Sub Division NWR-23 during 2021-22 2022.04.27 2022.06.26 14.13 16.96 (Jul'22) 0.00 (Jul'22) Dharambir Singh Detail Report
Graph / Photo
95 Construction of Drain at ROB-36 road near Truck Market (Towards NH24) under Sub-Division East Road-I of Division East Road, PWD during 2023-24. 2023.09.18 2023.12.16 13.10 Nation Star Enterprises Detail Report
Graph / Photo
96 Construction of Drain from YC Electrical Vehicle Shop to Subhash Nagar Drain on 100’ Road Patel Chowk Road under Sub-Div. WR-15, Division West-Road -1. dg. 2022-23 2022.05.27 2022.09.23 9.05 3.51 (May'23) 0.00 (May'23) Sanjay Enterprises Detail Report
Graph / Photo
97 Construction of rain water harvesting in the DM Office and SDM Office Saket and SDM office Mehrauli, M.B. Road, Saket. 2023.05.10 2023.06.09 8.22 Mohan Lal Detail Report
Graph / Photo
98 Road Restoration (balance work) B-Block Road, Mangolpuri cut by Delhi Jal Board 2022.06.12 2022.06.26 6.43 0.00 (Nov'23) Sanjay Kaura Detail Report
Graph / Photo
99 Desilting of Sump well of Shakti Nagar, Sawan Park, Roshanara Bagh i/c Repairing of Pump, all around the year 2022.06.12 2023.06.11 5.89 4.15 (Mar'23) 0.00 (Mar'23) Kuldeep Traders 100% Work Completed Detail Report
Graph / Photo
100 Construction of Foot Over Bridge on Ring Road at Sanyas Ashram, Bela Road, Sanskrit Mahavidhyalaya Near ISBT, Kashmere Gate, Delhi (SH. Electrical Works) 2017.09.17 2017.11.16 3.07 SUGANDHA ELECTRICALS Detail Report
Graph / Photo
101 A/R and M/O to various roads under Division NW R-2, Sub Division NWR-21 (Mangolpuri and Sultanpuri Constituency roads) dg. 2016-17. SH- Misc. Repair works. (3rd Call) 2016.08.29 2016.11.26 PG Forefieited Detail Report
Graph / Photo
102 AR and MO various roads under PWD Sub Divn I SWR II during 2016-17 SH Desilting of Drains under Section-I Pankha Road Area New Delhi 2017.06.09 2017.12.05 Work foreclosed on 18/10/2017 Detail Report
Graph / Photo
103 Providing and fixing M. S. Grill at central verge from Chhawla Village to BDO office, at Najafgarh Bijwasan Road (ID 1173) under PWD division SWR-II, New Delhi. 2020.09.14 2020.10.13 WORK not started Detail Report
Graph / Photo
104 Providing and laying tactile and making footpath accessible for differently abled persons on Pramod Mahajan Marg and J Block Road, New Delhi 2022.03.18 2022.05.01 running Detail Report
Graph / Photo
105 Making Disabled friendly footpath and repair of drain on MB Road under SR-11, PWD, New Delhi 2022.03.18 2022.05.01 61.83 (Feb'23) 0.00 (Feb'23) work in progress Detail Report
Graph / Photo
106 Repair of footpath at various locations on Nelson mandela road under Sub division V 2022.04.04 2022.06.03 Work in progress Detail Report
Graph / Photo
107 Construction of Flyover with Ramps, Footpath, Road Work including Road Signage, Street Light works, Drainage, Horticulture, Mural Works & allied works at Road No. 56 between Anand Vihar ROB and Apsara Border ROB, New Delhi (EPC Mode 2022.09.10 2023.12.08 10047.97 (Jun'23) 0.00 (Nov'23) carpeting over ramp A2 Detail Report
Graph / Photo
108 Corridor Development and Street Network/ Connectivity Plan for the influence zone of the corridor between Punjabi Bagh Flyover and Raja Garden Flyover 2022.09.10 2023.12.08 15431.80 (Jun'23) 0.00 (Nov'23)

Work is in progress.

Detail Report
Graph / Photo
109 Repair/Renovation of office of Assistant Engineer-4, Sub Division SR-14 2022.07.20 2022.09.02 work in progress Detail Report
Graph / Photo
110 Providing Commercial Inspection Vehicle for EE PWD, Division South Road-1 2022.06.01 2023.05.31 work in progress Detail Report
Graph / Photo
111 Maintenance and services of Computers Printers installed at Sub Divisions and Division SR-1 2022.07.25 2024.07.24 0.00 (Nov'23) work in progress Detail Report
Graph / Photo
112 Providing services of Maintenance Vans for day to day repair work 2022.07.30 2024.07.29 35.07 (May'23) 0.00 (Nov'23) Work in progress Detail Report
Graph / Photo
113 Providing services of Maintenance Vans for day to day repair work 2022.07.30 2024.07.29 17.52 (May'23) 0.00 (Nov'23) work in progres Detail Report
Graph / Photo
114 Construction of Shed with seating block Changing room Pump room and UGT tank at East Vinod Nagar sports complex Delhi 2022.12.14 2023.05.12 0.00 (Oct'23) Work in progress. 45% work has been done. Detail Report
Graph / Photo
115 Construction of Cement Concrete Road near Bio-remediation Waste Water Treatment Plant at 100 Foota Road. 2023.04.25 2023.07.24 Work in progress Detail Report
Graph / Photo
116 Construction of Officers, Public Toilet (Gents and Ladies) and roof treatment of Enforcement Branch HQ at Transport Authority, 5/9 under Hill Road , Delhi -54. 2023.03.16 2023.05.15 In-porgress Detail Report
Graph / Photo
117 Providing and Fixing Grass paver block on the unpaved area from Mandi Cut to Arjangarh on Left Hand Side on Acharya Shree Tulsi Marg (M.G.Road), NH-236. 2023.01.20 2023.02.18 work in progress Detail Report
Graph / Photo
118 Improvement and reconstruction of footpath on various roads (Mathura Road, Bhairon Marg and Ring Road under Division M-321, Delhi on urgent basis in view of G-20 SUMMIT 2023. 2023.02.12 2023.04.14 0.00 (Nov'23) In-progress Detail Report
Graph / Photo
119 Strengthening of M. G. Road to Ghitorni Village Road & Improvement of footpath for accessibility of disable persons of M.G. Road to Ghitorni Village Road and provision of Jersey Barrier at Aaya Nagar Road under Sub-Division SR-15, Division South Road-1 at New Delhi 2023.02.17 2023.03.16 work in progress Detail Report
Graph / Photo
120 Development of road, footpath, kerbstone, etc. at enterance & exit of Sadar Bazar Metro Station at Dwarka Approach Road (Road ID- 1712) Under PWD Division South West Road-I, Sub Division-I New Delhi 2022.11.03 2023.02.02 0.00 (Aug'23) Work completed Detail Report
Graph / Photo
121 Construction of new footpath, Repairing of existing footpath on Pankaj Juyal Marg & Birla Vidya Niketan Marg, Repair of boundary wall in front of Saket Court on Pankaj Juyal Marg and providing and placing jersey barrier on Press Enclave Road and Mandir Marg. 2023.02.04 2023.03.03 0.00 (Nov'23) work in progress Detail Report
Graph / Photo
122 General repair & maintenance work 2022.09.27 2023.06.26 Work in progress Detail Report
Graph / Photo
123 Restoration of caved-in/settled road in emergency situation on various road of all Sub-Divisions under PWD Division South Road-1/Sub Division SR-14 during 2022-23 2022.10.06 2023.04.05 Running Detail Report
Graph / Photo
124 Providing, running and maintaining Water Sprinkler Anti Smog Gun on hire basis at various locations 2022.10.06 2023.03.05 work in progress Detail Report
Graph / Photo
125 Providing and fixing road signage boards under Sub-Division SER-21, SER-22, SER-23, SER-24 and SER-25 2023.01.20 2023.03.19 55% Detail Report
Graph / Photo
126 Construction of Shed with seating block, Changing room, Pump room and UGT tank at East Vinod Nagar sports complex, Delhi. 2022.12.14 2023.05.12 0.00 (Nov'23) work in 40 % progress. Detail Report
Graph / Photo
127 Providing and fixing road signage boards under Sub-Division SER-21, SER-22, SER-23, SER-24 and SER-25 2023.01.20 2023.03.19 50% Detail Report
Graph / Photo
128 Misc. Civil work i/c providing channel section, MS Sheets for installation of Lifts at Aali Village and Harkesh Nagar FOB, as per requirement of Electrical wing. 2023.07.22 2023.08.21 Work in Progress Detail Report
Graph / Photo
129 Providing additional staircase from Skywalk towards Moti Bagh, MS staircase for underground sump, provision for additional railing over skywalk, Covering of Skywalk with CGI sheet roofing & C/o wall with MS Grill towards Moti bagh at FOB Durgabai Deshmukh Metro Station, Ring Road New Delhi. 2023.06.29 2023.10.28 2.00 % (Jun'23) Work in Progress Detail Report
Graph / Photo
130 Remodelling of culvert drain near N Block and Kerb Channel on Hansraj Gupta Marg 2023.06.09 2023.07.23 15% Detail Report
Graph / Photo
131 Removal of already dumped and dumped unclaimed malba by unknown persons under Sub Division SER-24 2023.05.16 2023.08.15 50% Detail Report
Graph / Photo