Corridor Development and Street Network/ Connectivity Plan for the influence zone of the corridor between Punjabi Bagh Flyover and Raja Garden Flyover
Office Name
Flyover Divn F-11/Flyover Div F-13
History Sheet     Abstract of Cost             NIT Document
Progress Details
Date of Start: 10/09/2022
Date of Completion: 08/12/2023
Expected Date of Completion: 08/12/2023
Actual Completion Date:
Payment
Civil:  10121.20 Lacs (Mar 2024)
% Progress : % (Mar 2024)
Present Position
Civil :  06/02/2024

Moti Nagar Flyover is completed and inaugurated by Hon’ble Chief Minister, Delhi  on 13.03.2024 , and opened for public use. 

 

Punjabi Bagh flyover work is in progress. 

Bottlenecks
Civil :  06/02/2024

Moti Nagar Flyover is completed and inaugurated by Hon’ble Chief Minister, Delhi  on 13.03.2024 , and opened for public use. 

 

Punjabi Bagh flyover work is in progress. 

Milestone
S.No. Activity Date of Start Target Date of Completion Revised Date of Completion Actual Date of Completion Progress (%) Remarks
1 Foundation Pile 01/02/2023 28/02/2023 -- 28/02/2023 100.00 Completed
2 Foundations Pile Cap 01/02/2023 12/03/2023 -- 12/03/2023 100.00 Completed
3 UP Ramp 30/04/2023 31/07/2023 -- 04/07/2023 100.00 Completed
4 Down Ramp 27/03/2023 30/06/2023 -- 30/06/2023 100.00 Completed
5 Sub- Structure Pier Shaf 01/03/2023 31/05/2023 -- 31/05/2023 100.00 Completed
6 Sub- Structure Pier Cap 01/05/2023 30/06/2023 -- 30/06/2023 100.00 Completed
7 RCC Girder (Casting ) 01/05/2023 11/07/2023 -- 11/07/2023 100.00 Completed
8 Girder Launching 08/07/2023 30/07/2023 -- -- 0.00 In-Progress
9 Deck Slab 01/08/2023 30/09/2023 -- -- 0.00 In-Porgress
10 Crash Barrier 01/09/2023 30/09/2023 -- -- 0.00 In-Progress
11 Handover 01/09/2023 15/10/2023 -- -- 0.00 In-Progress
12 Steel Girder 01/08/2023 31/08/2023 -- -- 0.00 In-Progress