C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc
Office Name
Education East & North East Maint Divn
History Sheet         Background Note         NIT Document
T.S. Amount
2458.24 Lacs
Dated
30/11/2021
Tender Amount
1553.88 Lacs
Dated
07/03/2022
Progress Details
Date of Start: 26/03/2022
Date of Completion: 19/02/2023
Expected Date of Completion: 31/08/2024
Actual Completion Date:
Contractor
M/s K L Arora & Son
Payment
Civil:  459.24 Lacs (Jan 2025)
% Progress : % (Jan 2025)
Present Position
Civil :  02/07/2024
Tower A - Finishing & development work under progress and will be completed by the end of 30th June 2024 and will be handed over by 15.07.2024 Tower B - is not taken up due to existency of trees in the proposed building plan regarding the same this office has written a letter to HOS to not being taken up due to tree in building plan. MP Hall - Work completed. DIET Block - Structural work completed of 2/3 building portion and structural work of remaining 1/3 portion of 2nd floor under progress except 2 no. classrooms and 1 staircase held up as there are branches of tree in the building line for which approval is pending for prunning of trees from forest department. Tile work & finishing work under progress in structurally completed 2/3 building portion and will be completed by 31.08.2024
Bottlenecks
Civil :  02/07/2024
Tower A - Finishing & development work under progress and will be completed by the end of 30th June 2024 and will be handed over by 15.07.2024 Tower B - is not taken up due to existency of trees in the proposed building plan regarding the same this office has written a letter to HOS to not being taken up due to tree in building plan. MP Hall - Work completed. DIET Block - Structural work completed of 2/3 building portion and structural work of remaining 1/3 portion of 2nd floor under progress except 2 no. classrooms and 1 staircase held up as there are branches of tree in the building line for which approval is pending for prunning of trees from forest department. Tile work & finishing work under progress in structurally completed 2/3 building portion and will be completed by 31.08.2024