Renovation of toilet Blocks And Misc. works at Auditorium
Office Name
History Sheet                
Tender Amount
25.13 Lacs
Dated
15/12/2014
Progress Details
Date of Start: 11/01/2015
Date of Completion: 10/04/2015
Expected Date of Completion: 20/09/2016
Actual Completion Date: 31/12/2016
Payment
Present Position
Civil :  09/05/2017
Work Delete.
Bottlenecks
Civil :  09/05/2017