Road - Maintenance Workसड़क - रखरखाव का कार्य
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 Comprehensive Maintenance of Ring Road/Outer Ring Road under North Maintenance Zone, PWD, Delhi SH: Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work 2020.05.30 2022.05.29 3194.88 554.24 (Jul'22) 0.00 (Jul'22) MAHAVIR PRASAD GUPTA AND SONS Work in Progress Detail Report
Graph / Photo
2 Widening and Stengthening of Road from Najafgarh Dhansa Road to Jhuljhuli Morh via Ghummanhera Village, Delhi. 2015.01.08 2015.11.07 2057.50 Mahavir Parsad Gupta & Sons Work in Progress Detail Report
Graph / Photo
3 Re-development of Chadini Chowk Road in between Lal Jain Mandir to Fateh Puri Mosque. 2013.10.12 2014.04.11 1343.02 Satya Parkash & Bros. Pvt. Ltd. Detail Report
Graph / Photo
4 Resurfacing improvement strengthening riding surface of roads ..... road division 2020.01.13 2020.04.08 1272.87 882.72 (Jan'23) 0.00 (Jan'23) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
5 Providing Data Entry/Computer Operators, Diary Dispatcher/LDC/ Office Clerk, MTS/Messengers, LMV Drivers, Peon etc. for various offices under Project Circle, SRD Project Division-I and DHC & ND/ Central (M-451) 2022.07.21 2025.07.20 878.94 61.00 (Jan'23) 0.00 (Jan'23) RAKSHAK SECURITAS PVT. LTD. Detail Report
Graph / Photo
6 Construction of FoB/Skywalk from Supreme Court Metro Station to Additional Building Supreme Court and Supreme Court Main Campus on Mathura Road, New Delhi 2022.07.16 2023.01.16 831.11 165.57 (Jan'23) 0.00 (Jan'23) M/s Chaudhary Construction Company Pvt. Ltd.

Work in progress

Detail Report
Graph / Photo
7 Strengthening of Outer Ring Road from Gandhi Vihar to Burari Flyover under Sub Division-1, Division C&ND-Road New Delhi. 2022.06.24 2022.08.23 690.38 737.88 (Dec'22) 0.00 (Dec'22) SBG Infracon Pvt Ltd Detail Report
Graph / Photo
8 Strengthening / Resurfacing of (1) Seemapuri Road from Road No. 64 to Road No. 62 (2) GTB Hospital Road from Red Light to Agrawal Sweet (3) CNG West Side road (4) GTB Hospital road from GT Road to Agrawal Sweets (5) G.T.B. Hospital Road from Road No. 64 to Road No. 68 (6) Captain Javed Ali Marg (7) Gandhi Nagar Main Market Road (8) Road No. 75B Ext. (Bhartendu Harish Chander Marg from Yamuna Sports Complex to Karkari More flyover (9) Vishwas Nagar Road (60’0” wide). 2020.02.28 2020.06.26 675.69 777.41 (Oct'22) 0.00 (Oct'22) Pawan Kumar Work in progress Detail Report
Graph / Photo
9 Remodeling of drain from 25 futa road, Meet nagar to Loni Gole Chakkar at Road No.-63, Construction of sump well at loni Gole Chakkar & MIG/ LIG Flat, Providing and laying K-9 pipe from Loni gole Chakkar to Drain No-01 & Construction of pump House, Electrical & mechanical Services at Loni Gole Chakkar & MIG/ LIG Flat. 2022.03.31 2022.07.28 657.45 100.00 (Sep'22) 0.00 (Sep'22) K. L. ARORA & SON Detail Report
Graph / Photo
10 Providing stone Matrix Asphalt(SMA) under Sub Division-II, South West Road-II Najafgarh, New Delhi 2021.11.23 2022.01.21 581.89 224.77 (Oct'22) 0.00 (Oct'22) Pawan Kumar Detail Report
Graph / Photo
11 Strengthening of Najafgarh Jharoda Road ic raising of depressed road at Ekta Vihar under Sub Division II South West Road II PWD New Delhi. ID 1231 2019.10.16 2020.02.12 567.80 236.37 (Jul'20) 0.00 (Jul'20) Pawan Kumar WORK IN PROGRESS Detail Report
Graph / Photo
12 Improvement and strengthening of Road No. 63, Delhi (From Bhopura Border to Loni Gol Chakkar except flyover). 2019.12.14 2020.03.12 541.95 M/s Roadtech Detail Report
Graph / Photo
13 Widening of carriageway including shifting of central verge and footpath of Outer Ring Road from Majnu ka Tila Red Light to Wazirabad Flyover (Under 77 corridor improvement plan) in Division C&ND-R New Delhi dg. 2022-23 2022.11.08 2023.03.07 532.40 AMOCON Detail Report
Graph / Photo
14 Comprehensive repair and maintenance of various roads under sub division M- 2132. 2019.11.21 2020.11.20 460.10 504.82 (Sep'22) 0.00 (Sep'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
15 A/R & M/O Various roads under East Road Sub Division-III, Division East Road (M 212) during 2019-20. (SH:- Comprehensive maintenance of road) 2019.10.15 2020.10.14 455.11 418.02 (May'22) 0.00 (May'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
16 Comprehensive repair and maintenance of various roads under sub division M- 2134. 2019.11.21 2020.11.20 433.62 599.23 (Sep'22) 0.00 (Sep'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
17 Improvement and strengthening of Road No. 59, Delhi (From Khajuri Gole Chakkar to outer Ring Road Except Wazirabad Yamuna Bridge). 2020.01.13 2020.04.05 432.05 281.82 (Nov'20) 0.00 (Nov'20) M/s Roadtech Detail Report
Graph / Photo
18 Strengthening of Narwana Road from Mother Dairy T-Point to Panch Mahal Awas during 2017-18 2018.04.19 2018.07.17 402.83 79.00 (Jun'19) 0.00 (Jun'19) A S INFRATECH Work in Progress Detail Report
Graph / Photo
19 stopping vibration and noise 2013.02.26 2013.06.25 398.44 K.L. Arora & Son Sanctioned Detail Report
Graph / Photo
20 Providing remedial measures for stopping vibration and noise due to flyover to Outer Ring Road near Ber Sarai, Munirka and Vasant Vihar. 2013.02.26 2013.06.25 398.44 K.L. Arora & Son Sanctioned Detail Report
Graph / Photo
21 Strengthening of Prithvi Singh Dagar Marg ID 1175 from RawtaMorh Dhansa Road to Daurala Border under PWD Division- South West Road-II New Delhi. 2019.10.16 2020.02.12 388.15 0.84 (Apr'22) 0.00 (Apr'22) Pawan Kumar UNDER TENDERING PROCESS Detail Report
Graph / Photo
22 Providing, running and maintaining truck mounted Anti Smog Gun on hire basis at various locations 2022.05.19 2023.05.18 372.34 P. R. S. Yash & Co. Detail Report
Graph / Photo
23 Improvement of RUB surrounding area and construction of new additional sump at RUB Badarpur under Sub Division SER-24 in Division SER-2, New Delhi and Enhancement of substation, etc 2021.11.02 2022.03.01 371.37 289.08 (Nov'22) 0.00 (Nov'22) Jamshed Ali and Sons Detail Report
Graph / Photo
24 Improvement and Strengthening of Loni Road from G.T. Road to Loni Gole Chakkar. 2022.05.08 2022.08.05 357.04 207.93 (Dec'22) 0.00 (Dec'22) Pawan Kumar Detail Report
Graph / Photo
25 Replacement of damaged old 900mm Dia RCC pipe with Providing and Laying 1200mm dia RCC Pipe from Som Bazar Chowk to Mungeshpur drain at Najafgarh Nangloi Road. (Road ID -1230) 2022.04.18 2022.10.14 339.47 131.12 (Oct'22) 0.00 (Oct'22) Dilshad Khan Detail Report
Graph / Photo
26 Development of play field in Govt. Boys Sr. Sec. School, Hiran Kudna, New Delhi. C/o 200 meters Synthetic Athletic Track, Change rooms, Reception, Coach rooms etc. including E & M works 2022.12.28 2023.08.25 330.41 Desan International work has been recently awarded to the agency. Detail Report
Graph / Photo
27 A/R and M/O to Sub Division-14 of South Road-1 for Comprehensive Maintenance of Press Enclave Road, Mandir Marg, Pankaj Juyal Marg, NBCC Plaza Road, Pramod Mahajan Marg, Family Court Road J-Block Road, H-Block Road Gurudwara Road, Asian market Road, Khirki Road, Sheikh Sarai Phase-I Road no.1 & Road No.2, Road from H.No. C-11 to C-20 Malviya Nagar and Road in front of Mother International School during 2019-20. 2019.11.01 2020.10.31 317.62 488.34 (Jun'22) 0.00 (Jun'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
28 Strengthening of Rajpura Road from Tis Hazari Red Light to Civil Line Thana under SubDivision-4 of Division C& ND-Roads, New Delhi. (Width- ROW Below 30.00 meter) 2022.06.24 2022.10.23 313.49 Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
29 Strengthening of Road No. 68 (from Road No. 66 T-Point to Junction of Road No. 69). (From Railway line to Road No. 66 T-Point). 2019.09.02 2019.11.30 309.88 302.32 (Dec'21) 0.00 (Dec'21) MAHAVIR PRASAD GUPTA AND SONS work in progress Detail Report
Graph / Photo
30 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road-II PWD New Delhi 2019.09.10 2020.01.07 298.81 194.61 (Jul'20) 0.00 (Jul'20) SBG Infracon Pvt Ltd WORK IN PROGRESS Detail Report
Graph / Photo
31 Providing & fixing 80 mm thick Paver Block over Unpaved Shoulder Portion of Road in view of Anti Air Dust Pollution Measures for Rao Laxmi Chand Marg (ID 1174) under Sub Division 23 Division SWR-II, PWD, Delhi 2022.04.14 2022.08.11 296.33 323.76 (Dec'22) 0.00 (Dec'22) Bliss Associates Detail Report
Graph / Photo
32 Strengthening of Madhu Vihar Road (Road No. 57 to Joshi Colony T-Point) and Mandawali Road (House Tax Building to Agrasen Apartment) at I.P. Extension under PWD Division East (Road) 2018.04.16 2018.07.14 280.65 117.06 (Feb'22) 0.00 (Feb'22) JAP BUILDCON PRIVATE LIMITED Work in Progress Detail Report
Graph / Photo
33 Providing Tractor driven positive displacement rotary lobe pump & diesel engine pump set at different locations for removing water logging etc. during rainy season. 1st RECALL 2022.06.16 2022.10.15 274.22 284.01 (Sep'22) 0.00 (Sep'22) Aliyan Construction Company Detail Report
Graph / Photo
34 Improvement of approach road and construction side drain from Main Burari Road to Burari Transport Complex road. 2022.06.24 2022.10.23 250.03 50.00 (Oct'22) 0.00 (Oct'22) Aditya Enterprises Detail Report
Graph / Photo
35 A/R and M/O to various Roads under Division South Road -II, PWD during 2021-22 (SH:Filling the pot holes / patch repair on PWD Roads by Mobile Infrared Recycling Road Repair Machine under Sub-Division-I, II, III and IV) 2021.09.03 2022.09.02 246.96 295.79 (Jul'22) 0.00 (Jul'22) Trans Metalite India Limited Work in Progress Detail Report
Graph / Photo
36 Resurfacing of Satguru Ram Singh Marg (Road ID 1226), and improvement of footpath with Enhancement of exiting drain capacity under Sub Division- 21, SWR-II, PWD, New Delhi. 2023.01.18 2023.05.17 238.30 Surender Singh Detail Report
Graph / Photo
37 SITC of Pump Sets and related equipments 2021.12.21 2025.04.20 233.20 106.49 (Jun'22) 0.00 (Jun'22) VOGELSANG INDIA PVT LTD Detail Report
Graph / Photo
38 Comprehensive Maintenance of SSN Marg, 100 Foota Road and 60 Foota Road under the Jurisdiction SD-12 under SR-1 during 2019-20. 2019.11.01 2020.10.31 227.39 326.28 (Feb'22) 0.00 (Feb'22) Amrit Lal behl & Sons Detail Report
Graph / Photo
39 Providing and laying K-9 pipe from Pump House at Bhagat Singh Park to Drain No. 1 2022.05.05 2022.08.04 208.39 169.94 (Oct'22) 0.00 (Oct'22) Vinod Kumar Detail Report
Graph / Photo
40 A/R and M/O to Sub Division-11 of South Road-1 for Comprehensive Maintenance of Road under jurisdiction of Sub Division-11 during 2019-20 2019.11.01 2020.10.31 199.05 303.89 (Jan'22) 0.00 (Jan'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
41 Providing and fixing Paver Block on both side berm from KhairaMorh to Mitraon village and laying NP-4 pipe line from Dilawarpiao to Mitraon Sump under Sub Division-II, South West Road-II.(Road ID1227) 2022.02.26 2022.05.26 196.78 261.88 (Nov'22) 0.00 (Nov'22) Surender Singh Detail Report
Graph / Photo
42 Improvement and beautification of road between Dhaula Kuan to IGI airport NSG Xing (L.H.S). Phase-II 2022.10.20 2022.12.18 190.36 858.81 (Jan'23) 0.00 (Jan'23) Jagdish Prasad Meena Detail Report
Graph / Photo
43 Construction of RCC drain from NH-24 Ghazipur Dairy Farm to DTL office at Ghazipur Shamshan Ghat Road 2022.02.14 2022.07.13 173.56 52.00 (Jul'22) 0.00 (Jul'22) K. L. ARORA & SON Detail Report
Graph / Photo
44 Road Restoration (Road cut by Delhi Jal Board) at Bijwasan Road under Sub Division-24 SWR-II PWD, New Delhi. 2019.10.04 2020.01.01 173.51 A S Infratech Work in progress 96% Detail Report
Graph / Photo
45 EOR TO BCP SKV Babarpur, Delhi during 2022-23 (SH- Upgradation of existing building and other misc. repair works). 2022.09.14 2023.06.13 172.98 Shyam Sundar Tyagi Detail Report
Graph / Photo
46 1. EI Works 2. Replacement of faulty and damaged clocks of Ghantaghar 2022.07.07 2022.10.06 170.57 68.58 (Jan'23) 0.00 (Jan'23) SEHRA ELECTRIC works Detail Report
Graph / Photo
47 Civil and Electrical Works. 2019.03.06 2019.09.05 168.62 205.44 (Aug'21) 0.00 (Aug'21) Imaginearc Infrastructure Pvt. Ltd. Work in Progress. Detail Report
Graph / Photo
48 Alignment of footpath and extension of road adjacent to the Meena Bazar area on Urdu Bazar Road, acquired after encroachment drive, under SRD Division-I, Sub Division-I, PWD, New Delhi . 2018.07.13 2018.08.26 158.52 Sirohi Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
49 Comprehensive repair and maintenance of various roads under sub division M- 2132 2022.03.07 2023.03.06 157.14 34.39 (Aug'22) 0.00 (Aug'22) PRATAP SINGH Detail Report
Graph / Photo
50 Improvement of drainage system from RD 4350 (Near kali piyau) to RD 1200 (Near Jharoda village ) RHS on Najafgarh Bahadurgarh road Delhi. 2015.01.16 2015.05.15 155.22 B.M. & Sons Detail Report
Graph / Photo
51 Improvement and beautification of road between DhaulaKuan to IGI airport NSG Xing (L.H.S) 2022.09.29 2022.11.27 152.67 15.00 (Nov'22) 0.00 (Nov'22) Nitin Kumar Sharma Detail Report
Graph / Photo
52 1. Infrastructural Improvement and Renovation of Office Building, Toilet and open Ground at Science Centre no 3, Plot no 3, Link Road, Karol Bagh, New Delhi under Sub-Division-I of SRDP-II, PWD, New Delhi). (2) Infrastructural Improvement and Renovation at of the Building of Science Centre No. 3 Plot NO. 3, Link Road, Karol Bagh, New Delhi (Electrical works) 2022.03.06 2022.09.02 151.95 86.31 (Aug'22) 0.00 (Aug'22) B P Rai and Sons Detail Report
Graph / Photo
53 Comprehensive repair and maintenance of various roads under sub division M- 2134 2022.03.07 2023.03.06 149.82 25.00 (Jul'22) 0.00 (Jul'22) PRATAP SINGH Detail Report
Graph / Photo
54 Improvement of drainage system of Yamuna Vihar area. (SH.-Providing and laying K-9 pipe from Pump House at dividing road to Drain No.1). 2018.06.15 2018.10.14 149.16 162.12 (Dec'21) 0.00 (Dec'21) RAJESH KUMAR GUPTA Work in progress. Detail Report
Graph / Photo
55 Desilting of road side drain manually and mechanically with super sucker machine under Sub-Division East Road-I, Delhi 2019.03.14 2020.01.13 147.77 202.22 (Jun'20) 0.00 (Jun'20) Rajnish Yadav

Work in progress

Detail Report
Graph / Photo
56 1. Maintenance of E and M Services in Underpasses RUBs, Subways, FOBs, Drains, Fountains and Lifts. 2. Maintenance of Street Lights 2021.12.29 2022.12.28 144.24 Shaka Electrical India Detail Report
Graph / Photo
57 Desilting of road side drain manually and mechanically with super sucker machine 2018.05.24 2019.05.23 142.81 205.64 (Feb'22) 0.00 (Feb'22) M/s Shiva Construction Co.

Work in progress

Detail Report
Graph / Photo
58 Strengthening and Improvement of Drain, Footpath, Central Verge of Rani Jhansi Road (Idgah round about to Filmistan) 2014.04.05 2014.12.04 142.38 K Construction co Detail Report
Graph / Photo
59 Construction of sump well, Pump house and providing and laying K-9 Pipe from Gurudwara Road to Drain No. 01 and Providing and installation of storm pump set Gurudwara Road at Seelampur, Delhi 2022.04.08 2022.07.16 140.86 105.95 (Dec'22) 0.00 (Dec'22) Vinod Kumar Detail Report
Graph / Photo
60 Desilting of road side drains of Section I and II. 2019.03.14 2020.01.13 140.11 190.15 (Dec'19) 0.00 (Dec'19) Shiv Construction Co.

Work in progress

Detail Report
Graph / Photo
61 Civil Works: Mechanised Desilting of Drains & Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other Misc. Repair works of footpaths, Central Verge, Service roads etc. on other roads than ring road under Sub-Division NWR-21 2022.09.28 2023.09.27 138.10 Rajinder Prasad Detail Report
Graph / Photo
62 Improvement of riding surface of Najafgarh Phirni Road (Chhawla Stand) to BDO office and Radha Swami Satsang Deenpur to JhatikaraMorh on Najafgarh Bijwasan Road (ID 1173) under SWR-II ,PWD, New Delhi 2022.06.25 2022.07.24 137.22 M C Construction Detail Report
Graph / Photo
63 Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24 2022.09.28 2023.09.27 136.84 Rajender Prashad Detail Report
Graph / Photo
64 Providing services of Maintenance van under Sub-Division R-21 2022.07.18 2024.07.17 127.66 15.42 (Oct'22) 0.00 (Oct'22) GLOBE BUILDERS Detail Report
Graph / Photo
65 Providing services of Maintenance van under Sub-Division R-24 2022.07.21 2024.07.20 127.44 23.22 (Nov'22) 0.00 (Nov'22) GLOBE BUILDERS Detail Report
Graph / Photo
66 Civil work- Comprehensive repair works of footpaths, central verge, service roads etc. on other roads under Sub division NWR-23 2022.09.28 2023.09.27 127.41 Rajinder Prasad Detail Report
Graph / Photo
67 Providing services of Maintenance van under Sub-Division R-23 2022.07.21 2024.07.20 127.19 14.91 (Oct'22) 0.00 (Oct'22) GLOBE BUILDERS Detail Report
Graph / Photo
68 Providing services of Maintenance van under Sub-Division R-25 2022.07.15 2024.07.14 127.12 15.94 (Oct'22) 0.00 (Oct'22) GLOBE BUILDERS Detail Report
Graph / Photo
69 Remodelling of Drain at Patparganj Road from Nirman Vihar Red Light to Disused Canal Road 2022.02.14 2022.06.13 124.56 10.00 (Aug'22) 0.00 (Aug'22) K. L. ARORA & SON Detail Report
Graph / Photo
70 Day to day maintenance and repair of civil work such as Roads, Footpaths, Central Verge, Planter, filling of potholes, de-silting of drains, Tractor mounted pumps for de-watering of water logging etc. and other misc. work during 2021-22 2022.02.02 2023.02.01 118.91 ashok builders Detail Report
Graph / Photo
71 A/R and M/O to Sub Division-11 of South Road-1 for Comprehensive Maintenance of Road under jurisdiction of Sub Division-11- during 2021 2021.04.26 2022.04.25 116.74 RICHCON ENGINEERING COMPANY Work in progress Detail Report
Graph / Photo
72 Providing and fixing M. S. Grill at central verge from Chhawla Village to BDO office, at Najafgarh Bijwasan Road (ID 1173) under PWD division SWR-II, New Delhi. 2019.09.09 2019.11.07 114.71 25.00 (Jul'20) 0.00 (Jul'20) Awasthi Construction Co. WORK IN PROGRESS Detail Report
Graph / Photo
73 A/R and M/O to various roads under PWD Sub Division M-2132 dg. 2017-18. (SH-Anti carbonation painting work on concrete structure of 4 Nos Flyovers (Loni Flyover, Gokalpuri Flyover, Kahjuri Flyover and Nand Nagri Flyover) under Sub Division M-2132. 2018.04.05 2018.06.04 113.31 51.99 (Dec'21) 0.00 (Dec'21) Shamshad Ahmed work in progress Detail Report
Graph / Photo
74 A/R & M/O to various roads under Division East Road/(m212) PWD Delhi, during 2021-22 2021.04.01 2022.03.31 110.00 10.20 (May'22) 0.00 (May'22) Star security & Placement Services Detail Report
Graph / Photo
75 Construction of drain on Mathura Road at following locations (i) Jasola Apollo Metro Station area including connecting to existing drain (RHS).(ii) Near Sukhdev Vihar RD 400 to 1070 (LHS).(iii) Priyanka camp to infront of CRRI (RHS) 2021.07.17 2021.11.16 109.94 Satyam Construction Co. Detail Report
Graph / Photo
76 Improvement of riding surface of Najafgarh Phirni Road (Chhawla Stand) to BDO office and Radha Swami Satsang Deenpur to JhatikaraMorh on Najafgarh Bijwasan Road (ID 1173) under SWR-II ,PWD, New Delhi 2022.02.26 2022.03.27 109.21 Nirmit Construction Co. Detail Report
Graph / Photo
77 Desilting of road side storm water drain by Mannual & Super Sucker Machine on Various roads, under Sub Division-I &II 2022.06.04 2023.06.03 106.09 PRS yash & co Detail Report
Graph / Photo
78 Desilting of road side drains of Section I and II. 2019.03.15 2019.12.14 104.45 143.10 (Nov'21) 0.00 (Nov'21) Anmol Infratech Private Limited

Work in progress

Detail Report
Graph / Photo
79 Repair of footpath and drains on Khudiram Bose Marg from (Metro Pink Line) Pillar No. CP-02 to 52 2021.11.17 2022.01.15 103.36 3.00 (May'22) 0.00 (May'22) Rajesh Kumar Gupta Detail Report
Graph / Photo
80 Desilting of road side drain manually and mechanically with super sucker machine at Patparganj Road, Chitra Vihar Road, New Rajdhani Enclave Road, Vikas Marg, Disused Canal Road, Gagan Vihar Road, Narwana Road and Several others Road in I.P. Extension in the Sub-Division -I East Road, Delhi 2018.04.30 2019.03.01 102.72 21.44 (Nov'19) 0.00 (Nov'19) M/s Shiva Construction Co.

Work in progress

Detail Report
Graph / Photo
81 Desilting of road side drains 2018.05.24 2019.02.23 101.35 25.00 (Sep'19) 0.00 (Sep'19) M/s Shiva Construction Co.

Work in progress

Detail Report
Graph / Photo
82 A/R and M/O to Sub Division-14 of South Road-1 for Comprehensive Maintenance of Press Enclave Road Mandir Marg Pankaj Juyal Marg NBCC Plaza Road Pramod Mahajan Marg Family Court Road J-Block Road H-Block Road Gurudwara Road Asian market Road Khirk- 2021.04.26 2022.04.25 99.13 79.10 (May'22) 0.00 (May'22) S S Chauhan & Sons Work in progress Detail Report
Graph / Photo
83 Strengthening of road & upgradation of footpath at Khari Baoli Road under Sub Division-I of Division SRDP-I, New Delhi during 2022-23. Recall of Tender 2022.06.13 2022.08.12 97.61 M/s Roadtech Detail Report
Graph / Photo
84 Improvement and Strengthening of Dharamshilla Road at Vasundhra Enclave Delhi 2018.05.17 2018.06.30 95.76 39.37 (Jun'19) 0.00 (Jun'19) Chaudhary Construction Company Pvt. Ltd.

Work in progress

Detail Report
Graph / Photo
85 A/R & M/O to various roads under North East (B&R) Maintenance Division dg 2022-23. (SH:- Repair to riding surface of road & flyover under Sub Division M-2132). 2022.12.17 2023.02.14 93.98 Pawan Kumar Detail Report
Graph / Photo
86 Consultancy services for Structural Design and preparation of other documents for Construction of Bridge on Najafgarh drain at Tri Nagar/Inderlok, Karampura and Rampura, Delhi 2018.09.23 2021.03.22 93.37 Tandon Consultant Pvt. Ltd. work is in progress. Detail Report
Graph / Photo
87 Comprehensive Maintenence of Flyover , Subway, Tiranga chowk Island at IandFC Nallah etc. Of various roads under Sub Div-21 SWR-II, New Delhi. 2022.06.10 2023.06.09 93.21 Star security & Placement Services Detail Report
Graph / Photo
88 Comprehensive maintenance of various roads under Sub-Division East Road-I (Section-I&II) of Division East Road during 2022-23. (SH: Repair of footpath & Central Verge & Misc. Repair work.) 2023.01.19 2023.07.17 91.66 sabur alam Detail Report
Graph / Photo
89 Additional work for construction of service road from IOCL Petrol Pump to Indraprastha Metro Station along Ring Road beyond ITPO Project area, New Delhi 2022.06.27 2022.07.26 90.63 94.29 (Dec'22) 0.00 (Dec'22) A S INFRATECH Detail Report
Graph / Photo
90 Development of garden features and planting of trees,shrubs and ground covers along with integrated corridor at Pragati Maidan 2023.01.13 2023.04.12 88.96 Om Prakash Sharma Detail Report
Graph / Photo
91 Providing services of Computer Operators, LMV Drivers, MTS etc. in various offices under North Roads Division, PWD, Delhi 2022.04.18 2023.04.17 88.45 40.53 (Jan'23) 0.00 (Jan'23) K P Singh & Co. Detail Report
Graph / Photo
92 Providing services of Computer Operators, Clerks, Supervisor and MTS for Division and Sub Division Offices 2022.09.01 2023.08.31 87.31 Star security & Placement Services Detail Report
Graph / Photo
93 Providing services of Maintenance Van and supplying of various items on Ring Road and Ring Road Bypass 2023.01.11 2023.07.10 87.02 R. R. Realtors Detail Report
Graph / Photo
94 Widening of Road no 102 from Bharti Public School to Dallupura Road & Improvement of Kaccha Portion on Porta Cabin Road. 2018.06.27 2018.09.24 86.16 Y D Builders and hotels pvt. ltd Work in Progress Detail Report
Graph / Photo
95 A/R & M/O to various roads under Sub Division-1 of Division South Road-II, PWD during 2021-22 (SH: Providing Computer operator, MTS, Clerk and MLD, in Sub Division office, Division office and CE South office). 2021.10.17 2022.07.16 85.09 69.01 (Nov'22) 0.00 (Nov'22) TRENDY SECURITY SERVICES Work in Progress. Detail Report
Graph / Photo
96 Desilting of storm water drain at different vulnerable point on Najafgarh-Bijwasan & Goyala Deenpur Road under Sub Division-25 2023.01.26 2023.04.25 85.08 Surender Singh Detail Report
Graph / Photo
97 Providing services of Maintenance Van & supplying of various items for Arterial Roads 2022.06.14 2023.06.13 84.40 P. R. S. Yash & Co. Detail Report
Graph / Photo
98 Remodeling of Drain near Q-Pocket along CNG East side from Road No. 64 to Divider Road in Dilshad Garden Delhi 2022.02.25 2022.08.23 84.10 54.97 (Dec'22) 0.00 (Dec'22) BASAU CONSTRUCTION (INDIA) Detail Report
Graph / Photo
99 A/R & M/O Various Roads under SRD Project Division-I, PWD, New Delhi During 2018-19 (SH: Providing Data Entry/Computer Operators, Messengers, LMV Drivers, Clerical Staff etc. for various offices under Project Circle and SRD Division-I.) 2018.07.30 2019.06.29 83.90 67.79 (Apr'21) 0.00 (Apr'21) RAKSHAK SECURITAS PVT. LTD. Work in progress Detail Report
Graph / Photo
100 Desilting of Storm water Drain during monsoon2022 by Mechanical Operated Super Sucker Machines (NajafgarhDechaon Road, Najafgarh Jharoda Road & Najafgarh Dhansa Road ) under Sub-Division-II, SWR-II, Najafgarh New Delhi 2022.04.04 2022.12.03 83.41 115.12 (Dec'22) 0.00 (Dec'22) Surender Singh Detail Report
Graph / Photo
101 Providing services of Maintenance Van & supplying of various items for Outer Ring Road from Hanuman Setu to Wazirabad and Kingsway Camp Chowk via Timarpur Red Light 2022.06.14 2023.06.13 83.21 Nagendra and Company Detail Report
Graph / Photo
102 A/R & M/O to various roads under NE (B&R) Maintenance Division dg. 2022-23 (SH:- Repairing of underground old damaged pipe line on Gamri Road & Construction of boundary wall from Hanuman Mandir to Fire service station at Loni Road under PWD Sub Division M-2134) 2022.12.26 2023.02.23 82.94 Johri Constructions Detail Report
Graph / Photo
103 Construction of missing drain on outer ring road near SDMC booth & church 2022.07.06 2022.08.04 82.84 Nation Star Enterprises Detail Report
Graph / Photo
104 Restoration of road cut by Delhi Transco Limited (DTL) on Vedant Deshika Marg (ID-1200) and Shaheed Jeet Singh Marg (ID-22) under Sub-Division-III of South Road-II, PWD, New Delhi during 2021-22 2022.03.03 2022.05.02 81.09 AMOCON Detail Report
Graph / Photo
105 Providing, running and maintaining Anti Smog Gun mounted on moveable CNG truck on all roads falling under Bawana, Narela and Badli Constituency 2022.06.09 2022.12.05 81.06 88.27 (Jan'23) 0.00 (Jan'23) Sanjay Kaura Detail Report
Graph / Photo
106 Providing services and machineries for road maintenance of under sub-division-II of SRD Project Division-I 2022.10.14 2023.10.13 80.39 GOYAL & SONS Detail Report
Graph / Photo
107 Repair, Improvement and alteration of both side footpath of Shamnath Marg to make it PwD friendly 2022.06.17 2022.08.16 79.66 77.97 (Jan'23) 0.00 (Jan'23) M/s Jamshed Ali & Sons Detail Report
Graph / Photo
108 A/R and M/O Various Roads under SRD Project Division-I, PWD, New Delhi (SH-Providing Data Entry/Computer Operators, Messengers, LMV Drivers, Clerical Staff etc. for various offices under Project Circle and SRD Division-I.) 2017.10.01 2018.06.30 79.59 5.49 (Sep'19) 0.00 (Sep'19) K.P. Singh & Co. Work completed and final bill paid Detail Report
Graph / Photo
109 Comprehensive maintenance of various roads under East Road Sub-Division-III (Section-I & II) of Division East Road (M-212), PWD Delhi during 2022-23. (SH: Providing, running and maintaining Anti Smog Gun on hire basis at various locations). 2022.10.16 2023.07.15 79.38 Surender Singh Detail Report
Graph / Photo
110 Comprehensive maintenance of various roads under East Road Sub-Division-II of Division East Road (M-212), PWD Delhi during 2022-23. (SH: Providing, running and maintaining Anti Smog Gun on hire basis at various locations). 2022.10.16 2023.07.15 79.38 Surender Singh Detail Report
Graph / Photo
111 Comprehensive Maintenance of various roads under East Road Sub Division-III (Section I&II) of Division East Road (M 212), PWD Delhi during 2021-22. (SH:- Hiring of T&P and Supply of Labour & Materials for day to day maintenance of roads). 2022.04.24 2023.04.23 79.11 Ravinder Kumar Detail Report
Graph / Photo
112 Providing, running and maintaining Truck Mounted Anti Smog Gun on hire basis at various locations 2022.05.30 2023.05.29 77.68 30.69 (Jan'23) 0.00 (Jan'23) Gaurav Construction Co. Detail Report
Graph / Photo
113 Additional work for construction of access road from Pragati Power station and GAIL road to Ring Road beyond ITPO Project area, New Delhi 2022.06.27 2022.07.26 77.03 73.02 (Jan'23) 0.00 (Jan'23) A S INFRATECH Detail Report
Graph / Photo
114 Providing services for day to day Maintenance of all Roads & Supply of Material 2022.08.30 2023.02.28 76.76 MANMOHAN KUMAR Detail Report
Graph / Photo
115 Road restoration of city side service road from Khajuri chowk to Biharipur at MB Road cut by DJB under jurisdiction of Sub Division M-4, PWD (North East) Road Division dg. 2018-19. 2019.01.18 2019.03.04 75.94 80.24 (Sep'22) 0.00 (Sep'22) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
116 Repairing of damage footpath from Chandgi Ram Akhara to Wazirabad Flyover (LHS) under Sub Division-1, C&ND-R Division). 2nd RECALL 2022.06.14 2022.08.13 75.40 Paras Nath Singh Detail Report
Graph / Photo
117 Construction of RCC drain at Live Stock Road 2022.02.14 2022.06.13 75.35 40.00 (Jul'22) 0.00 (Jul'22) Ravinder Kumar Detail Report
Graph / Photo
118 (SH Supplying and fixing of new street light poles and cable for street lights at various locations on different roads and repairing of 30 Mtrs High Masts at ITO Chungi. 2019.03.12 2019.06.11 75.24 23.13 (Mar'20) 0.00 (Mar'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
119 Restoration of road cut by TPDDL from Chandrawal DJB Water Works to Nirmal Hriday including slip road of wazirabad flyover upto Red Light under jurisdiction of Sub Division -IV and I, C and ND-Roads Division dg 2022-23. 2022.12.14 2023.01.13 75.14 MANAV CONSTRUCTION COMPANY Detail Report
Graph / Photo
120 A/R and M/O to Sub-Division-15 of South Road-1 for Comprehensive Maintenance of Road under the Jurisdiction of Sub-Division SR-15 during 2021 2021.04.26 2022.04.25 74.56 107.98 (Jan'23) 0.00 (Jan'23) Ravi Tanwar Work in progress Detail Report
Graph / Photo
121 A/R & M/O to Various Roads under Sub-Division East Road-IV of PWD Division East Roads/ (M-212), Delhi during 2021-22. SH:- Repairing of deteriorated portion of road by patch work at UP Link road. 2022.03.30 2022.04.18 74.49 89.90 (May'22) 0.00 (May'22) SBG Infracon Pvt Ltd Detail Report
Graph / Photo
122 Desilting of drains during monsoon-2022 and Providing and Installation of Sewerage Pump at Different Vulenerable Location under sub division -23, Jaffarpur, New Delhi 2022.04.04 2022.12.03 74.41 72.31 (Oct'22) 0.00 (Oct'22) Surender Singh Detail Report
Graph / Photo
123 Providing service of Maintenance van required labours, Supply of materials, TandP for day to day upkeeping/maintenance of roads under, Sub division-II, SWR-II, Najafgarh New Delhi. 2022.03.03 2022.09.02 74.11 84.72 (Nov'22) 0.00 (Nov'22) Surender Singh Detail Report
Graph / Photo
124 Repair & improvement of existing footpath and fixing of MS railing at Hamilton Road from Lothian Gate Chowk to Kucha Mohtar Khan under Sub Division-I of Division SRDP-I, New Delhi 2022.05.12 2023.07.11 73.51 KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
125 Desilting of drain, Painting of kerb stone, M.S. grill, road marking, upkeeping of Subways/FOB, sprinkling of water, supply of materials for maintenance and repair of road and footpath etc 2022.02.14 2023.02.13 73.07 R R ENTERPRISES Detail Report
Graph / Photo
126 Repair & Improvement of footpath, Cycle track and Drainage system and approaches to Type-VII GPRA flats at T-Point of DDU Marg & Minto Road and Improvement of Road sided Berms footpath & Drainage system at Mirdard Road and Turkman Road 2022.04.18 2022.05.17 72.99 KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
127 A/R & M/O to various roads under North East (B&R) Maintenance Division dg 2022-23. (SH:- Providing and supplying Maintenance van, kachra Van, Pump and sewerman on various roads under sub division M- 2132 Delhi) 2022.06.19 2023.04.14 72.94 Sandeep Kumar Detail Report
Graph / Photo
128 Providing Data Entry Computer Operators, Messengers, LMV Drivers Clerical Staff etc for various offices under Project Circle and SRD Division I 2019.09.16 2020.09.15 72.93 79.09 (Jan'21) 0.00 (Jan'21) Passion Sports Academy Detail Report
Graph / Photo
129 A/R & M/O to Various Roads under Sub-Division East Road-IV of PWD Division East Roads/ (M-212), Delhi during 2021-22. SH:- Repairing of Marginal Bund road both side at Vikas marg underpass ITO chungi towards yamuna bank FOB. 2022.03.15 2022.04.13 72.78 Mahavir Parsad Gupta & Sons Detail Report
Graph / Photo
130 Repair and improvement of existing footpaths and Central Verges of H C Sen Road, Lothian Road and Jama Masjid Road under Sub Division-I of Division SRDP-I, New Delhi 2022.07.30 2022.09.29 72.33 90.37 (Sep'22) 0.00 (Sep'22) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
131 Providing services of Data Entry/Computer Operators, Messengers, LMV Drivers, MTS, Clerical Staff etc. for the office of Circle (NE) and NE Road Division and Sub Divisions. 2022.04.02 2023.04.01 71.67 STAR SECURITY AND PLACEMENT SERVICES Detail Report
Graph / Photo
132 Civil Work 2018.09.15 2018.12.13 71.41 8.06 (Feb'20) 0.00 (Feb'20) Akhil Kumar Constructions

Work in progress

Detail Report
Graph / Photo
133 Providing, running and maintaining Anti Smog Gun on hire basis at various locations. 2022.06.20 2023.04.19 71.38 Gaurav Construction Co., PAN: AEMPG9236L, Address: F-70, Prashant Vihar, Delhi-110085 Detail Report
Graph / Photo
134 Repairing of Jafrabad side drain from Jafrabad Gali No-9 to Gali No. 45 on Road No. 66 is missing portion damages by the civic agencies under Sub Division 2. 2019.02.10 2019.06.09 71.34 80.70 (Dec'21) 0.00 (Dec'21) Vinod Kumar Work in progress Detail Report
Graph / Photo
135 Providing services of Maintenance Van and supplying of various items 2021.12.06 2022.12.05 70.97 71.40 (Oct'22) 0.00 (Oct'22) Maa Vaishno Developers Detail Report
Graph / Photo
136 Repairing and Improvement of Magazine Road from Khyber Pass Crossing to Road No. 50 under Sub Division-1, C and ND-Roads, New Delhi 2022.04.14 2022.07.13 70.77 115.86 (Aug'22) 0.00 (Aug'22) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
137 Providing services of Computer Operators, Clerk, Supervisor and MTS for Division and Sub Division Offices 2021.08.17 2022.08.16 70.62 35.69 (Sep'22) 0.00 (Sep'22) ARMOUR SECURITY INDIA PVT LTD Detail Report
Graph / Photo
138 Providing, running and maintaining truck mounted Anti Smog Gun on hire basic at various locations on Najafgarh Dhansa Road, Najafgarh Jharoda Road, Najafgarh Nangloi Road, Najafgarh Dichaon Road, Najafgarh Phirni Road and Najafgarh Kakrola Road 2022.06.22 2023.04.21 70.37 25.00 (Jan'23) 0.00 (Jan'23) Surender Singh Detail Report
Graph / Photo
139 Providing services of Computer Operator, MTS, Clerk, Supervisor etc for circle office, Division office and Sub Division office 2022.08.01 2023.01.31 70.08 35.08 (Jan'23) 0.00 (Jan'23) Rakshak Securitas Pvt. Ltd. Detail Report
Graph / Photo
140 Road Restoration cut by DJB, BSES, IGL at various location under sub division-V during 2022-23 Division SWR-II, New Delhi 2022.10.18 2022.12.01 70.05 48.37 (Jan'23) 0.00 (Jan'23) Mahavir Prasad Gupta & Sons Detail Report
Graph / Photo
141 A/R & M/O Various Roads under Shahdara Road Maint. Division M-211,During 2022-23. (SH: Providing, running & maintaining Anti Smog Gun mounted on moveable CNG truck at various locations under Sub Division M-2111) (Modified & IInd Call). 2022.10.01 2023.06.27 70.00 P. R. S. Yash & Co. Detail Report
Graph / Photo
142 A/R & M/O Various Roads under Shahdara Road Maint. Division M-211,During 2022-23. (SH: Providing, running & maintaining Anti Smog Gun mounted on moveable CNG truck at various locations under Sub Division M-2114) (Modified & IInd Call). 2022.10.01 2023.06.27 70.00 P. R. S. Yash & Co. Detail Report
Graph / Photo
143 Improvement and repair of footpath at Khalsa Road both side footpath from Mall Road to Roop Nagar Gol Chakkar 2022.06.17 2022.08.16 69.77 51.68 (Jan'23) 0.00 (Jan'23) Gupta Associates Detail Report
Graph / Photo
144 Patch repair of Various Road under Sub Division-II/SRD-1, PWD, New Delhi 2022.02.25 2022.03.12 69.69 103.37 (Jun'22) 0.00 (Jun'22) Awasthi Construcion Co. Detail Report
Graph / Photo
145 Repair & improvement of existing footpath and Central Verge of N. S. Marg from Daryaganj Red Light to Lal Qila Red Light under Sub Division-I of Division SRDP-I, New Delhi 2022.07.30 2022.09.29 69.69 104.50 (Sep'22) 0.00 (Sep'22) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
146 A/R and M/O to various roads under Sub Division-I and IV of Division South Road-II, PWD during 2022-23 (SH:Providing, running and maintaining Water Sprinkler Anti Smog Gun and Sprinkler Water Tanker on hire basis at various locations) [2nd Call]. 2022.12.08 2023.06.07 69.52 5.00 (Jan'23) 0.00 (Jan'23) Samridhi Construction Detail Report
Graph / Photo
147 Construction of drain in West Parmanand Colony (MCD area) towards I and FC drain under Sub. Division-I, PWD Division (C and ND)-R, New Delhi 2022.04.20 2022.06.19 69.24 Ram Singh Detail Report
Graph / Photo
148 Day to day maintenance and repair work in arterial road and other road under Matia Mahal Constituency. 2022.04.18 2022.10.17 69.16 79.99 (Oct'22) 0.00 (Oct'22) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
149 Comprehensive Maintenance of various roads under East Road Sub Division-II of Division East Road (M 212), PWD Delhi during 2021-22. (SH:- Hiring of T&P and Supply of Labour & Materials for day to day maintenance of roads) 2022.04.24 2023.04.23 69.10 29.13 (Jan'23) 0.00 (Jan'23) Ravinder Kumar Detail Report
Graph / Photo
150 Comprehensive Maintenance of various roads under East Road Sub Division-I of Division East Road (M 212), PWD Delhi during 2021-22. (SH:- Hiring of T&P and Supply of Labour & Materials for day to day maintenance of roads). 2022.04.24 2023.04.23 68.91 Ravinder Kumar Detail Report
Graph / Photo
151 A R and M O various road under Sub Division M 2113 during 2018 19 SH Covering of drain of Babarpur Road after necessary misc repair work SECTION II Balance Work 3rd CALL 2018.10.28 2019.02.24 68.65 80.71 (Nov'19) 0.00 (Nov'19) RAHUL CONSTRUCTION COMPANY Work in progress Detail Report
Graph / Photo
152 A/R and M/O to various road under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18 SH Comprehensive Maintenance of road 2018.03.01 2018.11.25 68.51 D.P. Associates Work completed. Detail Report
Graph / Photo
153 Providing security guards at Circle office (NE), Division Office (NE) Road, Sub Division M-2132 & M-2134 and enquiry office. 2018.10.28 2019.10.27 67.99 65.84 (Mar'20) 0.00 (Mar'20) RAKSHAK SECURITAS PVT. LTD. Work in progress. Detail Report
Graph / Photo
154 Maintenance, Repair of street lights and High Masts i/c monitoring of street Light Lift and Escalators at various locations under PWD-251. SH-Comprehensive Maintenance Operation Watch and ward of lifts and Escalators. 2018.10.05 2019.10.04 67.55 56.48 (Sep'20) 0.00 (Sep'20) Techno Industries Limited Detail Report
Graph / Photo
155 Strengthening of Maharaja Agarsen Road under the Jurisdiction of South East Road-2 during 2022-23 (Road ID 957) 2022.05.29 2022.06.28 67.51 83.70 (Sep'22) 0.00 (Sep'22) RK Brothers and Co Detail Report
Graph / Photo
156 Re-development of Boundary Wall of Nagia Park Round About at Inderchand Shastri Marg under Sub Division-2 of Division C&ND-R during the year 2022-23 2022.08.12 2022.10.11 67.48 Singh Construction Co. Detail Report
Graph / Photo
157 Improvement of drain at Maa Anandmayee Marg under the jurisdiction of SER2/21, New Delhi 2022.06.09 2022.08.08 67.42 84.19 (Oct'22) 0.00 (Oct'22) Nasir Ali Detail Report
Graph / Photo
158 Repair and Restoration of damaged and settled road due to works done by DJB In Bijwasan Village on kapashera-Bijwasan road under sub division -IV /SWR-II/PWD, New Delhi during 2022-2023 2023.01.09 2023.02.07 67.40 Pawan Kumar Detail Report
Graph / Photo
159 Construction of drain from Chhata Rail Bridge to Hanuman Mandir on SPM Marg under Sub Division-I of SRD-I, New Delhi 2022.01.21 2022.05.22 67.17 P. R. S. Yash & Co. Detail Report
Graph / Photo
160 Repairing & Improvement of footpath at Pragati Maidan, Mathura Road 2022.06.10 2022.07.09 66.82 41.22 (Aug'22) 0.00 (Aug'22) D.P. Associates Detail Report
Graph / Photo
161 RMO various roads in North East Delhi under the jurisdiction of M-251 during 18-19, Delhi. SH-Supplying and fixing of street lights pole fittings laying of cable etc at different locations 2018.11.05 2019.01.04 66.32 24.94 (Oct'19) 0.00 (Oct'19) M/s Shaka Electrical (India) Detail Report
Graph / Photo
162 Complete maintenance of different PWD Roads Vikas Marg (From ITO crossing to Karkari More), Mother Dairy Road (From Laxmi Nagar Metro Station to Mother Dairy), Noida Link Road From Akshardham to Noida Border Chilla. 2023.01.14 2024.01.13 66.19 Raj KumarSaini Detail Report
Graph / Photo
163 Improvement of R.H.S footpath from Ring Road Civil Lines Police Station to Tis Hazari Court Red Light for barrier free walking track. (1st RECALL) 2022.10.04 2022.11.03 66.07 City Housing Constructions Detail Report
Graph / Photo
164 A/R & M/O to various roads under North East Building & Road Maintenance Division dg 2022-23. (SH:- Misc repair work at various roads under sub division M-2132). 2022.07.15 2022.10.12 65.48 Sat Const. Co. Detail Report
Graph / Photo
165 Desilting of Storm Water Drain at vanurable location of Najafgarh Kakrola road, Najafgarh Dhansa Road, Najafgarh-Dichaon Road, Najafgarh Jharoda Road, Najafgarh Phirni Road & Najafgarh Nangloi Road ) under Sub Div-II ,SWR II,PWD, Najafgarh New Delhi) 2023.01.26 2023.04.25 64.27 Surender Singh Detail Report
Graph / Photo
166 Operation and Maintenance of storm water pumps and D.G. sets of pump houses in North East area under PWD Division M-251 Delhi. 2019.03.18 2020.02.17 64.24 74.65 (Jun'20) 0.00 (Jun'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
167 Road Marking at Various Roads, Bus Lane, Zebra Crossing etc. with Thermoplastic Paint. 2022.08.18 2022.10.17 64.21 Sethi Construction Detail Report
Graph / Photo
168 Repair and improvement of existing footpath and Central Verge of N. S. Marg Balance Work under Sub Division-I of SRDP-1. 2022.08.20 2022.09.09 64.19 96.27 (Sep'22) 0.00 (Sep'22) KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
169 Providing services for day to day Maintenance of Ring Road and supplying of various items (1st RECALL) 2022.02.09 2023.02.08 64.14 323.84 (Aug'22) 0.00 (Aug'22) RANJIT CONSTRUCTION COMPANY Detail Report
Graph / Photo
170 Improvement of L.H.S footpath from (Ring Road Civil Lines Police Station to Tis Hazari Court Red Light) for barrier free walking track for differently abled people at Rajpur Road. 2nd RECALL 2022.08.12 2022.10.11 63.75 39.89 (Aug'22) 0.00 (Aug'22) Narendra Kumar Detail Report
Graph / Photo
171 Comprehensive maintenance of DBSOLX developed Complaint Tracker system at GNEC New Delhi 2022.12.24 2025.12.23 63.49 DBSOLX Detail Report
Graph / Photo
172 Providing services of Data Entry/Computer Operators, Messengers, LMV Drivers, MTS, Clerical Staff etc. for the office of Circle (NE) and NE Road Division. 2019.01.21 2020.02.20 63.23 73.01 (Dec'21) 0.00 (Dec'21) TRENDY SECURITY SERVICES Work in progress Detail Report
Graph / Photo
173 Operation and Maintenance of storm water pumps and D.G. sets of pump houses in Shahdara area under PWD Division M-251 Delhi. 2019.03.18 2020.03.17 62.88 78.49 (Jul'20) 0.00 (Jul'20) Krishna Electreical Works Work in progress Detail Report
Graph / Photo
174 Anti-Pollution measures by providing services of GPS enabled hydraulic operated Sprinkler Truck Mount System under Sub Division NWR-24 2022.05.26 2023.05.25 62.85 30.37 (Jan'23) 0.00 (Jan'23) N Y Constructions Detail Report
Graph / Photo
175 Raising of footpath from Savitri Cinema Road to Bipin Chandra Pal Marg on Surya Sen Road and from Guru Ravidass Marg T Point to DDA Park on DDA Market Road 2022.06.03 2022.08.02 62.18 92.79 (Oct'22) 0.00 (Oct'22) NARESH KUMAR Detail Report
Graph / Photo
176 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Repair of road surface in patches on Road No-59 and 63 under sub division-2). 2019.06.10 2019.08.08 62.17 65.34 (Dec'21) 0.00 (Dec'21) Chaudhary Construction Company Pvt. Ltd. Work in progress. Detail Report
Graph / Photo
177 Construction of Toe Wall for protection of Green belt area on various University Road (North Campus.) under Sub Division-2 of Division C & ND - Roads during 2022-23 2022.10.11 2022.12.10 62.00 Naraniya Construction Company Detail Report
Graph / Photo
178 A/R and M/O to various roads under Sub Division-II and III of Division South Road-II, PWD during 2022-23 (SH:Providing, running and maintaining Water Sprinkler Anti Smog Gun and Sprinkler Water Tanker on hire basis at various locations). 2022.10.22 2023.04.21 61.97 Samridhi Construction Detail Report
Graph / Photo
179 Improvement and repair of footpath at Sudhir Boss Marg from Hindu College Chowk (Chaubhurjja Chowk) to ACP Office both side Footpath under Sub Division-4 of Division C and ND- Roads during 2022-23. 1st RECALL 2023.01.04 2023.03.03 61.90 Nurul Hak Detail Report
Graph / Photo
180 Desilting of Road side drains SECTION-II 2019.02.27 2019.08.25 61.84 95.66 (Aug'20) 0.00 (Aug'20) Ram Kumar Sharma Work in progress Detail Report
Graph / Photo
181 Comprehensive Maintenance of Gadaipur Bandh Road, Dera Bhatti Road and Mandi Road under the Jurisdiction of Sub Division-13 under South Road-1 2021.04.26 2022.04.25 61.75 53.44 (Feb'22) 0.00 (Feb'22) Ravi Tanwar Work in progress Detail Report
Graph / Photo
182 Desilting of drain, Painting of kerb stone, M.S. grill, road marking, upkeeping of Subways/FOB, sprinkling of water, supply of materials for maintenance and repair of road and footpath 2022.02.16 2023.02.15 61.75 RAMESH CHANDER Detail Report
Graph / Photo
183 Providing Water tanker and mobile truck with spray nozzles and mist gun to prevent dust pollution on various roads under this office 2022.10.06 2023.08.01 61.74 23.00 (Jan'23) 0.00 (Jan'23) Gaurav Construction Co. Detail Report
Graph / Photo
184 Providing service of 12 HP diesel pump sets and running Tractor PTO driven positive displacement rotary lobe pump on various locations 2022.06.10 2022.10.09 61.71 92.29 (Jan'23) 0.00 (Jan'23) Aditya Construction Detail Report
Graph / Photo
185 Desilting of storm water drain during monsoon-2022 by mechanical Super sucker machines on Najafgarh-Bijwasan Road under Sub Division-25 2022.04.04 2022.12.03 61.48 56.50 (Nov'22) 0.00 (Nov'22) Surender Singh Detail Report
Graph / Photo
186 A/R & M/O to various roads under North East (B&R) Maintenance Division dg 2022-23. (SH: Desilting of roads side drains under Sub Division M-2132 Delhi). 2022.06.15 2022.12.11 61.33 27.00 (Jan'23) 0.00 (Jan'23) Vinod Kumar Detail Report
Graph / Photo
187 Operation and comprehensive maintenance of lifts and escalators installed at Foot Over Bridges located on PWD roads in transyamuna area of East Delhi during 2022-23 2022.05.19 2023.05.18 61.16 9.59 (May'22) 0.00 (May'22) Techno Industries Limited Detail Report
Graph / Photo
188 Improvement work both sides under I.P. Flyover). 2nd RECALL 2022.08.18 2022.09.17 60.81 Kartik Construction & Co. Detail Report
Graph / Photo
189 Anti encroachments measures in front of Accident & Emergency Gate No.4 and repair/improvement of Roads/footpath in front of Lok Nayak Hospital, JLN Marg, New Delhi. 2022.07.07 2022.08.06 60.81 91.02 (Oct'22) 0.00 (Oct'22) R.D. Constructions Detail Report
Graph / Photo
190 Raising carriage way at Live Stock Road in Ghazipur Dairy Farm 2019.03.11 2019.06.08 60.78 57.80 (Nov'21) 0.00 (Nov'21) Shiva Construction

Work in progress

Detail Report
Graph / Photo
191 Routine maintenance , operation of DG Sets and Storm Water Pump Sets 2017.08.09 2018.08.08 60.72 H.N. Traders & Engineers Detail Report
Graph / Photo
192 Improvement of Service Road from Geeta Colony Thana to Mandi Khureji on Patparganj Road under PWD Division East(Road) M-212, Delhi during 2018-19 2019.03.07 2019.05.05 60.69 62.93 (Feb'22) 0.00 (Feb'22) Arif

Work in progress

Detail Report
Graph / Photo
193 Day to day maintenance & repair work at Ring Road and Arterial Road. 2022.06.23 2022.12.22 60.60 Bhardwaj Construction Co. Detail Report
Graph / Photo
194 Modification of u turn at Road No. 59 2018.12.14 2019.01.12 60.38 47.05 (Sep'22) 0.00 (Sep'22) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
195 Providing water tanker with GPS tracking system and hydraulic jet facilities for control dust pollution, day to day cleaning of kerb stone, crash barrier footpath, railing, plants and planters etc 2022.09.13 2023.06.12 60.22 P. R. S. Yash & Co. Detail Report
Graph / Photo
196 Providing and Fixing and Repairing Retro Reflective Signage boards on various roads under Division WR 1. 2023.01.12 2023.07.10 60.08 Upendra Singh Detail Report
Graph / Photo
197 Providing, Running and Maintaining the services of Hydraulic Anti SMOG Gun system with required labour and T and P. 2022.06.05 2023.03.01 59.40 24.83 (Jan'23) 0.00 (Jan'23) P. R. S. Yash & Co. Detail Report
Graph / Photo
198 Providing, Running and Maintaining the services of Hydraulic Anti SMOG Gun system with required labour and T and P 2022.05.29 2023.02.22 59.40 47.74 (Jan'23) 0.00 (Jan'23) P. R. S. Yash & Co. Detail Report
Graph / Photo
199 Providing, Running and Maintaining the services of Hydraulic Anti SMOG Gun system with required labour and T and P 2022.05.28 2023.02.21 59.40 P. R. S. Yash & Co. Detail Report
Graph / Photo
200 Remodeling of Drain at ROB-36 road from NH-24 to Jha furniture 2022.09.18 2022.12.16 59.21 APJ AND CO Detail Report
Graph / Photo
201 A/R & M/O to Various Roads under Sub-Division East Road-III of PWD Division East Roads/ (M-212), Delhi during 2022-23. (SH:-Patch repair works on various roads under East Road-III). 2022.06.29 2022.08.12 58.98 M/s Roadtech Detail Report
Graph / Photo
202 Repairing of road patches / Pot, holes of sizes & all depth, repair work of footpath C.V., service roads and other miscellaneous repair/ finishing works on Road No. 3 from Police Line to Rajiv Nagar and Kanjhawala Link road for one year, under sub division NWR-25. 2022.09.26 2023.09.25 58.87 Sanjay Kaura Detail Report
Graph / Photo
203 Anti-Pollution measures by providing services of GPS enabled hydraulic operated Sprinkler Truck Mount System under Sub Division NWR-22 2022.05.20 2023.05.19 58.80 30.00 (Jan'23) 0.00 (Jan'23) Dharambir Singh Detail Report
Graph / Photo
204 Restoration of roads cut by DJB from Som Bazar Chowk to Surukpur More and Other Balance Work under Sec II of Sub Division II Najafgarh New Delhi 2018.11.26 2019.02.23 58.61 Dhanna Ram & Sons WORK CLOSED Detail Report
Graph / Photo
205 Providing services and machineries for road maintenance of under sub-division-II of SRD Project Division-I 2022.02.24 2023.02.23 58.42 72.99 (Sep'22) 0.00 (Sep'22) P. R. S. Yash & Co. Detail Report
Graph / Photo
206 Road Marking at Various Roads, Bus Lane, Zebra Crossing etc. with Thermoplastic Paint. (1st RECALL) 2022.09.29 2022.11.28 58.27 Sunrise Overseas Detail Report
Graph / Photo
207 Desilting of drains and disposal of silt/malba under Sub Division NR-15-Section-I 2022.03.30 2022.09.25 58.26 90.40 (Sep'22) 0.00 (Sep'22) Sujan Singh Detail Report
Graph / Photo
208 Day to day maintenance and repair work in Ring Road and Ring Road Bypass 2021.12.10 2022.06.09 58.15 84.84 (Aug'22) 0.00 (Aug'22) D.P. Associates Detail Report
Graph / Photo
209 Repair of footpath & Service lane of Outer Ring Road from District Centre to Najafgarh Drain under Sub Division WR-13 2023.01.12 2023.03.12 57.94 Kundu Nirman Detail Report
Graph / Photo
210 Day to day maintenance and repair of civil work such as Footpaths, Central Verge, Planter, drains, Roads, filling of potholes, mechaniz/manual de-silting of drains etc. and other misc. work during-2021-22 2022.02.12 2023.02.11 57.88 R R ENTERPRISES Detail Report
Graph / Photo
211 Making Cast in Situ Jersey Barrier at Deshraj Bhatia Marg, i/c bollards, Signages and Benches at various locations in Ballimaran Constituency 2022.02.03 2022.04.03 57.62 71.49 (Jul'22) 0.00 (Jul'22) B P Rai and Sons Detail Report
Graph / Photo
212 Improvement & repair of footpath at Vikas Marg, Sachivalaya Loop, Slip Road & JLN Marg under Sub-Division-3 of Division C&ND-Roads, New Delhi during 2022-23 2022.10.20 2023.01.19 57.62 R. R. Realtors Detail Report
Graph / Photo
213 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Repair and Improvement of footpath on both side From Railway line flyover to Road no. 66 T-Point under Sub Division M-4) 2019.08.10 2019.11.07 57.53 72.14 (Dec'21) 0.00 (Dec'21) Rajesh Kumar Gupta Detail Report
Graph / Photo
214 Providing and fixing chamfered tile , C.C work and other civil work 2022.08.09 2022.10.07 57.32 TKN Developers Detail Report
Graph / Photo
215 A/R & M/o repair and improvement of footpath and berm portion of Naya Bazar Road under Sub Division-1 of Division SRDP-1 during 2022-23. 2022.05.12 2022.07.11 57.31 31.67 (Oct'22) 0.00 (Oct'22) TKN Developers Detail Report
Graph / Photo
216 A/R & M/O to Various Roads under Sub-Division East Road-III of PWD Division East Roads/ (M-212), Delhi during 2021-22. SH:-Patch repair works on various roads under East Road III. 2022.03.15 2022.04.13 57.23 70.17 (Jun'22) 0.00 (Jun'22) M/s Roadtech Detail Report
Graph / Photo
217 Providing Services of Computer Operator Clerk etc. for the offices of SE South Division SR-1 and Sub-Divisions 2021.03.12 2021.09.06 57.15 58.25 (Jan'22) 0.00 (Jan'22) Harshidhi Security Service Detail Report
Graph / Photo
218 Providing services of GPS enabled hydraulic operated water Sprinkler Truck Mount System under Sub Division NWR-25. (Re-call) 2022.10.31 2023.08.27 57.09 266.42 (Dec'22) 0.00 (Dec'22) Dinesh Kumar Buildwell Detail Report
Graph / Photo
219 Providing services of Outsourcing staff in Division NWR-2, Sub Division NWR-21, Sub Division NWR-22, Sub Division NWR-23, Sub Division NWR-24, Sub Division NWR-25 and Hon’ble Health Minister’s Office 2022.07.23 2023.07.22 57.02 32.23 (Jan'23) 0.00 (Jan'23) Planet Security Group Detail Report
Graph / Photo
220 Raising of footpath from Surya Sen Marg to Guru Ravi Dass Marg on KPS Road and from E Block to Alaknanda Road on E Block Road 2022.06.03 2022.08.02 56.93 85.27 (Nov'22) 0.00 (Nov'22) R. N. Construction Company Detail Report
Graph / Photo
221 Road Restoration Cut by various agencies at Various Roads under Sub Division-I, New Delhi. 2022.05.28 2022.06.27 56.86 65.16 (Oct'22) 0.00 (Oct'22) Mahavir Prasad Gupta & Sons Detail Report
Graph / Photo
222 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Providing protection wall, footpath and repair of road, drain, misc. work at Community Centre side road no. 65 and Babarpur Road under Sub Division M-4). 2019.08.09 2019.10.07 56.81 67.37 (Dec'21) 0.00 (Dec'21) Vinod Kumar Detail Report
Graph / Photo
223 Repairing of footpath of Boulevard Road and Road No.-47 2022.01.24 2022.03.23 56.80 37.70 (Mar'22) 0.00 (Mar'22) R.D. Constructions Detail Report
Graph / Photo
224 Providing, running and maintaining Anti Smog Gun on hire basis at various locations 2022.07.08 2023.05.07 56.76 38.48 (Jan'23) 0.00 (Jan'23) Jagdish Prasad Meena Detail Report
Graph / Photo
225 Providing, running and maintaining Anti Smog Gun on hire basis at various locations 2022.07.08 2023.05.07 56.76 41.24 (Jan'23) 0.00 (Jan'23) Jagdish Prasad Meena Detail Report
Graph / Photo
226 Day to day maintenance and repair work in Ring Road and Ring Road Bypass. 2022.08.15 2023.02.14 56.58 Ram Singh Detail Report
Graph / Photo
227 Providing, running and maintaining Anti Smog Gun on hire basis at various locations 2022.07.02 2023.05.01 56.56 45.28 (Jan'23) 0.00 (Jan'23) Vision Constructions Detail Report
Graph / Photo
228 Providing, Running and Maintaining the services of Hydraulic Anti SMOG Gun system with required labour and T and P 2022.05.28 2023.02.21 56.50 29.90 (Jan'23) 0.00 (Jan'23) Sanjay Kaura Detail Report
Graph / Photo
229 Restoration of Road at various locations cut by various agencies under jurisdiction of Sub Division_I of Division South Road_II PWD Delhi during 2022_23 2022.09.30 2022.11.29 56.50 68.75 (Jan'23) 0.00 (Jan'23) Sanjay Enterprises Detail Report
Graph / Photo
230 Providing, running and maintaining Anti Smog Gun on hire basis at various locations under Sub Div-III 2022.06.22 2023.04.21 56.42 25.00 (Jan'23) 0.00 (Jan'23) Surender Singh Detail Report
Graph / Photo
231 Improvement of footpath at Barafkhana Chowk to Clock Tower &Roshanara Road under Sub-Division-4 2022.09.07 2022.11.06 56.39 99.29 (Jan'23) 0.00 (Jan'23) UR Construction Detail Report
Graph / Photo
232 Providing services and machineries for road maintenance of arterial roads 2022.12.21 2023.12.20 56.37 K.P. Singh & Co. Detail Report
Graph / Photo
233 Providing services of Maintenance Van and supplying of various items for Arterial Roads 2022.03.24 2023.03.23 56.28 194.05 (Oct'22) 0.00 (Oct'22) Paras Nath Singh Detail Report
Graph / Photo
234 Anti-Pollution measures by providing services of GPS enabled hydraulic operated Sprinkler Truck Mount System under Sub Division NWR-25 2022.05.20 2023.05.19 56.19 30.00 (Jan'23) 0.00 (Jan'23) Jitender Singh Detail Report
Graph / Photo
235 Restoration of road cut by DJB for the work of "Providing and laying main 800mm dia including construction of sump well for carriage of treated effluent water from STP Kondli to Smriti Van/Lake and for nearby DDA and MCD parks" under Sub-Div. East Road-II of Division East Road/(M-212) during 2022-23. 2022.09.26 2022.11.24 56.18 M/s Roadtech Detail Report
Graph / Photo
236 Construction of missing drain at Radha Swami Ashram to Dichaon village both side at Najafgarh Dichaon Road, under SuB Division-II, SWR-II, Najafgarh, New Delhi. 2022.12.15 2023.03.14 55.98 PK Enterprises Detail Report
Graph / Photo
237 Patch work and repair of road at various location under sub division-V during 2022-23 Division SWR-II, New Delhi 2022.06.02 2023.06.01 55.90 Karambir Rana Builders Detail Report
Graph / Photo
238 Redevelopment of Delhi Gate to Dariyaganj Red light Central Verge and footpath at Netaji Subhash Marg under Division-SRD-1/Sub Division-II, PWD, New Delhi 2022.04.02 2022.06.01 55.69 46.84 (Oct'22) 0.00 (Oct'22) B.P. Rai & sons Detail Report
Graph / Photo
239 Replacement of damaged slab & repair of footpath from Burari Authority to Burari Morh under Sub Division-1 C&ND-Road Division 2022.06.20 2022.09.19 55.62 321.78 (Sep'22) 0.00 (Sep'22) Anil Enterprises Detail Report
Graph / Photo
240 Providing the services of Computer Operators and MTS 2022.04.13 2023.03.12 55.47 Paras Nath Singh Detail Report
Graph / Photo
241 Repairing of footpath, Channels & Road Cuts damaged etc. by various service providing agency i.e. DJB, BSES, MTNL, Vodafone, Airtel, Jio, Unfilter Water Supply & Other Service Providers 2022.03.01 2022.03.31 55.47 83.18 (Oct'22) 0.00 (Oct'22) P. R. S. Yash & Co. Detail Report
Graph / Photo
242 Repair of footpath at Gokhle Road from Kashmere Gate Metro to G.T. Road under SubDivision-I of Division SRDP-I, New Delhi 2022.05.12 2022.07.11 55.37 19.93 (Oct'22) 0.00 (Oct'22) K S Builders Detail Report
Graph / Photo
243 Providing and laying Stone Matrix Asphalt (SMA), under Sub Div-21 of SWR-II PWD New Delhi 2022.06.02 2022.07.01 55.27 68.10 (Sep'22) 0.00 (Sep'22) Karambir Rana Builders Detail Report
Graph / Photo
244 Restoration of Jaitpur road damaged due to leakage of Delhi Jal Board pipe line at different location during 2020-21 under jurisdiction of SER-2/22 2021.07.10 2021.10.09 55.27 69.00 (Sep'22) 0.00 (Sep'22) MANAV CONSTRUCTION COMPANY Detail Report
Graph / Photo
245 PF Stainless steel railing at the balcony and entrance grill main door for enhancing the strength and safety in each flat at Judicially Officers Residential complex Sec 26 Rohini Del 2022.09.16 2023.01.15 55.12 SHASHANK ELECTRICALS Work in progress Detail Report
Graph / Photo
246 Anti-Pollution measures by providing services of GPS enabled hydraulic operated Sprinkler Truck Mount System under Sub Division NWR-21 2022.05.20 2023.05.19 55.11 13.00 (Jan'23) 0.00 (Jan'23) GLOBE BUILDERS Detail Report
Graph / Photo
247 Providing, running and maintaining Anti Smog Gun on hire basis at various locations under sub division 24 2022.06.22 2023.04.21 54.97 25.00 (Jan'23) 0.00 (Jan'23) Surender Singh Detail Report
Graph / Photo
248 Providing, running and maintaining Anti Smog Gun on hire basis at Goyla Deenpur Road and Najafgarh Bijwasan Road under sub division 25 2022.06.22 2023.04.21 54.97 25.00 (Jan'23) 0.00 (Jan'23) Surender Singh Detail Report
Graph / Photo
249 Improvement of footpath toe wall and other miscellaneous Civil work on various University Roads under Sub-Division-4 of Division C and ND-R, New Delhi dg. 2022-23. 2022.12.21 2023.02.20 54.91 Gupta Associates Detail Report
Graph / Photo
250 Improvement & Repair of footpath on Various Road like Bhamashah Road From Mall Road to Nanak Piao Gurudwara & Polo Road From Shani Mandir to Jahanara Road & Bhamashah to Shani Mandir under Sub Division-2 of Division C&ND-Roads, New Delhi during 2022-23 2022.10.22 2022.12.21 54.81 K.P. Singh & Co. Detail Report
Graph / Photo
251 Improvement of Footpath at Chitra Vihar road under Sub-Division East Road-I under Division East Road/(M-212) Delhi. dg. 2022-2023 2022.09.18 2022.12.16 54.76 Uday Raj Pandey Detail Report
Graph / Photo
252 Rehabilitation of Rohtak Road (NH-10) at Tikri Border under PWD, Maintenance Division West-2 Roads, New Delhi, during 2021-22. 2022.03.28 2022.05.26 54.66 Sethi Construction Detail Report
Graph / Photo
253 Providing, running and maintaining Anti Smog Gun on hire basis at various locations).under Sub Div-I, SWR-II, PWD , New Delhi. 2022.06.22 2023.04.21 54.48 21.00 (Jan'23) 0.00 (Jan'23) Surender Singh Detail Report
Graph / Photo
254 Painting with Synthetic Enamel Paint, Road Marking Paint, repair/ fixing siganages board and railing on various road under Sub Division- 2I, SWR-II/PWD, New Delhi 2022.06.25 2023.06.24 54.44 Bishwa Mohan Jha Detail Report
Graph / Photo
255 Providing the services of maintenance van along with labour for day to day maintenance 2021.12.02 2022.12.01 54.26 Jagdish Prasad Meena Detail Report
Graph / Photo
256 Repair of footpath of city side at MB Road Shastri Park to Khajuri Chowk for making the proper accessibility for differently abled persons. 2018.11.28 2019.01.26 54.19 26.90 (Dec'21) 0.00 (Dec'21) Sachin Prakash Work in progress Detail Report
Graph / Photo
257 A/R & M/O to Various Roads under Sub. Div. East Road-IV of Division East Road (M-212), PWD dg. 2022-23. (SH: Providing Service of Data Entry/Computer Operators & Peon for Division office and Sub. Division offices). 2022.06.21 2023.06.20 54.18 37.30 (Jan'23) 0.00 (Jan'23) RAKSHAK SECURITAS PVT. LTD. Detail Report
Graph / Photo
258 A/R & M/O to various roads under Sub Division-I of Division South Road-II, PWD during 2022-23. (SH:- Providing, running and maintaining Water Sprinkler Anti Smog Gun on hire basis at various locations). 2022.06.25 2023.04.24 54.11 60.69 (Jan'23) 0.00 (Jan'23) ABHILEKH YADAV Detail Report
Graph / Photo
259 De-silting and Cleaning of road side storm water drains of Ring Road and Arterial Roads 2022.03.04 2022.11.03 54.03 0.95 (May'22) 0.00 (May'22) Ram Singh Detail Report
Graph / Photo
260 Day to day maintenance and repair work in arterial road and other road under Chandni Chowk Constituency. 2022.04.04 2022.10.03 53.89 PRS yash & co Detail Report
Graph / Photo
261 Provision of RCC drain and Improvement of footpath and road surface at DY CM office link road at narwana road under Sub Division East Road-IV of Division East Road during 2022-23. 2023.01.31 2023.04.30 53.84 Bansal Construction Co. Detail Report
Graph / Photo
262 Providing services of GPS enabled hydraulic operated sprinkler (Track Mount System) mounted mayuri type on CNG Truck with required labour and T and P 2022.10.05 2023.07.01 53.80 Sanjeev Kumar Detail Report
Graph / Photo
263 Providing, supply and Fixing pink sand stone elephant statue/sculpture at airport road near Maharam Nagar, New Delhi. 2023.01.16 2023.04.15 53.59 Surender Singh Detail Report
Graph / Photo
264 A/R & M/O to various roads under Sub Division-2 of Division South Road-II, PWD during 2022-23. (SH:- Providing, running and maintaining Water Sprinkler Anti Smog Gun on hire basis at various locations). 2022.06.25 2023.04.24 53.52 ABHILEKH YADAV Detail Report
Graph / Photo
265 Providing services of GPS enabled hydraulic operated water Sprinkler Truck Mount System under Sub Division NWR-23 2022.10.31 2023.08.27 53.39 Gaurav Construction Co. Detail Report
Graph / Photo
266 Repair of carriageway of various roads under the jurisdiction of Sub Division-2 2022.07.15 2022.09.12 53.23 Sacred Construction Private Limited Detail Report
Graph / Photo
267 Improvement of Rajniwas Road footpath from Shamnath Marg to Rajpur Road for barrier free walking track under Sub-Division-4 of Division C&ND-Roads during 2022-23 2022.10.04 2022.11.03 53.07 Dinesh Kumar Detail Report
Graph / Photo
268 Comprehensive maintenance of various roads under East Road Sub-Division-I (Section-I & II) of Division East Road (M-212), PWD Delhi during 2022-23. (SH: Providing, running and maintaining Anti Smog Gun on hire basis at various locations). 2022.10.16 2023.07.15 52.92 Surender Singh Detail Report
Graph / Photo
269 Providing Services of Computer Operator Clerk etc. for the offices of SE South Division SR-1 and Sub-Divisions. 2020.08.05 2021.01.31 52.86 72.18 (Jul'21) 0.00 (Jul'21) HARSHIDHI SECURITY SERVICES, PAN: AAFFH4918Q, Address: A-86 BHAGWAT, GARDEN EXTN. UTTAM NAGAR Detail Report
Graph / Photo
270 Improvement & Repair of footpath on BBM Road From Mall Road to Najafgarh Drain under Sub-Division-2 of Division C&ND-Roads, New Delhi during 2022-23. 2022.10.22 2022.12.21 52.85 Aditya Construction Detail Report
Graph / Photo
271 Painting of kerb stone at various road 2022.08.18 2023.02.17 52.63 43.96 (Jan'23) 0.00 (Jan'23) Aditya Construction Detail Report
Graph / Photo
272 Mechanised desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-21 2022.04.03 2023.04.02 52.62 49.82 (Jan'23) 0.00 (Jan'23) Sethi Construction Detail Report
Graph / Photo
273 Providing services of GPS enabled hydraulic operated water Sprinkler Truck Mount System under Sub Division NWR-21. (Re-call) 2022.10.16 2023.07.12 52.61 15.00 (Jan'23) 0.00 (Jan'23) Jitender Singh Detail Report
Graph / Photo
274 Road restoration of city side service road from Biharipur to Toll Tax at M B Road (Khajuri chowk to Sabhapur Village) cut by DJB under PWD Sub Division M-2134). 2019.11.09 2020.02.06 52.48 65.63 (Dec'21) 0.00 (Dec'21) Ravinder Kumar Detail Report
Graph / Photo
275 Repair of footpath on various Arterial roads. 1st RECALL 2022.03.24 2022.06.23 52.37 83.22 (Aug'22) 0.00 (Aug'22) P. R. S. Yash & Co. Detail Report
Graph / Photo
276 A/R & M/O to various roads under Sub Division-3 of Division South Road-II, PWD during 2022-23. (SH:- Providing, running and maintaining Water Sprinkler Anti Smog Gun on hire basis at various locations). 2022.06.25 2023.04.24 52.35 ABHILEKH YADAV Detail Report
Graph / Photo
277 A/R & M/O to various roads under North East Building & Road Division Maintenance dg 2022-23. (SH: Providing Water tanker and mobile truck with spray nozzles & mist gun to prevent dust pollution on various roads under this office) 2022.06.02 2023.03.28 52.26 M/s Madhu Construction Company Detail Report
Graph / Photo
278 Repair of footpath from Yamuna Vihar to Khajuri Chowk for making the proper accessibility for differently abled persons under sub division -2. 2019.03.15 2019.05.13 52.26 55.98 (Sep'22) 0.00 (Sep'22) Nirmit Construction Co. Work in progress. Detail Report
Graph / Photo
279 Anti-Pollution measures by providing services of GPS enabled hydraulic operated Sprinkler Truck Mount System under Sub Division NWR-23 2022.05.20 2023.05.19 52.21 18.01 (Aug'22) 0.00 (Aug'22) Gaurav Construction Co. Detail Report
Graph / Photo
280 A/R & M/O to roads under Section-I & II, Sub-Division East Road-I under PWD Division East Roads/ (M-212), Delhi during 2021-22. (SH:- Restoration of various road cut by Delhi Jal Board) 2021.12.21 2022.02.18 51.89 65.62 (Jan'23) 0.00 (Jan'23) Kundu Nirman Detail Report
Graph / Photo
281 Repair of footpath at Mall Road Extension from Azadpur Underpass to Mahindra Park Junction under Sub Division NR-12 2022.06.18 2022.08.16 51.77 685.04 (Oct'22) 0.00 (Oct'22) sabur alam Detail Report
Graph / Photo
282 Thermoplastic Road marking paint on various roads under Sub Division NWR-24. 2022.09.07 2023.02.04 51.67 Sethi Construction Detail Report
Graph / Photo
283 Improvement of drainage system at Swaroop Nagar Road 2022.04.14 2022.06.13 51.55 64.39 (Aug'22) 0.00 (Aug'22) Kulwant Singh Detail Report
Graph / Photo
284 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Improvement of Central verge with Providing and Fixing MS Grill from Khajuri flyover to Signature Bridge under Sub Division 2). 2019.06.10 2019.08.08 51.54 62.28 (Sep'22) 0.00 (Sep'22) K P Singh & Co. Work in progress. Detail Report
Graph / Photo
285 Comprehensive Maintenance of SSN Marg 100 Foota Road and 60 Foota Road under the Jurisdiction SD-12 under SR-1 2021.04.26 2022.04.25 51.51 45.33 (Feb'22) 0.00 (Feb'22) Ravi Tanwar Work in progress Detail Report
Graph / Photo
286 Repairing and Improvement of existing CC pavement of Road No. 46 under Sub Division-1, C and ND-Roads, New Delhi 2022.04.14 2022.07.13 51.18 81.37 (Aug'22) 0.00 (Aug'22) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
287 Comprehensive Maintenance of PWD Roads under SRD Project Division-I, Sub-Division-II, PWD, New Delhi Dg. 2017-18 (SH- Misc. Repair Work) 2017.07.27 2018.03.26 51.05 0.00 (Mar'18) 63.64 % (Mar'18) Satyam Construction Company Work completed and final bill paid Detail Report
Graph / Photo
288 Road restoration of Road No. 63, Road No. 66, Tanki Road and Loni Road cut by DJB under PWD NE (B&R) Division dg. 2022-23 2022.06.29 2022.12.25 51.02 Pawan Kumar Detail Report
Graph / Photo
289 Providing services of Maintenance Van and supplying of various items 2022.02.16 2022.08.15 51.00 76.32 (Aug'22) 0.00 (Aug'22) P.R.S Yash & Co. Detail Report
Graph / Photo
290 Providing services of GPS enabled hydraulic operated water Sprinkler Truck Mount System under Sub Division NWR-24. (Re-call) 2022.10.16 2023.07.12 50.88 Prashant Gahlot Detail Report
Graph / Photo
291 Improvement of Green Belt/Zone-3 along Chandni Chowk Road. 2022.08.16 2022.10.15 50.56 KAMAAL CONSTRUCTION CO. Detail Report
Graph / Photo
292 Multi Modal Integration (MMI) Plans of East Vinod Nagar Metro Stations under Sub Division-3 of Division East Road/(M-212), Delhi. During 2021-22. (SH: - Redevelopment Works at East Vinod Nagar Metro Station). 2022.04.11 2022.08.08 50.56 Mohd Arif Detail Report
Graph / Photo
293 Improvement of footpath on Nandi Vithi Marg 2022.06.30 2022.07.29 50.52 75.41 (Oct'22) 0.00 (Oct'22) Ravi Tanwar Detail Report
Graph / Photo
294 Thermoplastic Road marking paint on various roads under Section-1, Sub Division NWR-21 2022.09.07 2023.12.06 50.41 Sethi Construction Detail Report
Graph / Photo
295 Replacement of old burnout cables at Central verge under NWESD-III 2022.06.10 2022.09.09 50.29 21.01 (Jul'22) 0.00 (Jul'22) Bhagat Associates Detail Report
Graph / Photo
296 Providing service of 12 HP diesel pump sets and running Tractor PTO driven positive displacement rotary lobe pump on various locations 2022.06.09 2022.10.08 50.18 Kulwant Singh Detail Report
Graph / Photo
297 Raising and Missing of drain construction from Deenpur to Goyla Dairy under sub division-25 2022.01.28 2022.03.28 50.18 69.09 (Oct'22) 0.00 (Oct'22) Surender Singh Detail Report
Graph / Photo
298 Repair of footpath , central verge at various location and other Miscellaneous works under Sub Division-II, SWR-II, Najafgarh, New Delhi 2021.09.01 2022.02.28 50.17 268.14 (Jul'22) 0.00 (Jul'22) Sirohi Construction Co Detail Report
Graph / Photo
299 Providing and laying 1200mm dia. NP4 Pipe along with MCD road from Shyamkunj bus stop to Najafgarh drain at Goyla Deenpur Road. 2022.12.15 2023.02.14 50.16 PK Enterprises Detail Report
Graph / Photo
300 Providing services of GPS enabled hydraulic operated sprinkler (Track Mount System) mounted mayuri type on CNG Truck with required labour and T and P 2022.10.05 2023.07.01 49.92 Sanjeev Kumar Detail Report
Graph / Photo
301 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18. SH-Repair of road damaged during rainy season 2017.11.30 2018.01.13 49.61 Awasthi Construction WORK COMPLETED Detail Report
Graph / Photo
302 Construction of MLA office Seelampur Constituency (AC 65) On Road No. 66 and Gokalpuri Constituency (AC 68) MLA office at Loni PWD Yard On Main Wazirabad Road under Sub Division M-2132 2022.07.08 2022.10.05 49.60 JABIR HUSSAIN Detail Report
Graph / Photo
303 Repair of service road and footpath at EA road from Baba Shyam Giri Mandir to CISF Lady Hostel. 2019.01.19 2019.03.19 49.53 60.77 (Dec'19) 0.00 (Dec'19) M/s. Satyam Construction Work in progress. Detail Report
Graph / Photo
304 Filling of polysulfide in construction and expansion joint on CC Pavement and providing and fixing of W-metal beam at Ring Road bypass 2022.04.13 2022.06.12 49.01 52.61 (Aug'22) 0.00 (Aug'22) R.D. Constructions Detail Report
Graph / Photo
305 Restoration of road cut by DJB at Najafgarh-Dhansa Road, Najafgarh Dichaon Road and Najafgarh Phirni Road under Sub Division-II , SWR-II, Najafgarh , New Delhi 2022.10.18 2022.12.17 48.95 35.58 (Jan'23) 0.00 (Jan'23) Mahavir Prasad Gupta & Sons Detail Report
Graph / Photo
306 Repair existing drain from Bajgheda chowk to Bamdoli Bus stand and provide facilities of footpath above drain (both sides) on Bajgheda chok to bamdoli bus stand under Subdivision 25 2022.04.19 2022.07.18 48.91 Bishwa Mohan Jha Detail Report
Graph / Photo
307 Replacement of Accidental/Defective/Fault/Burnout of Octagonal Street Poles, Panel, Cables, Street Light, Wiremesh and Flood Lights etc other associates works. 2023.01.25 2023.03.24 48.75 R.S. Electric Co. Detail Report
Graph / Photo
308 Day to day maintenance and repair work in arterial road and other road 2022.03.21 2023.03.20 48.49 41.22 (Sep'22) 0.00 (Sep'22) D.P. Associates Detail Report
Graph / Photo
309 Restoration of road cut by JIO DIGITAL and IGL for laying of cables/pipe line on Anuvrat Marg under Sub Division-III of Division South Road-II, PWD New Delhi during 2022-23. 2022.05.07 2022.07.06 48.45 Dhanna ram and sons Detail Report
Graph / Photo
310 Providing Data Entry/Computer Operators, Diary Dispatcher/LDC/Office Clerk, MTS/Messengers, LMV Drivers, Peon, Housekeeper/Sweeper etc. for various offices under Project Circle, SRD Division-I, SRD Division-II, and DHC & ND/ Central (M-451) 2021.12.26 2022.03.25 48.34 68.51 (Jul'22) 0.00 (Jul'22) M/s Trendy Security Services Detail Report
Graph / Photo
311 Providing services of GPS enabled hydraulic operated sprinkler (Track Mount System) mounted mayuri type on CNG Truck with required labour and T and P 2022.10.05 2023.07.01 48.16 ASH NARAYAN SINGH Detail Report
Graph / Photo
312 Construction of damaged retaining wall at culvert/Nallah/Drain on traffic signal of Ambedkar Road and other locations of Ghazipur Road Trilokpuri Delhi under East Road Sub Division-III, Division East Road (M-212) During 2022-23 2023.01.10 2023.05.09 48.01 NARANIYA CONSTRUCTION. CO. Detail Report
Graph / Photo
313 Repairing of Drain in front of Oxford School to Ramleela ground corner opposite Saint Cecilia School, Vikaspuri under Sub-Division WR-14, Division WR-1 during 2022-23 2022.06.16 2022.08.14 47.85 Jeetender Kumar Verma Detail Report
Graph / Photo
314 Day to Day maintenance and repair of Arterial and other Roads 2022.03.21 2022.09.20 47.76 925.50 (Jan'23) 0.00 (Jan'23) D.P. Associates Detail Report
Graph / Photo
315 A/R & M/O other PWD Roads under SRD Division-I, PWD, New Delhi dg. 2018-19 (SH:- Repairing of Khari Baoli Road drainage and footpath from Church Mission Road to Naya Bazar under Sub Division-I.) 2019.06.30 2019.09.29 47.54 53.94 (Sep'20) 0.00 (Sep'20) TKN Developers Detail Report
Graph / Photo
316 Deployment of security Personnel at Chandni Chowk Road 2022.04.08 2023.04.07 47.40 V R INDIA SECURITY SERVICES PVT. LTD. Detail Report
Graph / Photo
317 Repair of damaged footpath at Dharam Marg and Bhai Kanhaiya ji Marg ITI Road and Captain Anuj Nayyar Marg under Sub Division WR-11 2022.07.27 2022.09.24 47.19 ashok builders Detail Report
Graph / Photo
318 Providing service of Maintenance van required labours, Supply of materials, TandP for day to day upkeeping/maintenance of roads under, Sub division-II, SWR-II, Najafgarh New Delhi. 2022.10.24 2023.04.23 47.16 Surender Singh Detail Report
Graph / Photo
319 Day to day maintenance and repair work in arterial road and other road. 2022.11.02 2023.05.01 47.04 Narendra Kumar Detail Report
Graph / Photo
320 Repair works of footpath, kerb channel, Berm and making Kerb Ramp of Delhi University (North Campus) Roads and adjacent Roads 2022.03.31 2022.05.30 47.04 194.82 (Sep'22) 0.00 (Sep'22) Aditya Construction Detail Report
Graph / Photo
321 A/R & M/O to various roads Sub-Division East Road-II under PWD Division East Road /(M-212) during 2021-22. SH: Desilting of road side drains of Section I & II. 2022.03.30 2022.09.25 47.02 28.00 (Aug'22) 0.00 (Aug'22) Vinod Kumar Detail Report
Graph / Photo
322 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Patch repair work at Loni Road, Road No. 68 and Road No. 65 under PWD Sub Division 4 for newly taken over roads under section-2). 2019.07.11 2019.07.25 47.01 58.56 (Dec'21) 0.00 (Dec'21) MAHAVIR PRASAD GUPTA AND SONS Work in progress. Detail Report
Graph / Photo
323 Road Restoration of Road No. 56 under Sub-division M-2111 cut by DJB 2019.10.20 2019.12.18 47.00 69.50 (Apr'21) 0.00 (Apr'21) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
324 Miscellaneous repair work on Service Road and near Rashtriya Smriti Sthal Ring Road between Shantivan to Mangi Bridge. 2023.01.11 2023.03.10 46.89 Ram Singh Detail Report
Graph / Photo
325 Providing mobile diesel pump set with delivery pipe 2022.06.09 2022.10.08 46.86 Narendra Kumar Detail Report
Graph / Photo
326 Installation of signage boards & Repair of damaged & missing signage boards at various location under Sub Division-II, SWR-II, Najafgarh New Delhi. 2022.07.11 2023.01.10 46.48 35.98 (Oct'22) 0.00 (Oct'22) Upendra Singh Detail Report
Graph / Photo
327 Thermoplastic Road marking paint on various roads under Section-I, PWD Sub Division NWR-22. 2022.09.08 2023.05.06 46.42 Dinesh Kumar Buildwell Detail Report
Graph / Photo
328 Construction of Crash Barrier wall at Madhu Vihar Road under Patparganj Constituency under Sub-Division East Road-IV of PWD Division East Roads/ (M-212), Delhi during 2022-23 2023.01.31 2023.03.31 46.33 Dinesh Chand Sharma Detail Report
Graph / Photo
329 Comprehensive Maintenance of PWD Roads under SRD Project Division-I, Sub-Division-I, PWD, New Delhi Dg. 2017-18 (SH- Misc. Repair Work) 2017.07.27 2018.01.26 46.29 Satyam Construction Company Detail Report
Graph / Photo
330 Improvement of Drainage System on Sudhir Bose Marg from Khalsa Road to ACP Office Maurice Nagar. (1st RECALL) 2022.10.11 2022.12.10 46.27 A R Construction Detail Report
Graph / Photo
331 Improvement of Drainage System and footpath along Rao Laxmi Chand Marg Road ID 1174 from Khaira morh to Khaira Village New Delhi 2018.07.14 2018.11.10 46.23 Bishwa Mohan Jha foreclosed Detail Report
Graph / Photo
332 Desilting of Storm water drain during monsoon-2022 under Sub division -24, SWR-II,PWD, New Delhi 2022.04.04 2022.12.03 46.15 70.08 (Dec'22) 0.00 (Dec'22) Surender Singh Detail Report
Graph / Photo
333 Repair of Road Patch work at various locations under Sub Division-II, SWR-II, Najafgarh New Delhi 2022.06.28 2023.06.27 46.14 Karambir Rana Builders Detail Report
Graph / Photo
334 Providing services of GPS enabled hydraulic operated sprinkler (Track Mount System) mounted mayuri type on CNG Truck with required labour and T and P 2022.10.05 2023.07.01 46.13 Sanjeev Kumar Detail Report
Graph / Photo
335 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of drains by chassis mounted high pressure suction cum jetting machine under Sub Division 4). 2019.06.30 2019.08.28 46.10 52.96 (May'20) 0.00 (May'20) Maan Builders Work in progress. Detail Report
Graph / Photo
336 Road restoration of Burari Road from Kingsway Camp to Dhaka Village red light, Gandhi Vihar Road, Main Burari Road and Parmanand Road cut by TPDDL under Sub-Division-1 of Division (C & ND) – Roads, New Delhi. 1st RECALL 2022.03.24 2022.05.23 46.05 Paras Nath Singh Detail Report
Graph / Photo
337 De-silting and Cleaning of road side storm water drains of Ring Road & Arterial Roads). 2023.01.26 2023.09.25 45.95 R R Realtors Detail Report
Graph / Photo
338 Providing and Fixing M.S Grill at Kapashera Bijwasan road (From SKV Kapashera to Golakdham Mandir)(Balance Work). 2022.11.04 2022.12.03 45.94 26.95 (Nov'22) 0.00 (Nov'22) Upendra Singh Detail Report
Graph / Photo
339 Providing and fixing Paver Block on berms from Som Bazar Chowk to Bhardurgarh Border LHS at Najafgarh Jharoda Road under Sub Division-II, SWR-II New Delhi. 2022.12.15 2023.04.14 45.93 PK Enterprises Detail Report
Graph / Photo
340 A/R & M/O to various PWD Roads under Sub Division-IV of Division South Road - II, PWD, during 2022-23. (SH:- Repair of storm water drain and footpath at various locations on Outer Ring Road (Chirag Delhi Flyover to Africa Avenue T-Junction). 2022.10.21 2022.12.20 45.92 Puneet Sehrawat Detail Report
Graph / Photo
341 A/R & M/O Various Roads under Shahdara Road Maint. Division M-211,During 2022-23. (SH: Providing, running & maintaining Anti Smog Gun mounted on moveable CNG truck at various locations under Sub Division M-2113) (Modified & 1ST Call). 2022.07.28 2023.04.23 45.90 38.25 (Jan'23) 0.00 (Jan'23) Gaurav Construction Co. Detail Report
Graph / Photo
342 Repairing and Raising of footpath from Nangloi Stand to Bani Camp under Sub Division-II, SWR-II, Najafgarh, New Delhi 2021.11.27 2022.01.26 45.86 Surender Singh Detail Report
Graph / Photo
343 Miscellaneous repair work in Division office and Sub Division –I & V office. 2022.07.12 2022.11.11 45.69 7.94 (Sep'22) 0.00 (Sep'22) Jitender Detail Report
Graph / Photo
344 Repair and renovation of subway and development of near by area and other Misc work balance work under Sub Division 2. 2019.03.16 2019.05.14 45.45 49.00 (Dec'21) 0.00 (Dec'21) Rajesh Kumar Gupta Work in progress. Detail Report
Graph / Photo
345 Improvement of Direction Signage board. (SH: Replacement and Installation of Signage board under PWD Sub-Division East Road-III during 2022-23). 2022.12.12 2023.01.10 45.24 Sunrise Overseas Detail Report
Graph / Photo
346 Repairing of footpath, NMV Lane, etc. by various service providing agency 2022.02.24 2022.04.23 45.19 67.66 (Oct'22) 0.00 (Oct'22) GOYAL & SONS Detail Report
Graph / Photo
347 Urgent repair of footpath and Central verge in Sultanpuri area under Sub Division NWR-21 2022.08.15 2022.10.14 45.13 R.K.Construction Company Detail Report
Graph / Photo
348 Repair and Beautification of Round about under Hari Nagar Constituency 2022.06.08 2022.08.06 45.09 VIKAS INFRATECH Detail Report
Graph / Photo
349 A/R & M/O various road under Shahdara Road Division during 2022-23. (SH: Providing services of Computer Operator ,Clerical staff & MTS for offices under Shahdara Circle M and Shahdara Road Division (M-211).). 2022.06.17 2023.06.16 45.08 45.86 (Jan'23) 0.00 (Jan'23) placement security services Detail Report
Graph / Photo
350 Providing, Running and Maintaining the services of Hydraulic Anti SMOG Gun system with required labour and T and P. 2022.05.27 2023.02.20 45.06 25.70 (Jan'23) 0.00 (Jan'23) ASH NARAYAN SINGH Detail Report
Graph / Photo
351 Mechanised desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-22 2022.03.31 2023.03.30 44.94 51.31 (Sep'22) 0.00 (Sep'22) Jitender Singh Detail Report
Graph / Photo
352 Repair and Maintenance of footpath /central verge and other misc. work on various roads of under Sub Division-21, SWR-II, PWD, New Delhi 2021.09.01 2021.12.31 44.84 Sirohi Construction Co Detail Report
Graph / Photo
353 Repair of footpath of Najafgarh road from Subhash Nagar Crossing to Janakpuri East Metro station 2022.06.26 2022.08.24 44.78 ASH NARAYAN SINGH Detail Report
Graph / Photo
354 Patch work and repair of road at various location under Sub Division-III dg 2022-23 Division SWR-II, New Delhi 2022.08.17 2023.08.16 44.70 41.82 (Jan'23) 0.00 (Jan'23) Karambir Rana Builders Detail Report
Graph / Photo
355 A/R & M/O Various Roads under Shahdara Road Maint. Division M-211,During 2022-23. (SH: Providing, running & maintaining Anti Smog Gun mounted on moveable CNG truck at various locations under Sub Division M-2112) (Modified & IInd Call). 2022.10.01 2023.06.27 44.69 28.70 (Jan'23) 0.00 (Jan'23) NARAIN INFRATECH Detail Report
Graph / Photo
356 Improvement & Repair of footpath at Lucknow Road (From Police Station Timarpur to Mall Road and Timarpur Road & from ORR to Bansal Sweets Both Side under Sub-Division-2. 2022.08.23 2022.10.22 44.68 8.99 (Aug'22) 0.00 (Aug'22) Ram Singh Detail Report
Graph / Photo
357 SITC of Highmast, Poles i/c Replacement of HPSV Fittings with LED Fittings at Various Locations of Roads of Greater Kailash 2022.07.16 2022.10.15 44.61 JAGLAN CONSTRUCTION Detail Report
Graph / Photo
358 Providing services and machineries for road maintenance of under sub-division-I of SRD Project Division-I 2022.02.24 2023.02.23 44.49 Goyal Construction Co. Detail Report
Graph / Photo
359 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Improvement of Central verge with Providing and Fixing MS Grill from Maujpur Red light to Gokalpuri Red Light on Road No.-66 under Sub Division2 2019.06.08 2019.08.06 44.27 46.62 (Sep'22) 0.00 (Sep'22) K P Singh & Co. Work in progress. Detail Report
Graph / Photo
360 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of Road side drain of Road No. 63, Tanki Road, Yamuna Vihar Dividing Road and Yamuna Vihar Road (From C-1 to C-5)..... 2019.06.27 2019.10.24 44.19 77.70 (Dec'21) 0.00 (Dec'21) Vinod Kumar Work in progress. Detail Report
Graph / Photo
361 Supplying and Installation of Street Light Pole along with LED Fittings and Laying of UG Cables at Dark Spot due to Accidental/Missing places at Scattered Location under EMD South East PWD, New Delhi.(dg. 2021-22) 2021.11.21 2022.03.20 44.15 24.74 (May'22) 0.00 (May'22) S M Electrotech Pvt. Ltd. Detail Report
Graph / Photo
362 Disposal of unclaimed malba/building rubbish lying on footpath, Carriage way, Central Verge, Berm Portion of roads under WR-1 2022.05.04 2022.10.30 44.13 RAMESH CHANDER Detail Report
Graph / Photo
363 Improvement of drainage system & footpath at road from Babosa Chowk to ORR, Rohini Sector14, Prashant Vihar dg. 2021-22. 2022.06.05 2022.08.03 44.12 10.93 (Jan'23) 0.00 (Jan'23) Laxman Detail Report
Graph / Photo
364 Security Guards for various offices under SRDP-I, PWD, Govt. of Delhi 2022.04.08 2023.10.07 44.05 V R INDIA SECURITY SERVICES PVT. LTD. Detail Report
Graph / Photo
365 Providing services for special inspection, analysis of existing structure, conducting tests and preparation of remedial measures report including Bill of Quantities (BOQ) for Repair and Rehabilitation of ISBT flyover (Yudhister Setu) Delhi 2018.10.05 2019.01.02 44.00 M/s Projects Consulting India Pvt. Ltd

Work in progress

Detail Report
Graph / Photo
366 Restoration of road cut made by various agencies at Qutub Road under Sub Division-2 of SRD Project Division-2, PWD , New Delhi dg. 2022-23. 2022.11.17 2022.12.01 43.98 Sirohi Construction Co Detail Report
Graph / Photo
367 Painting of Kerb Stone, Crash Barrier, M.S. Railing etc. of Arterial Roads, Ring Road and Ring Road Bypass. 2022.08.23 2022.11.22 43.87 315.99 (Jan'23) 0.00 (Jan'23) Nasimuddin Detail Report
Graph / Photo
368 Desilting and Cleaning of road side storm water drains. 2023.01.27 2023.09.26 43.85 Ram Singh Detail Report
Graph / Photo
369 AR and MO various Road under PWD Division South Road-1 Sub Division SR-11 during 2017-18. SH De-silting of drains by super sucker 2018.04.09 2018.11.04 43.85 Maan Builders

work completed

Detail Report
Graph / Photo
370 Repairing and restoration of footpaths berms at Najafgarh Phirni Road Post Demolition Drives under Sub Division-II, SWR-II, Najafgarh New Delhi 2021.12.24 2022.02.23 43.84 PRS yash & co Detail Report
Graph / Photo
371 Providing security guards at Circle office (NE), Division Office (NE) Road, Sub Division M-2132 and M-2134 and enquiry office. 2019.12.07 2020.12.05 43.80 56.36 (Sep'22) 0.00 (Sep'22) Eagle Eye Security and House Keeping Services Detail Report
Graph / Photo
372 Raising of existing storm water drain i/c repair and restoration of damaged/broken drain at places along Shri Maa Anandmayee Marg near ESIC Hospital 2021.03.26 2021.05.24 43.69 51.73 (Mar'22) 0.00 (Mar'22) Jagdish Prasad Meena Detail Report
Graph / Photo
373 Restoration of road cut by DTL near Narmada Local Shopping centre to Gangotri enclave shopping centre on Savitri Cinema Road under Sub Division SER-24 2022.06.02 2022.07.01 43.67 65.22 (Oct'22) 0.00 (Oct'22) M/s Roadtech Detail Report
Graph / Photo
374 Road Restoration Cut by various agencies like DJB Transco and BSES at Palam dabri road under sub division I New Delhi 2019.08.02 2019.09.30 43.52 ASH NARAYAN SINGH work completed Detail Report
Graph / Photo
375 Road Restoration work at various places cut by Delhi Jal Board, BSES, MTNL & various agencies in Hari Nagar area under Sub Division WR-11, Division WR-1, dg. 2022-23. New Delhi 2022.06.27 2022.08.25 43.44 54.09 (Jan'23) 0.00 (Jan'23) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
376 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of Road No. 66 Moujpur Road, Brahmpuri road, Sewadham Road and Road No. 59 under Sub Division 2) Section-2. 2019.06.30 2019.10.27 43.24 48.04 (Dec'21) 0.00 (Dec'21) Vinod Kumar Work in progress. Detail Report
Graph / Photo
377 Comprehensive Maintenance of PWD Roads under SRD Project Division-I, Sub-Division-II, PWD, New Delhi Dg. 2018-19 (SH-Misc. Repair Work) 2018.05.29 2018.11.28 43.21 0.00 (Apr'19) 106.58 % (Apr'19) Satyam Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
378 Providing and Laying of paver blocks, raising of drain and repairing of footpath at Goyla Dairy and other misc. work under sub division-25 2021.08.19 2021.12.16 42.91 121.83 (Apr'22) 0.00 (Apr'22) Sirohi Constructon Company Detail Report
Graph / Photo
379 Housekeeping of FOBs and Subways, cleaning and epoxy painting of overhead gantry, signage boards including providing manpower for cleaning of footpath, kerb channel, bell mouth, side of berms, central verge of Ring Road & Ring Road Bypass (1st RECALL) 2022.02.12 2022.08.11 42.88 122.74 (Aug'22) 0.00 (Aug'22) M/s Roadtech Detail Report
Graph / Photo
380 Repairing of all services of The Mall Road from Timarpur Red Light to Burari Road Intersection (1st Recall) 2022.02.12 2023.02.11 42.71 Maa Vaishno Developers Detail Report
Graph / Photo
381 Improvement of central verge of Shri Maa Anandmayee Marg from Indira Kalyan Vihar red light to MB Road T Point under PWD Sub Division SER-2/21 2021.08.01 2021.10.31 42.66 83.84 (Nov'22) 0.00 (Nov'22) Jagdamba Enterprises Detail Report
Graph / Photo
382 A/R & M/O to various roads under East Road-1, under PWD East Road Division dg. 2021-22. SH: Repair of Road surface on Pusta road. 2022.03.15 2022.04.03 42.61 M/s Roadtech Detail Report
Graph / Photo
383 Repair of footpath of river side at MB Road Shastri Park to 3.5 Pusta for making the proper accessibility for differently abled persons under Sub Division-4). 2019.01.30 2019.03.30 42.52 43.66 (Oct'19) 0.00 (Oct'19) Ramesh Chand Work in progress Detail Report
Graph / Photo
384 Providing Services of Computer Operators, Clerk and MTS Multi Tasking Staff in PWD North West Electrical Maintenance Division, S 2021.06.28 2022.06.27 42.43 M/s Sona Engineers Detail Report
Graph / Photo
385 Mechanised desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-23 2022.04.06 2023.04.05 42.42 13.61 (Aug'22) 0.00 (Aug'22) WORK CEE Detail Report
Graph / Photo
386 Providing services of GPS enabled hydraulic operated sprinkler (Track Mount System) mounted mayuri type on CNG Truck with required labour and T&P. (Modified) 2022.10.05 2023.07.01 42.34 Sanjeev Kumar Detail Report
Graph / Photo
387 Repairing of Polycarbonate Sheet roofing and epoxy of various FOBs and Subways including Mis. repair works to footpath from Nigam Bodh Ghat to Vidhan Sabha & other finishing work 2022.03.02 2023.03.01 42.29 222.83 (Aug'22) 0.00 (Aug'22) Sushil Kumar Detail Report
Graph / Photo
388 Patch repair work at Various Roads under Sub Division-I, New Delhi. 2022.08.01 2023.07.31 42.26 70.70 (Sep'22) 0.00 (Sep'22) Sethi Construction Detail Report
Graph / Photo
389 Miscellaneous repair work for Mathura Road and other locations 2022.10.18 2022.11.06 42.25 Kartik Construction & Co. Detail Report
Graph / Photo
390 Repairing of damaged Footpath and Brick Wall along Drain at Vidya Marg (Dada Satram Mamtani Marg) 2022.06.13 2022.08.11 42.25 VIKAS INFRATECH Detail Report
Graph / Photo
391 Urgent repair of kerb stone and footpath in Rohini area under Section-II, PWD Sub Division NWR-22 2022.09.08 2022.11.07 42.23 36.92 (Oct'22) 0.00 (Oct'22) Dinesh Kumar Buildwell Detail Report
Graph / Photo
392 Repair of berm and paving of unpaved area under jurisdiction of Sub Division-2 of Division C and ND- Roads, New Delhi during 2022-23. 2022.12.22 2023.02.21 42.21 Aditya Construction Detail Report
Graph / Photo
393 Raising of footpath from Guru Nanak Market to Lala Lajpat Rai Marg 2022.06.03 2022.07.02 42.09 62.93 (Oct'22) 0.00 (Oct'22) Sirohi Construction Co Detail Report
Graph / Photo
394 Repairing of damaged Footpath & Laying of tactile tile on Pankha Road from Uttam Nagar T-Point to Dabri More round about 2022.06.27 2022.08.25 41.98 RAMESH CHANDER Detail Report
Graph / Photo
395 Urgent repair of kerb stone and footpath in Rohini area under Section-1, PWD Sub Division NWR-22 2022.09.08 2022.11.06 41.92 35.32 (Oct'22) 0.00 (Oct'22) RAVINDRA SINGH Detail Report
Graph / Photo
396 Restoration of Roads under Sub Division M-2114 during 2019-20 cut by various agencies. (Recall) 2019.12.10 2020.12.09 41.87 51.71 (Nov'21) 0.00 (Nov'21) Shekhar FINAL BILL UNDER PROCESS IN SUB-DIVISION OFFICE Detail Report
Graph / Photo
397 Improvement of footpath & repair of berms of right side portion of D.B Gupta road (from Kalka Dass Chowk to Military Road) 2022.03.30 2022.06.26 41.72 93.94 (Aug'22) 0.00 (Aug'22) Satyam Construction Co. Detail Report
Graph / Photo
398 Civil Works Cleaning of roads including Carriageway, Footpaths Central verge, Service Roads etc within the right of way, Mechanized Repairing of Pot Holes, Maintenance and Cleaning other Misc Repair Works 2022.04.23 2022.08.22 41.64 0.17 (May'22) 0.00 (May'22) Manav Construction Co. Detail Report
Graph / Photo
399 Providing of Maintenance Van with labours, T&P for day to day upkeeping / maintenance of roads and sprinkling of waters on roads under sub division - 21, New Delhi 2022.06.30 2023.06.29 41.59 Prashant Gahlot Detail Report
Graph / Photo
400 Road restoration for repairing of road, footpath, drain and other miscellaneous work on the roads under Sub-Division-3 of Division (C & ND) – Roads, New Delhi. 2022.10.20 2023.04.19 41.56 Ram Singh Detail Report
Graph / Photo
401 Upgradation of Street Light from GK-2 to Alaknanda Market at Savitri Cinema PWD Road under PWD South East New Delhi 2017.05.18 2017.09.17 41.43 Sona Engineers Detail Report
Graph / Photo
402 Construction of damaged retaining wall at culvert/Nallah/Drain on traffic signal of Ambedkar Road and other locations of Ghazipur Road Trilokpuri Delhi under East Road Sub Division-III, Division East Road (M-212) During 2022-23 2022.10.21 2023.02.17 41.26 Dinesh Chand Sharma Detail Report
Graph / Photo
403 A/R and M/O Various Roads under Sub. Div. East Road-IV of Division East Road (M-212), PWD dg. 2019-20. 2019.05.18 2020.05.17 41.25 45.99 (Jul'20) 0.00 (Jul'20) RAKSHAK SECURITAS PVT. LTD.

Work in progress

Detail Report
Graph / Photo
404 Housekeeping of FOB & Ghanta Ghar Roshnara Gol Chakkar, Yamuna Bazar under pass and cleaning and epoxy painting of overhead gantry, signage board including providing manpower for cleaning of footpath, side of berms, central verge of various roads 2022.10.11 2023.04.10 41.05 NARESH KUMAR Detail Report
Graph / Photo
405 Repairing of drain and development of adjacent area of footpath including replacement of NP-4 Pipe opposite WHO Building 2022.06.10 2022.08.09 41.03 51.25 (Sep'22) 0.00 (Sep'22) Maa Vaishno Developers Detail Report
Graph / Photo
406 Providing security guards at Circle office (NE), Division Office (NE) Road, Sub Division M-2132 and M-2134 and enquiry office 2022.03.25 2023.03.24 40.92 30.86 (Jan'23) 0.00 (Jan'23) UNIVERSAL SECURITY AND PLACEMENT SERVICES Detail Report
Graph / Photo
407 Improvement of damaged footpath and missing footpath, central verge on Najafgarh Jharoda Road under Sub Division-II, SWR-II, New delhi 2022.09.13 2023.01.12 40.90 Manav Construction Co. Detail Report
Graph / Photo
408 Desilting of drains at various road under sub division -21, SWRII/PWD, New Delhi. 2023.01.26 2023.04.25 40.89 Surender Singh Detail Report
Graph / Photo
409 Providing Service of Data Entry/Computer Operators and Peon for Division office and Sub. Division offices 2018.04.29 2019.04.28 40.68 20.96 (Jul'20) 0.00 (Jul'20) RAKSHAK SECURITAS PVT. LTD.

Work in progress

Detail Report
Graph / Photo
410 Providing, running and maintaining Anti Smog Gun on hire basis at various locations under Karol Bagh ,Sadar Bazar &Ballimaran Constituency 2022.09.29 2023.01.26 40.67 P. R. S. Yash & Co. Detail Report
Graph / Photo
411 Painting of Kerb stone and Planters etc 2022.08.23 2023.02.22 40.67 Nasimuddin Detail Report
Graph / Photo
412 Repair and Improvement of Parmanand Colony School Road 2022.03.11 2022.06.10 40.61 Altatech Infrahydro Pvt. Ltd. Detail Report
Graph / Photo
413 Repairing of damaged Footpath From Uttam Nagar T-Point to Lala Ganesh Das Khatri Marg Red Light on Najafgarh Road under Sub Division WR-12 and WR-13. 2023.01.12 2023.03.12 40.28 Dinesh Baittha Detail Report
Graph / Photo
414 Providing services of Data Entry/Computer Operators, Messenger, Clerical Staff, Peon, etc. for the office of EE(E) M-351, AE(E)M-3511, AE(E)M-3512 & AE(E) M-3513 GNCT OF DELHI 2022.05.26 2023.05.25 40.23 13.25 (Dec'22) 0.00 (Dec'22) SHAKTI ENTERPRISES Detail Report
Graph / Photo
415 Day to day maintenance and repair of civil work such as Footpaths, Central Verge, Planter, drains, filling of potholes, de-silting of drains etc. and other misc. work during 2021-22 2022.02.12 2023.02.11 40.22 25.50 (Mar'22) 0.00 (Mar'22) Ramesh Chander Detail Report
Graph / Photo
416 Comprehensive Maintenance of Bandh Road and Dera Bhatti Road 2019.10.31 2020.10.30 40.19 50.24 (Mar'22) 0.00 (Mar'22) Samridhi Construction Detail Report
Graph / Photo
417 Road Marking with Thermoplastic Paint on various road. 2022.09.14 2022.11.13 40.16 Sethi Construction Detail Report
Graph / Photo
418 Providing and laying RCC pipe at Chirag Enclave Road 2022.06.05 2022.07.04 40.13 49.86 (Sep'22) 0.00 (Sep'22) Jagdish Prasad Meena Detail Report
Graph / Photo
419 Construction of Crash Barrier at Median Portion of Ambedkar Road (Block 13 to 18) Trilokpuri Delhi-91 2022.03.30 2022.05.28 40.11 Mohd Arif Detail Report
Graph / Photo
420 A/R & M/O to various roads under North East (B&R) Maintenance Division dg 2022-23. (SH:- Road Marking Paint / Zebra Marking Paint at various roads under sub division M-2132). 2022.12.14 2023.02.11 40.00 Sat Const. Co. Detail Report
Graph / Photo
421 Raising & repairing of footpath on Road No. 13 A in left side upto Agra Canal 2022.07.03 2022.08.02 39.89 139.66 (Nov'22) 0.00 (Nov'22) Raj Enterprises Detail Report
Graph / Photo
422 A/R & M/O to Various Roads under Sub-Division East Road-IV of PWD Division East Roads/ (M-212), Delhi during 2021-22. SH:- Providing of security arrangements and sweeping/ cleaning arrangement at Division office, Sub Division, Chhath ghat, and on Fob's under Sub Division East Road-IV . 2022.03.29 2023.03.28 39.88 10.69 (Oct'22) 0.00 (Oct'22) Sk Group and allied services Detail Report
Graph / Photo
423 (SH- Maintenance and Operation of DG Sets, Pumps, Motors and all other E and M accessories). 2019.01.15 2020.01.14 39.81 54.68 (Nov'20) 0.00 (Nov'20) ANAND ELECTRICALS Detail Report
Graph / Photo
424 Construction of RCC Box drain from DDA Park to Sai Mandir and under Nangli Metro Station at Najafgarh kakrola Road under Sub Division-II, SWR-II, Najafgarh New Delhi 2021.10.07 2021.11.20 39.76 M/s DA Construction Co. Detail Report
Graph / Photo
425 A/R & M/O various road under Shahdara Road Division during 2019-20.(SH: Providing services of Computer Operator ,Clerical staff & MTS for offices under Shahdara Circle (M) and Shahdara Road Division.). 2020.06.01 2021.05.31 39.73 50.63 (Aug'21) 0.00 (Aug'21) TRENDY SECURITY SERVICES work in progress Detail Report
Graph / Photo
426 Providing jersy barrier and other misc. repair work for toe wall along the pitching at MB Road city side service road from Khajuri chowk to PR Vatika under. 2019.02.28 2019.04.28 39.41 44.99 (Dec'19) 0.00 (Dec'19) M/s B.M. & Sons Work in progress. Detail Report
Graph / Photo
427 Re-development of Parmanand Colony School Road under Jurisdiction of Sub Division-1 2022.06.17 2022.07.16 39.18 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
428 Construction of Porta Cabin AAMC at 25 Foota Road, Phase-7, Shiv Vihar and Safede wali Jameen, Gali No.14, Murgi Farm, Maan Singh Nagar, Old Mustafabad, Delhi 2022.04.13 2022.07.11 39.10 JABIR HUSSAIN Detail Report
Graph / Photo
429 Patch Repair work at various locations of road under jurisdiction of Sub Division-I of SRDP-I, PWD New Delhi 2022.10.10 2022.11.09 39.10 M/s Roadtech Detail Report
Graph / Photo
430 Patch repair work at Road No. 65 from Jafrabad Metro Station to Keshav Chowk under PWD Sub Division M-4. 2019.10.06 2019.11.19 39.07 43.59 (Feb'20) 0.00 (Feb'20) Pawan Kumar Detail Report
Graph / Photo
431 AR and MO various road under PWD Division South Road-1 Sub Division SR-14 during 2017-18. SH Improvement of road side drain and berms near outer ring road at Apeejay School Road Seikh Sarai Ph-1 2017.07.14 2017.08.12 38.93 Samridhi Construction

work completed

Detail Report
Graph / Photo
432 Repair of footpath at Sarai Phoos Road from Baraf Khana to Pul Mithai under Sub Division-I of Division SRDP-I, New Delhi 2022.05.12 2022.07.11 38.86 GOYAL & SONS Detail Report
Graph / Photo
433 Patch repair on various roads. 1st RECALL 2022.08.24 2023.02.23 38.82 M/s Roadtech Detail Report
Graph / Photo
434 Repair of footpath of Satguru Ram Singh Marg from Mayapuri crossing to Lajwanti crossing 2022.07.31 2022.09.28 38.79 Dushyant Enterprises Detail Report
Graph / Photo
435 Improvement of drain on Jaitpur road to avoid overflow of water on road under SER-2/22 2022.02.04 2022.05.03 38.78 57.43 (Jan'23) 0.00 (Jan'23) Pawan Kumar Jha Detail Report
Graph / Photo
436 A/R & M/O to various roads under CRMSD M-4421of CRMD M-442 during 2014-15 (SH: General Upkeep). 2015.01.24 2015.05.23 38.76 Bhawani Constructions Detail Report
Graph / Photo
437 A/R & M/O to various roads under North East (B&R) Maintenance Division dg 2022-23. (SH:- Patch repair work on various roads under PWD Sub Division M-2132). 2022.07.03 2022.08.31 38.67 M/s Roadtech Detail Report
Graph / Photo
438 Correction of Storm water drain from Tuda Mandi to Delhi gate by Re-laying 900mm dia pipes , under Sub Div-II, SWR-II, Najafgarh, New Delhi 2022.06.01 2022.06.30 38.62 37.86 (Nov'22) 0.00 (Nov'22) S P construction co Detail Report
Graph / Photo
439 A/R & M/O to various roads under NE (B&R) Maintenance Division dg. 2022-23. (SH: Painting & Road Marking on various roads under sub division M-2134). 2023.01.08 2023.02.21 38.61 Mohd Arif Detail Report
Graph / Photo
440 Restoration of road cut by DTL from Outer Ring Road to Narmada Local Shopping centre on Savitri Cinema Road under Sub Division SER-24 cut by Delhi Transco Ltd. 2022.05.15 2022.06.14 38.52 57.73 (Oct'22) 0.00 (Oct'22) M/s Roadtech Detail Report
Graph / Photo
441 Cleaning of roads inculding Carriageway, Footpaths Central verge, Service Roads etc within the right of way, Mechanised Repairing of Pot Holes, Maintenance and Cleaning other Misc Repair Works 2022.04.23 2022.08.22 38.50 Niharika Detail Report
Graph / Photo
442 Comprehensive maintenance of various roads under East Road Sub. Division -III of Division East Road /(M-212) during 2022-23. (SH: Provision of thermoplastic paint & Glow studs under section-I & II of Sub-Division East Road-III). 2022.11.04 2023.02.01 38.49 VEER SINGH DAHIYA Detail Report
Graph / Photo
443 RMC Work in Berm and kerb channels in various roads. 2023.01.27 2023.05.26 38.41 Balaji Construction Co. Detail Report
Graph / Photo
444 Improvement of footpath, central verge and Providing and Fixing M.S. Railing on footpath 2022.03.02 2022.03.31 38.38 44.28 (Sep'22) 0.00 (Sep'22) Nagendra and Company Detail Report
Graph / Photo
445 A/R & M/O to various roads under Sub-Division East Road-II of PWD Division East Road(M-212), Delhi during 2022-23. SH:- R.C.C. Slab on the drain at KG Road and Road No. 102 and Raising of service road at Road No. 102 2022.07.22 2022.09.19 38.34 Sandeep Kumar Detail Report
Graph / Photo
446 Disposal of unclaimed malba, building rubbish etc. from the Various Roads under Sub-Division-2, New Delhi. 2022.09.27 2023.09.26 38.20 PRS yash & co Detail Report
Graph / Photo
447 Repair of footpath & Central Verge at places from Subhash Nagar Chowk to Raja Garden Chowk under Rajouri Garden under SubDivision WR-15, Division WR-1). (Revised) 2022.06.27 2022.09.24 38.13 31.99 (Aug'22) 0.00 (Aug'22) Sanjay Enterprises Detail Report
Graph / Photo
448 Repairing of damaged Footpath and Laying of tactile tile on Pankha Road from Uttam Nagar T-Point to Dabri More round about. Recall 2022.07.31 2022.09.28 38.11 Jeetender Kumar Verma Detail Report
Graph / Photo
449 MOEI, Pump, Lifts of Subway, Under Deck and FOB on Delhi PWD Roads under PWD Electrical Division South during 2018-19. (SH-Operation of lifts). 2019.02.05 2020.02.04 38.00 37.00 (Sep'22) 0.00 (Sep'22) KAUSHIK DIESEL GENERATOR Detail Report
Graph / Photo
450 D/o Horticulture Land scaping work at Mayur Vihar, New Delhi, Barapullah Phase-III 2021.07.22 2022.11.18 37.99 Pioneer Horticulturist Pvt. Ltd Detail Report
Graph / Photo
451 Providing services of TATA 407 tempo for day-to-day maintenance work and light pruning of trees on different PWD roads. 2022.11.19 2023.11.18 37.96 Classic Nursery and Landscape Detail Report
Graph / Photo
452 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of Road side Drain at Gamri Road, service road of M.B. Road and Service Road Eastern Approach Road, Seelampur Road, 2019.06.30 2019.10.27 37.83 54.23 (Sep'22) 0.00 (Sep'22) Sharma Construction Co. Work in progress. Detail Report
Graph / Photo
453 Providing and laying Stone Matrix Asphalt (SMA), under Sub Div-21 of SWR-II PWD New Delhi 2021.09.07 2021.10.06 37.81 RK Brothers and Co Detail Report
Graph / Photo
454 Providing and Fixing factory made RCC Bollards and signages board at different roads in Karol Bagh under jurisdiction of Sub Division-3 of SRD Project Division-2 during 2022-23 ). 2023.01.09 2023.03.09 37.71 Satyam Construction Co. Detail Report
Graph / Photo
455 A/R & M/O to various roads under North East Building & Road Maintenance Division dg 2022-23. (SH:- Remodeling of SW drain at Loni Road at Delhi) 2022.07.02 2022.09.29 37.69 Sat Const. Co. Detail Report
Graph / Photo
456 A/R & M/O to various roads under Sub-Division East Road-IV of PWD Division East Roads, Delhi during 2022-23. (SH:- Repairing of deteriorated portion of road by patch work). 2022.10.07 2022.12.05 37.68 M/s Roadtech Detail Report
Graph / Photo
457 Restoration of Mehrauli Badarpur road from Ghiyasuddin Tughlaks Tomb MB Road to T Point Guru Ravi Dass Marg near Majeedia Hospital under Sub Division SER-24 cut by Delhi Transco Ltd. 2022.02.12 2022.04.11 37.67 Karambir Rana Builders Detail Report
Graph / Photo
458 Construction of Crash Barrier wall at Madhu Vihar Road under Patparganj Constituency under Sub-Division East Road-IV of PWD Division East Roads/ (M-212), Delhi during 2022-23 2022.10.21 2022.12.19 37.66 Prem Sagar Detail Report
Graph / Photo
459 A/R and M/O to various roads under PWD Sub Division M-2132 dg. 2017-18. (SH- Repair of service road from Gagan T-Point to Nand Nagri Flyover). 2018.04.05 2018.05.04 37.50 Pawan Kumar cancelled Detail Report
Graph / Photo
460 Reconstruction & improvement of footpath on Pyarelal road (Gurudwara road to Saraswati marg) and other misc. repair work under jurisdiction of Sub Division-3 of SRD Project Division-2. 2023.01.28 2023.03.28 37.45 Prem Sagar Detail Report
Graph / Photo
461 Patch repair on Various Roads i.e. JLN Marg, NS Marg, Mahawat Khan Road, Vishnu Digamber Marg & few portion of DDU Marg 2022.06.09 2022.07.08 37.42 71.76 (Oct'22) 0.00 (Oct'22) Awasthi Construction Co. Detail Report
Graph / Photo
462 Repair of Footpath and Berm Portion on AD-1 to BF-31(Tagore Garden), DE131 to Community Hall, J. Krishnatrey Marg and Tanki Wala Marg under SubDivision WR-15, Division WR-1, under Rajouri Garden and Tagore Garden area. during 2022-23 2022.07.27 2022.09.24 37.40 Sanjay Kaura Detail Report
Graph / Photo
463 Repair of footpath and other repair works 2022.03.14 2022.04.27 37.30 44.07 (May'22) 0.00 (May'22) Prem Sagar Detail Report
Graph / Photo
464 Cleaning of roads inculding Carriageway, Footpaths Central verge, Service Roads etc within the right of way, Mechanised Repairing of Pot Holes, Maintenance and Cleaning other Misc Repair Works 2022.04.23 2022.08.22 37.26 Niharika Detail Report
Graph / Photo
465 Repair and Restoration of drain from Kapashera Chowk to Cosmos Farm and provide facilities of footpath above drain (both sides) on Kapashera Bijwasan drain 2021.09.24 2021.12.23 37.23 291.02 (Sep'22) 0.00 (Sep'22) ASHWINI KUMAR PANDEY Detail Report
Graph / Photo
466 A/R & M/O to various roads Sub-Division East Road-III under PWD Division East Road /(M-212) during 2021-22. SH: Desilting of road side drains of Section I & II. 2022.03.22 2022.09.17 37.19 23.00 (Sep'22) 0.00 (Sep'22) Maan Builders Detail Report
Graph / Photo
467 Providing and laying BC of Delhi Cant flyover at Pankha Road (ID 1155) under SWR-II/PWD, New Delhi 2022.08.17 2022.09.16 37.16 37.57 (Oct'22) 0.00 (Oct'22) Karambir Rana Builders Detail Report
Graph / Photo
468 A/R & M/O to Various Roads Sub-Division East Road-IV under PWD Division East Roads/ (M-212), Delhi during 2021-22. SH:- Road marking and bus lane marking painting on UP Link road and Vikas Marg 2021.11.23 2021.12.22 37.11 26.72 (Oct'22) 0.00 (Oct'22) Uday Raj Pandey Detail Report
Graph / Photo
469 Repairing and Improvement of Approach Road-I from Road No.-47 to Nichlosan Road under Sub Division-1/SRDP-I 2022.06.09 2022.07.08 36.79 55.13 (Oct'22) 0.00 (Oct'22) M/s Roadtech Detail Report
Graph / Photo
470 Repair of Footpath to Jupiter Apartment to Priya Apartment, Krishi Apartment to D.A.V School, under Vikaspuri , under Sub Division WR-14 2022.07.31 2022.09.28 36.76 RAMESH CHANDER Detail Report
Graph / Photo
471 Construction of welcome gates at various market entrances in Paschim Vihar under Sub Division NWR-24.) (Re-call) 2022.10.01 2022.12.29 36.70 Jitender Singh Detail Report
Graph / Photo
472 Patch repair work at various locations under Sub Division -III, New Delhi 2021.09.30 2021.10.29 36.61 44.93 (Apr'22) 0.00 (Apr'22) Nirmit Construction Co. Detail Report
Graph / Photo
473 Disposal of unclaimed malba, building rubbish etc. (1st RECALL) 2022.05.14 2023.05.13 36.56 64.92 (Jan'23) 0.00 (Jan'23) Aditya Enterprises Detail Report
Graph / Photo
474 A/R and M/O Various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Road Marking Work in Ballimaran and Sadar Bazar Constituencies 2017.12.01 2018.02.28 36.55 Manish Chandak Work Completed Detail Report
Graph / Photo
475 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Provision of Maintenance Van with required labour with T and P to attend day to day maintenance under Karol Bagh Constituency. 2017.10.07 2018.09.28 36.54 9.09 (Jun'19) 0.00 (Jun'19) Zahid Hussain (B-26) Work completed Detail Report
Graph / Photo
476 Civil Works Cleaning of roads including Carriageway, Footpaths Central Central verge, Service Roads etc within the right of way, Mechanized Repairing of Pot Holes, Maintenance and Cleaning other Misc Repair Works 2022.04.23 2022.08.22 36.53 Bishwa Mohan Jha Detail Report
Graph / Photo
477 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Providing of protection wall and other civil repair work at Gari Mendu Road under Sub Division 4). 2019.06.10 2019.07.09 36.48 46.77 (Dec'21) 0.00 (Dec'21) Sandeep Kumar Work in progress. Detail Report
Graph / Photo
478 Desilting and Cleaning of road side storm water drains 2022.03.04 2022.09.03 36.18 24.63 (Jun'22) 0.00 (Jun'22) R R Realtors Detail Report
Graph / Photo
479 Reconstruction of damaged drain from TCL Building to Pamposh footover bridge including beautification and repair of subway near Masjid Moth on Outer Ring Road under the jurisdiction of division SER-2 2021.05.25 2021.08.22 36.11 54.11 (Oct'21) 0.00 (Oct'21) S. S. Chauhan & Sons Detail Report
Graph / Photo
480 Providing security services of security Guard under PWD Division West Road-2 office and Sub division WR-21, WR-22, WR-23 , WR-24 and 25 2021.12.11 2022.12.10 36.08 19.63 (Sep'22) 0.00 (Sep'22) M/s Planet Security Group Detail Report
Graph / Photo
481 Construction of missing and damaged footpath on Bhao Rao Devras Marg and Major Ashwani Kanwa Marg under Section-II, Sub Division NWR-24. 2022.10.01 2022.11.29 36.07 44.18 (Jan'23) 0.00 (Jan'23) SHARMA & SHARMA ENTERPRISES Detail Report
Graph / Photo
482 Comprehensive Maintenance of Street Light at various Road and Operation and Maintenance of DG Sets, Sub Station and Dewatering Pumpsets at various under passes and Operation Maintenance of Fountains installed at Clock Tower, Ghantaghar 2021.10.17 2022.10.16 36.00 27.97 (Jul'22) 0.00 (Jul'22) Esquire-Tech Detail Report
Graph / Photo
483 Facelifting and beautification on Valmiki Park at Road No. 48 under Sub Division-2 of Division C&ND-Roads, PWD, New Delhi during 2022-23 2022.09.15 2022.11.14 35.89 Kartik Construction & Co. Detail Report
Graph / Photo
484 Patch repairing work on various roads 2022.09.14 2022.11.13 35.89 Pawan Kumar Detail Report
Graph / Photo
485 Restoration of various roads cut by DJB under section-I & II, Sub Division East Road-I of Division East Road/(M-212), Delhi during 2021-22. 2022.06.29 2022.08.12 35.81 Awasthi Construcion Co. Detail Report
Graph / Photo
486 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Repairing of road surface between Bank Colony red light and Nand Nagri red Light under sub division-2). 2019.06.07 2019.07.06 35.76 42.88 (Oct'19) 0.00 (Oct'19) Pawan Kumar Work in progress. Detail Report
Graph / Photo
487 Restoration of Mehrauli Badarpur Road from Airforce Station Garrision Engg Gate to Suraj Kund Road turn point under Sub Division SER-24 cut by Delhi Transco Ltd 2022.01.07 2022.02.06 35.74 50.01 (Nov'22) 0.00 (Nov'22) Karambir Rana Builders Detail Report
Graph / Photo
488 Road Restoration work at various roads after laying water supply/sewer line by Delhi Jal Board During 2022-23 under Sub Division-III. 2022.06.29 2022.07.28 35.72 M/s Roadtech Detail Report
Graph / Photo
489 Repair of drain and rehabilitation of Footpath from Kali Mata Mandir to Sagarpur Flyover at Pankha Road (ID 1155) under Sub Division-21, SWR-II/PWD, New Delhi. 2022.09.13 2022.10.27 35.63 Bishwa Mohan Jha Detail Report
Graph / Photo
490 Operation and Maintenance of sewage/storm water pumps, DG sets at Vrs. location under PWD M-251. (SH- Desilting by super sucker machine/Removing of floating material of Sumps at various pump houses in Trans Yamuna area) 2019.03.02 2019.05.01 35.49 44.35 (Oct'19) 0.00 (Oct'19) Krishna Electrical works Detail Report
Graph / Photo
491 Road restoration of the road cut by various agency under PWD NE (B and R) Division dg. 2021-22 2022.04.25 2022.10.21 35.36 42.41 (Sep'22) 0.00 (Sep'22) Vinod Kumar Detail Report
Graph / Photo
492 A/R and M/O various roads under SRD Division-I, Sub-Division-II, PWD, New Delhi, dg. 2018-19. (SH-Providing and laying Ductile Iron pipe line near Zakir Hussain College at J.L.N. Marg, New Delhi to avoid flooding at JLN Marg). 2018.10.13 2018.12.12 35.33 43.45 (Sep'19) 0.00 (Sep'19) M/s. Satyam Construction Work in progress Detail Report
Graph / Photo
493 Providing services of Maintenance Vehicle with labour & T & P etc. under Sub Division NWR-21 for one year 2022.07.16 2023.07.15 35.31 GLOBE BUILDERS Detail Report
Graph / Photo
494 Repairing of footpath and rising of toe wall under Burari Flyover and Burari area under Sub Division-1 of Division C and ND- Roads during 2022-23. 1st RECALL 2022.12.29 2023.02.28 35.15 UR Construction Detail Report
Graph / Photo
495 Improvement of Direction Signage board. (SH: Replacement and Installation of Signage board under PWD Sub-Division East Road-1 during 2022-23). 2022.11.03 2023.01.01 35.15 Sethi Construction Detail Report
Graph / Photo
496 Repair of footpath , central verge at various location and other Miscellaneous works under Sub Division-II, SWR-II, Najafgarh, New Delhi 2021.08.06 2022.02.05 35.10 Vinita Enterprises Detail Report
Graph / Photo
497 Road Restoration charge for the work of P/L water supply network, sewer line and cable network in Mayur Vihar Phase-III and Ghazipur dairy farm in Section-I of PWD Sub-Division East Road-II. 2019.01.14 2019.03.14 34.91 44.46 (Jul'20) 0.00 (Jul'20) Dinesh Chand Sharma

Work in progress

Detail Report
Graph / Photo
498 Providing facility of footpath and restoration of drain from Cosmos Farm to Pushpanjali Cut and provide facilities of footpath above drain (both sides) on Kapashera Bijwasan drain 2022.03.10 2022.06.09 34.89 36.25 (Sep'22) 0.00 (Sep'22) BANSIWAL CONSTRUCTION COMPANY Detail Report
Graph / Photo
499 Renovation of Workshop (WS-1) 1st floor (Mezzanine Floor) to provide space for Studio-III for DAP at IGDTUW, Kashmere Gate under SRD Division- I, Sub-Division-III, PWD, New Delhi. (SH-Civil works and Electrical works). 2018.07.14 2018.10.13 34.69 0.00 (Apr'19) 43.14 % (Apr'19) K.P. Singh & Co. Work Completed and final bill paid Detail Report
Graph / Photo
500 Repair and Restoration of patches under Sub Division -IV, New Delhi 2022.07.11 2023.07.10 34.68 24.28 (Jan'23) 0.00 (Jan'23) Karambir Rana Builders Detail Report
Graph / Photo
501 Improvement of footpath on DB Gupta Road from Kalka Das Chowk to Anand Parbat T Point LHS Side to make it pedestrian friendly and other misc repair work on Road no. 3, Road no. 4, Road no. 5 and Military Road under jurisdiction of Sub Division-III of SRD Project Division-II 2022.07.15 2022.11.11 34.52 Satyam Construction Co. Detail Report
Graph / Photo
502 Providing and fixing jersey barrier cum flower pots at Various roads under Sub-Division-2 of Division SRD Project-1 during the year 2021-22 2022.04.04 2022.05.03 34.50 51.21 (Aug'22) 0.00 (Aug'22) GOYAL & SONS Detail Report
Graph / Photo
503 Painting and other Miscellaneous works under Sub Division-III, SWR-II, , New Delhi 2021.09.15 2022.03.14 34.38 Surender Singh Detail Report
Graph / Photo
504 Providing and fixing railing on footpath from Som bajar (Bahadurgarh mor to Anaj mandi) on Najafgarh Jharoda Road under PWD Division, South West Road-II. ( ID-1230) 2022.10.11 2022.12.10 34.38 Rajeshwar Kumar Detail Report
Graph / Photo
505 Construction of 3 No's Welcome Gate at Palam Dabri Road under Sub Division-21, SWR-II, PWD New Delhi 2022.05.16 2022.06.29 34.36 Upendra Singh Detail Report
Graph / Photo
506 Repair and Restoration of roof and doors of inspection chamber drain and repair of Expansion joints on Bharthal Road under sub division 24, SWR-II,PWD, New Delhi. 2022.05.12 2022.07.10 34.35 Sehgal and Sons Detail Report
Graph / Photo
507 Providing Maintenance Van with required labour and T & P to attend day to day maintenance work for various roads under the jurisdiction of Sub Division-II 2022.02.18 2023.02.17 34.31 7.37 (Jun'22) 0.00 (Jun'22) Mohd Akram Detail Report
Graph / Photo
508 A/R & M/O to various roads Sub-Division East Road-IV under PWD Division East Road /(M-212) during 2021-22. SH: Desilting of road side drains of Section I & II. 2022.04.17 2022.10.13 34.28 25.00 (Jul'22) 0.00 (Jul'22) AJAY CONSTRUCTIONS AND ENGINEERS Detail Report
Graph / Photo
509 Improvement of drainage system and riding surface near DM (East) office at Pusta road Sub-Division East Road-I under PWD Division East Road, Delhi During 2021-22 2022.04.10 2022.06.08 34.03 Awasthi Construcion Co. Detail Report
Graph / Photo
510 Repair and maintenance of storm water drain on Ramleela ground road, Ashok Nagar 2022.05.27 2022.08.25 33.98 Jeetender Kumar Verma Detail Report
Graph / Photo
511 SITC of Structure cabling and CCTV System for underpasses under North Zone 2022.06.23 2022.07.22 33.95 AAAVAA Technologies Pvt. Ltd. Detail Report
Graph / Photo
512 Patch repair work of various bituminous road 2022.09.14 2022.12.13 33.95 A S INFRATECH Detail Report
Graph / Photo
513 Patch repair of various roads under the jurisdiction of Sub Division-II 2022.04.05 2022.05.04 33.88 69.15 (Aug'22) 0.00 (Aug'22) Sethi Construction Detail Report
Graph / Photo
514 Repairing of 30 Meter High Mast. 2019.05.03 2019.07.02 33.76 Dev Engineers Detail Report
Graph / Photo
515 Restoration of road cut by Delhi Transco Limited from Adhchini to PTS on Sri Aurobindo Marg under Sub Division-II of Division South Road-II, during 2021-22. 2022.05.14 2022.07.13 33.60 41.73 (Jan'23) 0.00 (Jan'23) MANAV CONSTRUCTION COMPANY Detail Report
Graph / Photo
516 Construction of sump well, drain and providing pipe line near loni gole chakker fire station at Loni Road under PWD Sub Division M-2134 2019.10.17 2019.12.15 33.52 41.58 (Sep'21) 0.00 (Sep'21) Sandeep Kumar Detail Report
Graph / Photo
517 A/R & M/O various road under Shahdara Road Division during 2020-21.(SH: Providing Services of Security Guard for watch & ward in the office of PWD Division Shahdara Road office Sub -Division M-2111,M-2112, M-2113 & M-2114.). 2020.06.01 2021.05.31 33.46 12.46 (Apr'21) 0.00 (Apr'21) Stallion Security WORK RESCIND UNDER CLAUSE 3. Detail Report
Graph / Photo
518 Restoration of road cutting for laying 200/300/400 mm dia pipeline from Bachat Bazar near Tuda Mandi Najafgarh to Nangli Dairy on main Shivaji Road, under Sub Division-II, SWR-II, Najafgarh New Delhi 2021.12.02 2022.04.01 33.43 28.46 (Jul'22) 0.00 (Jul'22) Karambir Rana Builders Detail Report
Graph / Photo
519 Providing and fixing MS Grill on footpath at New Rohtak Road from Ram Swaroop Vidyarthi Marg to Rani Jhansi Road 2022.03.02 2022.03.31 33.36 38.07 (Oct'22) 0.00 (Oct'22) Sehgal and Sons Detail Report
Graph / Photo
520 Patch repair of various road under the jurisdiction of Sub Division-I 2022.04.05 2022.05.04 33.32 70.80 (Aug'22) 0.00 (Aug'22) Sethi Construction Detail Report
Graph / Photo
521 Providing Services of Watch & Ward of Subways Scattered at various Location on PWD Roads under PWD South East, New Delhi dg. 2022-23 2022.07.09 2023.07.08 33.31 Friends Detective Security Services Detail Report
Graph / Photo
522 Improvement and other miscellaneous repair work at Ring Road Bypass. (1st RECALL) 2022.10.22 2022.12.21 33.29 Furkan Builders Detail Report
Graph / Photo
523 Painting and repair of FOBs near Yamuna Vihar C-Block, Ambedkar College, T.R. Sahawney and Bhopura Border under Sub Division 2. 2019.10.06 2019.12.04 33.23 37.91 (Dec'21) 0.00 (Dec'21) M. I. Builder Detail Report
Graph / Photo
524 Providing services and machineries for road maintenance of Outer Ring Road from Wazirabad Flyover to Burari Flyover including signature bridge approaches and Jagat pur Flyover 2022.08.17 2023.05.16 33.22 18.31 (Jan'23) 0.00 (Jan'23) Aditya Construction Detail Report
Graph / Photo
525 Providing running Tractor PTO with water pump and fuel etc. 2022.06.01 2022.07.30 33.03 P.L. Construction Detail Report
Graph / Photo
526 Desilting work on various road 2022.12.14 2023.04.13 33.00 K.P. Singh & Co. Detail Report
Graph / Photo
527 Development of open space above entry and exit tunnel at Ring Road towards Pragati Maidan, New Delhi. 1st RECALL 2022.10.26 2022.12.25 32.96