S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 Comprehensive Maintenance of Ring Road/Outer Ring Road under North Maintenance Zone, PWD, Delhi SH: Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work 30/05/2020 29/05/2022 3194.88 540.33 (Jun'21) 0.00 (Jun'21) MAHAVIR PRASAD GUPTA AND SONS Work in Progress Detail Report
Graph / Photo
2 Widening and Stengthening of Road from Najafgarh Dhansa Road to Jhuljhuli Morh via Ghummanhera Village, Delhi. 08/01/2015 07/11/2015 2057.50 Mahavir Parsad Gupta & Sons Work in Progress Detail Report
Graph / Photo
3 Re-development of Chadini Chowk Road in between Lal Jain Mandir to Fateh Puri Mosque. 12/10/2013 11/04/2014 1343.02 Satya Parkash & Bros. Pvt. Ltd. Detail Report
Graph / Photo
4 Resurfacing improvement strengthening riding surface of roads ..... road division 13/01/2020 08/04/2020 1272.87 876.72 (Sep'21) 0.00 (Sep'21) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
5 Strengthening of Ring Road between Nigam Bodh Ghat to Metcalf House Xing under Sub-Division-3 of Division C and ND-Roads. 06/10/2017 05/02/2018 699.17 Winner Construction Pvt. Ltd. Detail Report
Graph / Photo
6 Strengthening / Resurfacing of (1) Seemapuri Road from Road No. 64 to Road No. 62 (2) GTB Hospital Road from Red Light to Agrawal Sweet (3) CNG West Side road (4) GTB Hospital road from GT Road to Agrawal Sweets (5) G.T.B. Hospital Road from Road No. 64 to Road No. 68 (6) Captain Javed Ali Marg (7) Gandhi Nagar Main Market Road (8) Road No. 75B Ext. (Bhartendu Harish Chander Marg from Yamuna Sports Complex to Karkari More flyover (9) Vishwas Nagar Road (60’0” wide). 28/02/2020 26/06/2020 675.69 735.50 (Sep'21) 0.00 (Sep'21) Pawan Kumar Work in progress Detail Report
Graph / Photo
7 Strengthening of Najafgarh Jharoda Road ic raising of depressed road at Ekta Vihar under Sub Division II South West Road II PWD New Delhi. ID 1231 16/10/2019 12/02/2020 567.80 236.37 (Jul'20) 0.00 (Jul'20) Pawan Kumar WORK IN PROGRESS Detail Report
Graph / Photo
8 Improvement and strengthening of Road No. 63, Delhi (From Bhopura Border to Loni Gol Chakkar except flyover). 14/12/2019 12/03/2020 541.95 M/s Roadtech Detail Report
Graph / Photo
9 Widening of Main Burari Road from chainage 0.00-1.00 Km and Strengthening of the road from Outer Ring Road to Burari Morh (Chainage 0.00-3.00 Km) under Sub-Division-1 of C&ND-Roads 26/01/2018 25/05/2018 467.69 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
10 Comprehensive repair and maintenance of various roads under sub division M- 2132. 21/11/2019 20/11/2020 460.10 490.32 (Jun'21) 0.00 (Jun'21) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
11 A/R & M/O Various roads under East Road Sub Division-III, Division East Road (M 212) during 2019-20. (SH:- Comprehensive maintenance of road) 15/10/2019 14/10/2020 455.11 256.00 (Jul'21) 0.00 (Jul'21) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
12 Comprehensive repair and maintenance of various roads under sub division M- 2134. 21/11/2019 20/11/2020 433.62 587.39 (May'21) 0.00 (May'21) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
13 Improvement and strengthening of Road No. 59, Delhi (From Khajuri Gole Chakkar to outer Ring Road Except Wazirabad Yamuna Bridge). 13/01/2020 05/04/2020 432.05 281.82 (Nov'20) 0.00 (Nov'20) M/s Roadtech Detail Report
Graph / Photo
14 Strengthening of Narwana Road from Mother Dairy T-Point to Panch Mahal Awas during 2017-18 19/04/2018 17/07/2018 402.83 79.00 (Jun'19) 0.00 (Jun'19) A S INFRATECH Work in Progress Detail Report
Graph / Photo
15 stopping vibration and noise 26/02/2013 25/06/2013 398.44 K.L. Arora & Son Sanctioned Detail Report
Graph / Photo
16 Providing remedial measures for stopping vibration and noise due to flyover to Outer Ring Road near Ber Sarai, Munirka and Vasant Vihar. 26/02/2013 25/06/2013 398.44 K.L. Arora & Son Sanctioned Detail Report
Graph / Photo
17 Resurfacing of Balbir Saxena Marg (ID-545), Mahender Kumar Jain Marg (ID-531), Shri Krishna Chaitanya Mahaprabhu Marg, Ch. Dilip Singh Marg (ID-530), Siri Fort Road (ID-146), Gautam Nagar Road (ID-534) and Sudershan Cinema Road (Id 533) under Sub Division-I and Ch. Hukum Chand Marg (ID-1257), Hauz Khas Village Road (ID-128), Green Park Main Market Road (ID-33) & N. K. Pandey Marg (ID-31) under Sub Division-II of Division South Road-II, PWD during 2019-20. 14/11/2019 13/01/2020 397.78 607.92 (Sep'21) 0.00 (Sep'21) M. C. Construction Co. Work in Progress Detail Report
Graph / Photo
18 Strengthening of Prithvi Singh Dagar Marg ID 1175 from RawtaMorh Dhansa Road to Daurala Border under PWD Division- South West Road-II New Delhi. 16/10/2019 12/02/2020 388.15 Pawan Kumar UNDER TENDERING PROCESS Detail Report
Graph / Photo
19 A/R and M/O to Sub Division-14 of South Road-1 for Comprehensive Maintenance of Press Enclave Road, Mandir Marg, Pankaj Juyal Marg, NBCC Plaza Road, Pramod Mahajan Marg, Family Court Road J-Block Road, H-Block Road Gurudwara Road, Asian market Road, Khirki Road, Sheikh Sarai Phase-I Road no.1 & Road No.2, Road from H.No. C-11 to C-20 Malviya Nagar and Road in front of Mother International School during 2019-20. 01/11/2019 31/10/2020 317.62 393.62 (Aug'21) 0.00 (Aug'21) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
20 Strengthening of Road No. 68 (from Road No. 66 T-Point to Junction of Road No. 69). (From Railway line to Road No. 66 T-Point). 02/09/2019 30/11/2019 309.88 296.12 (Nov'20) 0.00 (Nov'20) MAHAVIR PRASAD GUPTA AND SONS work in progress Detail Report
Graph / Photo
21 Re-surfacing of Shaheed Jeet Singh Marg (ID-22), Qutub Institutional area (ID-35) and Satsang Vihar Marg (ID-49) under Sub Division-III and Guru Govind Singh Marg (ID-529) under SD-IV of South Road-II during 2019-20. 09/11/2019 08/01/2020 308.57 325.08 (Feb'21) 0.00 (Feb'21) Pawan Kumar Work in Progress Detail Report
Graph / Photo
22 Comprehensive repair of roads, footpaths, drain, painting etc. under Sub Division NR-12, Division North Roads, PWD, Delhi during the year 2019-20 03/12/2019 27/10/2020 307.90 212.65 (Apr'21) 0.00 (Apr'21) ESS Kay Const. Work in Progress Detail Report
Graph / Photo
23 A/R & M/O to various roads under Division South Road-II, PWD during 2020-21 (SH: Providing Security arrangement for Division Office, Sub Division Office - I, II, III, IV and Various locations) 10/03/2021 09/03/2022 302.08 7.57 (Jul'21) 0.00 (Jul'21) Friends Detective Security Services Detail Report
Graph / Photo
24 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road-II PWD New Delhi 10/09/2019 07/01/2020 298.81 194.61 (Jul'20) 0.00 (Jul'20) SBG Infracon Pvt Ltd WORK IN PROGRESS Detail Report
Graph / Photo
25 Strengthening of Madhu Vihar Road (Road No. 57 to Joshi Colony T-Point) and Mandawali Road (House Tax Building to Agrasen Apartment) at I.P. Extension under PWD Division East (Road) 16/04/2018 14/07/2018 280.65 110.07 (Jan'20) 0.00 (Jan'20) JAP BUILDCON PRIVATE LIMITED Work in Progress Detail Report
Graph / Photo
26 Improvement of drainage system on GT Road from Ghanta Ghar to Najafgarh Drain, under Sub-Division-2 of Division CandND-R, New Delhi. 08/01/2019 07/05/2019 245.78 295.77 (Sep'21) 0.00 (Sep'21) S S Chauhan & Sons Detail Report
Graph / Photo
27 Comprehensive Maintenance of SSN Marg, 100 Foota Road and 60 Foota Road under the Jurisdiction SD-12 under SR-1 during 2019-20. 01/11/2019 31/10/2020 227.39 242.89 (Jun'21) 0.00 (Jun'21) Amrit Lal behl & Sons Detail Report
Graph / Photo
28 AR and MO to various Roads under Division North West Road 1 dg 2019 20 SH Providing services of Maintenance vehicle with labour and TandP etc for all sub division for one year 19/06/2019 18/06/2020 226.61 GLOBE BUILDERS Detail Report
Graph / Photo
29 Strengthening, improvement of footpath and providing and fixing Retro reflective road signages and upgradation street lighting of Shiva Road connecting Sector 7 and 8 in Rohini, Delhi. SH- providing footpath and drains Shiva Road ...( balance work). 20/01/2018 18/07/2018 215.30 243.86 (May'19) 0.00 (May'19) Kundu Nirma Detail Report
Graph / Photo
30 AR and MO to Sub Division_I of South Road_II for Comprehensive Maintenance of Sirifort Road Balbir Saxena Marg August Kranti Marg Asiad Games Village Road and other roads under jurisdiction of Sub Division_I 30/10/2019 29/10/2020 213.73 233.11 (Sep'21) 0.00 (Sep'21) Pawan Kumar Work in Progress Detail Report
Graph / Photo
31 Improvement of approach road and construction of side drain from Main Burari Road to Burari Transport Complex road under Sub Division - 1 of Division C and ND - Roads, New Delhi. RECALL 19/07/2021 18/11/2021 211.21 Kundu Nirman Detail Report
Graph / Photo
32 Strengthening of wazirabad flyover and slip road under Sub Division1 of Division CandND-Road New Delhi. 02/03/2019 01/07/2019 209.26 322.27 (Jan'20) 0.00 (Jan'20) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
33 A/R and M/O to various Roads under Division North West Road-2, PWD dg. 2019-20. SH- Providing services of maintenance vehicle, labour and T and P for all sub division for one year). 18/07/2019 17/07/2020 207.93 60.66 (Jul'20) 0.00 (Jul'20) GLOBE BUILDERS Detail Report
Graph / Photo
34 Detailed Third Party Inspection Quality Assurance for Comprehensive Development of Corridor (Outer Ring Road) between Mukarba Chowk to Wazirabad Chowk. SH: Consutruction of Flyovers, Loops, Bridges across supplementary drain, FOBs, Footpath, Cycle Track, Widening of Road on embankment, Rain Water Harvesting Scheme, Electrical works and other allied works. 15/07/2013 14/07/2015 199.90 0.00 (May'18) 97.00 % (May'18) Delhi Technological University

Work Completed.

Detail Report
Graph / Photo
35 A/R and M/O to Sub Division-11 of South Road-1 for Comprehensive Maintenance of Road under jurisdiction of Sub Division-11 during 2019-20 01/11/2019 31/10/2020 199.05 283.47 (Aug'21) 0.00 (Aug'21) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
36 Restoration of road cut by DJB for laying of 1000 mm dia MS water line from Chor Piou to Karala OHT under Sub Division WR-22, PWD Division West Road-2 during 2019-20 26/08/2019 23/11/2019 195.80 27.52 (Aug'20) 0.00 (Aug'20) M C Constructions Company work Detail Report
Graph / Photo
37 Name of corridor Sarai Kale Khan to IGI Airport incl areas covering Redevelopment of General Pool Residential Accommodation GPRA colonies at Kidwai Ngr Nauroji Ngr Netaji Ngr Sarojini Ngr Mohamadpur Thyagrajngr Kasturba Ngr and AIIMS trauma centre 10/07/2018 06/01/2019 191.70 114.23 (Sep'21) 0.00 (Sep'21) Craphts Cons. Pvt. Ltd. Work in progress Detail Report
Graph / Photo
38 Construction of Foot Over Bridge at Metcalf House Main Gate of Ring Road under Sub Division 3 of Division CND Roads New Delhi SH Civil and Electrical Work 20/03/2019 19/09/2019 190.46 163.88 (Jun'21) 0.00 (Jun'21) Fiberfill Engineer Detail Report
Graph / Photo
39 Road Restoration (Road cut by Delhi Jal Board) at Bijwasan Road under Sub Division-24 SWR-II PWD, New Delhi. 04/10/2019 01/01/2020 173.51 A S Infratech Work in progress 96% Detail Report
Graph / Photo
40 Civil and Electrical Works. 06/03/2019 05/09/2019 168.62 205.44 (Aug'21) 0.00 (Aug'21) Imaginearc Infrastructure Pvt. Ltd. Work in Progress. Detail Report
Graph / Photo
41 A/R and M/O to Sub Division-II of South Road-II for Comprehensive Maintenance of Aurobindo Marg, Ch. Hukum Chand Marg, Ch. Jhandu Singh Marg, Ch. Harsukh Marg, Hauz Khas Village Road, N.K. Pandey Marg and Green Park Market Road. 30/10/2019 29/10/2020 162.61 204.77 (Sep'21) 0.00 (Sep'21) M/s Roadtech Work in Progress Detail Report
Graph / Photo
42 SH: Providing services of Computer Programmers, Data Entry/Computer Operators, Personal Secretary , Messengers, LMV Drivers, Peon , Clerical Staff etc. for the office of E-in-C , Pr. CE , CE(E) M , Circle C & ND -M & C & ND -R Division. 08/09/2017 07/09/2018 158.94 RAKSHAK SECURITAS PVT. LTD. Detail Report
Graph / Photo
43 Alignment of footpath and extension of road adjacent to the Meena Bazar area on Urdu Bazar Road, acquired after encroachment drive, under SRD Division-I, Sub Division-I, PWD, New Delhi . 13/07/2018 26/08/2018 158.52 Sirohi Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
44 Improvement of drainage system from RD 4350 (Near kali piyau) to RD 1200 (Near Jharoda village ) RHS on Najafgarh Bahadurgarh road Delhi. 16/01/2015 15/05/2015 155.22 B.M. & Sons Detail Report
Graph / Photo
45 Improvement of drainage system of Yamuna Vihar area. (SH.-Providing and laying K-9 pipe from Pump House at dividing road to Drain No.1). 15/06/2018 14/10/2018 149.16 158.39 (Sep'20) 0.00 (Sep'20) RAJESH KUMAR GUPTA Work in progress. Detail Report
Graph / Photo
46 Desilting of road side drain manually and mechanically with super sucker machine under Sub-Division East Road-I, Delhi 14/03/2019 13/01/2020 147.77 202.22 (Jun'20) 0.00 (Jun'20) Rajnish Yadav

Work in progress

Detail Report
Graph / Photo
47 Desilting of road side drain manually and mechanically with super sucker machine 24/05/2018 23/05/2019 142.81 202.07 (Oct'19) 0.00 (Oct'19) M/s Shiva Construction Co.

Work in progress

Detail Report
Graph / Photo
48 Strengthening and Improvement of Drain, Footpath, Central Verge of Rani Jhansi Road (Idgah round about to Filmistan) 05/04/2014 04/12/2014 142.38 K Construction co Detail Report
Graph / Photo
49 Desilting of road side drains of Section I and II. 14/03/2019 13/01/2020 140.11 190.15 (Dec'19) 0.00 (Dec'19) Shiv Construction Co.

Work in progress

Detail Report
Graph / Photo
50 AR and MO to Sub Division_III of South Road_II for Comprehensive Maintenance of Aruna Asif Ali Marg Vedant Dehika Marg Anuvrat Marg Shaheed Jeet Singh Marg Qutub Round About Marg and others Road under jurisdiction of Sub Division_III 30/10/2019 29/10/2020 135.88 166.33 (Sep'21) 0.00 (Sep'21) Bishwa Mohan Jha Work in Progress Detail Report
Graph / Photo
51 A/R and M/O Various Roads under Division Central and New Delhi - Roads, PWD during 2018-19. SH_Providing services of Data Entry/Computer Operators, Personal Secretary, Clerical Staff, Messengers, Messenger cum Peon and Peon for the office of, Pr. 20/09/2018 19/09/2019 130.38 107.74 (Jan'20) 0.00 (Jan'20) RAKSHAK SECURITAS PVT. LTD. Detail Report
Graph / Photo
52 A/R and M/O to various Roads under Division North West Road-2 dg. 2018-19. SH- Providing services of Maintenance vehicle with labour and T and P etc. for all sub division for one year). (Re-call) 22/06/2018 21/06/2019 129.86 75.85 (May'19) 0.00 (May'19) GLOBE BUILDERS Detail Report
Graph / Photo
53 Replacing existing Hollow U Shape Crash Barrier of I.P Flyover with R.C.C. Crash Barrier including repair of spalling of concrete under C and ND- Roads Division. 03/10/2018 02/01/2019 118.60 137.57 (Jan'20) 0.00 (Jan'20) D.P. Associates Detail Report
Graph / Photo
54 Providing and fixing M. S. Grill at central verge from Chhawla Village to BDO office, at Najafgarh Bijwasan Road (ID 1173) under PWD division SWR-II, New Delhi. 09/09/2019 07/11/2019 114.71 25.00 (Jul'20) 0.00 (Jul'20) Awasthi Construction Co. WORK IN PROGRESS Detail Report
Graph / Photo
55 Profile correction of road from Sarita Vihar FOB to Park and Near Bus Stand to Khadar Road disturbed due to U turn and widening of road on Road No. 13 A. 24/11/2019 23/12/2019 114.57 141.96 (Jun'21) 0.00 (Jun'21) Awasthi Construction Co. Detail Report
Graph / Photo
56 A/R and M/O to various roads under PWD Sub Division M-2132 dg. 2017-18. (SH-Anti carbonation painting work on concrete structure of 4 Nos Flyovers (Loni Flyover, Gokalpuri Flyover, Kahjuri Flyover and Nand Nagri Flyover) under Sub Division M-2132. 05/04/2018 04/06/2018 113.31 45.16 (Aug'20) 0.00 (Aug'20) Shamshad Ahmed work in progress Detail Report
Graph / Photo
57 A/R & M/O to various roads under Division East Road/(m212) PWD Delhi, during 2021-22 01/04/2021 31/03/2022 110.00 Star security & Placement Services Detail Report
Graph / Photo
58 Desilting of road side drains of Section I and II. 15/03/2019 14/12/2019 104.45 140.49 (Nov'20) 0.00 (Nov'20) Anmol Infratech Private Limited

Work in progress

Detail Report
Graph / Photo
59 A/R and M/O Various Roads under Division Central and New Delhi - Roads , PWD during 2018-19. SH_Providing services of security guard for watch and ward for the office of circle C and ND -M and C and ND- R Division. 16/10/2018 15/10/2019 103.53 86.30 (Dec'19) 0.00 (Dec'19) Stallion Security and Services Detail Report
Graph / Photo
60 Desilting of road side drain manually and mechanically with super sucker machine at Patparganj Road, Chitra Vihar Road, New Rajdhani Enclave Road, Vikas Marg, Disused Canal Road, Gagan Vihar Road, Narwana Road and Several others Road in I.P. Extension in the Sub-Division -I East Road, Delhi 30/04/2018 01/03/2019 102.72 21.44 (Nov'19) 0.00 (Nov'19) M/s Shiva Construction Co.

Work in progress

Detail Report
Graph / Photo
61 Desilting of road side drains 24/05/2018 23/02/2019 101.35 25.00 (Sep'19) 0.00 (Sep'19) M/s Shiva Construction Co.

Work in progress

Detail Report
Graph / Photo
62 M/o different roads under Hort. Sub Division (Central and New Delhi), Hort. Division (East) M, PWD, Delhi dg 2018-19 08/03/2019 07/04/2019 99.71 19.15 (Nov'19) 0.00 (Nov'19) Chandra Farm and Nursery Detail Report
Graph / Photo
63 Restoration of roads under Sub Division-1 of Division South Road-2 damaged by DJB during 2019-20. 23/05/2020 22/08/2020 98.88 121.22 (Sep'21) 0.00 (Sep'21) Ram Singh Work in Progress. Detail Report
Graph / Photo
64 Improvement and Strengthening of Dharamshilla Road at Vasundhra Enclave Delhi 17/05/2018 30/06/2018 95.76 39.37 (Jun'19) 0.00 (Jun'19) Chaudhary Construction Company Pvt. Ltd.

Work in progress

Detail Report
Graph / Photo
65 Complete Maintenance of Hort. work of different roads (Main Mall Road, Delhi University Road, Vikas Bhawan Road, Raj Niwas Road, Flag Staff Road, Shamnath Marg etc.) and C. C. Paralled Road from Burari Chowk to Wazirabad under HSD (Central and New De 10/08/2018 09/08/2019 93.64 45.61 (Sep'19) 0.00 (Sep'19) Rathore Contractor and Supplier Detail Report
Graph / Photo
66 Consultancy services for Structural Design and preparation of other documents for Construction of Bridge on Najafgarh drain at Tri Nagar/Inderlok, Karampura and Rampura, Delhi 23/09/2018 22/03/2021 93.37 Tandon Consultant Pvt. Ltd. work is in progress. Detail Report
Graph / Photo
67 (ISBT to Wazirabad Flyover Road, Ring road, BBM Road, Gandhi Vihar Road, Lucknow Road, Main Burari Road, Parmanand School Road, Timarpur Road etc.) under HSD (Central and New Delhi). HD-East, PWD, Delhi dg 2018-19 01/08/2018 31/07/2019 86.20 42.84 (Nov'19) 0.00 (Nov'19) PLANTS CARE Detail Report
Graph / Photo
68 Widening of Road no 102 from Bharti Public School to Dallupura Road & Improvement of Kaccha Portion on Porta Cabin Road. 27/06/2018 24/09/2018 86.16 Y D Builders and hotels pvt. ltd

Work in progress

Detail Report
Graph / Photo
69 A/R & M/O Various Roads under SRD Project Division-I, PWD, New Delhi During 2018-19 (SH: Providing Data Entry/Computer Operators, Messengers, LMV Drivers, Clerical Staff etc. for various offices under Project Circle and SRD Division-I.) 30/07/2018 29/06/2019 83.90 67.79 (Apr'21) 0.00 (Apr'21) RAKSHAK SECURITAS PVT. LTD. Work in progress Detail Report
Graph / Photo
70 A/R and M/O to PWD Roads under Sub Division-3 of Division C and ND Roads dg. 2017-18. SH_Anti-carbonation painting of Ring Road by Pass Flyover. 03/05/2018 02/08/2018 82.49 Aliyan Constaruction Company Detail Report
Graph / Photo
71 A/R and M/O Various Roads under SRD Project Division-I, PWD, New Delhi (SH-Providing Data Entry/Computer Operators, Messengers, LMV Drivers, Clerical Staff etc. for various offices under Project Circle and SRD Division-I.) 01/10/2017 30/06/2018 79.59 5.49 (Sep'19) 0.00 (Sep'19) K.P. Singh & Co. Work completed and final bill paid Detail Report
Graph / Photo
72 Road restoration of city side service road from Khajuri chowk to Biharipur at MB Road cut by DJB under jurisdiction of Sub Division M-4, PWD (North East) Road Division dg. 2018-19. 18/01/2019 04/03/2019 75.94 71.54 (Dec'19) 0.00 (Dec'19) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
73 Replacement of Expansion joints of Nauroji Nagar flyover Africa Avenue flyover on Ring Road and IIT Delhi flyover on Outer Ring Road New Delhi 16/06/2019 15/11/2019 75.50 Sanfield (India) Limited

Work in Progress

Detail Report
Graph / Photo
74 (SH Supplying and fixing of new street light poles and cable for street lights at various locations on different roads and repairing of 30 Mtrs High Masts at ITO Chungi. 12/03/2019 11/06/2019 75.24 23.13 (Mar'20) 0.00 (Mar'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
75 Surfacing work of Mangolpuri flyover under Sub Division NWR-25. 12/05/2018 25/06/2018 73.77 SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
76 Providing Data Entry Computer Operators, Messengers, LMV Drivers Clerical Staff etc for various offices under Project Circle and SRD Division I 16/09/2019 15/09/2020 72.93 79.09 (Jan'21) 0.00 (Jan'21) Passion Sports Academy Detail Report
Graph / Photo
77 Strengthening, Improvement of footpath and providing and fixing retro-reflective road signages and upgradation of street lighting on kalamandir Road, LP Road (Tank Road) and B-Block Road in Mangolpuri, Delhi. (SH- Microsurfacing of Bituminous Road.) 26/01/2019 25/04/2019 72.45 49.65 (Aug'19) 0.00 (Aug'19) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
78 A/RandM/O PWD Roads under Sub-Division I of Division CandND Roads during 2018 19 SH Desilting of Drains on various roads. 12/02/2019 11/08/2019 71.71 96.77 (Jan'20) 0.00 (Jan'20) M/s K.P Singh & Co. Detail Report
Graph / Photo
79 Civil Work 15/09/2018 13/12/2018 71.41 8.06 (Feb'20) 0.00 (Feb'20) Akhil Kumar Constructions

Work in progress

Detail Report
Graph / Photo
80 Repairing of Jafrabad side drain from Jafrabad Gali No-9 to Gali No. 45 on Road No. 66 is missing portion damages by the civic agencies under Sub Division 2. 10/02/2019 09/06/2019 71.34 78.92 (Aug'19) 0.00 (Aug'19) Vinod Kumar Work in progress Detail Report
Graph / Photo
81 AR and MO to Various Roads under Sub Division NW R 14 PWD Division NW R 1 dg 2018 19 SH Comprehensive desilting of drains of various categories and sizes along PWD roads 05/04/2018 02/10/2018 70.78 Shiv Shakti Enterprises Detail Report
Graph / Photo
82 Providing services of Computer Operators, Clerk, Supervisor and MTS for Division and Sub Division Offices 17/08/2021 16/08/2022 70.62 ARMOUR SECURITY INDIA PVT LTD Detail Report
Graph / Photo
83 Providing and installation retro reflective road signages on Main Burari Road from Outer Ring Road to Hiranki Bandh under PWD, Sub Division-1 C&ND-R 06/03/2018 05/06/2018 69.82 3.77 (Dec'19) 0.00 (Dec'19) Fiberfill Engineer Detail Report
Graph / Photo
84 A R and M O various road under Sub Division M 2113 during 2018 19 SH Covering of drain of Babarpur Road after necessary misc repair work SECTION II Balance Work 3rd CALL 28/10/2018 24/02/2019 68.65 80.71 (Nov'19) 0.00 (Nov'19) RAHUL CONSTRUCTION COMPANY Work in progress Detail Report
Graph / Photo
85 A/R and M/O to various road under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18 SH Comprehensive Maintenance of road 01/03/2018 25/11/2018 68.51 D.P. Associates Work completed. Detail Report
Graph / Photo
86 Providing security guards at Circle office (NE), Division Office (NE) Road, Sub Division M-2132 & M-2134 and enquiry office. 28/10/2018 27/10/2019 67.99 65.84 (Mar'20) 0.00 (Mar'20) RAKSHAK SECURITAS PVT. LTD. Work in progress. Detail Report
Graph / Photo
87 Improvement of road from House No. 264, Kalyan Vihar to G.T. Karnal Road near Tripolia Gate under Sub-Division-2, of P.W.D. Division (C and ND)-Road, New Delhi. Recall of Tender 21/06/2018 20/08/2018 67.75 1.06 (Jun'19) 0.00 (Jun'19) Gaurav Construction Co. Detail Report
Graph / Photo
88 Maintenance, Repair of street lights and High Masts i/c monitoring of street Light Lift and Escalators at various locations under PWD-251. SH-Comprehensive Maintenance Operation Watch and ward of lifts and Escalators. 05/10/2018 04/10/2019 67.55 56.48 (Sep'20) 0.00 (Sep'20) Techno Industries Limited Detail Report
Graph / Photo
89 Providing and Fixing M.S. Railings in Central Verge of Road No. 45 from Chandgi Ram Akhada Red Light to Majnu ka Tila Gurudwara Red Light under Sub- Division-I, PWD Division (C and ND)-R. 10/01/2019 09/04/2019 66.68 33.32 (Sep'19) 0.00 (Sep'19) Ram Singh Detail Report
Graph / Photo
90 RMO various roads in North East Delhi under the jurisdiction of M-251 during 18-19, Delhi. SH-Supplying and fixing of street lights pole fittings laying of cable etc at different locations 05/11/2018 04/01/2019 66.32 24.94 (Oct'19) 0.00 (Oct'19) M/s Shaka Electrical (India) Detail Report
Graph / Photo
91 Providing and Fixing SFRC Railing in Central Verge at Main Burari Road from Bengali Colony to Hiranki Bandh and Improvement of berm on Swaroop Nagar Road New Delhi RECALL 01/03/2019 31/05/2019 65.91 50.46 (Aug'19) 0.00 (Aug'19) Gaurav Construction Co. Detail Report
Graph / Photo
92 A/R and M/O to Sub Division-IV of South Road-II for Comprehensive Maintenance of (1. A-1 Block, Panchsheel Enclave Road, 2. B,C and D Block Panchsheel Enclave Road, 3. S-Bend Road and 4. Guru Govind Singh Marg). 24/10/2019 23/10/2020 65.31 97.70 (Sep'21) 0.00 (Sep'21) AMOCON Work in Progress Detail Report
Graph / Photo
93 A/R and M/O to Sub Division-III of South Road-II for Comprehensive Maintenance of under jurisdiction of Sub Division-III Roads during 2021 20/04/2021 19/04/2022 65.25 Nagendra and Company Detail Report
Graph / Photo
94 Widening of road from Kalindi Kunj Park Red Light to FOB Saheen Bagh to prevention of traffic jam and pollution at Road No 13 A under PWD SER 2 New Delhi 02/06/2018 01/08/2018 65.16 105.53 (Aug'21) 0.00 (Aug'21) Awasthi Construcion Co., PAN: ACGPA1281M, Address: A-35, VEER SINGH COLONY, BUDH VIHAR, PHASE-II, NEW DELHI-110086 30% Detail Report
Graph / Photo
95 Providing and Fixing SFRC Railing in island and repair of footpath below wazirabad flyover under Sub Division-1, CandND-Roads Division, New Delhi. 05/01/2019 04/04/2019 64.92 67.17 (Oct'19) 0.00 (Oct'19) Irshad Ahmed Detail Report
Graph / Photo
96 Construction of drain on Swaroop Nagar Road (60ft. Road) from Swaroop Nagar Morh to I and FC Channel (RHS) under Sub-Division-I, PWD Division C and ND -Roads, New Delhi. 28/12/2018 27/05/2019 64.91 39.95 (Feb'20) 0.00 (Feb'20) Dinesh Kumar Goyal Detail Report
Graph / Photo
97 A/R and M/O to Sub Division-II of South Road-II for Comprehensive Maintenance of Aurobindo Marg, Ch. Hukum Chand Marg, Ch. Jhandu Singh Marg, Ch. Harsukh Marg, Hauz Khas Village Road, N.K. Pandey Market Road during 2021 20/04/2021 19/04/2022 64.56 SHARVAN CONSTRUCTION CO. Detail Report
Graph / Photo
98 Widening of culvert across irrigation drain near Bengali Colony at Main Burari Road under Sub Division I of Division C & ND-Roads New Delhi. 3rd Call of Tender 01/11/2018 28/02/2019 64.46 78.13 (Feb'20) 0.00 (Feb'20) Mls Rajat Construction Co. Detail Report
Graph / Photo
99 Operation and Maintenance of storm water pumps and D.G. sets of pump houses in North East area under PWD Division M-251 Delhi. 18/03/2019 17/02/2020 64.24 74.65 (Jun'20) 0.00 (Jun'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
100 Widening of road no. 13 A from Shaheen Bagh Market to Chaudhary Charan Singh Park (Kalindi Kunj) Red Light Market side) 22/04/2019 09/10/2020 63.31 26.77 (Mar'21) 0.00 (Mar'21) Awasthi Construction Co. 15% Detail Report
Graph / Photo
101 Providing services of Data Entry/Computer Operators, Messengers, LMV Drivers, MTS, Clerical Staff etc. for the office of Circle (NE) and NE Road Division. 21/01/2019 20/02/2020 63.23 71.43 (Sep'20) 0.00 (Sep'20) TRENDY SECURITY SERVICES Work in progress Detail Report
Graph / Photo
102 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2018-19 (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-22.) 31/03/2018 25/12/2018 63.12 4.49 (Sep'20) 0.00 (Sep'20) WORK CEE Detail Report
Graph / Photo
103 SH:Improvement of road side drain & footpath at B-4 & B-5 Block in Paschim Vihar 19/12/2015 31/05/2016 63.02 0.00 (Aug'16) 100.00 % (Aug'16) Pragati Constructions Bill awaited from contractor Detail Report
Graph / Photo
104 Operation and Maintenance of storm water pumps and D.G. sets of pump houses in Shahdara area under PWD Division M-251 Delhi. 18/03/2019 17/03/2020 62.88 78.49 (Jul'20) 0.00 (Jul'20) Krishna Electreical Works Work in progress Detail Report
Graph / Photo
105 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Repair of road surface in patches on Road No-59 and 63 under sub division-2). 10/06/2019 08/08/2019 62.17 63.78 (Nov'19) 0.00 (Nov'19) Chaudhary Construction Company Pvt. Ltd. Work in progress. Detail Report
Graph / Photo
106 A/R and M/O PWD Roads under Sub-Division-1 of Division C and ND Roads during 2018-19. SH_Repairing and covering of drain slab from Swaroop Nagar Morh to Kaushik Enclave at Main Burari Road and BurariGarhi to Surya Appartment on Swaroop Nagar Road (60 17/12/2018 16/06/2019 62.14 31.82 (Dec'19) 0.00 (Dec'19) Mls Rajat Construction Co. Detail Report
Graph / Photo
107 Shifting of Footpath and drain and Providing RCC retaining wall to prevention of traffic jam Pollution and encroachment from FOB Saheen Bagh to Kalindi Kunj Park Red Light at Road No 13 A under PWD Division SER 2 New Delhi 29/05/2018 28/07/2018 61.95 100.50 (Aug'21) 0.00 (Aug'21) Awasthi Construcion Co., PAN: ACGPA1281M, Address: A-35, VEER SINGH COLONY, BUDH VIHAR, PHASE-II, NEW DELHI-110086 62% Detail Report
Graph / Photo
108 Desilting of Road side drains SECTION-II 27/02/2019 25/08/2019 61.84 95.66 (Aug'20) 0.00 (Aug'20) Ram Kumar Sharma Work in progress Detail Report
Graph / Photo
109 Raising carriage way at Live Stock Road in Ghazipur Dairy Farm 11/03/2019 08/06/2019 60.78 56.39 (Aug'20) 0.00 (Aug'20) Shiva Construction

Work in progress

Detail Report
Graph / Photo
110 Routine maintenance , operation of DG Sets and Storm Water Pump Sets 09/08/2017 08/08/2018 60.72 H.N. Traders & Engineers Detail Report
Graph / Photo
111 Improvement of Service Road from Geeta Colony Thana to Mandi Khureji on Patparganj Road under PWD Division East(Road) M-212, Delhi during 2018-19 07/03/2019 05/05/2019 60.69 61.41 (Oct'19) 0.00 (Oct'19) Arif

Work in progress

Detail Report
Graph / Photo
112 Modification of u turn at Road No. 59 14/12/2018 12/01/2019 60.38 45.54 (Sep'19) 0.00 (Sep'19) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
113 A/R and M/O Various road under sub Division WR-11, Division- WR-I, New Delhi during 2018-19. (SH Comprehensive desilting of drains by mechanical/manual means of various categories and sizes along PWD roads.) 08/03/2019 03/09/2019 59.36 45.63 (Jan'21) 0.00 (Jan'21) RichCon Engineering Company WORK IN PROGRESS Detail Report
Graph / Photo
114 Restoration and further improvement of damaged/deteriorated service road near crown plaza red light 22/11/2020 19/03/2021 59.35 73.69 (Mar'21) 0.00 (Mar'21) Awasthi Construction Co. Detail Report
Graph / Photo
115 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2018-19 (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-24.) 29/03/2018 23/12/2018 59.33 Rajnish Yadav Detail Report
Graph / Photo
116 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (SH- Repair of drain and providing footpath at Guru Virja Nand Marg from Naveen Apartment to Rani Bagh fruit Market (Right Side) under sub Division NWR-24.) 16/07/2018 28/09/2018 58.80 24.83 (Mar'19) 0.00 (Mar'19) Jitender Singh Detail Report
Graph / Photo
117 Restoration of roads cut by DJB from Som Bazar Chowk to Surukpur More and Other Balance Work under Sec II of Sub Division II Najafgarh New Delhi 26/11/2018 23/02/2019 58.61 Dhanna Ram & Sons WORK CLOSED Detail Report
Graph / Photo
118 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Repair and Improvement of footpath on both side From Railway line flyover to Road no. 66 T-Point under Sub Division M-4) 10/08/2019 07/11/2019 57.53 69.55 (Aug'20) 0.00 (Aug'20) Rajesh Kumar Gupta Detail Report
Graph / Photo
119 Providing Services of Computer Operator Clerk etc. for the offices of SE South Division SR-1 and Sub-Divisions 12/03/2021 06/09/2021 57.15 38.84 (Aug'21) 0.00 (Aug'21) Harshidhi Security Service Detail Report
Graph / Photo
120 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Providing protection wall, footpath and repair of road, drain, misc. work at Community Centre side road no. 65 and Babarpur Road under Sub Division M-4). 09/08/2019 07/10/2019 56.81 65.95 (Nov'20) 0.00 (Nov'20) Vinod Kumar Detail Report
Graph / Photo
121 A/R & M/O various roads uner PWD, NWR-2 dg. 2018-19. (SH- Repairing of surface of ramp of elevated corridor and providing and fixing crash barrier on Guru Gowalkar Marg (Road No.3) under Sub Division NWR-25.) 05/01/2019 18/02/2019 56.43 70.51 (Nov'19) 0.00 (Nov'19) M C Constructions Company Detail Report
Graph / Photo
122 A/R and M/O to Sub Division-I of Division South Road-II, PWD for Comprehensive maintenance of under jurisdiction of Sub Division-I Roads during 2021 20/04/2021 19/04/2022 56.02 Nagendra and Company Detail Report
Graph / Photo
123 A/R and M/O to various roads under PWD Division NWR-2 during 2017-18. (SH- Comprehensive Repair of road footpath, drain, painting etc. under Sub division NWR-22.) 15/10/2017 13/03/2018 55.95 Arif Detail Report
Graph / Photo
124 Improvement of Side berms, Drain, Dwarf wall, M.S. Railing on Service Road on near Rashtriya Smriti Sthal Ring Road between Shantivan to Mangi Bridge under Sub Division 3 of Division CandND Roads, New Delhi. 12/12/2018 11/03/2019 55.89 36.50 (Oct'19) 0.00 (Oct'19) S S Chauhan & Sons Detail Report
Graph / Photo
125 Restoration of roads cut by Delhi Jal Board for laying of sewer line from Malka Ganj chowk to Daulat Ram College under Sub-Division-II of Division C and ND-Roads, New Delhi. 09/03/2019 08/09/2019 55.84 67.78 (Jul'19) 0.00 (Jul'19) Aditya Construction Detail Report
Graph / Photo
126 A/R and M/O to various roads under PWD Division NWR-2 dg. 2018-19. (SH- Improvement of Footpath and berm portion of Bhao Rao Dev Ras Marg under Sub-Division, NWR-24.) 03/07/2018 30/09/2018 55.17 57.71 (Oct'19) 0.00 (Oct'19) Laxman Detail Report
Graph / Photo
127 A/RandM/O PWD Roads under Sub Division 3 of Division CandND-Roads during 2018-19. SH Desilting and cleaning of road side storm water drains. 06/02/2019 05/08/2019 54.86 81.19 (Dec'19) 0.00 (Dec'19) Ram Singh Detail Report
Graph / Photo
128 A/R and M/O to various roads under Sub Division-I of Division South Road-II PWD during 2020-21 (SH:Providing Computer operator MTS Clerk and MLD in Sub Division office Division office and CE South office). 08/03/2021 07/09/2021 54.25 44.52 (Aug'21) 0.00 (Aug'21) HARSHIDHI SECURITY SERVICES, PAN: AAFFH4918Q, Address: A-86 BHAGWAT, GARDEN EXTN. UTTAM NAGAR Detail Report
Graph / Photo
129 Repair of footpath of city side at MB Road Shastri Park to Khajuri Chowk for making the proper accessibility for differently abled persons. 28/11/2018 26/01/2019 54.19 25.60 (Oct'19) 0.00 (Oct'19) Sachin Prakash Work in progress Detail Report
Graph / Photo
130 A/R and M/O to various roads under PWD Division NWR-2 during 2017-18. (SH- Connection of drain from Petrol Pump through Transport Authority to ESI Hospital at K.N.katju Marg, Rohini, Delhi under Section-II, Sub Division NWR-23.) 22/04/2018 05/07/2018 54.00 20.81 (Oct'19) 0.00 (Oct'19) GLOBE BUILDERS Detail Report
Graph / Photo
131 Construction of R.C.C. drain in place of damaged brick drain at Mangal Bazar Road (H-Block), Jahangirpuri under Sub-Division NR-11 29/05/2020 27/07/2020 53.98 M T Builders work in progress and 60% work completed Detail Report
Graph / Photo
132 A/R and M/O Various Roads under PWD, Sub Division WR-12, Division WR-1, New Delhi dg. 2018-19. (SH Improvement of Service Lane along Pankha Road from C-2 Red Light to old pankha Road cut) 14/02/2019 13/05/2019 53.94 67.39 (Nov'20) 0.00 (Nov'20) Rajpal Sehgal Detail Report
Graph / Photo
133 Providing and fixing of RCC Jersey Barrier on Narela - Bawana Road from Ramdev Chowk to Railway Crossing Narela, Delhi under Sub-Division NR-13 (Section-II) 28/03/2020 26/05/2020 53.88 VV Associates 20% work completed, Slow progress due to labour shortage because of Covid-19 Pandemic Detail Report
Graph / Photo
134 Providing Services of Computer Operator Clerk etc. for the offices of SE South Division SR-1 and Sub-Divisions. 05/08/2020 31/01/2021 52.86 72.18 (Jul'21) 0.00 (Jul'21) HARSHIDHI SECURITY SERVICES, PAN: AAFFH4918Q, Address: A-86 BHAGWAT, GARDEN EXTN. UTTAM NAGAR Detail Report
Graph / Photo
135 Comprehensive Maint. of Street light at vrs road, Operation of DG Sets, Dewatering pump at vrs under pass, Operation of Fountain at Clock Tower Ghantaghar 12/07/2020 11/10/2021 52.62 57.86 (Aug'21) 0.00 (Aug'21) SEHRA ELECTRIC works

Work in Progress

Detail Report
Graph / Photo
136 Road restoration of city side service road from Biharipur to Toll Tax at M B Road (Khajuri chowk to Sabhapur Village) cut by DJB under PWD Sub Division M-2134). 09/11/2019 06/02/2020 52.48 64.28 (Nov'20) 0.00 (Nov'20) Ravinder Kumar Detail Report
Graph / Photo
137 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2018-19 (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-21.) Re-call. 05/05/2018 29/01/2019 52.41 Rajnish Yadav Detail Report
Graph / Photo
138 Repair of footpath from Yamuna Vihar to Khajuri Chowk for making the proper accessibility for differently abled persons under sub division -2. 15/03/2019 13/05/2019 52.26 52.06 (Aug'20) 0.00 (Aug'20) Nirmit Construction Co. Work in progress. Detail Report
Graph / Photo
139 AR and MO to Various Roads under Sub Division NW R 11 PWD Division NW R 1 dg 2018 19 SH Comprehensive desilting of drains of various categories and sizes along PWD roads 09/03/2019 06/06/2019 52.14 Raj Associates Detail Report
Graph / Photo
140 SITC of 16 Meters LED High Mast and Street light with pole of height 08 Meters and 12 Meters at Nimri Colony road and various other locations under Wazirpur Constituency. 03/04/2019 02/07/2019 51.66 38.37 (Mar'20) 0.00 (Mar'20) M/s Shaka Electrical (India) 3RD RA BILL PAID RS. 1210060/- Detail Report
Graph / Photo
141 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Improvement of Central verge with Providing and Fixing MS Grill from Khajuri flyover to Signature Bridge under Sub Division 2). 10/06/2019 08/08/2019 51.54 60.99 (Oct'19) 0.00 (Oct'19) K P Singh & Co. Work in progress. Detail Report
Graph / Photo
142 Comprehensive Maintenance of PWD Roads under SRD Project Division-I, Sub-Division-II, PWD, New Delhi Dg. 2017-18 (SH- Misc. Repair Work) 27/07/2017 26/03/2018 51.05 0.00 (Mar'18) 63.64 % (Mar'18) Satyam Construction Company Work completed and final bill paid Detail Report
Graph / Photo
143 M/o Hort. Work at Khaira Road from Khaira More to Jhuljhuli More via Ghummenhera Village under Hort.Sub.Divn-South-II/South/PWD, New Delhi during 2019-20. SH: - Horticulture. Works. 07/10/2019 04/04/2020 50.61 Paras Enterprises WORK IN PROGRESS. Detail Report
Graph / Photo
144 Strengthening, Improvement of footpath, Providing and fixing Retro-reflective road signages horticulture work and upgradation of street lighting on Parwana Road, Delhi. (SH- Microsurfacing of Bituminous road.) 26/01/2019 25/04/2019 50.49 24.91 (Jul'19) 0.00 (Jul'19) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
145 Repair of footpath , central verge at various location and other Miscellaneous works under Sub Division-II, SWR-II, Najafgarh, New Delhi 01/09/2021 28/02/2022 50.17 Sirohi Construction Co Detail Report
Graph / Photo
146 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18. SH-Repair of road damaged during rainy season 30/11/2017 13/01/2018 49.61 Awasthi Construction WORK COMPLETED Detail Report
Graph / Photo
147 Repair of service road and footpath at EA road from Baba Shyam Giri Mandir to CISF Lady Hostel. 19/01/2019 19/03/2019 49.53 60.77 (Dec'19) 0.00 (Dec'19) M/s. Satyam Construction Work in progress. Detail Report
Graph / Photo
148 C/o drain from Mount Kailash Boundary to Kailash Colony Metro Station on Lala Lajpat Rai (Side of F Block) Road in GK-1 area under SER-2/23, PWD, New Delhi (Road ID- 969). 26/01/2021 25/04/2021 49.13 60.46 (Jul'21) 0.00 (Jul'21) Sirohi Construction Co Detail Report
Graph / Photo
149 Improvement of drain from Kalkaji Mandir to Govindpuri Metro Station on Shri Maa Anandmayee Marg under PWD Sub Division SER-2/21 during 2019-20. 02/01/2020 01/03/2020 48.96 43.90 (Aug'21) 0.00 (Aug'21) Jagdish Associates Detail Report
Graph / Photo
150 AR and MO to Various Roads PWD Division NW R 1 dg 2018 19 SH Desilting of drains of various roads of Shalimar Bagh area and Ring Road from Azadpur flyover to Punjabi Bagh flyover under Sub Division NW R 14 03/03/2019 31/05/2019 48.95 Sethi Construction Detail Report
Graph / Photo
151 AR and MO to Various Roads PWD Division NW R 1 dg 2018 19 SH Desilting of drains of various roads of Pitampura area and Road no 41 Wazirpur Depot to Madhuban chowk under Sub Division NW R 14 03/03/2019 31/05/2019 48.92 Sethi Construction Detail Report
Graph / Photo
152 A/R and M/O to various roads under PWD division NWR-2, during 2017-18.(SH - Providing and fixing signage boards on various roads under division NWR-2.) 14/12/2017 11/02/2018 48.65 S.N.I. INFRATECH PVT LTD Detail Report
Graph / Photo
153 Maint.Elect Con charg of St.Ltg.on PWD Rds under Zone M3(SH Day to day Maint.oprtn of EI LT Panel boards S/Stn.DG sets dewatering pumps on under pass/RUB at Lawrence Rd 1or 2 Zakhira main Tin Shed Ashok Vihr Prembari Pul vrs subwys FOBs undr Zone M3) 11/06/2019 10/06/2020 47.94 A K Electric Works FIRST RA BILL RS. 1660401/- WORK IN PROGRESS Detail Report
Graph / Photo
154 A/R & M/O other PWD Roads under SRD Division-I, PWD, New Delhi dg. 2018-19 (SH:- Repairing of Khari Baoli Road drainage and footpath from Church Mission Road to Naya Bazar under Sub Division-I.) 30/06/2019 29/09/2019 47.54 53.94 (Sep'20) 0.00 (Sep'20) TKN Developers Detail Report
Graph / Photo
155 A/R and M/O to various roads under PWD division NWR-2 during 2018-19. (SH- Dismantling of existing weaked one side drain slab and casting new with raising of footpath and drain etc on B-6 Road under Section-I, Sub Division NWR-23.) 15/09/2018 13/12/2018 47.03 27.49 (Sep'19) 0.00 (Sep'19) Laxman Detail Report
Graph / Photo
156 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Patch repair work at Loni Road, Road No. 68 and Road No. 65 under PWD Sub Division 4 for newly taken over roads under section-2). 11/07/2019 25/07/2019 47.01 57.38 (Dec'19) 0.00 (Dec'19) MAHAVIR PRASAD GUPTA AND SONS Work in progress. Detail Report
Graph / Photo
157 Road Restoration of Road No. 56 under Sub-division M-2111 cut by DJB 20/10/2019 18/12/2019 47.00 69.50 (Apr'21) 0.00 (Apr'21) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
158 AR and MO to Various Roads under Sub Division NW R 13 PWD Division NW R 1 dg 2018 19 SH Comprehensive desilting of drains of various categories and sizes along PWD roads 09/03/2019 06/06/2019 46.71 Raj Associates Detail Report
Graph / Photo
159 A/R and M/O to various roads under PWD Division NWR-2 during 2019-20 (SH- Providing and fixing of railings on central verge, footpath on Outer Ring Road from Pillar No. A02 to 30 of elevated Corridor, Delhi under Sub-Division NWR-25) 25/03/2019 23/05/2019 46.44 41.42 (Sep'19) 0.00 (Sep'19) Jitender Singh Detail Report
Graph / Photo
160 Comprehensive Maintenance of PWD Roads under SRD Project Division-I, Sub-Division-I, PWD, New Delhi Dg. 2017-18 (SH- Misc. Repair Work) 27/07/2017 26/01/2018 46.29 Satyam Construction Company Detail Report
Graph / Photo
161 Improvement of Drainage System and footpath along Rao Laxmi Chand Marg Road ID 1174 from Khaira morh to Khaira Village New Delhi 14/07/2018 10/11/2018 46.23 Bishwa Mohan Jha foreclosed Detail Report
Graph / Photo
162 Strengthening, Improvement of footpath, Providing and fixing Retro-reflective road signages and upgradation of street lighting of roads under Sector-14 in Rohini, Delhi. (SH- Microsurfacing of Bituminous road.) 26/01/2019 25/04/2019 46.22 46.88 (Jul'19) 0.00 (Jul'19) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
163 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of drains by chassis mounted high pressure suction cum jetting machine under Sub Division 4). 30/06/2019 28/08/2019 46.10 52.96 (May'20) 0.00 (May'20) Maan Builders Work in progress. Detail Report
Graph / Photo
164 Construction of RCC drain in front of Hauz Khas Enclave along Service Road on Sri Aurobindo Marg _ID_96_ under Sub Division_II of Division South Road_II PWD New Delhi during 2021_22 09/06/2021 08/10/2021 45.65 Samridhi Construction Detail Report
Graph / Photo
165 Providing and fixing stainless steel railing on footpath between Ram Charan Aggarwal Chowk to W Point Tilak Bridge under Sub Division- 3 of Division C and ND- Roads, New Delhi. 06/12/2018 05/02/2019 45.57 S S Chauhan & Sons Detail Report
Graph / Photo
166 Repair and renovation of subway and development of near by area and other Misc work balance work under Sub Division 2. 16/03/2019 14/05/2019 45.45 47.86 (Oct'19) 0.00 (Oct'19) Rajesh Kumar Gupta Work in progress. Detail Report
Graph / Photo
167 A/R and M/O Various Roads under Sub Division WR-13, Division WR-1, New Delhi dg. 2018-19. (SH- Repair and Maintenance of Drain and Footpath of Tilak Vihar Main Road and Drain (from ESIC office to Gurudwara Road) on 20-Block Tilak Nagar Road). 03/02/2019 02/06/2019 45.29 56.27 (Feb'20) 0.00 (Feb'20) S P Construction Detail Report
Graph / Photo
168 A/R and M/O PWD roads under Sub-Division-1, 2 and 3 of Division CandND-R dg 2017-18. SH_providing man power for day to day claening of footpath, side berms, main carriageway and central verge at various roads. 07/04/2018 05/10/2018 45.09 RAKSHAK SECURITAS PVT. LTD. Detail Report
Graph / Photo
169 AR and MO to Various Roads PWD Division NW R 1 dg 2018 19 SH Desilting of drains of various roads under Wazirpur Vidhan Sabha of Sub Division NW R 12 09/03/2019 06/06/2019 44.99 Nagendra and Company Detail Report
Graph / Photo
170 Repair and Maintenance of footpath /central verge and other misc. work on various roads of under Sub Division-21, SWR-II, PWD, New Delhi 01/09/2021 31/12/2021 44.84 Sirohi Construction Co Detail Report
Graph / Photo
171 A/R and M/O PWD Roads under Sub Division-1 of Division C and ND-Roads during 2018-19. SH_Patch repair of various roads. 27/10/2018 26/04/2019 44.36 7.30 (Jan'20) 0.00 (Jan'20) Nitin Kumar Sharma Detail Report
Graph / Photo
172 Ag. No. 35/HDM-314/PWD/14-15 27/08/2014 26/01/2015 44.28

work completed

Detail Report
Graph / Photo
173 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Improvement of Central verge with Providing and Fixing MS Grill from Maujpur Red light to Gokalpuri Red Light on Road No.-66 under Sub Division2 08/06/2019 06/08/2019 44.27 45.51 (Dec'19) 0.00 (Dec'19) K P Singh & Co. Work in progress. Detail Report
Graph / Photo
174 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of Road side drain of Road No. 63, Tanki Road, Yamuna Vihar Dividing Road and Yamuna Vihar Road (From C-1 to C-5)..... 27/06/2019 24/10/2019 44.19 76.59 (Aug'20) 0.00 (Aug'20) Vinod Kumar Work in progress. Detail Report
Graph / Photo
175 Providing services for special inspection, analysis of existing structure, conducting tests and preparation of remedial measures report including Bill of Quantities (BOQ) for Repair and Rehabilitation of ISBT flyover (Yudhister Setu) Delhi 05/10/2018 02/01/2019 44.00 M/s Projects Consulting India Pvt. Ltd

Work in Progress

Detail Report
Graph / Photo
176 AR and MO various Road under PWD Division South Road-1 Sub Division SR-11 during 2017-18. SH De-silting of drains by super sucker 09/04/2018 04/11/2018 43.85 Maan Builders

work completed

Detail Report
Graph / Photo
177 Providing security guards at Circle office (NE), Division Office (NE) Road, Sub Division M-2132 and M-2134 and enquiry office. 07/12/2019 05/12/2020 43.80 55.09 (Sep'21) 0.00 (Sep'21) Eagle Eye Security and House Keeping Services Detail Report
Graph / Photo
178 AR and MO TO VARIOUS ROADS UNDER SUB DIVISION NW R 14 PWD NW R 1 DURING 2017 18 SH IMPROVEMENT OF EXISTING DRAINAGE SYSTEM AND RAISING OF MAIN CARRIAGE WAY AND BERM PORTION NEAR DA STAFF QUARTERS AT MAIN HAIDERPUR ROAD 24/02/2018 24/04/2018 43.53 54.32 (May'19) 0.00 (May'19) Gaurav Construction Co. Detail Report
Graph / Photo
179 Road Restoration Cut by various agencies like DJB Transco and BSES at Palam dabri road under sub division I New Delhi 02/08/2019 30/09/2019 43.52 ASH NARAYAN SINGH work completed Detail Report
Graph / Photo
180 M/o Different Hort. Work at Ring Road Bypass, Belondron Road, Rajghat Red Light to Mangi Bridge (Ring Road), Kisan Ghat Road and different parks near Salim Garh Fort Islands under Hort. Sub Division (Central and New Delhi), Hort. Division (East), PWD. 30/05/2019 29/11/2019 43.26 61.78 (Nov'20) 0.00 (Nov'20) Rathore Contractor and Supplier Detail Report
Graph / Photo
181 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of Road No. 66 Moujpur Road, Brahmpuri road, Sewadham Road and Road No. 59 under Sub Division 2) Section-2. 30/06/2019 27/10/2019 43.24 46.96 (Aug'20) 0.00 (Aug'20) Vinod Kumar Work in progress. Detail Report
Graph / Photo
182 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2019-20. (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-24.) 14/04/2019 08/01/2020 43.22 41.76 (Sep'20) 0.00 (Sep'20) Anmol Infratech Private Limited Detail Report
Graph / Photo
183 A/R and M/O to various roads under PWD Division NWR-2 during 2017-18 (SH- Providing and fixing M.S.Railing on Maharaja Agarsen Marg (42A), Deepali Chowk to Vijay Vihar, Delhi under Sub Division NWR-21.) 13/04/2018 11/06/2018 43.21 Sanjay Kaura Detail Report
Graph / Photo
184 Comprehensive Maintenance of PWD Roads under SRD Project Division-I, Sub-Division-II, PWD, New Delhi Dg. 2018-19 (SH-Misc. Repair Work) 29/05/2018 28/11/2018 43.21 0.00 (Apr'19) 106.58 % (Apr'19) Satyam Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
185 M/o Different Hort. Work at Ring Road Bhairon Road T point to Rajghat Red light around I.G. Stadium, Delhi Sachivalaya Road and Vikas Marg Islands under Hort. Sub Division (Central and New Delhi), Hort. Division (East), PWD, Delhi during 2019-20 06/06/2019 05/11/2019 43.13 23.72 (Aug'20) 0.00 (Aug'20) PLANTS CARE Detail Report
Graph / Photo
186 M/o Hort. works of different roads under Hort. Division (Central and New Delhi), Hort. Division (East), PWD, Delhi during 2019-20. SH-Complete maintenance of roads from Hanuman Setu ISBT to Kingsway Camp Chowk, Ring Road, Chandgi Ram Akhada to Wazira 05/08/2019 04/02/2020 43.08 46.92 (Aug'20) 0.00 (Aug'20) Raj KumarSaini Detail Report
Graph / Photo
187 Providing and Laying of paver blocks, raising of drain and repairing of footpath at Goyla Dairy and other misc. work under sub division-25 19/08/2021 16/12/2021 42.91 Sirohi Constructon Company Detail Report
Graph / Photo
188 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2019-20 (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-23.) 14/04/2019 08/01/2020 42.76 46.95 (Sep'20) 0.00 (Sep'20) Anmol Infratech Private Limited Detail Report
Graph / Photo
189 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2019-20 (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-22.) 14/04/2019 08/01/2020 42.60 Anmol Infratech Private Limited Detail Report
Graph / Photo
190 Repair of footpath of river side at MB Road Shastri Park to 3.5 Pusta for making the proper accessibility for differently abled persons under Sub Division-4). 30/01/2019 30/03/2019 42.52 43.66 (Oct'19) 0.00 (Oct'19) Ramesh Chand Work in progress Detail Report
Graph / Photo
191 Providing Services of Computer Operators, Clerk and MTS Multi Tasking Staff in PWD North West Electrical Maintenance Division, S 28/06/2021 27/06/2022 42.43 M/s Sona Engineers Detail Report
Graph / Photo
192 A/R and M/O PWD Roads under Sub Division-3 of Division C and ND-Roads during 2018-19. SH_Patch repair on various roads. 27/10/2018 26/04/2019 42.08 18.96 (Jul'19) 0.00 (Jul'19) National Builders Detail Report
Graph / Photo
193 Restoration of Roads under Sub Division M-2114 during 2019-20 cut by various agencies. (Recall) 10/12/2019 09/12/2020 41.87 40.25 (Nov'20) 0.00 (Nov'20) Shekhar FINAL BILL UNDER PROCESS IN SUB-DIVISION OFFICE Detail Report
Graph / Photo
194 Maintenance of Hort. works under Section-I, HSD (East), HD (East), PWD, GNCTD, Delhi dg 2018-19 03/08/2018 02/08/2019 41.82 20.59 (Sep'19) 0.00 (Sep'19) Raj KumarSaini Detail Report
Graph / Photo
195 Upgradation of Street Light from GK-2 to Alaknanda Market at Savitri Cinema PWD Road under PWD South East New Delhi 18/05/2017 17/09/2017 41.43 Sona Engineers Detail Report
Graph / Photo
196 A/R and M/O Various Roads under Sub. Div. East Road-IV of Division East Road (M-212), PWD dg. 2019-20. 18/05/2019 17/05/2020 41.25 45.99 (Jul'20) 0.00 (Jul'20) RAKSHAK SECURITAS PVT. LTD.

Work in progress

Detail Report
Graph / Photo
197 Construction of missing drain with footpath (LHS) and repair of footpath (RHS) at Burari Road from Radio Colony to Nirankari Colony gate. 06/03/2019 05/06/2019 41.21 0.93 (Jan'20) 0.00 (Jan'20) Satyam Construction Co. Detail Report
Graph / Photo
198 AR and MO to Various Roads under Sub Division NW R 13 PWD Division NW R 1 dg 2018 19 SH Comprehensive desilting of drains of various categories and sizes along PWD roads 05/04/2018 02/10/2018 40.82 Shiv Shakti Enterprises Detail Report
Graph / Photo
199 A/R and M/O Various Roads under Sub Division WR-13, Division WR-I, New Delhi during 2018-19. (SH Re-development of Parking area of Sub Division office and stackyard on Outer Ring Road near Keshopur Depot.) 08/03/2019 07/08/2019 40.74 50.83 (Sep'20) 0.00 (Sep'20) Nand Kishore Yadav Detail Report
Graph / Photo
200 Providing Service of Data Entry/Computer Operators and Peon for Division office and Sub. Division offices 29/04/2018 28/04/2019 40.68 20.96 (Jul'20) 0.00 (Jul'20) RAKSHAK SECURITAS PVT. LTD.

Work in progress

Detail Report
Graph / Photo
201 A/R and M/O Various road under sub Division WR-14, Division- WR-I, New Delhi during 2018-19. (SH Comprehensive desilting of drains by mechanical/manual means of various categories and sizes along PWD roads.) 08/03/2019 03/09/2019 40.33 41.28 (Sep'20) 0.00 (Sep'20) WORK CEE work in progress Detail Report
Graph / Photo
202 Comprehensive Maintenance of Bandh Road and Dera Bhatti Road 31/10/2019 30/10/2020 40.19 49.14 (Aug'21) 0.00 (Aug'21) Samridhi Construction Detail Report
Graph / Photo
203 AR and MO VARIOUS ROADS OF PWD UNDER NW R 1 DG 2017 18 SH REPAIR OF TILE WORK AT UNDERPASS MADHUBAN CHOWK UNDER DIVISION R 1 SUB DIVISION NW R 15 2nd Call 05/07/2018 05/09/2018 40.14 Pawan Kumar Gupta Work forclosed Detail Report
Graph / Photo
204 Road Restoration work of Road cut by the DTL on Outer Ring Road and 235 extn. road under Sub-Division WR13, Division WR-1, New Delhi (ID 201810151443151) 30/06/2019 29/11/2019 40.13 44.71 (Aug'20) 0.00 (Aug'20) ASH NARAYAN SINGH work in progress Detail Report
Graph / Photo
205 Strengthening, Providing and fixing Retro-reflective road signages and upgradation of street lighting on roads Hans Raj Marg, Guru Virja Nand Marg and M-2K Sant Nagar, Delhi under PWD Maintenance Zone M-3 (SH- Microsurfacing of Bituminous road.) 10/03/2019 07/06/2019 39.91 Pawan Kumar Detail Report
Graph / Photo
206 (SH- Maintenance and Operation of DG Sets, Pumps, Motors and all other E and M accessories). 15/01/2019 14/01/2020 39.81 54.68 (Nov'20) 0.00 (Nov'20) ANAND ELECTRICALS Detail Report
Graph / Photo
207 Construction of RCC Box drain from DDA Park to Sai Mandir and under Nangli Metro Station at Najafgarh kakrola Road under Sub Division-II, SWR-II, Najafgarh New Delhi 07/10/2021 20/11/2021 39.76 M/s DA Construction Co. Detail Report
Graph / Photo
208 Pdg services for Spl insp analysis of existing structure conducting tests and prep of remedial measures report incl BOQ for Repair and Rehab. of (i) Lodhi Road Intersection flyover (ii) Oberoi Hotel Intersection flyover (iii) Chirag Delhi flyover. 05/10/2018 24/12/2018 39.75 M/s Projects Consulting India Pvt. Ltd

Work in Progress

Detail Report
Graph / Photo
209 A/R & M/O various road under Shahdara Road Division during 2019-20.(SH: Providing services of Computer Operator ,Clerical staff & MTS for offices under Shahdara Circle (M) and Shahdara Road Division.). 01/06/2020 31/05/2021 39.73 50.63 (Aug'21) 0.00 (Aug'21) TRENDY SECURITY SERVICES work in progress Detail Report
Graph / Photo
210 A/R & M/O Various roads under Sub Division WR-15, Division WR-1, New Delhi dg. 2018-19. (SH: Installation of Gantry Board on miscellaneous location under Rajouri garden Constituency Sec-II.) 07/01/2019 06/04/2019 39.70 48.99 (Nov'20) 0.00 (Nov'20) Sethi Construction WORK IN PROGRESS Detail Report
Graph / Photo
211 Providing jersy barrier and other misc. repair work for toe wall along the pitching at MB Road city side service road from Khajuri chowk to PR Vatika under. 28/02/2019 28/04/2019 39.41 44.99 (Dec'19) 0.00 (Dec'19) M/s B.M. & Sons Work in progress. Detail Report
Graph / Photo
212 Change of faulty and undersize cable of street light of Burari Road and BBM Road 07/11/2020 06/02/2021 39.41 16.00 (Mar'21) 0.00 (Mar'21) BHAGWAT ASSOCIATES

Work in Progress

Detail Report
Graph / Photo
213 AR and MO to Various Roads under Sub Division NWR 11 PWD Division NWR 1 dg 2018 19 SH Comprehensive desilting of drains of various categories and sizes along PWD roads SECOND CALL 28/04/2018 24/10/2018 39.35 Sanjay Kaura Detail Report
Graph / Photo
214 Providing and fixing Grass Grids of road side berms near Smriti Sthal Ring Road under Sub Division 3 of Division C and ND - Roads, New Delhi. 06/03/2019 05/05/2019 39.32 45.87 (Oct'19) 0.00 (Oct'19) Aditya Construction Detail Report
Graph / Photo
215 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2018-19 (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under Sub Division NWR-23.) 29/03/2018 23/12/2018 39.08 WORK CEE Detail Report
Graph / Photo
216 Patch repair work at Road No. 65 from Jafrabad Metro Station to Keshav Chowk under PWD Sub Division M-4. 06/10/2019 19/11/2019 39.07 43.59 (Feb'20) 0.00 (Feb'20) Pawan Kumar Detail Report
Graph / Photo
217 AR and MO various road under PWD Division South Road-1 Sub Division SR-14 during 2017-18. SH Improvement of road side drain and berms near outer ring road at Apeejay School Road Seikh Sarai Ph-1 14/07/2017 12/08/2017 38.93 Samridhi Construction

work completed

Detail Report
Graph / Photo
218 A/R & M/O to various roads under CRMSD M-4421of CRMD M-442 during 2014-15 (SH: General Upkeep). 24/01/2015 23/05/2015 38.76 Bhawani Constructions Detail Report
Graph / Photo
219 A/R and M/O to various Roads under division NWR-2, during 2019-20. SH- Providing services of Outsourcing staff in Division NWR-2, Sub Division NWR-21, Sub Division NWR-22, Sub Division NWR-23, Sub Division NWR-24 and Honble PWD Ministes Office. 01/07/2019 06/07/2019 38.36 20.64 (Aug'20) 0.00 (Aug'20) MANOMAY Detail Report
Graph / Photo
220 AR and MO to Various Roads under Sub Division NWR 12, PWD Division NW R 1 dg 2018 19 SH Comprehensive desilting of drains of various categories and sizes along PWD roads 05/04/2018 02/10/2018 38.33 shiv shakti construction Detail Report
Graph / Photo
221 Improvement of inner roads of Navsena Apartment at Road No.43 near Anukampa Chowk, Pitampura, Delhi. 27/06/2019 24/10/2019 38.00 26.18 (Dec'19) 0.00 (Dec'19) S. S. ENTERPRISES Detail Report
Graph / Photo
222 MOEI, Pump, Lifts of Subway, Under Deck and FOB on Delhi PWD Roads under PWD Electrical Division South during 2018-19. (SH-Operation of lifts). 05/02/2019 04/02/2020 38.00 32.33 (May'20) 0.00 (May'20) KAUSHIK DIESEL GENERATOR Detail Report
Graph / Photo
223 D/o Horticulture Land scaping work at Mayur Vihar, New Delhi, Barapullah Phase-III 22/07/2021 18/11/2022 37.99 Pioneer Horticulturist Pvt. Ltd Detail Report
Graph / Photo
224 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Desilting of Road side Drain at Gamri Road, service road of M.B. Road and Service Road Eastern Approach Road, Seelampur Road, 30/06/2019 27/10/2019 37.83 53.28 (Nov'20) 0.00 (Nov'20) Sharma Construction Co. Work in progress. Detail Report
Graph / Photo
225 Providing and laying Stone Matrix Asphalt (SMA), under Sub Div-21 of SWR-II PWD New Delhi 07/09/2021 06/10/2021 37.81 RK Brothers and Co Detail Report
Graph / Photo
226 A/RandM/O PWD Roads under Sub Division 2 of Division CandND Roads during 2018-19 SH Desilting and cleaning of road side storm water drains. 20/02/2019 19/08/2019 37.67 63.86 (Sep'20) 0.00 (Sep'20) M/s K.P Singh & Co. Detail Report
Graph / Photo
227 A/R and M/O to various roads under PWD Sub Division M-2132 dg. 2017-18. (SH- Repair of service road from Gagan T-Point to Nand Nagri Flyover). 05/04/2018 04/05/2018 37.50 Pawan Kumar cancelled Detail Report
Graph / Photo
228 Maintenance of Trees, Shrubs and Hedge. 07/03/2019 06/03/2020 37.36 Raj KumarSaini Detail Report
Graph / Photo
229 Repair and Restoration of drain from Kapashera Chowk to Cosmos Farm and provide facilities of footpath above drain (both sides) on Kapashera Bijwasan drain 24/09/2021 23/12/2021 37.23 ASHWINI KUMAR PANDEY Detail Report
Graph / Photo
230 A/R and M/O PWD Roads under Division C and ND Roads during 2018-19. SH_Mechanized Potholes Repairs on various Bituminous Roads. 08/02/2019 07/02/2020 36.86 Y D Builders and hotels pvt. ltd Detail Report
Graph / Photo
231 Maintenance and Electrical Consumption Charges of Street Light under Central and New Delhi Zone during 2019-20 13/01/2020 12/01/2021 36.63 41.44 (Aug'21) 0.00 (Aug'21) Stallion Security and Services

Work in Progress

Detail Report
Graph / Photo
232 Patch repair work at various locations under Sub Division -III, New Delhi 30/09/2021 29/10/2021 36.61 Nirmit Construction Co. Detail Report
Graph / Photo
233 A/R and M/O Various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Road Marking Work in Ballimaran and Sadar Bazar Constituencies 01/12/2017 28/02/2018 36.55 Manish Chandak Work Completed Detail Report
Graph / Photo
234 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Provision of Maintenance Van with required labour with T and P to attend day to day maintenance under Karol Bagh Constituency. 07/10/2017 28/09/2018 36.54 9.09 (Jun'19) 0.00 (Jun'19) Zahid Hussain (B-26) Work completed Detail Report
Graph / Photo
235 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Providing of protection wall and other civil repair work at Gari Mendu Road under Sub Division 4). 10/06/2019 09/07/2019 36.48 45.86 (Aug'21) 0.00 (Aug'21) Sandeep Kumar Work in progress. Detail Report
Graph / Photo
236 AR and MO VARIOUS ROADS OF PWD DIVISION NW R 1 UNDER SUB DIVISION NW R 13 DURING 17 18 SH RAISING OF CENTRAL VERGE AT ROAD NO 40(ID : 26744) 26/06/2017 23/09/2017 36.16 Globe Builders Detail Report
Graph / Photo
237 Reconstruction of damaged drain from TCL Building to Pamposh footover bridge including beautification and repair of subway near Masjid Moth on Outer Ring Road under the jurisdiction of division SER-2 25/05/2021 22/08/2021 36.11 50.00 (Sep'21) 0.00 (Sep'21) S. S. Chauhan & Sons Detail Report
Graph / Photo
238 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Repairing of road surface between Bank Colony red light and Nand Nagri red Light under sub division-2). 07/06/2019 06/07/2019 35.76 42.88 (Oct'19) 0.00 (Oct'19) Pawan Kumar Work in progress. Detail Report
Graph / Photo
239 Operation and Maintenance of sewage/storm water pumps, DG sets at Vrs. location under PWD M-251. (SH- Desilting by super sucker machine/Removing of floating material of Sumps at various pump houses in Trans Yamuna area) 02/03/2019 01/05/2019 35.49 44.35 (Oct'19) 0.00 (Oct'19) Krishna Electrical works Detail Report
Graph / Photo
240 Strengthening, Improvement of footpath and providing and fixing retro-reflective road signages and upgradation of street lighting on road under Sector-11, Rohini, Delhi. (SH- Microsurfacing of Bituminous road.) 26/01/2019 25/04/2019 35.39 28.71 (Sep'19) 0.00 (Sep'19) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
241 A/R and M/O various roads under SRD Division-I, Sub-Division-II, PWD, New Delhi, dg. 2018-19. (SH-Providing and laying Ductile Iron pipe line near Zakir Hussain College at J.L.N. Marg, New Delhi to avoid flooding at JLN Marg). 13/10/2018 12/12/2018 35.33 43.45 (Sep'19) 0.00 (Sep'19) M/s. Satyam Construction Work in progress Detail Report
Graph / Photo
242 Repair of footpath , central verge at various location and other Miscellaneous works under Sub Division-II, SWR-II, Najafgarh, New Delhi 06/08/2021 05/02/2022 35.10 Vinita Enterprises Detail Report
Graph / Photo
243 Strengthening, Improvement of footpath and providing and fixing retro-reflective road signages on road from pocket A-1 to F-3 and road from pocket F-3 to H-4 in sector-11, Rohini, Delhi . (SH- Microsurfacing of Bituminous road.) 26/01/2019 25/04/2019 34.94 25.45 (Jul'19) 0.00 (Jul'19) Mahavir Parsad Gupta & Sons Detail Report
Graph / Photo
244 Road Restoration charge for the work of P/L water supply network, sewer line and cable network in Mayur Vihar Phase-III and Ghazipur dairy farm in Section-I of PWD Sub-Division East Road-II. 14/01/2019 14/03/2019 34.91 44.46 (Jul'20) 0.00 (Jul'20) Dinesh Chand Sharma

Work in progress

Detail Report
Graph / Photo
245 Renovation of Workshop (WS-1) 1st floor (Mezzanine Floor) to provide space for Studio-III for DAP at IGDTUW, Kashmere Gate under SRD Division- I, Sub-Division-III, PWD, New Delhi. (SH-Civil works and Electrical works). 14/07/2018 13/10/2018 34.69 0.00 (Apr'19) 43.14 % (Apr'19) K.P. Singh & Co. Work Completed and final bill paid Detail Report
Graph / Photo
246 Lowering of carriageway at Tripolia Gate near Jain Colony on G.T. Road, New Delhi 08/12/2018 07/02/2019 34.65 43.32 (Jul'19) 0.00 (Jul'19) Ashok Kumar Rathi Detail Report
Graph / Photo
247 Complete maintenance of work 20/04/2018 19/04/2019 34.56 RAVINDRA SINGH Detail Report
Graph / Photo
248 Painting and other Miscellaneous works under Sub Division-III, SWR-II, , New Delhi 15/09/2021 14/03/2022 34.38 Surender Singh Detail Report
Graph / Photo
249 Strengthening of Road no.43 (Guru Harkishan Marg) from Britania Chowk Light to Outer Ring road at West Enclave, Delhi.(SH- Microsurfacing of Bituminous road.) 10/03/2019 07/06/2019 34.31 Pawan Kumar Detail Report
Graph / Photo
250 A/R and M/O to various roads under PWD division NWR-2 during 2017-18.(SH- Providing crash barrier at Parshuram Marg, Sector-6 and 7 dividing road, Rohini, Delhi under Sub Division NWR-22.) 22/02/2018 22/04/2018 34.25 Suraj Associates Detail Report
Graph / Photo
251 A/R and M/O to various roads under PWD Division NWR-2 during 2017-18 (SH- Repair of SW drain of Parwana Road near Dera Gajhi Khan Jhuggi camp and Road No.43, Pitampura under Sub Division NWR-24.) 04/01/2018 04/03/2018 34.09 Sanjay Kaura Detail Report
Graph / Photo
252 A/R and M/O PWD Roads under Sub Division-3 of Division CandND Roads during 2018-19. Sub-Head Urgent repair work on Ring Road from I.P. Metro Station to Shantivan BZM Marg I.P. Marg Vikas Marg etc. 17/09/2018 16/11/2018 33.96 3.80 (May'19) 0.00 (May'19) Paras Nath Singh Detail Report
Graph / Photo
253 AR and MO VARIOUS ROADS OF PWD UNDER NW R 1 DG 2017 18 SH PROVIDING AND FIXING STEEL RAILING AT OUTER RING ROAD UNDER SUB DIVISION NW R 15 28/01/2018 28/03/2018 33.94 Gaurav Construction Co. Detail Report
Graph / Photo
254 SH_Thermoplastic paint, providing and fixing road furniture safety item on various roads. 21/12/2018 20/02/2019 33.91 0.08 (May'19) 0.00 (May'19) Aditya Construction Detail Report
Graph / Photo
255 Repairing of 30 Meter High Mast. 03/05/2019 02/07/2019 33.76 Dev Engineers Detail Report
Graph / Photo
256 Installation of Gantry and DSM signange boards on various locations to change the name from Ghanta Ghar to Shaheed Pawan Sahani Chowk under WR 11 and installation of boards in Ashok Nagar Area 31/03/2021 30/07/2021 33.67 Upendra Singh Detail Report
Graph / Photo
257 Construction of sump well, drain and providing pipe line near loni gole chakker fire station at Loni Road under PWD Sub Division M-2134 17/10/2019 15/12/2019 33.52 41.58 (Sep'21) 0.00 (Sep'21) Sandeep Kumar Detail Report
Graph / Photo
258 A/R & M/O various road under Shahdara Road Division during 2020-21.(SH: Providing Services of Security Guard for watch & ward in the office of PWD Division Shahdara Road office Sub -Division M-2111,M-2112, M-2113 & M-2114.). 01/06/2020 31/05/2021 33.46 12.46 (Apr'21) 0.00 (Apr'21) Stallion Security WORK RESCIND UNDER CLAUSE 3. Detail Report
Graph / Photo
259 Painting and repair of FOBs near Yamuna Vihar C-Block, Ambedkar College, T.R. Sahawney and Bhopura Border under Sub Division 2. 06/10/2019 04/12/2019 33.23 37.08 (Nov'20) 0.00 (Nov'20) M. I. Builder Detail Report
Graph / Photo
260 AR TO MO TO VARIOUS ROADS UNDER PWD DIVISION NWR 1 DELHI DURING 2018 19 SH REPAIRING/REPLACEMENT OF DAMAGED MISSED RAILINGS AND CENTRAL VERGE AT MAHARAJA AGGRASEN MARG AND GOPAL MANDIR MARG UNDER SUB DIVISION NW R 14 13/02/2019 13/04/2019 33.03 Sethi Construction Detail Report
Graph / Photo
261 RECARPETING OF SERVICE ROADS OF ROAD NO 37 INDERLOK TO KESHAVPURAM RED LIGHT UNDER NW R 1 AND SUB DIVISION NW R 12 13/02/2019 13/04/2019 32.93 Awasthi Construction Detail Report
Graph / Photo
262 A/R and M/O to various Roads under division NWR-2, during 2018-19. (SH- Providing services of Outsourcing staff in Division NWR-2, Sub Division NWR-21, Sub Division NWR-22, Sub Division NWR-23, Sub Division NWR-24 and Honble PWD Ministers Office.) 28/06/2018 27/06/2019 32.86 40.52 (Nov'19) 0.00 (Nov'19) HARSHIDHI SECURITY SERVICES Detail Report
Graph / Photo
263 Providing & fixing Retro Reflective Signage Boards on various roads under SRD Project Division-I, Sub Division-I, PWD New Delhi. 07/01/2018 06/03/2018 32.80 Fiberfill Engineer Work Completed and final bill paid Detail Report
Graph / Photo
264 Removing vegetation weets at berm portion and providing CC pavements in berm portion near Jharoda Border Police Post, under Sub Division-II, SWR-II, Najafgarh New Delhi 15/09/2021 29/10/2021 32.64 Surender Singh Detail Report
Graph / Photo
265 A/R and M/O Various Roads under Project Circle, SRD Division-I, PWD, New Delhi dg. 18-19 (SH-Security Guards for various offices under Project Circle PWD, Govt., of Delhi.) 07/08/2018 06/08/2019 32.44 37.23 (Dec'20) 0.00 (Dec'20) VIHANGAM SECURITY SERVICES PVT LTD Work in progress Detail Report
Graph / Photo
266 Road and Footpath Restoration work at Lal Sai Marg, Pankha Road, Dabri Road etc. Cut by BSES, DTL, and other telecom agencies under Sub Division WR-12, Division WR-1, PWD, New Delhi 24/06/2019 23/08/2019 32.40 40.28 (Aug'20) 0.00 (Aug'20) ASH NARAYAN SINGH work in progress Detail Report
Graph / Photo
267 Remodling of existing drain at Road No. 42-A Naharpur Side 02/06/2015 31/07/2015 32.33 6.24 (Dec'19) 90.00 % (Dec'19) Satya Narain work in progress Detail Report
Graph / Photo
268 Misc. Repair works. 05/09/2016 03/12/2016 32.09 0.00 (Aug'16) 0.10 % (Aug'16) Raj Associates work in progress Detail Report
Graph / Photo
269 Construction of Brick Drain on Slip Roads under Hanuman Setu and improvement of footpath, kerb channel, bell mouth etc. under Sub Division-3 of Division C and ND- Roads, New Delhi. 28/01/2019 27/04/2019 31.78 37.33 (Dec'19) 0.00 (Dec'19) Aliyan Constaruction Company Detail Report
Graph / Photo
270 Repair of footpath of LIG Road and bituminous work LIG and MIG Road under PWD Sub Division M-2134. 15/10/2019 13/12/2019 31.68 11.09 (Dec'19) 0.00 (Dec'19) Pawan Kumar Detail Report
Graph / Photo
271 A/R and M/O PWD Roads under Sub Division-1 of Division C and ND-R during 2018-19. SH_ Repairing of various roads. 24/01/2019 23/04/2019 31.48 33.16 (Jun'19) 0.00 (Jun'19) Aditya Construction Detail Report
Graph / Photo
272 A/R & M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH:- Arrangement of sewerman along with required T&P for cleaning of the drain, sump i/c disposal of floating malba etc on day to day basis at Road No. 63,Tanki Road , Yamuna Vihar Dividing Road & Yamuna Vihar Road (From C-1 to C-5), Loni road (Loni Gole Chakkar to U P Border), Gokalpuri Road, Noor-E-Ilahi road, Road No. 66, Moujpur Road, Brahmpuri road, Sewadham Road and Road No. 59 under Sub Division 2). 15/09/2019 12/03/2020 31.46 14.18 (Dec'19) 0.00 (Dec'19) RAM KUMAR SHARMA Detail Report
Graph / Photo
273 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Improvement of Central verge with Providing and Fixing MS Grill from Bhopura Border to Gagan T-Point on Road No. 63 under Sub Division 2) - 2nd Call 10/06/2019 08/08/2019 31.45 39.16 (Oct'19) 0.00 (Oct'19) Surender Singh Work in progress. Detail Report
Graph / Photo
274 Repair and Maintenance of footpath /central verge and other misc. work on various roads of under Sub Division-21, SWR-II, PWD, New Delhi 06/08/2021 05/12/2021 31.36 Vinita Enterprises Detail Report
Graph / Photo
275 M/o different Hort. works under Hort. Sub Division (C and ND), Hort. Divn. (East), PWD, Delhi dg 2018-19 26/10/2018 25/10/2019 31.17 17.52 (Sep'19) 0.00 (Sep'19) Shivam Enterprises Detail Report
Graph / Photo
276 Up-gradation of street light on PWD Roads recently Taken over from MCD (1) Dharm Appartment to Sabdhavana Apartment near narwana road Patparganj Delhi (2) Services road from Jhilmil metro station to Dilshad garden metro station road via chintamani restror (3) Vivek Vihar Road (from arya samaj mandir to PNT Colony (4) baburam School Delhi. 02/07/2017 01/09/2017 31.12 4.08 (Nov'20) 0.00 (Nov'20) Sona Engineers Detail Report
Graph / Photo
277 Road Restoration of various roads cut by various agency for laying of services under Section-I, Sub Division-I, East Road M-212 Delhi 27/02/2019 28/03/2019 31.01 32.85 (Jun'21) 0.00 (Jun'21) A S INFRATECH

Work in progress

Detail Report
Graph / Photo
278 A/R & M/O various road under Shahdara Road Division during 2020-21. (SH: Providing Services of Security Guard for watch & ward in the office of PWD Division Shahdara Road office Sub -Division M-2111,M-2112,M-2113 & M-2114.) (Balance work). IIIrd Call. 25/02/2021 07/10/2021 30.94 12.65 (Jul'21) 0.00 (Jul'21) Rakshak Securitas Pvt. Ltd. work in progress Detail Report
Graph / Photo
279 AR and MO VARIOUS ROADS OF PWD UNDER NW R 1 DG 2017 18 SH REPAIR OF TILE WORK AT UNDERPASS MADHUBAN CHOWK UNDER DIVISION R 1 SUB DIVISION NW R 15 02/04/2018 01/07/2018 30.81 Shiv Shakti Enterprises Detail Report
Graph / Photo
280 A/R and M/O PWD Roads under Sub-Division-3 of Division C and ND Roads during 2018-19. SH_Repair of drainage system, dwarf wall, footpath, making table top and other miscellaneous work, between Kisan Ghat Road to Shantivan Xing. 09/11/2018 08/01/2019 30.68 19.04 (Nov'19) 0.00 (Nov'19) BASAU CONSTRUCTION (INDIA) Detail Report
Graph / Photo
281 AR and MO to various road under PWD Division SWR II Sub Division III dg. 2019 20. SH Providing and Fixing Signages work in Sub Division III under AC 34 Matiala. 03/09/2019 17/10/2019 30.65 Anil Engineering Works WORK IN PROGRESS Detail Report
Graph / Photo
282 A/R and M/O PWD Roads under Sub Division 3 of Division CandND Roads during 2018 19. Sub Head Repair of footpath on court road under Hill Road and Raj Niwas Marg and Making disabled footpath friendly and other Miscellaneous work. 25/05/2018 24/08/2018 30.61 10.58 (Aug'19) 0.00 (Aug'19) Ram Singh Detail Report
Graph / Photo
283 A/R and M/O various Roads under SRD Project Sub-Division-III/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Repair of C.C. Kerb Channel and space between carriage way and footpath. 30/01/2018 29/05/2018 30.40 Rajesh Gupta (Rohini) Work Completed Detail Report
Graph / Photo
284 Providing and fixing paver blocks and laying C.C. in the road Side / Berm for Hard Paving to reduce the dust pollution in Jahangirpuri Hot Spot area under Sub-Division NR-14, Delhi 09/06/2020 08/07/2020 30.35 Samridhi Construction Work in progress and 80% work completed Detail Report
Graph / Photo
285 Providing and Fixing Jersey Barrier in central verge at Sameer Bhan Marg from Dharamshilla Cancer Hospital upto Mod Appartment. 07/03/2019 05/05/2019 30.28 5.82 (Jan'20) 0.00 (Jan'20) Bansal Construction Co

Work in progress

Detail Report
Graph / Photo
286 A/R and M/O to various roads under PWD Sub Division M-2132 dg. 2017-18. (SH- Repair of road surface from outer ring road to Wazirabad Bridge on Road No. 59). 05/04/2018 04/05/2018 30.21 Pawan Kumar Cancelled Detail Report
Graph / Photo
287 A/R and M/O Various road under sub Division WR-13, Division- WR-I, New Delhi during 2018-19. (SH Comprehensive desilting of drains by mechanical/manual means of various categories and sizes along PWD roads.) 08/03/2019 03/09/2019 30.19 WORK CEE WORK IN PROGRESS Detail Report
Graph / Photo
288 A/R and M/O Various road under sub Division WR-15, Division- WR-I, New Delhi during 2018-19. (SH Comprehensive desilting of drains by mechanical/manual means of various categories and sizes along PWD roads.) 08/03/2019 03/09/2019 30.08 WORK CEE Detail Report
Graph / Photo
289 Providing and fixing of steel grill in the central verge at Kushal Cinema Road under Sub Division NR-11 29/05/2020 12/07/2020 30.08 Sethi Construction Work in progress and 25% work completed Detail Report
Graph / Photo
290 Maint.and Elect.Conp.charges of st.Ltg.at vrs.rds under PWDNWED(SH SITC of 8Mtrs.Height GI Octagonal St.Lt.poles at Eklavya Marg,16Mtrs.High Mast and Shifting of existing 10Mtrs.Height poles against accidental poles vrs.rds Shakurpur Constituency,Del 03/04/2019 02/06/2019 29.93 7.78 (Mar'19) 30.00 % (Mar'19) M/s Shaka Electrical (India) 2ND RA BILL PAID RS.2212451/- WORK IN PROGRESS Detail Report
Graph / Photo
291 (SH Desilting by super sucker machine/removing of floating material of sumps at various pump houses in Trans Yamuna area ) 30/06/2017 29/10/2017 29.81 Ram Charan Bansal Detail Report
Graph / Photo
292 AR and MO TO VARIOUS ROAD UNDER PWD DIVISION NW R 1 DURING 2017 18 SH COMPREHENSIVE MAINTENANCE OF FOOTPATH UNDER SUB DIVISION NW R 14 08/11/2017 06/05/2018 29.81 Sujan Singh Detail Report
Graph / Photo
293 A/R and M/O to various roads under sub division NWR-21, PWD Division NWR-2 dg. 2017-18. (SH- Repair of drain, footpath at Jagdamba Road, Sultanpuri, Delhi.) 24/02/2018 24/05/2018 29.79 Sanjay Kaura Detail Report
Graph / Photo
294 AR and MO TO VARIOUS ROADS UNDER PWD DIVISION NW R 1 DELHI DURING 2018 19 SH MISC REPAIR WORKS OF VARIOUS ROADS OF SHALIMAR BAGH AREA UNDER SUB DIVISION NW R 14. 20/02/2019 20/05/2019 29.75 Sethi Construction Detail Report
Graph / Photo
295 ROAD RESTORATION WORK ON VARIOUS ROAD UNDER PWD DIVISION NORTH WEST ROAD 1 SUB DIVISION NW R 13 DURING 2017 18 08/11/2017 06/05/2018 29.61 Pawan Kumar Gupta Detail Report
Graph / Photo
296 Road Restoration cut by Delhi Jal Board (DJB) from Chhawla Stand to Chhawla Police Station (Najafgarh - Bijwasan road) under Sub Division -25, SWR-II PWD, New Delhi 24/09/2021 23/10/2021 29.56 ashok builders Detail Report
Graph / Photo
297 Removal of malba & disposal at approved MCD dumping ground. 09/07/2015 08/07/2016 29.55 0.00 (Aug'16) 33.00 % (Aug'16) Sanjay Kaura work in progress,Provisional EOT granted upto 30.09.2016. Detail Report
Graph / Photo
298 Restoration of Sri Aurobindo Marg (PTS Red light to Yusuf Sarai FOB) and other various roads under Sub. Div.-II of Division South Road-II, PWD, New Delhi dg. 2020-21. 03/08/2020 02/11/2020 29.45 35.80 (Aug'21) 0.00 (Aug'21) Puneet Sehrawat Work in Progress Detail Report
Graph / Photo
299 Shifting of street light poles NVT Marg and Sant Kripal Marg Road 05/12/2020 04/03/2021 29.36 25.15 (Jun'21) 0.00 (Jun'21) SEHRA ELECTRIC works

Work in Progress

Detail Report
Graph / Photo
300 SH REPAIR OF DAMAGED STORM WATER DRAINS AT JHULELAL MANDIR MARG MAHARISHI DAYANAND MARG AND GYAN SHAKTI MARG UNDER SUB DIVISION NW R 14 21/12/2018 18/02/2019 29.15 Pawan Kumar Gupta Detail Report
Graph / Photo
301 A/R and M/O Roads under PWD North Roads, Delhi during 2018-19 (SH- Repair of damaged drain at front of gali No-6 Samaypur Badli on Main Bawana Road under Sub Division NR-14) 06/06/2019 03/09/2019 29.02 Rajesh Gupta (GTB) Work not started Detail Report
Graph / Photo
302 Essential maintenance of the critical areas for SRD Project Division-I, Sub-Division-I, PWD, New Delhi Dg. 2018-19. 29/05/2018 28/11/2018 29.01 0.00 (Jan'19) 36.00 % (Jan'19) Rajesh Gupta (GTB) Work Completed and final bill paid Detail Report
Graph / Photo
303 Operation and Maintenance of sewage/storm water pumps, DG sets at Vrs. location under M-251. (SH-Replacement of Defective pipes, NRV and Repairing of Pumps and motors at Diff. location in transyamuna area as and when required basis). 09/02/2019 08/10/2019 28.99 36.22 (Jan'20) 0.00 (Jan'20) Krishna Electreical Works Detail Report
Graph / Photo
304 AR and MO to Various Roads PWD Division NW R 1 dg 2018 19 SH Desilting of drains of various roads under Shalimar Bagh Vidhan Sabha of Sub Division NW R 15 09/03/2019 06/06/2019 28.97 Nagendra and Company Detail Report
Graph / Photo
305 SH CONSTRUCTION OF BOUNDARY WALL AND BEAUTIFICATION OF FOOTPATH BADLI MORE TO HADERPUR MORE SIDE AREA 21/12/2018 18/02/2019 28.93 Sanjay Kaura Detail Report
Graph / Photo
306 A/R & M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH:- Repair of Bank Colony Road under Sub Division-2). 30/06/2019 29/07/2019 28.93 35.75 (Dec'20) 0.00 (Dec'20) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
307 Road restoration under sub division NWR-25 03/08/2017 03/10/2017 28.84 Sudesh Kumar Detail Report
Graph / Photo
308 Maintenance of Garden Features. 05/03/2019 04/04/2020 28.83 31.80 (Mar'21) 0.00 (Mar'21) Raj KumarSaini Detail Report
Graph / Photo
309 (SH- Repair/ Improvement of berm, footpath and drain at Jaipur Golden Hospital, Sector-3, Rohini, Delhi under Sub Division NWR-22.) 07/01/2018 06/05/2018 28.80 Ajay Kumar Detail Report
Graph / Photo
310 Providing and Fixing SFRC railing in Central Verge of Burari Road from Burari Crossing to Parmanand Chowk C and ND- Roads, New Delhi. 05/10/2018 27/11/2018 28.67 0.72 (Feb'20) 0.00 (Feb'20) Furkan Builders Detail Report
Graph / Photo
311 SH-Providing, planting, displaying of plants on desirable places from Rajghat Red Light to Vijay Ghat Nursery, Ring Road Island, Kisan Ghat, Ring Road Bypass etc 12/04/2019 11/05/2019 28.66 2.59 (Mar'20) 0.00 (Mar'20) Green India Nursery Detail Report
Graph / Photo
312 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (SH- Patch repair work at Mangolpuri Thana Road under sub division NWR-21.)(Re-call) 01/07/2019 30/07/2019 28.65 35.29 (Sep'19) 0.00 (Sep'19) Jitender Singh Detail Report
Graph / Photo
313 A/R and M/O to various roads under PWD division NWR-2, during 2017-18. (SH- Providing of missing railings on central verge, footpath and other miscellaneous work on Outer Ring Road between Mangolpuri to Madhuvan Chowk, Delhi under Sub Division NWR-25 12/01/2018 12/03/2018 28.62 B.L. Yadav Detail Report
Graph / Photo
314 A/R and M/O to various roads under PWD division NWR-2 during 2017-18. (Sh- Misc repair on various roads under Sub Division NWR-24.) 01/04/2018 27/09/2018 28.58 Jitender Singh Detail Report
Graph / Photo
315 Providing and fixing gantries including signage board at PWD roads and fixing signage board at different locations under PWD Sub Division 2 29/09/2019 27/11/2019 28.56 16.10 (Feb'21) 0.00 (Feb'21) Hak Construction Co Detail Report
Graph / Photo
316 A/R and M/O PWD Roads under Sub Division-1 of Division C&ND-Roads during 2017-18. SH: - Making of existing footpath for differently enabled friendly and miscellaneous repair of footpath on various roads 02/01/2018 01/05/2018 28.20 S S Chauhan & Sons Detail Report
Graph / Photo
317 Operation and Maintenance of DG. Sets, Sub Station, Pump sets for underpasses, Subways including general maintenance of subways, FOBs and underneath of flyover 29/11/2018 28/12/2019 27.98 18.02 (May'20) 0.00 (May'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
318 M/o Hort. work attached to Ring Road from (Bhairon Marg T-point to Moolchand Flyover), Bhairon Marg from Ring Road to Mathura Road under HSD-South-III/HD-South/PWD/New Delhi/dg. 2018-19. (SH: Maintenance of Hort. work). 14/02/2019 13/02/2020 27.97 9.23 (Dec'20) 0.00 (Dec'20) Ashok Kumar Contractors abdfa0012c Work in progress Detail Report
Graph / Photo
319 Maintenance of street light High Mast subway underdeck and FOB lights on Delhi PWD road under PWD South Zone. 17/01/2019 15/07/2019 27.89 4.70 (Jun'19) 0.00 (Jun'19) V.K. Electricals Detail Report
Graph / Photo
320 A/R and M/O to various roads under PWD Division NWR-2 during 2019-20 (SH- Desilting of Drains and Removal of Malba/ sludge etc. under the jurisdiction of Sub-Division NWR-25.) 03/06/2019 02/06/2020 27.77 33.70 (Jul'20) 0.00 (Jul'20) Jitender Singh Detail Report
Graph / Photo
321 SITC of 16 Meters LED High Mast at various roads in Pitampura under NWED, PWD, Delhi. 20/09/2019 19/12/2019 27.76 Dev Engineers WORK IN PROGRESS Detail Report
Graph / Photo
322 Removal of Floating materials SECTION II 06/12/2018 02/08/2019 27.59 33.43 (Aug'20) 0.00 (Aug'20) Sharma Construction Co. Work in progress Detail Report
Graph / Photo
323 Providing service of Maintenance van required labours, TandP for day to day upkeeping/maintenance of roads under, Sub division-II, SWR-II, Najafgarh New Delhi 06/08/2021 05/02/2022 27.51 Nagendra and Company Detail Report
Graph / Photo
324 A/R and M/O various roads under SRD Division-I, PWD, New Delhi dg. 2018-19. (SH-Rehabilitation of storm water drainage system and repair of footpath and carriageway on Naya Bazar Road). 21/02/2019 20/04/2019 27.44 34.19 (Jan'20) 0.00 (Jan'20) TKN Developers work in progress Detail Report
Graph / Photo
325 Misc. Repair works. 26/08/2016 23/11/2016 27.33 0.00 (Aug'16) 0.10 % (Aug'16) A.B. Associates work in progress Detail Report
Graph / Photo
326 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Repair of central verge and footpath Khajuri Chowk to DJB office at Road No 59 under sub division-2). 10/06/2019 09/08/2019 27.31 22.53 (Nov'20) 0.00 (Nov'20) Rajinder Prasad Work in progress. Detail Report
Graph / Photo
327 Operationalization of the Cycle Track at Shyama Prasad Mukherjee Marg from Hanuman Temple Bridge to Pul Mithai Bridge including repair of various deformities and resurfacing of the cycle track with coloured surfacing material (SH-Providing coulour 09/07/2018 08/09/2018 27.18 0.00 (Feb'19) 33.11 % (Feb'19) Satyam Construction Co. Work Completed and final bill paid Detail Report
Graph / Photo
328 A/R and M/O Various roads under PWD Division West Road-I, New Delhi dg. 2019-20. (SH Providing services of Watch and Ward in Subways, FOB, Division office and Sub-Divisions.) 30/06/2019 29/04/2020 27.14 31.44 (Nov'20) 0.00 (Nov'20) Planet Security Group work in progress Detail Report
Graph / Photo
329 A/R & M/O other roads under SRD Division-I, PWD, New Delhi dg. 2018-19 (SH: Repairing of footpath, fixing of grills & other Misc. work at Lothian Road under Sub Division-I) 22/06/2019 21/08/2019 27.12 26.50 (Oct'20) 0.00 (Oct'20) IKRAMUDDIN Detail Report
Graph / Photo
330 A/R and M/O various Road under Sub-Division M-2111 during 2019-20.(SH - Improvement of drainage below Anand Vihar FOB and Dismantling of Gantry at Railway Station.). 26/07/2019 23/09/2019 27.06 14.01 (Aug'21) 0.00 (Aug'21) B.P. Rai & sons WORK IN PROGRESS Detail Report
Graph / Photo
331 SITC of Decorative/Ornamental Street Lights Poles at Service Road and Green Area along Ring Road from AIIMS Flyover to South Extension under PWD South East New Delhi 10/11/2017 09/01/2018 26.94 M J ELECTRICALS & ELECTRONICS Detail Report
Graph / Photo
332 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Improvement of Shoulders and laying NP-2 Class (R.C.C Pipes) on Sadar Thana road 01/03/2018 29/05/2018 26.84 Rajesh Gupta (Rohini) Work Completed Detail Report
Graph / Photo
333 Painting kerb stone, wall, office rooms and Road marking / Zebra Marking at various roads under Sub Division 2. 21/10/2019 04/11/2019 26.69 24.35 (Aug'20) 0.00 (Aug'20) N.M. CONSTRUCTION CO. Detail Report
Graph / Photo
334 Maintenance and Electrical consumption charges of Street Lighting on PWD Roads under North Zone SH Comprehensive Maintenance of 02 Nos. Lift at Shakurpur Foot Over Bridge, Near Britania Chowk, Ring Road, Delhi 09/08/2019 08/08/2024 26.46 5.42 (Jun'20) 0.00 (Jun'20) Techno Industries Limited FIRST RA BILL PAID BY CV NO. 16 DATED 18.06.2020 RS 541760/- Detail Report
Graph / Photo
335 A/R and M/O to various roads under PWD division NWR-2, during 2017-18. (SH- Improvement of footpath and berm portion at Major Ashwani Kanva Marg, Paschim Vihar, Delhi under Sub Division NWR-24.) 10/01/2018 09/04/2018 26.45 26.25 (Sep'19) 0.00 (Sep'19) Divyanshu Enterprises Detail Report
Graph / Photo
336 Beautification of the Roads by planting of Creepers, Summer Seasonals and Perinial flowers etc 08/04/2019 07/05/2019 26.38 24.50 (May'21) 0.00 (May'21) Chandra Farm and Nursery Detail Report
Graph / Photo
337 A/R and M/O PWD roads under Sub Division-3 of Division C and ND- Roads during 2018-19. SH_Filling of construction joints with polysulphide sealant on Ring Road Bypass. 01/11/2018 31/12/2019 26.24 Furkan Builders Detail Report
Graph / Photo
338 RMO Street lights Pumps and EI of Vrs. underpass RUB ways Subways and underneath of Flyovers under M-251 . SH- Operation and Maint. of DG Sets Sub Station P/Sets for underpasses Subways i/c general Maint. of subways FOBs and underneath of flyover 12/11/2018 11/11/2019 26.07 23.43 (Jan'20) 0.00 (Jan'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
339 Strengthening, Improvement of footpath, providing and fixing retro-reflective road signages and upgradation of street lighting on road under Sector-3 in Rohini, Delhi. (SH- Microsurfacing of Bituminous road) Re-call 23/03/2019 20/06/2019 25.95 Pawan Kumar Detail Report
Graph / Photo
340 M/o Hort. work at Jawahar Lal Nehru Road, Asaf Ali Marg, Ranjit Singh Marg, Vivekanand Marg, Rajpur Road, Lala Hardev Sahai Marg, Bulword Road, Luthian Road under Hort. Sub Divn. (Project), PWD, New Delhi dg 2018-19 27/07/2018 26/08/2019 25.93 7.07 (Nov'19) 0.00 (Nov'19) Rathore Contractor and Supplier Detail Report
Graph / Photo
341 Strengthening of Road old GTK from Km. 21 to 24, Road No. A-4, A-5, 42-A and resurfacing of Service Road of ORR No. 26, Service Road of Ring Road on both sides and Road No. 38,37 Extn., Service Road of Outer Ring Road No. 26 and Road No. 43 by . 26/01/2019 25/04/2019 25.92 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
342 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19 (SH- Desilting of Drains and Removal of Malba/ sludge etc. under the jurisdiction of Sub-Division NWR-25.) 27/05/2018 26/05/2019 25.88 9.41 (Jul'19) 0.00 (Jul'19) Jitender Singh Detail Report
Graph / Photo
343 Providing and Fixing Signages board at Khaira Village Rawta Village and near Chhawla stand 18/10/2019 15/01/2020 25.88 Anil Engineering WORK IN PROGRESS Detail Report
Graph / Photo
344 AR and MO TO VARIOUS ROADS UNDER PWD DIVISION NW R 1 DELHI DURING 2018 19 SH MODIFICATION OF EXISTING CENTRAL VERGE AT RAMLEELA GROUND ROAD 13/02/2019 13/04/2019 25.64 Sethi Construction Detail Report
Graph / Photo
345 RESTORATION OF VARIOUS ROADS UNDER SUB DIVISION NW R 14 and DIVISION NW R 1 CUT BY VARIOUS AGENCIES FOR PROVIDING AND LAYING AND REPAIRING THEIR SERVICE LINES CABLES ETC DURING 2018 19 06/03/2019 02/09/2019 25.42 Sethi Construction Detail Report
Graph / Photo
346 A/R and M/O to various roads under PWD division NWR-2 during 2018-19. (SH- Misc. repair work under section-1, Sub Division NWR-23.) 13/12/2018 11/04/2019 25.41 29.72 (Sep'19) 0.00 (Sep'19) Arif Detail Report
Graph / Photo
347 Repair of road Surface of Moujpur Road (From Moujpur Red Light to Ghonda Chowk) under PWD Sub Division M-2132. 20/10/2019 18/11/2019 25.37 23.32 (Sep'21) 0.00 (Sep'21) Pawan Kumar Detail Report
Graph / Photo
348 AR AND MO VARIOUS ROADS PWD DIVISION NW R 1 DG 2017 18 SH MISC REPAIR WORK AT VARIOUS ROADS UNDER SUB DIVISION NW R 12 08/11/2017 06/05/2018 25.16 Sujan Singh Detail Report
Graph / Photo
349 Restoration of various roads under SRD Project Sub Division II SRD Project Division II PWD New Delhi SH Restoration of various road cuts by IGL and Vodafone at New Rohtak Road under Sub Division II 22/07/2019 19/10/2019 25.08 30.22 (Nov'20) 0.00 (Nov'20) Satyam Construction Co. Work in progress Detail Report
Graph / Photo
350 A/R and M/O to various roads under PWD division NWR-2, during 2017-18. (SH- Connecting R.C.C drain at B-4 Road corner to E-II, Astha Kunj, Sector-18, Rohini, Delhi under sub division NWR-23.) 10/01/2018 10/03/2018 25.05 Dinesh Kumar Detail Report
Graph / Photo
351 Cleaning of roads and levelling of berm portion (Old Delhi Gurgaon road, Bharthal road and Kapashera Bijwasan road)and other miscellaneous repair works under Sub Division- 24 24/09/2021 23/10/2021 24.84 ABHILEKH YADAV Detail Report
Graph / Photo
352 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2019-20. (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under section-II, Sub Division NWR-21.) (3rd call) 18/04/2019 12/01/2020 24.81 30.44 (Nov'20) 0.00 (Nov'20) RichCon Engineering Company Detail Report
Graph / Photo
353 R/R work of various roads cut by different civic agencies for laying cable, pipes, fault repair under PWD, Sub Division NWR-22, Division NWR-2 during 2018-19 (3rd Call). 26/03/2019 23/06/2019 24.78 27.86 (Sep'19) 0.00 (Sep'19) Jitender Singh Detail Report
Graph / Photo
354 A/R and M/O various roads under PWD, Division NWR-2 during 2018-19. (SH- Providing and fixing retro reflective road signages under Section-1, Sub Division NWR-23.) 17/12/2018 17/03/2019 24.67 29.30 (Jun'19) 0.00 (Jun'19) Sethi Construction Detail Report
Graph / Photo
355 M/o Hort. Work at approach road (from Palam Flyover to T-1 Crossing) under Hort. Sub Divn South-II/(Section-II) South/PWD/ New Delhi dg. 2019-20. Maintenance of Hort. Works 04/10/2019 03/10/2020 24.60 Rampal Singh AQAPS3857M WORK IN PROGRESS. Detail Report
Graph / Photo
356 Desilting of open drains, covered drains, Culverts, Pipe etc.). 15/05/2016 11/09/2016 24.50 0.00 (Aug'16) 95.00 % (Aug'16) Sanjay Kaura work in progress Detail Report
Graph / Photo
357 A/R and M/O to Various Roads under PWD Division NWR-2 dg. 2019-20. (SH- Comprehensive desilting of drains of various categories and sizes along PWD roads under section-I, Sub Division NWR-21.)(3rd call) 18/04/2019 12/01/2020 24.46 30.07 (Apr'21) 0.00 (Apr'21) RichCon Engineering Company Detail Report
Graph / Photo
358 Maintenance & Operation of Street light and High Mast light i/c monitoring of Street lights at various location under PWD M-251 4th Floor MSO Building IP State Delhi (SH: Comprehensive maintenance of Street Light in trans Yamuna Area) 08/11/2018 07/11/2019 24.35 19.09 (Jan'20) 0.00 (Jan'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
359 Road restoration under NWR-24 31/07/2017 29/08/2017 24.29 Gaurav Construction Co. Detail Report
Graph / Photo
360 R/R work of various roads cut by different civic agencies for laying cable, pipes, fault repair under PWD, Section-I, Sub Division NWR-23, Division NWR-2 during 2018-19. 25/02/2019 25/04/2019 24.26 30.00 (Nov'19) 0.00 (Nov'19) Gaurav Construction Co. Detail Report
Graph / Photo
361 A/R & M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH:- Repair work of shoulder and other civil work at Loni Road under PWD Sub Division 4). 15/09/2019 13/11/2019 24.26 24.24 (Nov'19) 0.00 (Nov'19) Rajesh Kumar Gupta Detail Report
Graph / Photo
362 Micro surfacing and Improvement of Footpath at Sant Sujan Singh Marg and Gangeshwar Dham Marg 27/12/2020 24/02/2021 24.21 Ram Prasad Singh & Sons Detail Report
Graph / Photo
363 Lifting of malba / floating material garbage etc. from PWD Roads on day to day basic etc. 07/10/2018 06/10/2019 24.17 19.54 (Oct'19) 0.00 (Oct'19) Sandeep Kumar Work in progress. Detail Report
Graph / Photo
364 Repair of drain, culvert etc. at Road No. 102, 108, 109, Live Stock Road and Kondli Gharoli Road 17/10/2018 15/12/2018 24.07 30.08 (Apr'21) 0.00 (Apr'21) Bala ji associates

Work in progress

Detail Report
Graph / Photo
365 M/o Hort. Work attached to Dev Prakash Shastri Marg, Under Hort.Sub.Divn.South-II/PWD, New Delhi during 2019-20.SH: -Maintenance of Hort. Works. 04/10/2019 03/10/2020 24.01 12.32 (Dec'20) 0.00 (Dec'20) Ashok Kumar Contractors abdfa0012c work in progress. Detail Report
Graph / Photo
366 Operation of Lifts Installed on FOB and Providing of Security Guards for Safe Guard of FOBs on PWD Roads under PWD EMD South East, New Delhi during 2021-22 08/10/2021 07/10/2022 23.99 R. Diamond Enterprises Detail Report
Graph / Photo
367 Painting with Synthetic Enamel Paint and Road Marking Paint on various road under Sub Division- 2I 06/08/2021 05/02/2022 23.98 Sethi Construction Detail Report
Graph / Photo
368 Making footpath disabled friendly of Princess Road, Model Town II Road and Model Town III Road under Sub Division NR-12 15/10/2020 11/02/2021 23.92 Zahid Hussain Detail Report
Graph / Photo
369 A/R and M/O PWD Roads under Sub-Division-3 of Division C and ND Roads during 2018-19. SH_Making disabled friendly footpath on Vidhan Sabha Road, Metcalf House Road and other miscellaneous repair work on these roads. 24/11/2018 23/02/2019 23.75 22.95 (Oct'19) 0.00 (Oct'19) Ram Singh Detail Report
Graph / Photo
370 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Patch repair work at Gamri Road, Seelampur and Zero pusta road under PWD Sub Division 4 for section-1). 11/07/2019 25/07/2019 23.74 28.25 (Nov'19) 0.00 (Nov'19) MAHAVIR PRASAD GUPTA AND SONS Work in progress. Detail Report
Graph / Photo
371 A/R and M/O PWD Roads under Sub Division - 3 of Division C and ND Roads, New Delhi during 2017-18. SH_Mechanized sweeping and cleaning of various roads. 4th call of tender 18/12/2017 17/09/2018 23.71 0.50 (Jul'19) 0.00 (Jul'19) Shubham Builders Detail Report
Graph / Photo
372 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Patch repair and potholes repair 23/10/2017 19/02/2018 23.71 Kundu Nirman WORK COMPLETED Detail Report
Graph / Photo
373 AR and MO to Various Roads under Sub Division NW R 15, PWD Division NW R 1 dg 2018 19 SH Comprehensive desilting of drains of various categories and sizes along PWD roads 05/04/2018 02/10/2018 23.59 Sanjay Kaura Detail Report
Graph / Photo
374 Maintenance and payment of electrical consumption charges of Street Lighting on PWD Roads under North Zone(SH Operation and Routine Maintenance of electrical installations,DG Sets,Dewatering pumps at Road No. 43 drain,Wazirpur Drain and Raja Park RUB 26/10/2018 25/10/2019 23.40 13.56 (Jul'19) 0.00 (Jul'19) DHARAM ENTERPRISES 4TH RA BILL PAID RS. 484482/- WORK IN PROGRESS Detail Report
Graph / Photo
375 A/R and M/O to various roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Kerb Stone, Railing and Central verge Painting. 02/10/2017 30/03/2018 23.34 Kashi Nath Jha Work completed Detail Report
Graph / Photo
376 Installation of Signage Board and other misc. work under Sub Divison-24 31/07/2021 26/01/2022 23.32 Bishwa Mohan Jha Detail Report
Graph / Photo
377 Strengthening, Improvement of footpath, Providing and fixing Retro-reflective road signages and upgradation of street lighting on roads Police Line Road, Amar Shaheed Bismil Marg and Phirni Road, Delhi ... (SH- Microsurfacing of Bituminouns roads) 10/03/2019 07/06/2019 23.32 Pawan Kumar Detail Report
Graph / Photo
378 A/R and M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH- Repair of footpath from Wazirabad Bridge to T point at Road No-59 for making the proper accessibility for differently abled persons in...... 10/06/2019 08/08/2019 23.16 22.38 (Dec'19) 0.00 (Dec'19) Sandeep Kumar Work in progress. Detail Report
Graph / Photo
379 A/R & M/O to various Roads under Sub Division-1 of Division South Road-II, PWD during 2021-22 (SH:-Providing and Fixing Speed Calming measures at August Kranti Marg, Balbir Saxena Marg, Shri Krishna Chaitanya Maha Prabhu Marg,Dilip Singh Marg, M.KJain Marg, Gautam Nagar Road, Sudarshan Cinema Road, Siri Fort Road, PR Block Road, NIFT Road, Subhash Chopra Marg). 25/09/2021 24/11/2021 22.99 Jagdamba Enterprises Detail Report
Graph / Photo
380 Repair of Footpath and Drain at Road on Road No-57A and IP Extension area. 05/09/2018 04/11/2018 22.98 26.01 (Sep'19) 0.00 (Sep'19) Bansal Construction Co

Work in progress

Detail Report
Graph / Photo
381 A/R & M/O to various roads under M-4423 during 2014-15 (SH: Miscellaneous repair work and repair of footpath from Mehrauli T-Point to Sainik Farm 18/01/2015 17/04/2015 22.76 Surender Singh Chouhan WORK COMPLETED Detail Report
Graph / Photo
382 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (SH- Repair of Junction of Bhagwan Parshuram Marg on Shiva road and Vidya Jain School road by SMA and patch repair on Road No. B-1, Service Road of Road no. 41-A under SD NWR-22 04/12/2018 01/02/2019 22.75 18.48 (May'19) 0.00 (May'19) Awasthi Construction Detail Report
Graph / Photo
383 A/R & M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH:- Providing services of sewerman along with required T&P for cleaning of the drain i/c disposal of floating material on day to day basis etc. under Sub Division-2). 05/12/2018 02/07/2019 22.62 11.99 (Oct'19) 0.00 (Oct'19) Sandeep Kumar Work in progress. Detail Report
Graph / Photo
384 A/R and M/O to Various Roads Sub-Division East Road-IV under PWD Division East Roads/ (M-212), Delhi during 2019-20. 26/06/2019 25/06/2020 22.58 33.94 (Jul'20) 0.00 (Jul'20) STAR SECURITY AND PLACEMENT SERVICES

Work in progress

Detail Report
Graph / Photo
385 Painting of Dabri Flyover under Sub Division- 2I, SWR-II, PWD, New Delhi 06/08/2021 05/09/2021 22.51 M A Builders Detail Report
Graph / Photo
386 Desilting of road side drains and culvert under Section-I.) 22/05/2016 18/10/2016 22.50 0.00 (Aug'16) 90.00 % (Aug'16) Sanjay Kaura work in progress Detail Report
Graph / Photo
387 Providing services of sewerman man along with required T and P for cleaning of the drain i/c disposal of floating material on day to day basis etc. under PWD ...... 06/10/2019 01/06/2020 22.42 9.23 (Jul'20) 0.00 (Jul'20) Ravinder Kumar Detail Report
Graph / Photo
388 Patch repair work of Najafgarh Dhansa and Najafgarh Kakrola Road of Section-I under Sub Division-II New Delhi 14/10/2019 12/12/2019 22.17 Sharma Construction Co. WORK IN PROGRESS Detail Report
Graph / Photo
389 Desilting of drains and culverts on Multan Nagar Section roads. 12/03/2016 09/07/2016 22.16 0.00 (Aug'16) 95.00 % (Aug'16) Ramesh Chander work in progress Detail Report
Graph / Photo
390 AR and MO to Various Roads under SWR-II PWD during 2019-20 SH Providing of Maintenance Van required labours T and P for day to day upkeeping maintenance of roads under sub division 21 New Delhi 02/08/2019 28/07/2020 22.08 Surender Singh work forclosed Detail Report
Graph / Photo
391 Desilting of road side drains and culvert under Section-II.) 22/05/2016 18/10/2016 22.02 0.00 (Aug'16) 90.00 % (Aug'16) Sanjay Kaura work in progress Detail Report
Graph / Photo
392 Desilting of drains and culverts of Rani Bagh, Pitampura Section roads.) 12/03/2016 09/07/2016 21.94 0.00 (Aug'16) 95.00 % (Aug'16) Ramesh Chander work in progress,Provisional EOT granted upto 30.09.2016. Detail Report
Graph / Photo
393 A/R and M/O PWD Roads under Sub-Division-I of Division C and ND-Roads during 2018-19. SH_Repairing of damaged drain and footpath at Main Burari Road at placed from Sant Nagar to Shalimar Palace. 03/09/2018 02/11/2018 21.87 9.56 (Nov'19) 0.00 (Nov'19) M H Builders Detail Report
Graph / Photo
394 AR and MO road under PWD Division South Road-1 Sub Division - I during 2017-18. SH Providing Fixing of Grills on center verge on M.B Road from Batra Red Light to Lado Sarai T-Point. 23/06/2017 22/07/2017 21.76 Narender Singh Yadav

work completed

Detail Report
Graph / Photo
395 A/R and M/O to Various Roads Sub-Division East Road-I under PWD Division East Roads/ (M-212), Delhi during 2018-19. 02/03/2019 31/03/2019 21.73 22.46 (Dec'19) 0.00 (Dec'19) Maa Vaishno Developers

Work in progress

Detail Report
Graph / Photo
396 A/R and M/O other PWD Roads under SRD Project Division-I, New Delhi Dg. 2017-18 (SH-Comprehensive Maintenance of Subway at JLN Marg and Sub Division-II Office at Ring Road Bypass). 06/01/2018 05/01/2019 21.64 STAR SECURITY AND PLACEMENT SERVICES Detail Report
Graph / Photo
397 A/R and M/O to various roads under PWD Division NWR-2 during 2017-18. (SH- Comprehensive Repair of road footpath, drain, painting etc. on Mangolpuri Constituency roads under Sub Division NWR-21.) 03/12/2017 02/03/2018 21.61 Jitender Singh Detail Report
Graph / Photo
398 A/R and M/O PWD roads under Sub Division-1 of Division C and ND Roads during 2017-18. SH_Patch repair of various roads. 07/11/2017 06/01/2018 21.54 Bansal Construction Co Detail Report
Graph / Photo
399 AR and MO TO VARIOUS ROADS UNDER DIVISION NORTH WEST ROAD I DURING 2018 19 SH REPAIRS OF DAMAGED FOOTPATH CONSTRUCTION OF PLANTER and FIXING OF M S GRILLS ETC AT THE ABDUL HAMEED MARG VALMIKI ROAD TRIWALUAR MARG KABIR DAS MARG and EKLAVYA MARG U 09/03/2019 07/04/2019 21.54 Aditya Construction Detail Report
Graph / Photo
400 Repair of roads under Section-II. 23/12/2018 01/01/2019 21.50 26.02 (Jun'19) 0.00 (Jun'19) ROAD TECH

Work in progress

Detail Report
Graph / Photo
401 AR and MO various roads of PWD under NW R 1 dg 2017 18 SH Providing and fixing ret ro ref lecti ve Cau tiona ry Man datory sig nages at various road under sub division NWR 12 05/10/2017 03/11/2017 21.44 Anil Engineering Works Detail Report
Graph / Photo
402 A/R and M/O to various Road under Sub Division NWR-21, PWD, Division NWR-2 during 2019-20. SH- Hiring Inspection Vehicle for S.E. North West, PWD Sectt, Deputy Secretary to CM and E.E. NWR-2 for official purpose.). 04/07/2019 03/07/2020 21.35 26.86 (Jun'21) 0.00 (Jun'21) Ram Prasad Singh & Sons Detail Report
Graph / Photo
403 Providing and operating mobile maintenance vehicle under Sub Division M-2134 16/07/2018 15/07/2019 21.32 12.71 (Oct'19) 0.00 (Oct'19) Sandeep Kumar Work in progress. Detail Report
Graph / Photo
404 A/R & M/O Various roads under Sub-Division M-2114 during 2021-22. (SH: Improvement of drain near Kali Mata Mandir at Road no.69). 17/07/2021 14/10/2021 21.31 Dinesh Chand Sharma Work is progress Detail Report
Graph / Photo
405 Removal of malba and disposal at approved MCD dumping ground from Section-II, Paschim Vihar area) 01/05/2016 27/10/2016 21.29 0.00 (Aug'16) 70.00 % (Aug'16) Sanjay Kaura work in progress Detail Report
Graph / Photo
406 AR and MO VARIOUS ROAD PWD UNDER DIVISION NORTH WEST ROAD 1 UNDER SUB DIVISION NW R 13 DELHI DURING 2018 19 SH REPAIR OF FOOTPATH AND OTHER MISC WORK AT ROAD NO 40 19/06/2019 17/08/2019 21.22 GAJE SINGH Detail Report
Graph / Photo
407 AR and MO to various roads under PWD Sub Division South Road-14 during 2017-18 SH Repair of footpath and Berms at Apeejay School Road Sheikh Sarai. 09/02/2018 09/04/2018 21.20 S S Chauhan & Sons

work completed

Detail Report
Graph / Photo
408 R/R of various roads cut by various agencies for laying cables, pipes, fault repair etc. under PWD Sub Division NWR-24, Division NWR-2 during 2018-19. 10/09/2018 09/10/2018 21.11 11.33 (Sep'19) 0.00 (Sep'19) Jitender Singh Detail Report
Graph / Photo
409 A/R and M/O to various roads under Division NWR-2, PWD dg. 2018-19 (SH- Providing services of maintenance vehicle with labour and T and P etc. for Section-I, Sub Division NWR-25 for one year.) 03/02/2019 02/02/2020 20.87 20.45 (Jul'20) 0.00 (Jul'20) K P Singh & Co. Detail Report
Graph / Photo
410 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (Sh- Patch repair of damaged roads by bituminous concrete under Section-I, under Sub Division NWR-23.) (Re-call) 01/07/2019 14/08/2019 20.87 25.82 (Oct'19) 0.00 (Oct'19) Jitender Singh Detail Report
Graph / Photo
411 Providing services of security guard for watch and ward of Division and Sub Division Office I,II,III,and IV, New Delhi 21/09/2021 20/09/2022 20.87 TMS Security Services Detail Report
Graph / Photo
412 AR and MO TO VARIOUS ROADS UNDER PWD NW R 1 DURING 2017 18 SH PROVIDING SECURITY ARRANGMENT AT VARIOUS LOCATIONS IN SUBWAYS UNDERPASS ETC UNDER SUB DIVISION NW R 14 FOR 5 MONTH 03/12/2017 01/05/2018 20.83 TRENDY SECURITY SERVICES Detail Report
Graph / Photo
413 Restoration of road & footpath cut by Delhi Jal Board at Various Roads under Sub Division-II of SRD Division-I, PWD, New Delhi. 28/12/2017 27/03/2018 20.81 A.R Infrastructure Work Completed and final bill paid Detail Report
Graph / Photo
414 R/R work of various roads cut by different civic agencies for laying cable, pipes, fault repair under PWD, Sub Division NWR-24, Division NWR-2 during 2018-19. (Re-call) 01/07/2019 30/07/2019 20.60 1.05 (Mar'21) 0.00 (Mar'21) Jitender Singh Detail Report
Graph / Photo
415 AR and MO TO VARIOUS ROADS UNDER DIVISION NW R 1 DURING 2018 19 SH ROAD BERM REPAIR OF SHAKURPUR ROAD AT ABDUL HAMID MARG VALMIKI MARG MAIN ROAD OF G BLOCK and H BLOCK and TRIWALUBAR MARG IN SHAKURPUR AREA UNDER DIVISION NW R 1 (SECOND CALL) 20/02/2019 05/04/2019 20.54 Raj Associates Detail Report
Graph / Photo
416 A/R & M/O various road under PWD SRD Division-I, Sub-Division-I, PWD, New Delhi dg. 2018-19 (SH:- Bitumen patch work on various road). 16/06/2019 15/12/2019 20.53 17.39 (Dec'20) 0.00 (Dec'20) M/s. Satyam Construction Work Just awarded Detail Report
Graph / Photo
417 Strengthening, Improvement of footpath, Construction of box drain and providing and fixing road signages and upgradation of road in Sector-20 Rohini. (SH- Microsurfacing of Bituminous road.) 08/03/2019 05/06/2019 20.45 23.10 (Jan'20) 0.00 (Jan'20) Pawan Kumar Detail Report
Graph / Photo
418 Restoration of road cut by TPDDL and other agencies for laying their services at various roads under Sub Division -1 of Division CandND-Roads, New Delhi. 29/06/2018 28/07/2018 20.43 Aditya Construction Detail Report
Graph / Photo
419 A/R and M/O various roads under SRD Project Division-I, New Delhi Dg. 2018-19 (SH- Comprehensive Maintenance of Subway at JLN Marg and Sub Division-II Office at Ring Road Bypass) 17/03/2019 16/03/2020 20.42 16.60 (Nov'20) 0.00 (Nov'20) STAR SECURITY AND PLACEMENT SERVICES work in progress Detail Report
Graph / Photo
420 Providing and fixing of railing on central verge of Stadium Road from Chhatrasal Stadium to G.T. Road under Sub Division NR-12 15/10/2020 13/12/2020 20.39 M/s R M constrution Detail Report
Graph / Photo
421 Removing vegetation weets, providing CC pavements in berm portion and removing malba from berm portion at Najafgarh Bijwasan road and Goyla Deenpur road under sub division-V,SWR-II, New Delhi 29/09/2021 28/10/2021 20.37 Bishwa Mohan Jha Detail Report
Graph / Photo
422 A/R & M/O various road under Shahdara Road Division during 2020-21. (SH: Providing Services of Security Guard for watch & ward in the office of PWD Division Shahdara Road office Sub -Division M-2111,M-2112,M-2113 & M-2114.) (Balance work). 29/11/2020 11/07/2021 20.32 Planet Security Group WORK RESCIND UNDER CLAUSE 5. Detail Report
Graph / Photo
423 A/R and M/O to Various Roads Sub. Div. East Road-IV under PWD Div. East(Road)/M-212 During 2018-19. 31/01/2019 16/03/2019 20.30 14.80 (Jul'20) 0.00 (Jul'20) M T Builders

Work in progress

Detail Report
Graph / Photo
424 Resurfacing of DCP office Road and Bhola Nath Nagar Road under Sub-Division M-2113 of Shahdara Road Maint. Division PWD. 04/11/2019 03/01/2020 20.29 20.72 (Apr'21) 0.00 (Apr'21) Nirmit Construction Co. Work in progress Detail Report
Graph / Photo
425 Road restoration estimate for repairing of road, footpath, drain and other miscellaneous work on the roads under Sub Division - 3 of Division C and ND- Roads, New Delhi 05/03/2019 04/05/2019 20.28 24.13 (Sep'19) 0.00 (Sep'19) Sushil Kumar Detail Report
Graph / Photo
426 Providing and fixing Road ..................... cautionary boards at various roads under jurisdiction of M-2134 16/09/2018 30/10/2018 20.27 24.52 (Oct'19) 0.00 (Oct'19) Sethi Construction Work in progress Detail Report
Graph / Photo
427 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (SH- Improvement of footpath and berm portion of Mahatma Hansraj Marg under Sub division NWR-24, Delhi). 03/02/2019 19/03/2019 20.22 25.17 (Nov'19) 0.00 (Nov'19) Jitender Singh Detail Report
Graph / Photo
428 A/R & M/O to various Roads under SRD Project Di-I PWD, New Delhi dg 2017-18 (SH: Repair of footpath and kachcha portion at Kotla road under Sub Division-II). 19/10/2017 18/12/2017 20.09 Satyam Construction Company Detail Report
Graph / Photo
429 Providing services of security guard for watch and ward of division I II III and Sub division IV New Delhi. 19/09/2019 14/09/2020 19.90 11.63 (May'20) 0.00 (May'20) City Commercial Services work completed Detail Report
Graph / Photo
430 Repair of footpath from Madhuban Red Light to Ganesh Chowk at Patparganj Road. 23/02/2019 24/03/2019 19.82 23.51 (Sep'19) 0.00 (Sep'19) Prem Sagar

Work in progress

Detail Report
Graph / Photo
431 A/R and M/O to various roads under SRD Project Division-I, PWD, New Delhi, during 2017-18. (SH- Repair of footpath and NMV Lane at SPM Marg under Sub-Division-I.) 14/08/2017 13/10/2017 19.80 0.00 (Mar'18) 15.78 % (Mar'18) RANJIT CONSTRUCTION COMPANY Work completed and final bill paid Detail Report
Graph / Photo
432 Comprehensive maintenance of Schindler make escalators at FOB Satya Niketan Ring Road and near Moti Bagh Gurudwara Ring Road 29/11/2018 28/11/2019 19.77 Schindler India Pvt Ltd Detail Report
Graph / Photo
433 A/R and M/O Various road under sub Division WR-13, Division- WR-I, New Delhi during 2019-20. (SH Comprehensive desilting of drains by mechanical/manual means of various categories and sizes along PWD roads.) (Balance Work) 06/07/2019 19/08/2019 19.73 25.51 (Feb'20) 0.00 (Feb'20) Jeetender Kumar Verma Work in Progress Detail Report
Graph / Photo
434 Patch repair work on various roads under Sub-Division-I, Section-I 23/12/2018 01/01/2019 19.71 24.54 (Jul'19) 0.00 (Jul'19) ROAD TECH

Work in progress

Detail Report
Graph / Photo
435 SITC of fountain at Maharaja Agrasen and canal road intersection Pitampura, Delhi 20/10/2018 19/01/2019 19.70 concept deesign technology Fountain water body not constructed by PWD Civil Wing. Hence, electric work can not be started. Detail Report
Graph / Photo
436 AR and MO TO VARIOUS ROADS OF PWD DIVISION NORTH WEST ROAD I DG 2017 18 SH REPAIR OF SERVICE ROAD WITH DENSE GRADED BITUMEN and BITUMINOUS CONCRETE FROM ANANDWAS GATE B BLOCK TO EKLAVYA MARG RED LIGHT and MAHINDRA CHOWK TO RAJA PARK GALI NO 2 ROA 25/04/2018 23/06/2018 19.59 Sanjay Kaura Detail Report
Graph / Photo
437 A/R and M/O PWD Roads under Sub Division-2 of Division CandND-Roads during 2018-19. SH_providing table top and road furniture at various Roads 14/06/2018 13/08/2018 19.58 Narender Kumar Detail Report
Graph / Photo
438 M/o different Hort. works under Hort. Sub Division (Central and New Delhi), Hort. Division (East) M, PWD, Delhi dg 2018-19 10/01/2019 09/06/2019 19.57 2.43 (Sep'19) 0.00 (Sep'19) Chandra Farm and Nursery Detail Report
Graph / Photo
439 Misc. repair work 29/03/2016 26/07/2016 19.54 0.00 (Aug'16) 100.00 % (Aug'16) SACHIN KUMAR work completed Detail Report
Graph / Photo
440 Providing Maintenance Van with required labour, Materials and T & P under Section-I & II. 17/08/2018 12/02/2019 19.48 19.81 (Dec'19) 0.00 (Dec'19) Bansal Construction Co

Work in progress

Detail Report
Graph / Photo
441 A/R and M/O PWD Roads under Sub Division-1 of Division CandND-Roads during 2018-19 Sub Head Providing maintenance van along with labour for day to day maintenance. 26/09/2018 25/09/2019 19.48 16.05 (Aug'20) 0.00 (Aug'20) K.P. Singh & Co. Detail Report
Graph / Photo
442 A/R and M/O PWD Roads under Sub Division-2 of Division CandND-Roads during 2018-19 Sub Head Providing maintenance van along with labour for day to day maintenance. 26/09/2018 25/09/2019 19.40 20.09 (Dec'19) 0.00 (Dec'19) Kuldeep Kumar Detail Report
Graph / Photo
443 Providing maintenance van with required labour and T and P 04/04/2019 30/12/2019 19.30 4.50 (Aug'20) 0.00 (Aug'20) R. N. Construction Company - Detail Report
Graph / Photo
444 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (Sh- Comprehensive repair of road footpath, drain, painting etc. under Sub Division NWR-22.) 25/02/2019 25/05/2019 19.18 12.49 (Jul'19) 0.00 (Jul'19) Jitender Singh Detail Report
Graph / Photo
445 Providing services of maintenance vehicle with labour and T & P in sub division M-3124 for section-II. 26/01/2016 25/01/2017 19.16 0.00 (Aug'16) 70.00 % (Aug'16) K.P. Singh & Co. work in progress Detail Report
Graph / Photo
446 AR and MO various roads under PWD Division South Road-I during 2017-18. SH- Hiring of One mechanical vacuum sweeper for two months 13/07/2017 10/09/2017 19.06 J. K. Contractor

work completed

Detail Report
Graph / Photo
447 A/R and M/O to Various Roads Sub-Division East Road-I under PWD Division East Roads/ (M-212), Delhi during 2018-19. 18/04/2019 01/06/2019 18.97 23.37 (Feb'20) 0.00 (Feb'20) Arif

Work in progress

Detail Report
Graph / Photo
448 Misc. repair work 08/04/2016 05/08/2016 18.96 0.00 (Aug'16) 100.00 % (Aug'16) Hare Ram Singh work complete Detail Report
Graph / Photo
449 M/o Hort. work at Netaji Subhash Marg under Hort. Sub Division (Project), Hort. Division (East), PWD, Delhi during 2019-20 10/05/2019 09/06/2020 18.95 7.61 (May'21) 0.00 (May'21) Raj KumarSaini Detail Report
Graph / Photo
450 Providing of water through water tanker for watering in plants. 03/02/2019 02/08/2019 18.94 16.90 (Sep'19) 0.00 (Sep'19) Raj KumarSaini Detail Report
Graph / Photo
451 A/R and M/O to various roads under PWD division NWR-2 during 2018-19. (SH- Repair of footpath and Central Verge amd painting of kerb stone at Dr. K.N.Katju Marg passing through Sector-13 to Sector-11, Rohini under Section-II, Sub Division NWR-23.) 10/09/2018 24/10/2018 18.78 Dharambir Singh Detail Report
Graph / Photo
452 AR and MO VARIOUS ROADS OF PWD DIVISION NW R 1 UNDER SUB DIVISION NW R 11 NW R 12 NW R 13 NW R 14 and NW R 15 DURING 2018 19 SH PROVIDING AND STACKING OF INSTANT CURING READY MIXED COLD BITUMINOUS CONCRETE COMPOUND FOR POTHOLE REPAIR 23/02/2019 24/03/2019 18.75 Gaurav Construction Co. Detail Report
Graph / Photo
453 A/R and M/O PWD Roads under Sub Division-3, of Division and ND-Roads during 2018-19 SH_Providing maintenance van with required labour and T and P to attend day to day repairs of road works. 03/01/2019 02/01/2020 18.74 21.14 (Apr'20) 0.00 (Apr'20) Paras Nath Singh Detail Report
Graph / Photo
454 Improvement of Footpath and berm portion at Sant Nagar, Rani Bagh Market Road under Section-1, Sub Division NWR-24. 11/11/2017 23/02/2018 18.68 Jitender Singh Detail Report
Graph / Photo
455 Thermoplastic Painting ,P/F Glow stud at central verge on Prithvi singh dagar marg and Jhatikra Road under Sub Division-III, SWR-II, , New Delhi 24/09/2021 23/10/2021 18.65 Sethi Construction Detail Report
Graph / Photo
456 Construction of speed breaker by bituminous concrete and P/F cautionary boards on different road on Rohini Delhi. 05/08/2016 03/10/2016 18.55 0.00 (Aug'16) 0.10 % (Aug'16) Jitendra Singh in progress Detail Report
Graph / Photo
457 A/R and M/O PWD Roads under Sub Division-1 of Division C and ND-Roads during 2018-19. SH_Repairing of central verge at Main Burari Road from ORR to Burari Morh. 27/10/2018 26/12/2018 18.55 Bansal Construction Co. Detail Report
Graph / Photo
458 Strengthening, Improvement of footpath and providing and fixing retro-reflective road signages and upgradation of street lighting on Sir Chotu Ram Marg (Road No. A-2) from Avantika Chowk to ...(SH- Microsurfacing of Bituminous road.) Re-call. 23/03/2019 20/06/2019 18.53 16.35 (Jan'20) 0.00 (Jan'20) Pawan Kumar Detail Report
Graph / Photo
459 A/R and M/O to Various Roads under Sub. Div. East Road-III of Div. East(Road)/M-212 During 2018-19. 31/01/2019 16/03/2019 18.49 19.21 (Sep'20) 0.00 (Sep'20) Bansal Construction Co

Work in progress

Detail Report
Graph / Photo
460 Road Restoration of various roads cut by different agencies on Shani Bazar Road, Sultanpuri Main Road, Jagdamba Road, NRS road under Sultanpuri and Sir chottu Ram Marg under PWD Sub Division NWR-21, Division NWR-2 during 2018-19. 28/07/2018 25/09/2018 18.49 Jitender Singh Detail Report
Graph / Photo
461 A/R and M/O to various roads under PWD Division NWR-2 during 2017-18.(SH- Miscellaneous Repair of drain at road no. 42 under sub- division NWR-24.) 10/01/2018 09/04/2018 18.40 Jai Builders Detail Report
Graph / Photo
462 sevices of computer operator in Division M-312, Sub Division M-3121, Sub Division M3122, Sub Division M-3123, Sub Division M-3124 & Hob’ble PWD Minister’s Office 18/01/2016 17/01/2017 18.36 0.00 (Aug'16) 68.00 % (Aug'16) D.P. Associates work in progress Detail Report
Graph / Photo
463 SH- Thermoplastic paint, rumble strips, road furniture and Precast RCC jersey barrier on Ring Road and Ring Road bye pass. 13/07/2019 12/09/2019 18.34 22.84 (Feb'20) 0.00 (Feb'20) Saya Construction Company Detail Report
Graph / Photo
464 Road Restoration cut by DJB from Mitraon Sump to MCD School on Najafgarh Dhansa Road under Sub Division-II, Division SWR-II 09/09/2019 23/10/2020 18.32 ASH NARAYAN SINGH WORK IN PROGRESS 30% Detail Report
Graph / Photo
465 RESTORATION OF VARIOUS ROADS UNDER SUB DIVISION NW R 11 AND DIVISION NW R 1 AND CUT BY VARIOUS AGENCIES DURING 2018 19 15/06/2019 12/09/2019 18.25 Sanjay Kaura Detail Report
Graph / Photo
466 Improvement of drainage system LBSH Road. 26/01/2019 26/03/2019 18.19 8.81 (Jul'20) 0.00 (Jul'20) Ashoka Construction Co.

Work in progress

Detail Report
Graph / Photo
467 A/R & M/O to various roads under PWD (North East) Road Division dg. 2018-19. (SH:- Providing and supplying the services of cleaner / coolie for cleaning of subways, FOB's etc. under Sub Division M-2132). 05/12/2018 04/12/2019 18.02 19.40 (Dec'19) 0.00 (Dec'19) V. V. Associates Work in progress. Detail Report
Graph / Photo
468 Providing services of maintenance vehicle with labour and T & P in sub division M-3124 for section-1 25/01/2016 24/01/2017 17.97 0.00 (Aug'16) 70.00 % (Aug'16) Ajay Kumar work in progress Detail Report
Graph / Photo
469 Annual Running Annual Running Maintenance and Operation of Street light and High Mast light i/c monitoring of Street lights at Vrs location under M-251. SH- Comprehensive maintenance of LED fittings in trans Yamuna Area 19/10/2018 18/10/2019 17.96 35.30 (Jan'20) 0.00 (Jan'20) M/s Shaka Electrical (India) Detail Report
Graph / Photo
470 A/R and M/O to various roads under PWD Division South West Road-I during 2018-19. SH- Providing of Maintenance Van with required Labour and TandP for Day to Day Upkeeping of Roads Under Sub Division-II. 28/03/2019 27/03/2020 17.87 Jayant Singh Detail Report
Graph / Photo
471 AR and MO Various Roads under PWD Division S.W R II New Delhi during 201819 SH Repair of roof and doors of inspection chamber of drain on Bharthal road Sub Division24 25/04/2019 23/06/2019 17.86 Surender Singh agreement forfeited Detail Report
Graph / Photo
472 AR and MO TO VARIOUS ROADS OF PWD DIVISION NORTH WEST ROAD I UNDER SUB DIVISION NORTH WEST ROAD 11 DG 2018 19 SH REPAIRS OF FOUNTAIN AND PLANTERS AT ROAD NO 44 and FINISHING WORK OF LAWRENCE ROAD UNDERPASS 3rd CALL 19/12/2018 18/03/2019 17.75 VV Associates Detail Report
Graph / Photo
473 A/R and M/O various roads under SRD Division-I, PWD, New Delhi during 2018-19. (SH-Improvement of drainage system at Various Roads under Sub Division-II) 13/07/2018 12/10/2018 17.70 0.00 (Jan'19) 21.69 % (Jan'19) A.R Infrastructure Work Completed and final bill paid Detail Report
Graph / Photo
474 Replacement of defunct storm water line from South Ganesh Nagar to Pandav Nagar Complex and raising of road level of Ganesh Chowk. 27/02/2019 13/03/2019 17.70 22.11 (Mar'21) 0.00 (Mar'21) Shiv Construction Co.

Work in progress

Detail Report
Graph / Photo
475 Strengthening, Improvement of footpath, Construction of box drain and providing and fixing road signages in Sector-21, Rohini, Delhi (SH- Microsurfacing of Bituminous road.) 08/03/2019 05/06/2019 17.69 21.39 (Jan'20) 0.00 (Jan'20) Pawan Kumar Detail Report
Graph / Photo
476 Restoration of Road cutting by various agencies under Sub Division-III dg 2019-20 Jafferpur Section Division SWR-II 05/08/2019 02/12/2019 17.67 20.20 (Jul'20) 0.00 (Jul'20) ASH NARAYAN SINGH work completed Detail Report
Graph / Photo
477 Restoration of various roads cut by various agency for laying of services under Section -II, Sub. Division-I, East Road M-212 Delhi 18/07/2019 16/08/2019 17.64 22.10 (Nov'19) 0.00 (Nov'19) ROAD TECH

Work in progress

Detail Report
Graph / Photo
478 A/R and M/O PWD roads under Sub Division-1 of Division C and ND Roads during 2017-18. SH_Providing and placing Jersey barriers at main Burari Road from Outer Ring Road to Hiranki Bandh. 07/09/2017 06/12/2017 17.62 Gaurav Construction Co. Detail Report
Graph / Photo
479 Providing and operating movable type Diesel Engine Pump set at various locations under sub division 2. 07/04/2019 21/10/2019 17.56 21.77 (Nov'19) 0.00 (Nov'19) Ravinder Kumar Work in progress. Detail Report
Graph / Photo
480 A/R and M/O Roads under Sub Division-I of Division CandND-Roads during 2018-19. SH Construction of boundary wall and fixing of barbed wire at Ramghat Wazirabad Delhi. 13/12/2018 12/05/2019 17.55 21.64 (Dec'19) 0.00 (Dec'19) M. A. Builders Detail Report
Graph / Photo
481 Annual Maintenance of Various Roads under Hort. Sub Division (Project), Hort. Division (East), PWD, Delhi during 2019-20 27/05/2019 26/05/2020 17.54 21.23 (May'21) 0.00 (May'21) Raj KumarSaini Detail Report
Graph / Photo
482 Mechanical desilting of road side storm water drain and sewer mixed drains and culvert by super sucker machine on Outer Ring Road, Road No 13, Bipin Chanderpal Marg, Gurudwara Road and EPDP 09/03/2019 04/10/2019 17.41 4.62 (Mar'21) 0.00 (Mar'21) Buland Constructions The 20% work has been completed.. Detail Report
Graph / Photo
483 AR MO to Various Roads under SWR II PWD during 201819 SH Providing of Maintenance Van required labours TP for day to day upkeeping maintenance of roads under sub division 21 New Delhi 11/04/2019 09/04/2020 17.32 Surender Singh work forclosed Detail Report
Graph / Photo
484 RMO various roads in North East Delhi under the jurisdiction of M-251 during 18-19, Delhi. (SH- Supplying and fixing of street lights pole, fittings, at khajoori flyover service road and other location under M-251) 07/04/2019 06/06/2019 17.28 S K Engineers Detail Report
Graph / Photo
485 A/R & M/O to Various Roads under Sub-Division East Road-II of PWD Division East Roads/ (M-212), Delhi during 2021-22. SH: Repair of Bituminous road in patches from NH-24 Ghazipur to Kondli Bridge 13/10/2021 12/12/2021 17.22 Kundu Nirman Detail Report
Graph / Photo
486 Road Restoration work at Block No. 6,7,8 Khicharipur road and Kalyanvas Road Delhi during 2018-19 07/03/2019 20/04/2019 17.21 11.83 (Jun'20) 0.00 (Jun'20) Bansal Construction Co

Work in progress

Detail Report
Graph / Photo
487 Improvement of road under SRD Project Sub Divn.-II/SRD Project Divn.-II, PWD, New Delhi. SH:- Providing and fixing M.S. Grill on Central verge at Azad Market road 04/01/2019 03/04/2019 17.20 19.69 (Sep'21) 0.00 (Sep'21) M/s Shakur Ahmed & sons Work in Progress Detail Report
Graph / Photo
488 M/o diff. Hort. works under Hort. Sub Divn. (East), HD East, GNCTD, Delhi dg 2018-19 06/10/2018 05/10/2019 17.13 17.11 (May'21) 0.00 (May'21) Paras Enterprises Detail Report
Graph / Photo
489 A/R & M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH:- Repairing of culverts and other misc. repair work at Loni Road under PWD Sub Division 4). 19/09/2019 17/11/2019 17.10 PVCON Engineering Co. Detail Report
Graph / Photo
490 A/R & M/O various road under Sub Division M-2112 during 2021-22. (SH. Providing and placing of RCC slab M-35 grade along service road, Road No. 58 and Polycarbonate sheet at Vishwakarma underpass). 16/10/2021 29/11/2021 17.06 Johri Constructions Detail Report
Graph / Photo
491 R/R of various roads cut by various agencies for laying cables, pipes, fault repair etc. under PWD Section-1, Sub Division NWR-23, Division NWR-2 during 2018-19. 28/08/2018 26/10/2018 17.04 Dinesh Kumar Detail Report
Graph / Photo
492 Improvement of Central Verge, Footpath and drainage system near New Ashok Nagar Metro Station 17/03/2019 30/04/2019 16.98 14.02 (Oct'20) 0.00 (Oct'20) Shiva Construction

Work in progress

Detail Report
Graph / Photo
493 Repairing of 30 Meter High Mast and Replacement of Conventional HPSV Fittings with LED Fittings at Scattered Location on PWD Road under PWD EMD South East New Delhi 23/09/2018 22/11/2018 16.97 Goel Electric Works 52% Work Completed Detail Report
Graph / Photo
494 SH MODIFICATION OF CROSSING and PROVIDING AND FIXING OF SFRC RAILINGS AT CENTRAL VERGE UNDER SHALIMAR BAGH ELEVATED ROAD UNDER SUB DIVISION NW R 14. 04/01/2019 17/02/2019 16.95 19.27 (May'19) 0.00 (May'19) TKN Developers Detail Report
Graph / Photo
495 A/R & M/O to various roads under PWD Sub Division M-2132 dg. 2017-18. (SH:- Repair of drain in PWD yard and P/L K-9 pipe). 27/02/2018 27/04/2018 16.83 Kunal Vashishth Agreement cancelled 25/04/2018 Detail Report
Graph / Photo
496 AR and MO TO VARIOUS ROADS OF PWD DIVISION NORTH WEST ROAD I UNDER SUB DIVISION NORTH WEST ROAD 11 DG 2018 19 SH REPAIRS OF FOUNTAIN AND PLANTERS AT ROAD NO 44 and FINISHING WORK OF LAWRENCE ROAD UNDERPASS 24/05/2018 21/08/2018 16.79 Jitender Singh Work resigned. Detail Report
Graph / Photo
497 A/R and M/O PWD Roads under Sub Division-3 of Division C and ND- Roads during 2018-19. SH_Making footpath disable friendly on Ghata Masjid Road, Nishad Raj Marg, I.G. Slip Road and other Miscellaneous repair work. 26/01/2019 25/03/2019 16.78 18.91 (Sep'19) 0.00 (Sep'19) Paras Nath Singh Detail Report
Graph / Photo
498 A/R & M/O various roads of PWD Division NW R-1 under sub division NWR-12, Delhi dg. 2018-19. (SH: Repair of footpath At Ashok Vihar PH-III and IV). 05/01/2019 03/02/2019 16.73 20.49 (May'19) 0.00 (May'19) Pawan Kumar Gupta Detail Report
Graph / Photo
499 Installation and repair of Signage Boards under Sub Division -21, New Delhi 20/09/2021 19/12/2021 16.69 AMAN CHOUDHARY Detail Report
Graph / Photo
500 A/R and M/O to various roads under PWD Division NWR-2 during 2017-18.(SH- Providing and applying 2.5mm thick thermoplastic road marking strips under sub- division NWR-24.) 10/01/2018 08/02/2018 16.63 Tripurari Prasad Singh Detail Report
Graph / Photo
501 AR AND MO VARIOUS ROADS UNDER DIVISION NW R 1DELHI DG 2018 19 SH MISC REPAIR OF FOOTPATH OF VARIOUS ROADS OF PITAMPURA AREA UNDER SUB DIVISION NW R 14. 06/03/2019 04/05/2019 16.63 Sanjay Kaura Detail Report
Graph / Photo
502 AR AND MO VARIOUS ROADS PWD DIVISION NW R 1 DG 2018 19 SH PATCH REPAIR WORK UNDER NW R 15. 06/03/2019 04/04/2019 16.63 Raj Associates Detail Report
Graph / Photo
503 A/R and M/O PWD roads under Sub Division -2 of Division C and ND-Road during 2018-19. SH_Improvement of drainage from Tripolia Gate (Kalyani Kunj/Gur Mandi Road) to Najafgarh Road. 24/11/2018 23/02/2019 16.58 JASWANT CONSTRUCTIONS Detail Report
Graph / Photo
504 Improvement of drainage system from Old Pandav Nagar Police Station to Shashi Garden More DTC bus stop, Kotla Road, Delhi 23/12/2018 20/02/2019 16.57 9.10 (Feb'20) 0.00 (Feb'20) KRISHAN KUMAR MISHRA

Work in progress

Detail Report
Graph / Photo
505 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (Sh-- P/F of missing steel railings at central verge and Planters on Dr. K.N.Katju Marg, B-5 and B-8 Road, Rohini, Delhi under Section-II, under Sub Division NWR-23.) 25/02/2019 25/04/2019 16.50 17.79 (Nov'20) 0.00 (Nov'20) Ashish Gupta Detail Report
Graph / Photo
506 Providing services for special inspection, analysis of existing structure, BOQ for Repair and Rehabilitation of Nehru Nagar Flyover ROB existing between Lajpat Nagar and Ashram Flyover on Ring Road (2nd Call). 21/03/2018 18/06/2018 16.50 Construma Consultancy Pvt. Ltd.

Work in Progress

Detail Report
Graph / Photo
507 Providing services of maintenance vehicle with labour and T & P in sub division M-3123 for section-I. 14/02/2016 13/02/2017 16.48 0.00 (Aug'16) 72.00 % (Aug'16) Ajay Kumar work in progress Detail Report
Graph / Photo
508 A/R and M/O to various roads under PWD Division NWR-2 during 2018-19. (SH- Beautification work at Road No.318 under Section-1, Sub Division NWR-21.) 17/06/2018 15/08/2018 16.44 Jitender Singh Detail Report
Graph / Photo
509 A/R and M/O PWD roads under Sub-Division-II of Division CandND-Roads during 2018-19. SH_Remodeling of drainage system by providing pipe drain at approaches instead of box drain for ease in cleaning and repair of road at truck parking Timarpur. 17/12/2018 16/02/2019 16.44 12.62 (Jun'19) 0.00 (Jun'19) JASWANT CONSTRUCTIONS Detail Report
Graph / Photo
510 A/R and M/O PWD roads under Sub-Division-II of Division CandND-Roads during 2018-19. SH_Desilting of drain by removing blockage by dismantling of slab over drain. 03/01/2019 01/05/2019 16.43 25.14 (Jun'19) 0.00 (Jun'19) K.P. Singh & Co. Detail Report
Graph / Photo
511 Repair of Footpath, Protection wall and drains 17/10/2018 30/11/2018 16.40 20.11 (Apr'21) 0.00 (Apr'21) Bala ji associates

Work in progress

Detail Report
Graph / Photo
512 A/R and M/O to various roads under SRD Project Division-I, PWD, New Delhi during 2017-18. (SH- Making footpath and Cycle track at Ranjeet Singh Marg over newly constructed drain, under Sub Division-II) 24/08/2017 23/10/2017 16.39 0.00 (Oct'17) 20.53 % (Oct'17) B P Rai and Sons Work completed and final bill paid Detail Report
Graph / Photo
513 Repair of service road at Road No.43 (Guru Harkishan Marg) Delhi. 27/06/2016 25/08/2016 16.36 Pawan Kumar work in progress,Provisional EOT granted upto 30.09.2016. Detail Report
Graph / Photo
514 SH- Repair work on Road No. 42-A under Sub Division NWR-21. 19/01/2018 19/03/2018 16.34 Sudesh Kumar Detail Report
Graph / Photo
515 Misc. Repair works 21/08/2016 18/11/2016 16.25 Raj Associates . Detail Report
Graph / Photo
516 SH- Comprehensive Maintenance of street lights, Replacement of accidental poles and providing wiremesh protection for feeder pillars at scattered location at Various Roads throughout the year.) 05/02/2019 04/02/2020 16.20 14.56 (Oct'19) 0.00 (Oct'19) Bhardwaj Brothers Detail Report
Graph / Photo
517 A/R & M/O various roads under PWD Sub-Division M-4422 during 2015-16 (SH: Repair of footpath, kerb stone etc on Pramod Mahajan Marg, Mandir Marg and Birla Vidya Niketan Marg, New Delhi. 22/06/2015 21/08/2015 16.19 Naresh Kumar Detail Report
Graph / Photo
518 A/R and M/O to various roads under PWD Division NWR-2 during. 2017-18 (SH- Providing services of maintenance vehicle with labour and T and P for Section-I, under Sub Division NWR-25.) 03/12/2017 02/12/2018 16.14 6.59 (Sep'19) 0.00 (Sep'19) ABHILEKH YADAV Detail Report
Graph / Photo
519 Strengthening, Improvement of footpath and providing and fixing retro-reflective road signages and upgradation of street lighting on roads at Sector-6, Rohini, Delhi. (SH- Microsurfacing of Bituminous road.) Re-call. 23/03/2019 20/06/2019 16.12 Pawan Kumar Detail Report
Graph / Photo
520 Restoration of Sri Aurobindo Marg ( PTS RED LIGHT to Qutub DJB pump house) and Basant Kaur Marg under Sub. Div. -V of Division South Road-II, PWD, New Delhi dg. 2020-21. 30/07/2020 29/10/2020 16.10 14.54 (Nov'20) 0.00 (Nov'20) AMOCON Work in Progress Detail Report
Graph / Photo
521 A/R & M/O various Roads under SRD Project Sub Division- I/SRD Project Division –II PWD, New Delhi,during 2017-18.SH:- Repair of central verge railing of link road, Panchkuiyan road and other repair work 20/03/2018