Norms set for the discharge of functions

MANUAL - 4

NORMS SET FOR THE DISCHARGE OF FUNCTIONS (SECTION 4(1)(B)(IV))

S.No. Activities Time taken / Norm Remarks
1 Preparation of preliminary drawings of a project 4 months after receipt of requisition from the client department
2 Receipt of final approval from the client. 3 months (Approx.)
3 Approval of drawings from the local bodies, DUAC, Fire department, Air safety department, Metro Railways etc. One year after submission of drawings.
4 Preparation of Preliminary estimate of the project 3 months (Building works)
1 month (Road works)
5 Receipt of administrative approval and expenditure sanction 6 months after submission of Preliminary Estimate (Approx.)
6 Appointment of consultants 3 months for both building & road works
7 Preparation of detailed estimates and NIT 3 months (Buildings & Road works)
8 Checking of detailed estimates and NIT 45 days (Building)
30 days (Road)
9 Call of tenders after approval of DE 30 days
10 Acceptance of tenders 60 days from date of receipt
11 Start of project in the field 30 days after acceptance (Maximum)
12 Disposal of extra / substituted items One month after initiation