NORMS SET FOR THE DISCHARGE OF FUNCTIONS (SECTION 4(1)(B)(IV))
| S.No. | Activities | Time taken / Norm | Remarks |
|---|---|---|---|
| 1 | Preparation of preliminary drawings of a project | 4 months after receipt of requisition from the client department | |
| 2 | Receipt of final approval from the client. | 3 months (Approx.) | |
| 3 | Approval of drawings from the local bodies, DUAC, Fire department, Air safety department, Metro Railways etc. | One year after submission of drawings. | |
| 4 | Preparation of Preliminary estimate of the project |
3 months (Building works) 1 month (Road works) |
|
| 5 | Receipt of administrative approval and expenditure sanction | 6 months after submission of Preliminary Estimate (Approx.) | |
| 6 | Appointment of consultants | 3 months for both building & road works | |
| 7 | Preparation of detailed estimates and NIT | 3 months (Buildings & Road works) | |
| 8 | Checking of detailed estimates and NIT |
45 days (Building) 30 days (Road) |
|
| 9 | Call of tenders after approval of DE | 30 days | |
| 10 | Acceptance of tenders | 60 days from date of receipt | |
| 11 | Start of project in the field | 30 days after acceptance (Maximum) | |
| 12 | Disposal of extra / substituted items | One month after initiation |