C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Daryapur kalan, Delhi.
Office Name
Education North Maint Divn
History Sheet     Abstract of Cost     Background Note        
T.S. Amount
3693.99 Lacs
Dated
02/01/2020
Progress Details
Date of Start: 30/05/2020
Date of Completion: 29/05/2021
Expected Date of Completion: 31/10/2022
Actual Completion Date:
Payment
Civil:   Lacs (Nov 2021)
% Progress :30.00 % (Nov 2021)
Present Position
Civil :  03/08/2022
Structure work completed. Partition work with bricks in progress. Tile, plaster and granite work is in progress. Truss work of MP Hall completed. Clading work with Dholpur sand stone in progress. Plumbing work is in progress. Coba work on terrace is in progress. Construction of UG tank is in progress.