Construction of additional SPS Class room in existing premises under Jurisdiction of District East and North East Delhi Priority II SH Const 182 Nos. of additional SPS class rooms in various schools under East and North East Education Division, PW
Office Name
Education East & North East Maint Divn
T.S. Amount
4029.10 Lacs
Dated
06/09/2018
Tender Amount
3699.32 Lacs
Dated
16/03/2019
Progress Details
Date of Start: 17/03/2019
Date of Completion: 11/12/2019
Expected Date of Completion: 11/12/2019
Actual Completion Date:
Contractor
M/s SPS Infrabuild Pvt. Ltd.
Payment
Civil:   Lacs (Oct 2019)
% Progress :28.00 % (Oct 2019)
Present Position
Civil :  04/10/2019
Work in Progress