Sub Work (Agreements) Details | |||||||
---|---|---|---|---|---|---|---|
S.No. | Sub Work Name |
P.E. Amount
Tender Amount |
Date of Start
Date of Completion |
Expected Date of Completion
Actual Date of Completion |
Fincl. Exp. % Prog |
MB
Bill |
Remarks |
1 | Repairing of 400 and 100TR Capacity Carrier make control AC Plant |
--
24.48 |
28/08/2021 27/11/2021 |
27/11/2021 27/11/2021 |
36.71 Lacs (Jan 2022)
% (Jan 2022) |
--
-- |
NIL |
2 | Comprehensive Maintenance of Johnson make Lifts |
--
23.05 |
05/01/2022 04/01/2024 |
04/01/2024 08/04/2022 |
13.21 Lacs (Jun 2023)
-- |
--
-- |
-- |
3 | Comprehensive maintenance of 1 No. x 400 TR chiller of Daikin Make installed at Vikas Bhawan-II |
--
16.15 |
28/02/2022 27/02/2023 |
27/02/2023 08/04/2022 |
24.16 Lacs (Jun 2023)
% (Jun 2023) |
--
-- |
-- |
4 | Comprehensive Maintenance of Johnson Lifts |
--
10.71 |
22/10/2020 21/10/2021 |
21/10/2021 21/10/2021 |
12.84 Lacs (Mar 2022)
% (Mar 2022) |
--
-- |
Work in Progress |
5 | Running Operation and Routine Maintenance of Central AC Plant |
--
8.11 |
09/04/2021 08/04/2022 |
08/04/2022 08/04/2022 |
14.91 Lacs (Mar 2023)
% (Mar 2023) |
--
-- |
NIL |
6 | Comprehensive Maint of carrier make AC Plant |
--
-- |
--
-- |
08/04/2022 |
--
-- |
--
-- |
Work in Progress |
7 | Comprehensive Maint of carrier make AC Plant |
--
-- |
--
-- |
08/04/2022 |
--
-- |
--
-- |
-- |
8 | Operation of carrier make AC Plant |
--
-- |
--
-- |
08/04/2022 |
--
-- |
--
-- |
Work in Progress |
9 | Comprehensive Maintenance of Johnson Lifts |
--
-- |
--
-- |
08/04/2022 |
--
-- |
--
-- |
Work in Progress |
10 | Comprehensive Maintenance of Johnson Lifts |
--
-- |
--
-- |
08/04/2022 |
--
-- |
--
-- |
Work in Progress |
11 | Comprehensive Maintenance of Johnson Lifts |
--
-- |
--
-- |
08/04/2022 |
--
-- |
--
-- |
-- |