Repair of old building wall, roof and floor, Grit wash plaster, sewerline, repair of stair case, replacement of windows.
Office Name
North Building Division
History Sheet     Abstract of Cost     Background Note        
T.S. Amount
98.27 Lacs
Dated
17/10/2019
Tender Amount
50.60 Lacs
Dated
18/11/2019
Progress Details
Date of Start: 18/11/2019
Date of Completion: 16/04/2020
Expected Date of Completion: 28/02/2021
Actual Completion Date: 28/02/2021
Contractor
M/s Saeed Builders
Payment
Civil:  51.80 Lacs (Nov 2020)
% Progress : % (Nov 2020)
  
Present Position
Civil :  27/04/2022
No works since previous month
Bottlenecks
Civil :  27/04/2022
No works since previous month