Construction of SPS Smart Class Rooms for 1500 Students in NSUT Campus, Sector-3, Dwarka, New Delhi.
Office Name
Education Project Division II
Tender Amount
2098.00 Lacs
Dated
10/11/2019
Progress Details
Date of Start: 13/09/2019
Date of Completion: 12/02/2020
Expected Date of Completion: 31/03/2021
Actual Completion Date: 20/01/2021
Contractor
M/s Aastha Engineers And Contractors
Payment
Civil:   Lacs (Dec 2020)
% Progress :10.00 % (Dec 2020)
Present Position
Civil :  03/04/2021
Work completed . EOT sanctioned. Final bill yet to be submitted by the agecny.
Bottlenecks
Civil :  03/04/2021
nil