Co 180 Nos of addl SPS classrooms at various schools under North Edu. Divn, PWD, Delhi including int. and ext. water supply, fire fighting system etc. Pkg 10
Office Name
Education North Maint Divn
T.S. Amount
3640.94 Lacs
Dated
31/08/2018
Tender Amount
3304.27 Lacs
Dated
17/03/2019
Progress Details
Date of Start: 17/03/2019
Date of Completion: 11/12/2019
Expected Date of Completion: 20/03/2022
Actual Completion Date: 20/03/2022
Contractor
M/s Tewatia Construction Pvt. Ltd.
Payment
Civil:  5154.19 Lacs (Mar 2023)
% Progress : % (Mar 2023)
Present Position
Civil :  11/07/2022
Work completed.