GGSSS Vijay Park,Moujpur,New Delhi
Office Name
Education East & North East Maint Divn/Education Elect Maint Division 2
History Sheet                
Progress Details
Date of Start: 11/03/2016
Date of Completion: 23/07/2016
Expected Date of Completion: 12/10/2017
Actual Completion Date: 12/10/2017
Contractor
M/s A. K. Builders
Payment
Present Position
Civil :  15/05/2018
16 Rooms Completed
Bottlenecks
Civil :  15/05/2018
Work completed