GGSSS Janta Flat Nand Nagari
Office Name
Education East & North East Maint Divn/Education Elect Maint Division 2
History Sheet     Abstract of Cost     Background Note        
Progress Details
Date of Start: 27/03/2016
Date of Completion: 08/08/2016
Expected Date of Completion: 30/06/2017
Actual Completion Date: 30/06/2017
Contractor
M/s M/s S.P.G Infraprojects Pvt Ltd
Payment
Present Position
Civil :  01/08/2019
64 Rooms & 1 MP Hall completed
Bottlenecks
Civil :  01/08/2019
Completed