GGSSS-3 Molarband
Office Name
Education South & South East Maint Divn
History Sheet         Background Note        
T.S. Amount
1672.10 Lacs
Dated
09/01/2016
Progress Details
Date of Start: 13/03/2016
Date of Completion: 25/07/2016
Expected Date of Completion: 31/03/2017
Actual Completion Date: 15/04/2017
Contractor
M/s Subham Builders
Payment
Civil:  3079.17 Lacs (Feb 2024)
% Progress : % (Feb 2024)
Present Position
Civil :  15/05/2018
completed