"Rehabilitation of rain water Harvesting System at SKV No. D- Block Janakpuri, New Delhi. "
Office Name
South West Building & Dwarka Court Maintenance Division
History Sheet                
Progress Details
Date of Start: 09/05/2016
Date of Completion: 08/07/2016
Expected Date of Completion: 08/07/2016
Actual Completion Date: 08/07/2016
Payment
Civil:  4.23 Lacs (Aug 2017)
% Progress :100.00 % (Aug 2017)
Present Position
Civil :  18/10/2016

Work Completed. Final bill yet to be submitted by agency.

Bottlenecks
Civil :  18/10/2016

null