Const of under ground water tank. Kalyan Vas-SKV
Office Name
East Building Division
History Sheet                
Progress Details
Date of Start: 05/11/2015
Date of Completion: 04/02/2016
Expected Date of Completion: 04/02/2016
Actual Completion Date: 24/04/2017
Payment
Present Position
Civil :  01/11/2017
Work Completed
Bottlenecks
Civil :  01/11/2017
Work completed