Repairs of outside plaster & Finishing
Office Name
South East Building Maintenance Division
History Sheet                
Progress Details
Date of Start: 21/07/2016
Date of Completion: 20/10/2016
Expected Date of Completion: 20/10/2016
Actual Completion Date: 28/01/2017
Payment
Civil:  11.78 Lacs (Feb 2017)
% Progress :100.00 % (Feb 2017)
Present Position
Civil :  26/07/2017
Estimate submitted to Principal vide letter No.23(05)/EE(N)/DB/PWD/16-17/ 1480 Dt.17.06.2016
Bottlenecks
Civil :  26/07/2017