SSS(Co-Ed) Holambi Kalan Block G
Office Name
Education North West Maint Divn
History Sheet         Background Note        
Tender Amount
1618.87 Lacs
Dated
27/02/2016
Progress Details
Date of Start: 25/02/2016
Date of Completion: 11/07/2016
Expected Date of Completion: 15/06/2017
Actual Completion Date: 17/07/2017
Contractor
M/s Shri Construction Co.
Payment
Civil:  481.26 Lacs (Jul 2018)
% Progress :100.00 % (Jul 2018)
Present Position
Civil :  16/11/2018
Work completed