C/o additional SPS Class rooms in existing premises under Jurisdiction Zone-17 of District West-B (Priority-I) (SH:- C/o SPS Type rooms, labs, MP Halls i/c internal & External water supply, sanitary installation and electrical installation, development of site and Fire Fighting System etc. at G.(Co.Ed) SSS Baprola) (Package-D)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet         Background Note        
T.S. Amount
1266.21 Lacs
Dated
11/01/2016
Tender Amount
1253.55 Lacs
Dated
26/02/2016
Progress Details
Date of Start: 29/02/2016
Date of Completion: 12/07/2016
Expected Date of Completion: 31/03/2017
Actual Completion Date: 15/05/2017
Contractor
M/s Satya Narain
Payment
Civil:  22.14 Lacs (Jul 2019)
% Progress :100.00 % (Jul 2019)
Present Position
Civil :  11/10/2019
Work completed & 100 rooms handed over.
Bottlenecks
Civil :  11/10/2019
Null