C/o additional SPS Class rooms in existing premises under Jurisdiction Zone-17 of District West-B (Priority-I) (SH:- C/o SPS Type rooms, labs, MP Halls i/c internal & External water supply, sanitary installation and electrical installation, development of site and Fire Fighting System etc. at Govt. School, Mundka) (Package-B)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet         Background Note         NIT Document
T.S. Amount
1259.82 Lacs
Dated
11/01/2016
Tender Amount
1246.72 Lacs
Dated
09/03/2016
Progress Details
Date of Start: 14/03/2016
Date of Completion: 26/07/2016
Expected Date of Completion: 15/03/2017
Actual Completion Date: 25/08/2017
Contractor
M/s Mathra Dass Ahuja & Sons
Payment
Civil:  29.36 Lacs (Dec 2023)
% Progress : % (Dec 2023)
Present Position
Civil :  11/10/2019
Work completed & 84 rooms handed over.
Bottlenecks
Civil :  11/10/2019
Null