GSKV Tikri Kalan (PACKAGE-A)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet         Background Note        
T.S. Amount
1921.73 Lacs
Dated
11/01/2016
Tender Amount
1897.94 Lacs
Dated
10/03/2016
Progress Details
Date of Start: 16/03/2016
Date of Completion: 28/07/2016
Expected Date of Completion: 31/03/2017
Actual Completion Date: 30/06/2017
Contractor
Mr B. L. INFRA PROJECTS PVT. LTD.
Payment
Present Position
Civil :  11/10/2019
Work completed 64 rooms handed over.
Bottlenecks
Civil :  11/10/2019
Null