Govt. school G-Block Vikaspuri (Package-C)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet         Background Note         NIT Document
T.S. Amount
16.85 Lacs
Dated
12/01/2016
Tender Amount
1660.73 Lacs
Dated
26/02/2016
Progress Details
Date of Start: 29/02/2016
Date of Completion: 12/07/2016
Expected Date of Completion: 15/01/2017
Actual Completion Date: 01/12/2017
Contractor
M/s Satish Builders
Payment
Present Position
Civil :  11/10/2019
Work completed & 52 rooms handed over.
Bottlenecks
Civil :  11/10/2019
Null