Education Work
Last Updated on: 24/05/2019
Report of E.O.R. Works of School - Progress
S. No. Name of School Sanction Amount
/ Date / No
Date of Start / Completion / Expected Expenditure / Progress Remarks View
South East Maintenance Circle
South East Building Maintenance Division
2017-18
1 Repair and renovation of DOE (Science and T.V. Branch) office 2nd floor at Old Gargi College Building Lajpat Nagar-IV, New Delhi during 2018-19. Agreement No .: 55/EE/South-East(Bldg.)M/PWD/2018-19 0.21 Cr.
19/09/2017

No. DE. 40(6)/86/SDB/Part file/2213-17/844 Dated: 19.09.2017

05/08/2018
04/11/2018
04/11/2018

Work in progress Detail Report
2 EOR to SKV Hari Nagar Ashram, New Delhi during 2015-16 (SH: 4 nos. class change of roof AC sheet to convert Ref Sand Stone roof & grider and T iron fram Kota Stone Slab flooring 25mm thick Kota stone slab

10/07/2015
09/09/2015
09/09/2015
0.10 Cr.
100.00 %
Detail Report
3 Renovation of Toilet Blocks & Repair to AC Sheet of Classrooms & Providing Water Proofing Treatment at Tughlakabad Village School



14/02/2015
0.14 Cr.
100.00 %
Detail Report
South East Elect Maintenance Division
2016-17
4 Special repair and replacement of EI and Fans in classroom and corridoors and renovation in the hall at SKV NO.2, Kalkaji, New Delhi (ID- 1925038) 0.11 Cr.
19/05/2016

2015000088, F.16/Estate/GSKV NO.2 Kalkaji, New D

14/08/2016
13/10/2016
13/10/2016

work in progress Detail Report
5 Special Repari of Ei & Fans, Panel and compound light in Govt. Sarvodaya Vidyalaya, Ali Ganj, New Delhi. 0.10 Cr.
01/06/2016

SV/AG/2016/348

14/08/2016
13/10/2016
13/10/2016

work in progress Detail Report
2015-16
6 Renovation of EI & replacement Electricals accessories at HARKESH NAGAR GGSSS (ID-1925341) 0.10 Cr.
18/03/2016

.

25/06/2016
24/07/2016
25/09/2016

Work in Progress Detail Report
7 Supply installation testing and commissioning of Surveillance system and flood light fitting at Deffence Colony,Block A-SNSKV-1924025 0.10 Cr.
30/09/2015

.

20/05/2016
19/06/2016

Work in Progress 95% Detail Report
8 Providing & fixing wiring,rewiring,DB,MCB,earthing,electrical light fittings,ceiling fans,flood light fitting and UG cable in GGSS No-3 Molar Band New Delhi. 0.07 Cr.
04/08/2015

.

23/04/2016
31/05/2016
31/05/2016

Work in Progress 80% Detail Report
9 RMO Swimming pool at Sister Nivedita Sarvodaya Kanya Vidyalay "A" Block Defence Colony,New Delhi.(SH:-Operation and Maintenance of electric pumps,fitration plants and allied equipment of swimming pool.) 0.05 Cr.
31/03/2016

.

17/05/2016
16/11/2016
16/11/2016

Work in Progress Detail Report
10 S/I/T/C of water cooler & RO System at Kalkaji,No.2-SKV (ID-1925038) 0.02 Cr.
27/12/2015

.

25/06/2016
24/07/2016
25/09/2016

Work in Progress Detail Report
SE (Education) M
EE (Education) M, East & North East
2017-18
11 Construction of Boundary wall at Newly proposed higher Secondary School at Geeta Colony Delhi. Agreement No .: 09/EE/Edu M (E & NE)/PWD/DS/2018-19 0.16 Cr.
10/10/2017

F. 17/Estate/Const./Boundary Wall/Geeta Colony/3627-30 dt. 10/10/2017

14/02/2019
14/05/2019
14/05/2019

20.00 %
Brick work in foundation in progress. Detail Report
EE (Education) (North West)
2014-15
12 Construction of Govt Sr Sec School Pucca Building at Rohini Sector4 Extension Delhi SH Annual Maintenance of Computers and other accessories in Division Office Edu M NW and Sub Division Offices Agreement No .: 04/EE/PWD/Edu(M)(NW)/2018-19 18.06 Cr.
24/06/2014

Chargeble to F.2(5)/2014-15/012274603 /Fin/infra/Exp4/542-552 dated 24.06.2014 amounting to Rs. 18.06 Cr.

26/07/2018
25/07/2019
25/07/2019

65.00 %
Work in progress Detail Report
EE (Education) M, C&ND
13 119/EE/2014-15 Agreement No .: 119/EE/2014-15

30/01/2015
28/02/2015
17/06/2015

40.00 %
Work completed. Detail Report
14 misc. repair works repair works at Bunglow No. 48. Ashoka Road, New Delhi Agreement No .: 01/EE/CBMD M- 433/2014-15

19/04/2014
03/05/2014
09/05/2014

WORK COMPLETED Detail Report
South Maintenance Circle
South Electrical Maintenance Division
2016-17
15 Providing and replacing of Ceiling and Exhaust fans in rooms, Corridoors and Toilets at SBV, J Block, Saket, New Delhi (ID-1923056) 0.07 Cr.
09/06/2016

01/07/2016
31/08/2016

90.00 %
Work in Progress Detail Report
16 Installastion of PA System with cable work at Dr. Ambedkar Nagar, Sector-IV No. 1, GGSSS (School Id -1923044) 0.06 Cr.
23/04/2016

GGSSS/No.1/Sect.4/A/N/804 Sanction group 201500003

20/08/2016
19/09/2016

0.01 %

Estimate submitted to Principal vide letter No.23(05)/EE(N)/DB/PWD/16-17/ 1404 Dt.10.06.2016

Detail Report
17 Providing and fixing fans, fittings, LED street light fittings etc. with necessary cabling etc. as reqd. at Govt. Girls Sr. Secondary School , Sector-V, Dr. Ambedkar Nagar, New Delhi-110062.(School Code: 1923050). 0.04 Cr.
04/07/2016

GGSSS No. 2/Sec.5/AN/2016 Sanction Group 2015000196

16/08/2016
15/09/2016

0.01 %
Work complted Detail Report
18 Repair/Re-innovation of security lights & wiring in a 4 nos. Bathroom at Mehrauli Qutab Sarvodaya Bal Sr. Sec. Vidyalaya. (School ID:- 19223120) under AE(E) EMSD-3 (M-South) PTS Malviya Nagar, New Delhi-110017. 0.04 Cr.
09/06/2016

SBSSV/QM/2016-17/50

13/07/2016
20/08/2016

90.00 %
Work in Progress Detail Report
19 Installation of R.O System at Dr. Ambedkar Nagar ,Sector-V , No-2-GGSSS-1923050.
04/07/2016

GGSSS No. 2/ Sec.5/AN/2016/ Sanction Group 2015000195,

20/08/2016
15/09/2016

0.01 %
work completed Detail Report
20 MOEI and Fans at various School under AE(E) M-4512




Detail Report
South Bldg & Saket Court Maintenance Division
21 A/R & M/O to Educational Building and other building under Sub-Division M-4223, M-422, New Delhi duging-2014-15 (SH:- Internal and External finishing work of school building at Saket and Pushp Vihar, New Delhi, section-I) Agreement No .: 22/EE/CBMDM-422/2014-15

24/06/2014
23/12/2014
0.11 Cr.
100.00 %
Detail Report
22 A/R & M/O to Educational Building and other building under Sub-Division M-4223, M-422, New Delhi duging-2014-15 (SH:- Misc. Civil work of School Building at Saket and Pushp Vihar, New Delhi, section-I). Agreement No .: 18/EE/CBMDM-422/2014-15

18/06/2014
17/10/2014
0.18 Cr.
100.00 %
Work completed & agreement closed Detail Report
23 A/R & M/O to Educational Building under Sub-Division M-4223, M-422, New Delhi, dg. 2014-15 (SH:- Repair of RCC column, beams, facia and other misc. repair work of school buildings at Saket and Pushp Vihar, New Delhi, section-1).

23/06/2014
22/12/2014
0.20 Cr.
100.00 %
Work completed & agreement closed. Detail Report
South West Maintenance Circle
South West Building & Dwarka Court Maintenance Division
2016-17
24 Re-boring of Tubewell at Bijwasan (Bharthal), SBV-1821032, New Delhi. 0.02 Cr.
19/04/2016

.

25/06/2016
24/07/2016

NA

Detail Report
2015-16
25 Construction of Double storeyed SPS type rooms for Cal lab,Library,Science labs,toilet for HOS & staff at Govt. Co.Ed.Edn.Dichaon Kalan,New Delhi. 0.98 Cr.
15/10/2015

.

18/12/2017
15/06/2019
15/06/2019
0.34 Cr.
100.00 %
completed Detail Report
26 C/o Boundary wall on the newly taken over plot at village Dera Mandi, New Delhi. 0.93 Cr.
03/11/2015

.

25/03/2016
24/07/2016
24/07/2016

75.00 %
DOSE PERTAIN TO THIS DIVISION Detail Report
27 EOR to Raja Ram Mohan Rai, Hauz Rani, New Delhi. (SH: laying of one borewell & installation of 1 Nos. R.O. System 0.10 Cr.
28/07/2015

.

23/05/2016
23/06/2016
23/06/2016

70.00 %
Dose not pertain to this Division Detail Report
28 Fixing of Hard Drawn febric wire in window in preventing monkey menance in all class room s , labs & other rooms at RSKV, Mehrauli, New Delhi. 0.10 Cr.
17/03/2016

.




30.00 %
Work in progress 30% Detail Report
29 Arrangement of Drinking water facility by bore well at GBSSS No. 1, Khanpur, New Delhi. (School ID : 1923020) 0.06 Cr.
31/07/2015

.

10/05/2016
09/06/2016

50.00 %
Tender re-call and date of opening 24-09-2016 Detail Report
30 EOR to Sarvodaya Co-ed Sr. Sec School at Pandwalan Kalan, New Delhi.(SH:- Construction of collapsed boundary wall). 0.06 Cr.
18/03/2016

22/06/2016
21/08/2016

20.00 %

Work in Progress

Work heldup due Electrical Work.

Detail Report
31 EOR Govt. Boys Sr. Sec. School, Shahbad Mohammadpur, New Delhi (SH- Renovation of toilet, improvement of building and other Misc. work), (School I.D. 1821041) (Building I.D. 18211676). 0.43 Cr.

28/06/2017
27/07/2017
27/07/2017

88.00 %
Work in progress Detail Report
32 (Sh- Construction of Home Science Lab, raising of basket ball court at GGSSS, Dichaon Kalan, New Delhi).

18/12/2018
15/06/2019
15/06/2019
0.34 Cr.
80.00 %
work in progress Detail Report
33 EOR to GGSSS, Bijwasan, Bharthal Road, New Delhi during 2017-18.(SH- Renovation of toilet and water proofing work). Agreement No .: 30/EE/CBMD/M-121/2018-19

18/06/2018
18/08/2018
18/06/2018

receiend Detail Report
34 EOR to GGSSS, Bijwasan, Bharthal Road, New Delhi during 2017-18.(SH- Renovation of toilet and water proofing work).

20/05/2018
18/06/2018
18/06/2018

RESCIND Detail Report
35 EOR to Govt Boys Sr. Sec. School at Goela Khurd New Delhi ( SH- Providing and installation of water treatment plant (R.O. Plant)).

21/03/2019
19/03/2020
19/03/2020

WORK IN PROGRESS Detail Report
36 EOR to Govt Boys Sr. Sec. School at Goela Khurd New Delhi ( SH- Providing and installation of water treatment plant (R.O. Plant)).

21/03/2019
19/03/2020
19/03/2020

work in progress Detail Report
37 EOR to Govt Co-ed Sr. Sec. School Sec-16 A, Dwarka New Delhi during 2018-19. (SH Repairing of boundary wall and providing water Pipe line).

17/06/2018
16/07/2018
16/07/2018
0.02 Cr.
60.00 %
WORK IN PROGRESS Detail Report
38 EOR to Govt Sarvodaya Kanya Vidyalaya Matiala, New Delhi.(Sh- Repair of roof of class rooms, renovation of toilet, water proofing, plaster work, improvement of drainage system and other misc. work).

07/11/2018
05/01/2019
05/01/2019
0.05 Cr.
80.00 %
WORK IN PROGRESS Detail Report
39 Renovation of toilet block with seepage treatment of main building and B- Block toilets ceiling, repair of windows of main building (EOR ID-20161444)




Tender is yet to be floted Detail Report
40 EOR to Govt. Co-ed Sr. Sec. School, Pochanpur, New Delhi.(Sh- Recharging rain water harvesting).

26/08/2018
24/09/2018
24/09/2018
0.08 Cr.
80.00 %
WORK IN PROGRESS Detail Report
41 EOR to Govt. Co-ed Sr. Sec. School, Site-II, Sector-6, Dwarka (ID 1821031), New Delhi-110075. (SH Re- boring of Tubewell).




TENDER CLOSED Detail Report
42 EOR to Govt. Co-ed Sr. Sec. School, Site-II, Sector-6, Dwarka (ID 1821031), New Delhi-110075. (SH Re- boring of Tubewell).




TENDER CLOSED. Detail Report
43 EOR to Govt. Co-ed. Sr. Sec. School at Daulatpur and Govt. Co-ed. Sr. Sec. School at Malikpur, New Delhi. (Sh- C/o Rain Water Harvesting System).

04/03/2019
02/05/2019
02/05/2019

WORK IN PROGRESS Detail Report
44 EOR to Govt. Co-ed. Sr. Sec. School, Raj Nagar Part-II, New Delhi during 2018-19.(Sh- Construction of toilet for children with special needs).

07/02/2019
07/04/2019
07/04/2019
0.05 Cr.
60.00 %
WORK IN PROGRESS Detail Report
45 EOR to Govt. Sarvodaya Vidyalaya (Jose Marti Sec-12, R.K. Puram, New Delhi during 2018-19.(Sh- C/o boundary wall toward Police Quarter, repair of school building and floor, reconstruction of the parapat wall above the library, plastering and white

07/11/2018
05/01/2019
05/01/2019
0.17 Cr.
60.00 %
WORK IN PROGRESS Detail Report
46 EOR to Govt. Sr. Sec. School, Safdarjung Enclave, New Delhi during 2018-19. (SH- Providing and fixing of water filteration RO plant).

22/02/2019
21/02/2020
21/02/2020
0.02 Cr.
65.00 %
WORK IN PROGRESS Detail Report
47 EOR to Pratibha Vikas Vidyalaya, Sec-10, Dwarka under Sub Division-III of SWBMD, New Delhi.(SH- Repairing of toilets, providing shed and other misc. works). (SW- Providing false ceiling, roller blinds, wall tiles and providing shed for music instrume

11/11/2018
09/01/2019
09/01/2019
0.03 Cr.
70.00 %
work in progress Detail Report
48 EOR to SBV Naraina, New Delhi during 2017-18.(SH- Raising of existing boundary wall with concertina coil and P/L kota stone flooring).

19/08/2018
16/11/2018
16/11/2018
0.05 Cr.
80.00 %
WORK IN PROGRESS Detail Report
49 EOR to setting up furnished lab and smart class rooms at SV Vasant Vihar (1720024), New Delhi during 2018-19.(Sh- Civil works). Agreement No .: 126/EE/CBMD/M-121/2018-19

15/10/2018
13/12/2018
13/12/2018

WORK IN PROGRESS Detail Report
50 EOR to Shaheed Captain Amit Verma School, C Block, Inderpuri, New Delhi during 2018-19.(Sh- Providing kota stone flooring in class rooms, corridors, waterproofing on roof in primary section).

19/08/2018
17/10/2018
17/10/2018
0.06 Cr.
60.00 %
WORK IN PROGRESS Detail Report
51 EOR to SKV Matiala, New Delhi under Sub Div-III of SWBMD during 2018-19.(Sh- Recharging of rain water harvesting system).

27/01/2019
25/02/2019
25/02/2019

work in progress Detail Report
52 EOR to SCSR Govt SKV No 1 Palam Enclave New Delhi

24/12/2018
21/02/2019
21/02/2019
0.04 Cr.
65.00 %
WORK IN PROGRESS Detail Report
West Maintenance Circle
Tihar Jail Complex & West Building Division
2015-16
53 EOR to Rajkiya Pratibha Vikas Vidyalaya, BE-Block, Hari Nagar, New Delhi. (SH:- Strenthening of building and renovation all toilets, labs, class rooms and misc. civil works i/c electrical and horticulture). 2.35 Cr.
22/04/2015

Vide Sanction group No. 2014000750/87-96 Dated 22-04-2015

08/03/2016
09/07/2016
30/09/2016
0.45 Cr.
65.00 %
 PE send to Education and sanction awaited Detail Report
West Electrical Maintenance Division
54 SITC of 3 Water Dispenser, 4 Water Cooler including EI work at SKV Hari Nagar (Clock Tower), New Delhi-64. (School ID 1514021)




Work Completed Detail Report
Project Circle
Project Electrical Division
2015-16
55 Renovation work at Swami Dayanand S.K.V. Old Rajender Nagar, New Delhi to develop as Model School. 0.54 Cr.
15/07/2015


30/06/2016

Work Completed

 

Detail Report
SRD Project Division 1
2015-16
56 Improvement of ground with drainage system and providing paver blocks, kota stone flooring in classroom & varandah, repair to boundary wall & other Misc. work at Idhgh road-GGSS 0.09 Cr.
05/06/2015

05/04/2016
04/06/2016

80.00 %
Completed Detail Report
2014-15
57 EOR to Govt.Sarvodaya Vidyalaya Gokhle Marg School,No.2,Mori Gate,Delhi. 0.43 Cr.
01/01/2015

15/04/2016
14/10/2016

10.00 %
Completed Detail Report
58 EOR to Govt Sr.Sec School, Chabi Ganj, Kashmere Gate, Delhi. (SH-Kota stone Flooring and Wall tile in seven Class rooms). 0.43 Cr.
01/01/2015




Detail Report
59 EOR to slabs beams, coloums chajjas by short creting replacement of old & damaged roof treatment and other misc repair work at Sarvodaya Kanya Vidyala,Ahataa Kedara Idgah road Delhi. 0.37 Cr.
09/02/2015

15/04/2016
14/07/2016

15.00 %
Completed Detail Report
60 EOR to Savitri Bai Phule Industrial Training Institute, Mori Gate, Delhi. dg. 2016-17 (SH-Renovation of COPA Lab and Drafting Room like profile sheet, False Ceiling and Virtrified Tiles) 0.37 Cr.
09/02/2015




Detail Report
61 Provision for Rain Water Harvesting Systems in Govt. Girls Sr. Sec. Schools at Bela Road Darya Ganj, Panama Building Jama Masjid, Chabi Ganj Kasmere Gate and S.K.V. No. 2 Jama Masjid under SRD Division-I, Sub-Division-III, PWD, New Delhi.

27/07/2018
26/11/2018
30/06/2019

WORK IN PROGRESS Detail Report
Shahdara Maintenance Circle
Karkardooma Court Division
2015-16
62 Providing Rain Water Harvesting pit, laying interlocking paver block in the ground and raising of boundary wall at Govt. Girls Sr. Sec. School at A Block, Nand Nagri, Delhi Building ID-11061019 0.36 Cr.
11/09/2015

F.16/const/GGSSS/Estate/Shahadara/Delhi/2660-2664

10/06/2016
09/10/2016
15/09/2016

76.00 %
work in progress Detail Report
63 providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. 0.36 Cr.
10/09/2015

01/05/2016
30/06/2016

0.01 %

work in progress

Detail Report
64 Construction of boundary wall at Govt. School Building mayo school and CBSE office in IP Extension Delhi. 0.34 Cr.
18/02/2016

F.16/Estate/site,IPE-I/2011/4139-40

17/07/2016
14/10/2016
14/10/2016

6.00 %

Estimate Sent to  Med. Dir.  GTB vide letter No.  20(02)/fl0Lok0vuq0ea0¼iwoZ½@yks0fu0fo0@2016&17@214 Dated 03.02.2017

Detail Report
65 Renovation of Classrooms, Corridor, Principal Room & Staff Room. 0.28 Cr.
14/03/2016

F.16/Estate/SKV/MPBM Shahadara/

16/06/2016
13/09/2016
13/09/2016

53.00 %

T.S. under process.

Detail Report
66 Renovation of Classrooms, Principal’s Room, Conference Room & Labs. 0.24 Cr.
02/03/2016

F.16/Estate/DIEt/Dilshad Garden/15-16

08/05/2016
05/08/2016
20/08/2016

86.00 %
work in progress Detail Report
67 const. of New cycle stand, Dismantling of tin shed and rovision of free path from toilet to first gate. 0.24 Cr.
30/03/2016

F.16/Estate/GGSSS/C-Block Vivek Vihar/2015-16/5003-5008

13/06/2016
12/07/2016
31/08/2016

11.00 %
Work in porgress Detail Report
68 Renovation of Principal Room, Staff Room and Laboratories. 0.23 Cr.
23/03/2016

F.16/Estate/Mansarovar Park/2015-16(4844-4849)

20/06/2016
18/08/2016
31/08/2016

71.00 %
Work in progress Detail Report
69 Renovation of Classrooms. 0.19 Cr.
20/08/2015

F.16/Estate/BID-11061482/North-East/GGSSS,C-Block,Dilshad Garden/2015-16

07/05/2016
05/07/2016
25/08/2016

66.00 %
Work in progress Detail Report
70 E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi 0.17 Cr.
20/08/2015

10/04/2016
09/06/2016

0.01 %

Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270

Detail Report
71 Provision of boundary wall with iron grill, footpath from second gate to the classrooms & along with boundary wall (Opposite of Park). 0.17 Cr.
28/09/2015

F.16/Const/Estate/GGSSS/VV/Delhi/2965-2969

02/05/2016
30/07/2016
31/08/2016

76.00 %
Work in Progress Detail Report
72 Renovation of MP Hall. 0.15 Cr.
05/08/2015

26/04/2016
24/06/2016

0.01 %
Work recently awarded. Detail Report
73 Renovation of M.P. Hall 0.15 Cr.
05/08/2015

F.16/Estatew/GGSSS/Dilshad Garden/C-Block/NE/2015-16

26/04/2016
04/06/2016
24/08/2016

66.00 %
work in progress Detail Report
74 Repair and renovation of toilets 0.11 Cr.
31/03/2016

F.16/Estate/SKV Shahadara

17/06/2016
15/08/2016
20/08/2016

91.00 %

 Detailed estimate  under process.

Detail Report
75 Repair of boundary wall and toilets. 0.11 Cr.
23/06/2015

2015000115

06/05/2016
03/08/2016
31/08/2016

86.00 %
Work in progress Detail Report
76 Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. 0.07 Cr.
22/08/2015

17/01/2016
30/04/2016

80.00 %
polycarbonate Detail Report
77 Renovation of Toilet, Swimming Pool and other misc. works. 0.07 Cr.
22/08/2015




Detail Report
78 Renovation of toilet & water module. 0.07 Cr.
26/06/2015

22/04/2016


0.01 %

Work Started.

Detail Report
79 Repair of Basketball Court Flooring. 0.06 Cr.
07/08/2015

2015000272

06/05/2016
19/06/2016
31/08/2016

25.00 %
site is not handed over to contractor since in the working areathe work of SPS Detail Report
80 Providing and fixing M.S.Sheet doors and other misc. work. 0.04 Cr.
05/11/2015

22/04/2016
21/05/2016

0.01 %

WORK COMPLETED

Detail Report
81 Construction of water module. 0.03 Cr.
05/11/2015

22/04/2016
20/06/2016

0.01 %
Work recently awarded. Detail Report
2014-15
82 Renovation of M.P. Hall with Toilet Block of G.S.K.V at E Block, Nand Nagri, Delhi 0.21 Cr.
01/01/2015

.

29/01/2016
28/05/2016
31/08/2016
0.07 Cr.
100.00 %
work in progress Detail Report
83 Waterproofing treatment of roof. 0.18 Cr.
14/01/2015

F.16/RSKV/SMV/2013/3329

08/04/2016
06/06/2016
31/08/2016
0.02 Cr.
100.00 %

In progress 80%

Detail Report
East Maintenance Circle
East Building Division
2015-16
84 renovation of toilets on second floor in pucca building Kalyanvas- 0.08 Cr.
28/07/2015

20151391




completed Detail Report
North Maintenance Circle
North Building Division
85 "EOR to SKV No-2 Adrash Nagar under Sub-Division NB-13 Model Town Delhi. (SH: - Replacement of window & misc. repair work). "

05/06/2018
04/10/2018
31/10/2018

Work in progress (5%) Detail Report
86 E.O.R of roof (water proofing treatment) and other misc. work like plinth protection, Door, window, plaster etc. at Govt. Co-ed. Sr. Sec. School, Ghoga, Delhi.

07/10/2018
06/12/2018
06/12/2018

Work in progress (15%) Detail Report
87 EOR TO G.B.S.S.S. at Badli, Delhi. (SH: - Construction of security guard room 2nd main gate for emergency exit, car/ motorcycle parking shed.

08/06/2018
07/11/2018
07/11/2018

Work in progress (40%) Detail Report
88 EOR TO G.B.S.S.S. at Badli, Delhi. (SH: - Development of backside of class rooms, path approaching class rooms & main entrance path.)

08/06/2018
07/11/2018
07/11/2018

Work in progress (40%) Detail Report
89 EOR to Govt.Sarovdaya Kanya Vidyalaya, Lalita block, Shastri Nagar, Delhi. (SH:- Renovation of Ground and first floor toilets, Renovation of Principal room, Staff room and Misc Repair Works.)

21/09/2017
20/12/2017
30/10/2018

Work in progress (80%) Detail Report
90 EOR to Non-residential Building under Sub-Division NB-13, Delhi during 2016-17. (SH: - Construction of R.C.C. boundary wall at Aryabhatt Polytechnic ,G.T. Karnal Road, Delhi).

21/08/2017
20/02/2018
20/03/2018

Work in progress (95%) Detail Report
91 EOR to SKV Badli. (SH:- Raising of existing Boundary wall.)

11/12/2017
10/03/2018
10/03/2018

Work in progress (90%) Detail Report
92 Repair and Raising of boundary wall & making pedestrian path around the boundary wall at Govt. Sarvodaya Co-ed. Sec. School, Auchandi, Delhi.

04/06/2018
03/10/2018
20/10/2018

Work in progress (60%) Detail Report
93 Water proofing treatment on Roof at Govt. Boys Sr. Sec. School No.2, J.J. Colony, Bawana, Delhi.

06/08/2018
05/11/2018
05/11/2018

Work in progress. (20%) Detail Report
94 Water proofing treatment on Roof at Govt. Boys Sr. Sec. School, Bawana, Delhi.

06/08/2018
05/11/2018
05/11/2018

Work in progress. (20%) Detail Report