Projects - All Sector
Click on Number to view the list
Amount in Lacs
Projects - All Sector
Less than 1 crore 1 crore to 5 crore 5 crore to 25 crore 25 crore to 100 crore More than 100 crore Total
Status Number Amount Number Amount Number Amount Number Amount Number Amount Number Amount
Work in Progress 2186 ₹ 40833.65 99 ₹ 22661.29 22 ₹ 15277.77 15 ₹ 79228.10 4 ₹ 198103.52 2326 ₹ 356104.34
Sanction Work not yet Started 3592 ₹ 87542.03 197 ₹ 46253.56 63 ₹ 57009.82 24 ₹ 153868.42 58 ₹ 9652034.60 3934 ₹ 9996708.43
Work yet to be Sanctioned 265 ₹ 5710.50 35 ₹ 7530.78 6 ₹ 6437.33 5 ₹ 33118.74 11 ₹ 537850.98 322 ₹ 590648.34
Conceptual Stage / Planning 17178 ₹ 119290.87 231 ₹ 54334.39 57 ₹ 56575.63 21 ₹ 110072.50 13 ₹ 338149.16 17500 ₹ 678422.55
Completed in 2019 - 20
Completed in 2018 - 19
Completed before 2018 - 19
* Total Amount of Projects