Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Sector-16, Dwarka ,New Delhi. (SH: Civil and Electrical Composite Work).
Office Name
Education South West Maint Divn
T.S. Amount
6692.93 Lacs
Dated
03/02/2021
Tender Amount
5058.13 Lacs
Dated
16/07/2021
Progress Details
Date of Start: 18/07/2021
Date of Completion: 17/07/2022
Expected Date of Completion: 30/06/2024
Actual Completion Date:
Contractor
M/s PNSC Infrastructure Pvt. Ltd
Payment
Civil:  869.97 Lacs (Mar 2024)
% Progress : % (Mar 2024)
Present Position
Civil :  09/04/2024
Initial Delay was due to delay in receiving local body approval. DUAC approval received on 19.09.2022. Building Plans approved by SE (Bldg.), MCD vide file No. 10106691 dt. 03.04.2023. All local body approval has been received. Structure drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed. Superstructure work started, RCC slab for floor-2 level is under progress.
Bottlenecks
Civil :  09/04/2024
Qutubapur- SANCTION WITHDRAWN (i). Site layout plan has been uploaded to MCD by consultant for approval on dated 25.05.2022 and property tax of land also has been deposited. (ii). There is no tree cutting and no transplanting required. (iii). Additional Commissioner MCD & CTP, MCD during meeting 3.10.2022 informed that due to urbanization of villages, this gram sabha land is now under control of DDA .MCD is yet to upload their observation regardfing Layout Plan . (iv) DO dated 17.11.2022 issed by E-in-C to VC, DDA regarding clarification required by MCD. Response is still awaited. (v) LoP was discussed during meeting in MCD on 27.03.2023. Minutes of Meeting is still awaited. Above Sanction Withdrawn by DoE vide letter no.F.16/Estate/Cons./ Pucca School/Qutubapur/ 1594-1601 Dated: 24.05.2023 .