GGSSS, Gautampuri, Delhi
Office Name
Education East & North East Maint Divn/Education Elect Maint Division 2
History Sheet     Abstract of Cost     Background Note        
Tender Amount
--
Dated
11/03/2016
Progress Details
Date of Start: 11/03/2016
Date of Completion: 23/07/2016
Expected Date of Completion: 30/01/2018
Actual Completion Date: 30/01/2018
Contractor
M/s A. K. Builders
Payment
Present Position
Civil :  01/08/2019
Work completed (36 rooms completed)
Bottlenecks
Civil :  01/08/2019
Completed