School of Patel Nagar (Package-B)
Office Name
Education West Maint Divn/Education Elect Maint Division 2
History Sheet                
T.S. Amount
1242.38 Lacs
Dated
12/01/2016
Tender Amount
1229.96 Lacs
Dated
10/03/2016
Progress Details
Date of Start: 14/03/2016
Date of Completion: 26/07/2016
Expected Date of Completion: 31/01/2017
Actual Completion Date: 20/09/2017
Contractor
M/s Tewatia Construction Pvt. Ltd.
Payment
Present Position
Civil :  30/01/2018
Work completed & 16 rooms handed over.
Bottlenecks
Civil :  30/01/2018
Null