GSSS at Mustafabad
Office Name
Education East & North East Maint Divn/Education Elect Maint Division 2
History Sheet                
Progress Details
Date of Start: 05/05/2016
Date of Completion: 05/05/2016
Expected Date of Completion: 05/05/2016
Actual Completion Date: 05/05/2016
Contractor
M/s M. C. Construction Co.
Present Position
Civil :  15/05/2018
Not available (Court Case is pending. Site not available)
Bottlenecks
Civil :  15/05/2018
Work completed