GGSSS Sultanpur Block F
Office Name
Education North West Maint Divn
History Sheet                
Progress Details
Date of Start: 27/03/2016
Date of Completion: 08/08/2016
Expected Date of Completion: 31/01/2017
Actual Completion Date: 15/03/2017
Contractor
Mrs M/S B L Infrastructure Projects Pvt.Ltd
Payment
Civil:  659.93 Lacs (Apr 2017)
% Progress :100.00 % (Apr 2017)
Present Position
Civil :  23/05/2017
Work completed