GBSSS Block A-6 Pocket-II Narela
Office Name
Education North West Maint Divn
History Sheet         Background Note        
Tender Amount
1396.86 Lacs
Dated
30/09/2016
Progress Details
Date of Start: 18/03/2016
Date of Completion: 30/07/2016
Expected Date of Completion: 30/06/2018
Actual Completion Date: 29/06/2018
Contractor
M/s Amar Construction Co.
Payment
Civil:  332.27 Lacs (Jul 2018)
% Progress :100.00 % (Jul 2018)
Present Position
Civil :  16/11/2018
work completed